Вы находитесь на странице: 1из 38

22 - 25 OCTOBER 2018 - BUENOS AIRES

Argentina's largest clean


energy congress & exhibition

2018 ARGENTINA
RENEWABLE ENERGY
REPORT

Written by
Mariyana Yaneva, Plamena Tisheva, Tsvetomira Tsanova
Edited by
Mariyana Yaneva

May 2018

@AIRECnews | #AIREC www.airecweek.com www .AIRECWEEK. com


CONTENTS

INTRODUCTION 3

POWER MARKET ARCHITECTURE AND INSTITUTIONS 4


WHOLESALE ELECTRICITY MARKET 4
MARKET PARTICIPANTS 6

ARGENTINA’S GRID INFRASTRUCTURE 7

THE RENOVAR PROGRAMME 10


ROUND 1 12
ROUND 2.0 16
PROJECTS PROGRESS 20
ROUND 3.0 20

SOLAR PV DEVELOPMENT IN ARGENTINA 21
SOLAR IRRADIATION AND GEOGRAPHICAL RESOURCE 21
CURRENT INSTALLED CAPACITY & POWER GENERATION 21
PROJECT LANDSCAPE AND CONSTRUCTION TIMELINES 22

WIND POWER DEVELOPMENT IN ARGENTINA 24


WIND SPEEDS AND GEOGRAPHICAL RESOURCE 24
CURRENT INSTALLED CAPACITY & POWER GENERATION 24
PROJECT LANDSCAPE AND CONSTRUCTION TIMELINES 25

FORECASTED INSTALLED CAPACITY OF WIND AND SOLAR


POWER PROJECTS BY 2025 27

FINANCING RENEWABLE ENERGY PROJECTS IN ARGENTINA 28


FODER AND WORLD BANK GUARANTEES 28
GREEN BONDS 30
PROJECT FINANCING 30

PROCURING RENEWABLE ENERGY TO C&I CUSTOMERS 31

OPPORTUNITIES IN DISTRIBUTED GENERATION, OFF-GRID


AND MINI-GRID 33

ENERGY STORAGE 35

REFERENCES & PHOTO CREDITS 36

www .AIRECWEEK. com


www.airecweek.com
INTRODUCTION

Argentina recently opened its electricity market to incorporate wide-scale clean


energy and is currently one of the most promising markets for renewables in Latin
America. The economic and political crisis at the turn of the millennium took its
toll on the Argentine electricity market, providing little incentive to generators and
distributors to further invest in increasing their generation and distribution capacity.
However, the country’s bold clean energy targets and recent update of the regulatory
framework has raised its profile for renewable energy investors. Argentina is targeting
an 8% share of renewables in its power mix by the end of 2018, going up to 12% by
2019, 16% by 2021, 18% by 2023 and 20% by 2025.

3 GW 10 GW

20%
18% 19%
17%

% of the total power demand


16%
14%
12%

8%
RenovAr Round 1.0
Existing + 1.1 GW - 2.75%
RenovAr Round 1.5
Auction 1.2 GW - 3.0%
2016 Legacy Conracts (R202)
0.5 GW - 1.5%
9%
Existing 0.8 GW - 1.8%

2018 2019 2020 2021 2022 2023 2024 2025


Note: Percentage of RE in toral demand calculate using P75 genartion estimates and 2018 projected demand

Source: Comisión Nacional de Energía Atómica - October 2017

With an overall grid-connected capacity of 754 MW at the end of March 2018,


renewables (excluding large hydro power plants) are currently generating around 2%
of the electricity in Argentina. The 8% target for the end of 2018 looks ambitious but
quite achievable if projects awarded in the RenovAr auction in 2016 get built in time,
CNEA, the National Atomic Energy Commission in Argentina has estimated.
This report will give you an overview of Argentina’s current power market architecture,
the RenovAr auctions programme (including detailed project description of the
rounds that took place so far), as well as the investment opportunities outside the
tenders, both in the commercial and industrial (C&I) sector and off-grid, small scale
developments.

Wind and solar power advances are explored in greater detail with an outline of the
latest capacity and generation figures, as well as project progress. Special attention is
also paid to financing schemes, grid issues and future development of energy storage.

www .AIRECWEEK. com www.airecweek.com 3


POWER MARKET ARCHITECTURE AND INSTITUTIONS

The institutional framework of the electricity sector in Argentina is defined by three


main government entities – the Ministry of Energy and Mines (MINEM), the National
Electricity Regulator (ENRE) and the wholesale electricity market operator Compañía
Administradora del Mercado Mayorista Eléctrico (better known as CAMMESA).

