INTERNSHIP REPORT
Aziz Cross Flyover on G.T Road Gujranwala
July 10, 2017
Submitted to:
ENGG NASIR ABBAS
Submitted by:
ADEEL AHMAD
1
ADEEL AHMAD BCTF13E033
2
ADEEL AHMAD BCTF13E033
Contents
1. About companies.................................................................................................................................4
2. ABSTRACT........................................................................................................................................4
3. RELEVANT FEATURE OF PROJECT...............................................................................................4
4. INTRODUCTION...............................................................................................................................5
5. TRAFFIC VOLUME...........................................................................................................................5
6. BASIC COMPONENTS OF AZIZ CRROSS FLY OVER..................................................................6
7. PROJECT STRUCTURE....................................................................................................................6
8. BOX GIRDER...................................................................................................................................10
9. I- GIRDER........................................................................................................................................12
10. PRE-STRESSED BOX GIRDER AND I-GIRDER......................................................................12
11. RETAINING WALL......................................................................................................................14
12. PANEL WALL...............................................................................................................................14
13. EARTH WORK.............................................................................................................................14
14. CONCRETE BATCHING PLANT................................................................................................15
15. SCOPE OF WORK........................................................................................................................16
16. WORK PROGRESS......................................................................................................................19
17.Duty at Flyover 4:.................................................................................................................................20
18.Work Experience:.................................................................................................................................20
3
ADEEL AHMAD BCTF13E033
1. About companies
Contractor(NLC)
NLC, the most dynamic public sector transportation and construction
organization has a proud history of offering landmark innovative and customized
solutions. It is founded in 1978. It is most reliable company in Pakistan. The construction
tender of Aziz Cross Gujranwala has been given to this firm. NLC won contract through
open bid on 4 Jan, 2016
Consultant(NESPAK)
NESPAK enjoys the status of presence one of the highest
engineering consultancy organizations in Asia and Africa. It is graded amongst the
world’s top 200 consulting companies. NESPAK was established in 1973 as a private
limited company by the Government of Pakistan. At Aziz Cross Flyover, NESPAK gives
best consultancy service to complete this project. All the work completed by contractor
has been examined by this firm.
2. ABSTRACT
The flyovers are constructed since early seventeen. The major impact of the flyover
construction to curb traffic congestion problem has assessed in terms of traffic
decongestion, time saving, fuel saving and emission reduction. However planning,
design, construction, and erection of fly-over consume great span of time. The report is
about Aziz Cross Flyover on G.T Road at Constructed in Gujranwala. There are 5-
Flyover constructed at G.T Road Gujranwala which have the different length, width and
curves. Superior seismic resistance and life span. Bridges and fly-over’s are structures
providing passageway over an problem without closing the way beneath. The required
passage may be for a road, railway or a valley.Bridge design is a compound problem,
calling for ingenuity and feasibility, while satisfying the basic requirement of safety and
economy. This is the mega project at Gujranwala, Punjab Pakistan. The designer
company of this project is National Engineering Service of Pakistan ( NESPAK ). And
Contractor is NLC(National Logistics Cell). The MD of NESPAK TARIQ have designed
it. I did internship at this project. My experience about this project is so good, I educated
many things from it.
4. INTRODUCTION
Aziz Cross known as Lohianwala Bypass is located at G.T Road Next To Lohianwala,
Gujranwala City, Punjab, Pakistan .Average Daily Traffic ( ADT ) 2.12 lakh heavy and low
traffic vehicles pass from this bypass of big cities like Lahore, Gujrat, Rawalpindi, Sialkot
including Gujranwala Local Traffic. It is the also Current and Incoming point of Gujranwala
City. It is called a back-bone of Gujranwala according to all aspects. National Engineering
Services Pakistan (NESPAK) was given the task of a complete design by the Communication
and Works Department for a signal-free interchange at Aziz Cross, Gujranwala. The construction
tender of Aziz Cross Gujranwala has been given to NLC company which is well-known
construction firm in Pakistan. The signal-free interchange at Pindi Bypass was request by the
citizens of Gujranwala because they were challenged many problems due to traffic shortage.
