VENDORS

SCAFFOLDING

PWHT

Tools & Equipment

Blinding-
deblinding /
Drop-install
flanges

Hydrotest

Passivation

Retubing /
Tube~Tubeshe
et Welding

Passivation

General
VENDORS
Preliminary / Post Inspections
Blinding / Deblinding
Bolt removal/installation
Dismantling /install covers
Structure support installation & removal
Lifting
Moving exchangers to ground level
Other works (based on site survey)
Heating Coil fixing, Ceramic wool fixing ,electrical connection between heating coil, panels, distribution panel &
recorders
PWHT on both tubesheets to be done simultaneously
PI controller, recorder 6/12 points, heating coil, Type K thermocouple wire, thermocouple attachment unit of
capacitor discharge method, ceramic beads, etc.,
Support with one end fixed and other end sliding to facilitate tube bundle expansion
PWHT as per Annexure 1

Tools & Equipment


Ring / Open End Spanners to suit M42/M48/xx studs
Hammers
Gas cutting equipment (in case of hot work removal of stubborn nuts)
Pneumatic Bolt remover eqpt, HydraulicTensioning/Torqueing equipment, tools & accessories
Wedges / Flange spreaders
Hydrotest Pump
High pressure hoses, fittings, pressure gauges for hydrotest
Pressure gauge calibration (Range 1.5 to 4 times)
Passivation Pump (Discharge 60m3/hr & head 50m / IS Motor or diesel operated pump
Hose connections / fittings / associated electrical fittings, 100Mtr cable per pump, panels, etc.,

Appropriate for the exchanger / tube dimension & specification, following tools shall be provided as per
estimated quantity; (TUBESHEET THICKNESS : 300mm / 250mm)
Tube cutters / Tube pullers / hydraulic puller / tube expander / grooving tool / flaring tool / expanding machine /
tube pulling machine / drilling machine / drill bits / reamer bits.
TIG Welding Machine, ER70S-2 Filler rods (Ø1.6mm) for tube ~ tubesheet welding
LC DPT Kit
Passivation Pump (Discharge 60m3/hr & head 50m / IS Motor or diesel operated pump
Hose connections / fittings / associated electrical fittings, 100Mtr cable per pump, panels, etc.,
Sufficient Electrical cables, fittings to reach required locations mentioned in scope
Crimping / Glanding by licensed electrician
Hose connections / fittings / associated electrical fittings, 100Mtr cable per pump, panels, etc.,

Documents
PQR

Main Works
Hydrotest must be done 3 times for U tube type and 2 times for fixed type
Bundle installation - Test Ring installation - test flange installation - Shell side initial hydrotest
Removal of Test Rings - Removal of test flanges - Installation of Channel covers - Tube side hydrotest
Install of shell cover - perform final shell side hydrotest
Tube ~ Tubesheet welding leaks to be rectified / hydrotest to be redone
Transportation & performing passivation by BPCL provided passivation chemical

Other Works
* Hose Fitting List to be estimated and reqd items to be requested to client
* Gasket list to be checked against phyical & eqpt drawing. Request client for any requirement
* Request for electrical construction power / EDG power in prescribed format

Assumptions
Gaskets will be provided by client
Bolts / Nuts (if needs replacement) will be provided by client
End blinds / Test rings / Test flanges will be provided by client

Manpower
Tig Welders - 8Nos
Qualified Electrical Safety Engineer - 1 Nos