The Ministry and its Secretaria de Energia Electrica (SEE) designs the national
energy policy and sets the broad regulatory framework.

ENRE is an autonomous entity responsible for regulating and supervising the


functioning of the national electricity market. It grants grid access licenses and
supervises compliance of generation, transmission and distribution entities with safety,
quality, technical and environmental standards set in the regulatory framework and
the license agreements.

Argentina is a federal country, so provinces also have the legal capacity to regulate
energy issues in their jurisdictions, implementing their own laws, regulations and
support policies. Provincial energy laws and regulations cannot contradict the national
regulatory framework but could build on it. Provincial electricity regulators (or ENRESP
under their Spanish acronym) regulate the electricity activity in their respective
provincial regulatory frameworks.

As the wholesale energy market administrator, CAMMESA coordinates dispatch


operations, determines wholesale prices, manages transactions in the national
interconnected system (Sistema Argentino de Interconexión, SADI), and acts as
off-taker in certain power purchase agreements (PPAs). The board of directors
includes equal representation of all market participants, including the Government of
Argentina, the generation companies, transmission and distribution utilities and large
power consumers.

WHOLESALE ELECTRICITY MARKET

All electricity transactions in the Argentine electricity sector are conducted through a
wholesale electricity market which acts as a clearing house for electricity trading. Set
up in 1992, the wholesale electricity market in Argentina is organized as a competitive
market, including a spot market and a term market (or contracts market). Prices on
the spot market are established on an hourly basis as a function of marginal cost of
production measured at the system's load center.

On the term market, quantities, prices and contractual conditions are agreed upon
directly between sellers and buyers. Generators declare their marginal costs

www .AIRECWEEK. com www.airecweek.com 4


POWER MARKET ARCHITECTURE AND INSTITUTIONS

semiannually. CAMMESA uses the semiannual marginal cost declarations from


thermal and hydro generators to determine seasonal dispatch schedules to minimize
energy cost in the spot market.

A stabilization fund, managed by CAMMESA, was designed to stabilize prices for end
users. Financed from the difference between the regulated and spot prices, the fund is
used when spot prices exceed the regulated price and replenished when the regulated
price exceeds the spot price. The following chart shows how the wholesale electricity
market in Argentina was designed to work.

Electricity Transmission Electricity


flow
flow Companies
Seasonal Regulated
Prices Customers

Generators Pool Distributors


administered by
Spot Prices CAMMESA
(limited by Other
RES 240-03) Generators Large
Stabilization Customers
Fund Traders Negotiated
Prices

SPOT MARKET

Large
Customers
Negotiated
Prices Other
Generators

Traders

CONTRACTS MARKET
Source: Endesa Americas SA SEC filing 2016

However, in the aftermath of the country’s 2001–2002 economic crisis, the market
was reorganized to become effectively controlled by CAMMESA. A government
decree declared a state of emergency in the energy sector from December 16, 2015
to December 31, 2017. Free bilateral trading was suspended and large customers were
obliged to buy electricity directly from CAMMESA. Wholesale prices were virtually
frozen and kept artificially below costs, therefore creating a structural deficit in
the operation of the market. The deficit has been covered with subsidies from the
Argentine government.

In February 2017, Resolution 19/2017 established generation remuneration based on


capacity by technology and scale. The remuneration is denominated in US dollars and
is converted at the exchange rate published by Argentina’s central bank on the last
day before termination of each period set by CAMMESA.

www .AIRECWEEK. com www.airecweek.com 5


POWER MARKET ARCHITECTURE AND INSTITUTIONS

MARKET PARTICIPANTS

The Argentine wholesale electricity market has four types of market participants or
agents: generators, transmission and distribution companies, traders and large users.
At the end of March 2018, the market had 353 participants registered as market
agents on the side of power generation:

*A self-generator is an
NUMBER OF electricity consumer
GENERATION
PARTICIPANTS that generates electric
energy as a byproduct,
GENERATORS 320 since its main purpose is
SELF-GENERATORS* 26 the production of goods
and/or services
CO-GENERATORS** 7
** A co-generator is
TOTAL 353 a market participant
who generates electric
energy and steam or
other type of energy for industrial, marketing, heating or cooling purposes jointly with
a third party.