5. TRAFFIC VOLUME
. The figure below show the conflict and the traffic count at Aziz Cross Gujranwala.
This image show that the Average Daily Traffic ( ADT ) moving on the Lohiawala bypass.
5
ADEEL AHMAD BCTF13E033
Pile
Pile-cap
Pier
Box Girder
Bottom slab
Top slab
Outer webs
Inner web
Barrier
Barrier
Top Slab
Bottom Slab
Canopy
Pier
Pile-cap
piles
7. PROJECT STRUCTURE
The structure is about Box Girder Cast in situ. Usually the most of the other countries used Box
Girder as a pre-cast. The structure of the project has a big task for designer NESPAK and
contractor NLC to manage every thing at site. NLC follows all the standards to do work at site for
complete this project. No doubt it’s a very complex structure but NLC managing all the crises.
The structure of the project can be separated into two categories as follow:
Sub-Structure
Super-Structure
Sub-Structure
6
ADEEL AHMAD BCTF13E033
Foundation is part of substructure. Substructure is the lower portion of the building or bridge
which conveys the dead load, live loads and other loads to the under sub-soil. According to
bridge construction the major parts of sub-structure as follow:
1. Piles
2. Piles Cap
3. Piers
4. Abutments
1. PILES
A deep foundation is a type of foundation which transfers building loads to the earth farther
down from the surface than a shallow foundation does, to a subsurface layer or a range of
depths. A pile is a vertical structural element of a deep foundation, driven or bored deep into
the pounded at the building site. The length of piles construct at Aziz Cross Flyover is
different according to soil condition. Normally piles length is 38m.
PILES
7
ADEEL AHMAD BCTF13E033
2. Piles Cap
a reinforced or mass concrete connecting beam cast around the head of a group of pilesenabli
ng it to act as a single unit to support the imposed load.
8
ADEEL AHMAD BCTF13E033
3. Piers
A pier, in architecture, is an erect care for a structure or superstructure such as an arch or
bridge. Sections of structural walls between openings (bays) can function as piers.
canopy
pier
4. Abutment
It refers to substructure at the end of the bridge span.
It supports;
Super structure load
Live load
9
ADEEL AHMAD BCTF13E033
8. BOX GIRDER
A box girder in which the main beams comprise girders in the shape of a hollow box. The box
girder usually comprises either pre-stressed concrete, structural steel.Box girder bridges are
usually used for highway flyovers. The box is typically rectangular or trapezoidal in cross-
section. At Aziz Cross Flyover trapezoidal box girder are used on site means cast-in-situ box
girder used. Box girder used in flyover 1,2,3,4. The dimension of box girder is as follow:
BOX GIRDER
REINFORCED
10
ADEEL AHMAD BCTF13E033
WEBS
BOTTOM SLAB
TOP SLAB
9. I- GIRDER
A I-girder bridge, in general, is a bridge that uses girders as the means of supporting the deck. A
I-girder bridge is very likely the most commonly built and utilized bridge in the world. Its design
is simple and easy. The span range is low and medium. At Aziz Cross flyover I-girder used
flyover 5.
11
ADEEL AHMAD BCTF13E033
I-GIRDER PRECAST
12
ADEEL AHMAD BCTF13E033
TENDONS IN WEBS
o Tendon
o Strands
Tendon:
A tendon is basically a steel cable used in Pre-stressed Concrete structural elements like beam,
column etc. It is a medium through which tensile stresses are tempted into the concrete. It perhaps
one single steel cable or a group of cables twisted together to pass through required quantity of
tensile stresses.
Strands:
Strands are made with 7 wires of cable that kept in duct pipe for pre-stressing.
13
ADEEL AHMAD BCTF13E033
11.RETAINING WALL
Retaining walls are relatively rigid walls used for supportive the soil mass crosswise
so that the soil may be retained at different levels on the two sides. They are used to guaranteed
soils between two different elevations. There are many kinds of materials that can be used to
make retaining walls like concrete blocks, poured concrete, treated timbers, rocks or boulders. At
Aziz cross flyover poured concrete retaining wall is used at flyover 5. There is the vibration of
train and pressure of heavy traffic.