On the consumption side, large consumers participating directly in the wholesale


market are classified into three categories:

• Major Large Users (Grandes Usuarios Mayores, or GUMAs), with capacity higher
than 1 MW and energy consumptions higher than 4,380 MWh/year
• Minor Large Users (Grandes Usuarios Menores, or GUMEs), with capacity between
30 KW and 2 MW, and
• Particular Large Users (Grandes Usuarios Particulares, or GUPAs), with capacity
between 30 kW and 100 kW.

At the distribution level, all clients with a medium demand of over 300 kW are
considered Grandes Usuarios en Distrubución Mayores (GUDI).

Each category has different requirements with respect to purchases of their energy
demand. For example, GUMAs are required to purchase 50% of their demand through
supply contracts and the remainder in the spot market, while GUMEs, GUPAs and
GUDIs are required to purchase all of their demand through supply contracts.

www .AIRECWEEK. com www.airecweek.com 6


POWER MARKET ARCHITECTURE AND INSTITUTIONS

At the end of March 2018, the Argentine wholesale electricity market had a total of
8,547 large consumers registered as market participants, as illustrated in the table
below.

NUMBER OF
TYPE OF CONSUMER
PARTICIPANTS
GRANDES USUARIOS MAYORES
415
(GUMA)
GRANDES USUARIOS MENORES
2,182
(GUME)
GRANDES USUARIOS PARTICULARES
25
(GUPA)
GRANDES USUARIOS EN
5,925
DISTRUBUCIÓN MAYORES (GUDI)

5,925 8,547

ARGENTINA’S GRID INFRASTRUCTURE

Argentina’s grid network currently includes about 14,000 km of 500 kV high-voltage


transmission lines and about 19,500 km of mid-voltage lines.

Internationally, the country has interconnections that allow electricity trading with
Brazil, Paraguay, Chile and Uruguay. When national electricity demand set a new
record of 26,320 MW on February 8, 2018, it was covered entirely by local generation,
without the need for imports. In comparison, peak annual demands in 2016 and 2017,
which were also registered in February, required 1,884 MW and 1,069 MW of imports,
respectively.

Since the country restructured and privatised its electricity sector in the 1990s,
the 500-kV transmission grid has been operated by Transener under a 95-year
concession.

Besides the high-voltage transmission system (STEEAT), which carries electricity


between regions, Argentina has a regional distribution system (STEEDT), which
operates at 132 kV/220 kV and links generators, distributors and large users within
regions.

www .AIRECWEEK. com www.airecweek.com 7


ARGENTINA’S GRID INFRASTRUCTURE

There are six regional companies:

• Transnoa - covers the northwestern region of the country, including the provinces
of Tucumán, Catamarca, La Rioja, Salta, Jujuy and Santiago del Estero
• Transnea - the north-eastern region, including the provinces of Formosa, Chaco,
Corrientes and part of Entre Ríos
• Transcomahue/EPEN - the region of El Comahue, covering the provinces of Río
Negro, Neuquén and part of La Pampa
• Transpa - serves the Patagonian region
• Transba - the province of Buenos Aires
• Distrocuyo - the provinces of San Juan and Mendoza

Details by voltage level and regions are available in the table below.

Transmission 500 kV 330 kV 220 kV 132 kV 66 kV 33 kV Total


system
High-voltage
14,195 563 6 14,763
(km)
Trunk
1,116 1,112 16,900 398 24 19,550
distribution (km)

Cuyo 641 626 1,267

Comahue 1,368 398 1,368

Buenos Aires 177 5,583 6,158

NEA 30 2,148 24 2,202

NOA 5,052 5,052

Patagonia 1,116 264 2,123 3,504


Source: CAMMESA, Informe Annual 2016

There are also independent transmission companies operating under technical license
by the STEEAT or STEEDT companies.

The transmission and distribution services in Argentina are performed under long-
term concessions with periodic rebidding. Edenor, Edesur and Edelap, the distribution
companies that once made up national utility SEGBA, account for a substantial part of
the Argentinian electricity distribution market.

www .AIRECWEEK. com www.airecweek.com 8


ARGENTINA’S GRID INFRASTRUCTURE

Transmission companies are responsible for the operation and maintenance of their
networks, but not for expanding the grid. Thus, expansion of transmission capacity
is mainly driven by its users. For example, to connect to the grid a renewable project
developer must seek a permit from the local transmission system operator, which
issues a preliminary decision for evaluation by CAMMESA. If approved by CAMMESA,
the decision is forwarded to ENRE, which issues a final decision on grid access,
followed by a five-day waiting period for contestations. The developer pays for the
line that connects the plant to the connection point.

Argentina’s grid is currently operating at near capacity


as electricity demand in recent years has increased
at a quicker pace than generation, transmission and
distribution capacities. Spare transmission capacity
that existed before the 2016 and 2017 renewable
energy and thermal energy auctions has already been
taken.
Despite this, the World Bank has indicated that Round
2 of the RenovAr programme is not expected to pose
significant problems to grid integration. The round
has incorporated some features to address concerns
related to limited transmission capacity. It has set
quotas per geographical region and technology,
including an Annex with information about available
capacity plus planned lines, and added a take-or-pay
clause, under which projects will be paid for energy
not dispatched if they become operational before the
expected transmission expansion. About half of the
awarded projects, or 940 MW out of 2,043 MW, have
such a clause in their contracts.

In view of the country’s renewable energy targets and


future expansion of intermittent renewables capacity Map – 500 kV lines. Source: CAMMESA
the Argentine government has asked the World Bank
for technical assistance and capacity building on renewables integration to improve
power sector planning and governance.

According to recent energy scenarios by the energy ministry, Argentina expects to add
between 14 GW and 18 GW of unconventional renewable energy capacity to reach 25%
generation from unconventional renewables by 2030.

www .AIRECWEEK. com www.airecweek.com 9


ARGENTINA’S GRID INFRASTRUCTURE

To follow demand growth and reinforce the transmission system in the short
term, the government plans to tender 2,825 km of 500 kV lines in 2018.

LEAT (Línea de Extra Alta Tensión) Río Diamante - Charlone (490 km, 600 MVA)
LEAT Atucha - Belgrano 2 + ET Belgrano 2 (35 km)
LEAT Belgrano 2-Smith + ET Smith (100 km, 1600 MVA)
LEAT Atucha 2- Plomer + ET Plomer + doble LEAT 35 km (Anillo GBA) - (130 km, 800
MVA)
LEAT Charlone - Junín-Plomer + ET Junín (415 km, 600 MVA)
LEAT Pto Madryn - Choele Choel + LEAT Vivoratá - Plomer (705 km)
LEAT Rodeo - La Rioja Sur + ET Rodeo + ET La Rioja Sur (300 km, 300 MVA)
LEAT Choele Choel - Bahía Blanca (340 km)
LEAT Sto Tomé - San Francisco-Malvinas + ET San Francisco (310 km, 450 MVA)

The ministry notes there are a number of challenges in the medium and long term.
These include keeping pace with demand growth, while improving security of supply,
and providing for dispatch of future renewables generation. As the country’s greatest
solar potential is in the Cuyo and NOA regions and wind in the southern region, both
away from the main demand zone, a network topology should be developed that
allows renewable power to travel from these areas to the points of greater demand.

According to a January 2018 booklet by the Agencia Argentina de Inversiones y


Comercio Internacional (AAICI), tenders will be launched throughout 2018 for seven
500 kV line projects totaling 2,175 km and representing investment of USD 2.2 billion.
They will be based on the public-private partnership model. AAICI lists the first seven
of the projects mentioned above

THE RENOVAR PROGRAMME

The RenovAr auction programme has the leading part in achieving Argentina’s
objective of 20% renewables in electricity consumption by 2025. It was launched in
May 2016 and has so far completed three bidding rounds, awarding 147 projects
with a combined capacity of 4,466 MW.

The public tendering mechanism involves a mix of incentives and guarantees and was
designed in a way that seeks to overcome some of the issues that hindered previous
attempts by the country to foster renewable energy development. An earlier auction
effort, the GENREN programme, was launched in 2009 with the aim to contract 1 GW
of renewable power but only a small part of the 895 MW awarded got constructed as
developers had difficulties obtaining financing.

www .AIRECWEEK. com www.airecweek.com 10


THE RENOVAR PROGRAMME

A key element of the new regime is the Fund for the Development of Renewable
Energies (Fondo para el Desarrollo de las Energias Renovables, FODER), which was
created to help mitigate risks and attract the much needed investments. FODER
is a public trust fund set up to provide guarantees and financing. The fund, run by
Argentina’s Investment and Foreign Trade Bank (Banco de Inversión y Comercio
Exterior, BICE), provides two type of guarantees to RenovAr winners -- a liquidity
guarantee, which ensures that project owners are paid for the electricity they
deliver to the grid, and a solvency guarantee, designed to reduce country risk. The
solvency guarantee allows project companies to exercise a put option under certain
circumstances and transfer their assets to FODER in exchange for cash compensation.