RETAINING WALL
12.PANEL WALL
Panel wall is used for the placement of poured concrete retaining wall. It’s the same
function of retaining wall. Panel wall is the new technology. It is easy to construct and placed.
Normally the pre-cast panel are used. At Aziz cross flyover panel are used all flyover ,loops and
ramp expect flyover 5 where poured concrete retaining wall is used.
PANELS
13.EARTH WORK
14
ADEEL AHMAD BCTF13E033
lot of earthwork is done at Aziz cross Flyover because the roads are provided along the sides of
Flyover. Service roads are provided along the roads and on drains.
15
ADEEL AHMAD BCTF13E033
15.SCOPE OF WORK
Piles 82
Pile Cap 16
Piers 13
Abutments 3
Spans 11
TABLE 01
16
ADEEL AHMAD BCTF13E033
Piles 64
Pile Cap 13
Piers 11
Abutments 3
Spans 10
TABLE. 02
3. FLYOVER 03 (Sialkot to Rawalpindi)
Piles 64
Pile Cap 13
Piers 13
Abutments 2
Spans 14
TABLE. 03
17
ADEEL AHMAD BCTF13E033
Piles 84
Pile Cap 20
Piers 18
Abutments 2
Spans 18
TABLE. 04
Piles 36
Pile Cap 4
Piers 4
Abutments 2
Spans 3
TABLE 05
18
ADEEL AHMAD BCTF13E033
16.WORK PROGRESS
FLYOVER 1, 2, 3 & 4.
TABLE. 06
19
ADEEL AHMAD BCTF13E033
TABLE. 08
17.Duty at Flyover 4:
Firstly I was appointed as internee on Flyover 4 at Aziz Cross Gujranwala under the supervisor
Mr. Salman Munawar. He treated me very well and taught me all thing that use in Flyover 4. Day
by day I was seeking knowledge and learnt a lot of things. I educated there all things like reading
drawings, how to deal with contractor, how to inspection of work etc.
When request reached from Contractor to the office(NESPAK). I had go for inspection with my
Supervisor. I I obeyed all the rules of my Company and did as they said.
18.Work Experience:
It was one of the most outstanding days of my time at work. After being introduced to everyone.
I have been working for main consulting firm NESPAK . They were very open and happy for me
to subsidize as much as I wanted to, and were open to any suggestions and ideas. This suddenly
made me feel comfortable and definitely made me feel as though I was part of the NESPAK
team. When I enter the company(NESPAK). I met Engineer Altamash Aourangzeb(ARE). Then I
met the Resident Engineer(RE)(Naveed Anwar) of NESPAK. he did welcome to me for joining
NESPAK company. He treated me very good and gave inspirational things, then he appointed as
internee on flyover 4(occasionally) under supervisor Salman Munawar. He taught me very well
and tell me a lot of technical terms initially, day by day he increased my knowledge. I followed
all the rules. Not even I learnt from supervisor, every staff of NESPAK fully co-operated with me
and lean me about all things that done at site. I learnt about many things at flyover 4,3,2,1. When
request of any site work reached at office, I checked and did inspection with my supervisor and
for gaining knowledge. I educated many things like read drawings, how to inspect work, how to
deal with contractor and others, and many more.
I have also worked with other supervisors that dealt me very good and help to gain more
experience. It was a good chance for me to gain experience and being technically strong.
Everybody help me out for my future career. Through experience and reflection, another
treasured lesson that I learned while working at was that in projects, specially when working in
prime stages of certain project, things may change very rapidly and vividly. Occasionally, I faced
problems with contractors who try to encourage client to follow their designs instead of the
20
ADEEL AHMAD BCTF13E033
engineer’s design. The client might agree with contractor. Client may accept proposals by the
contractor without any proper documents to judge or prove contractor design is correct. In such
situation, as an engineer I have to educate client about the importance of engaging engineers for
a project.
Overall, my work experience at was positive. I was very happy with the amount of things that I
have learnt and experienced in the 4 months of being a Student Engineer with the
company(NESPAK). I am so glad, and proud that I have accomplished my course, and I can now
graduate.
21