An additional optional guarantee was available to RenovAr bidders. The World Bank
provided a USD-480-million guarantee to backstop the government’s failure to fund
FODER when it needs to pay a put price. This guarantee backed projects in the first
two tenders, Rounds 1 and 1.5, of the RenovAr programme. In March 2018, the World
Bank approved another USD-250-million guarantee to support Round 2.

The RenovAr programme has so far attracted strong investor interest, which led
to significant oversubscription of the bidding rounds. Bidders compete to sign 20-
year power purchase agreements (PPAs) with CAMMESA, which acts as off-taker
on behalf of distribution utilities and wholesale market large users. Strike prices are
denominated in USD and adjusted annually.

Round Capacity Bids (MW) Capacity Average Price


tendered (MW) awarded (MW) USD/MWh

1 1,000 6,343 1,142 61

1.5 600 2,486 1,281 54

2.0 1,200 9,391 1,409 51

2 phase two 600 - 634

Round 1.5 and phase two of Round 2 competitions were launched upon announcing
the results of the original tenders, in order to take advantage of the large number of
offers presented.

www .AIRECWEEK. com www.airecweek.com 11


THE RENOVAR PROGRAMME

ROUND 1

The first RenovAr auction, Round 1, was announced in July 2016. It sought to award
1,000 MW (600 MW of wind, 300 MW of solar, 80 MW of biomass and biogas and 20
MW of small hydro).

A total of 123 bids were submitted, representing 6,343 MW of capacity, or more than
six times the volume sought. In October 2016, the government announced 17 winning
projects, totaling 1,108.6 MW -- 12 wind, four solar and one biogas project. Later that
month, 34 MW of biomass, biogas and small hydro projects were added to the winning
list after they agreed to match ceiling prices. A brief summary of contracted capacity
and prices achieved by technology is available in the graphs below.

Round 1 Contracted capacity (MW) by technology

SMALL HYDRO 11
BIOGAS 9
BIOMASS 15
SOLAR 400
WIND 707

Round 1 Average / Minimum price by technology


Average Price (USD/MWh) 154
Minimum Price (USD/MWh)
118
110 110 105 105

29.39 59.75 58.98


49.08

WIND SOLAR BIOMASS BIOGAS SMALL HYDRO

In total, Round 1 awarded 29 projects with a combined capacity of 1,142 MW and


average weighted price of USD 61.33/MWh. The complete list of projects follows.

www .AIRECWEEK. com www.airecweek.com 12


THE RENOVAR PROGRAMME

Technology Project name Capacity (MW) Bidder name Province

Vientos Los Hércules 97.2 Eren Santa Cruz


Villalonga 50 Genneia Buenos Aires
Chubut Norte 28.4 Genneia Chubut
García Del Río 10 Envision/Sowitec Buenos Aires
Cerro Alto 50 Envision Rio Negro
Los Meandros 75 Envision Neuquen
WIND Vientos Del Secano 50 Envision Buenos Aires
Garayalde 24.2 Pan American Energy/3 Gal Chubut
Enat/Seg/Otamendi/ N.
Kosten 24 Chubut
Cerro Dragón
La Castellana 99 CP Renovables Buenos Aires
C.T. Loma De La Lata (Pam-
Corti 100 Buenos Aires
paEnergía)
Arauco II (phase 1 and 2) 99.8 P.E. Arauco S.A.P.E.M. La Rioja
La Puna 100 Fieldfare/Isolux Salta
Cauchari 1 100 Jemse Jujuy
SOLAR
Cauchari 2 100 Jemse Jujuy
Cauchari 3 100 Jemse Jujuy
Río Cuarto 1 2 Biomas Crop Cordoba
Río Cuarto 2 1.2 Biomas Crop Cordoba
Yanquetruz 1.2 ACA/Fersi San Luis
BIOGAS
San Pedro Verde 1.4 Adeco Agro Santa Fe
FECOFE/Coop. Huinca
Huinca Renancó 1.6 Cordoba
Ranancó
Biogás Ricardone 1.2 Nacarato/Otros Santa Fe
Papelera Mediterránea/
Gen. Biomasa Santa Rosa 12.5 Corrientes
BIOMASS Lucena
Pindó Eco-Energía 2 Pindó Misiones
EMESA/Const. Elect. Del
C. C. Guaymallén - Salto 8 1.2 Mendoza
Oeste
EMESA/Const. Elect. Del
C. C. Guaymallén - Salto 6 1 Mendoza
Oeste
SMALL EMESA/Const. Elect. Del
HYDRO Dique Tiburcio Benegas 1.7 Mendoza
Oeste
EMESA/Const. Elect. Del
Triple Salto Unificado 0.5 Mendoza
Oeste
Rio Escondido 7 Patagonia Energia Rio Negro

www .AIRECWEEK. com www.airecweek.com 13


THE RENOVAR PROGRAMME

Unsuccessful solar and wind bidders from the first auction were given a chance to
take part in a follow-up tender, called Round 1.5, which was completed in November
2016. The required capacity was 600 MW, split into 400 MW of wind and 200 MW of
solar power. This time, there were quotas for the location of the projects. The awarded
capacity reached 1,281 MW, double the planned volume while prices were down about
10% between the two auctions, which were a short time apart.

Round 1.5 Contracted capacity (MW)

SOLAR 516
WIND 765

Average Price (USD/MWh)

Minimum Price (USD/MWh)

54.94
53.34
48
46

WIND SOLAR

The 59 projects awarded in these two tenders are located in 17 provinces across
the country. Argentina also converted 0.5 GW of legacy projects to the new legal
framework in 2016.

The full list of Round 1.5 winners is given n the next page.

www .AIRECWEEK. com www.airecweek.com 14


THE RENOVAR PROGRAMME

Technology Project name Capacity (MW) Bidder name Province

Pomona I 100 Genneia Rio Negro


La Banderita 36.8 Fravega/Lobo La Pampa
Petroquimica Comodoro
Del Bicentenario 100 Santa Cruz
Rivadavia
Loma Blanca 6 100 Isolux/Selena Chubut
Miramar 97.7 Isolux/Selena Buenos Aires
WIND
El Sosneado 50 EMESA Mendoza
Achiras 48 CP Renovables Cordoba
Golden Peaks/ Sinohydro/
Pampa 100 Buenos Aires
Otros
Arauco II (phase 3,4) 95 Arauco S.A.P.E.M. La Rioja
Vientos De Necochea 1 38 Centrales de la Costa Buenos Aires
Lavalle 17.6 EMESA Mendoza
Lujan De Cuyo 22 EMESA Mendoza
La Paz 14.1 EMESA Mendoza
Pasip 1.2 EMESA Mendoza
General Alvear 17.6 EMESA Mendoza
Cafayate 80 Fieldfare/Isolux Salta
Nonogasta 35 Energias Sustentables/Fides La Rioja
Fiambalá 11 Energías Sustentables Catamarca
Tinogasta 15 Ivanissevich/Deykoll Catamarca
Saujil 22.5 Energías Sustentables Catamarca
SOLAR Sarmiento 35 Soenergy San Juan
Ivanissevich/Energías Sus-
Ullum 3 32 San Juan
tentables
Anchoris 21.3 EMESA Mendoza
Caldenes Del Oeste 24.8 Quaatro San Luis
Ullum 4 13.5 Colway/Clavijo/Maresca San Juan
La Cumbre 22 Diaser San Luis
Energias Sustentables/
Ullum N2 25 San Juan
Fides/ Ivanissevich
Ullum N1 25 Energias Sustentables/Fides San Juan
Iglesia - Guañizuli 80 Jinkosolar San Juan
Las Lomitas 1.7 Latinoamericana San Juan

www .AIRECWEEK. com www.airecweek.com 15


THE RENOVAR PROGRAMME

ROUND 2.0

Round 2.0 of the RenovAr programme was launched in August 2017 with an objective
to contract 1,200 MW, with quotas per region and technology. The tender again drew
strong investor interest and was more than seven times oversubscribed. The results
were announced in November 2017 and showed a continued decline in prices with
1,408.7 MW of projects securing contracts. The government then decided to extend
the auction by 600 MW and awarded a further 634 MW of projects in a so-called
phase two of Round 2. Overall, 88 projects with a combined capacity of 2,043 MW
were successful in this bidding round.

Round 2 (phase 1) Contracted capacity (MW)

SMALL HYDRO 20.8


LAND FILL BIOGAS 13.1
BIOGAS 35
BIOMASS 117.2
SOLAR 556.8
WIND 665

156.8
Average Price (USD/MWh) 150
Minimum Price (USD/MWh)
129.2 128

106.7 98.9
92 89

41.2 43.5
37.3 40.4

WIND SOLAR BIOMASS BIOGAS LAND FILL SMALL


BIOGAS HYDRO

www .AIRECWEEK. com www.airecweek.com 16


THE RENOVAR PROGRAMME

The full list of winning projects from Round 2.0 is available in the table below.
Technology Project name Capacity (MW) Bidder name Province

Energetica I 79.8 CMS De Argentina S.A. Buenos Aires


Chubut Norte IV 82.8 Genneia S.A. Chubut
Chubut Norte III 57.6 Genneia S.A. Chubut
Vientos Fray Guen 100 Senvion GmbH Buenos Aires
WIND
La Genoveva 86.625 Central Puerto S.A. Buenos Aires
Cañada Leon 99 YPF Energía Eléctrica S.A. Santa Cruz
General Acha 60 Miguel Oneto La Pampa
Arauco II (phase 5 , 6) 100 Windar Renovables S.L. La Rioja
Tinogasta II 6.96 360 Energy S.A. Catamarca
Saujil II 20 360 Energy S.A. Catamarca
Nonogasta II 20.04 360 Energy S.A. La Rioja
Altiplano I 100 Neon SAS Salta
La Pirka 100 Monteverdi & Gray Group Catamarca
Ullum X 100 Monteverdi & Gray Group San Juan
SOLAR
Verano Capital Solar One 99.9 Monteverdi & Gray Group Mendoza
V.Maria Del Rio Seco 20 Neuss Fund LLC Córdoba
Cura Brochero 17 Neuss Fund LLC Córdoba
Villa Dolores 26.85 360 Energy S.A. Córdoba
Añatuya I 6 360 Energy S.A. Sgo Del Estero
EPEC Empresa Prov de
Arroyo del Cabral 40 Córdoba
Energ. de Cordoba
General Villegas 1.2 Maria Elena S.A. Buenos Aires
Arrebeef Energia 1.5 Arrebeef S.A. Buenos Aires
Bombal Biogas 1.2 Tanoni Hnos S.A. Santa Fe
Resener I 0.72 Mario Gustavo Pieroni Buenos Aires
Citrusvil 3 Citrusvil S.A. Tucuman
James Craik 2.4 Universum Invenio Limited Córdoba

BIOGAS San Francisco 2.4 Universum Invenio Limited Córdoba


Pollos San Mateo 2.4 Pollos San Matero S.A. Córdoba
Bio Justo Daract 1 Biomass Crop S.A. San Luis
Cotagro Cooperativa Agro-
Jigena I 1 Córdoba
pecuaria
Del Rey 1 Silvina Hacen Santa Fe
Recreo 2.4 Universum Invenio Limited Santa Fe
Bella Italia 2.4 Universum Invenio Limited Santa Fe

www .AIRECWEEK. com www.airecweek.com 17


THE RENOVAR PROGRAMME

El Alegre Bio 1 Antiguas Estancias Don Córdoba


Roberto S.A.
Avellaneda 6 Industrias Juan F. Secco S.A. Santa Fe
Villa Del Rosario 1 Crops Investments S.A. Córdoba
Ampliacion Bioelectrica 1.2 Biomass Crop S.A. Córdoba
BIOGAS Dos
Don Nicanor 1 Silvina Hacen Santa Fe

Don Roberto Bio 1 Antiguas Estancias Don San Luis


Roberto S.A.
Ampliacion 2 Central 1.2 Biomass Crop S.A. Córdoba
Bioelectrica
Ensenada 5 Industrias Juan F. Secco S.A. Buenos Aires
LANDFILL
Gonzalez Catan 5 Industrias Juan F. Secco S.A. Buenos Aires
BIOGAS
Ricardone II 3.12 Martín Alfredo Nacarato Santa Fe
Biomasa Unitan 6.6 Unitan S.A.I.C.A. Chaco
Generación Las Junturas 0.5 Emerald Resources SRL Córdoba
Prodeman Bioenergia 9 Prodeman Bioenergía S.A. Córdoba
Generacion Virasoro 3 Forestadora Tapebicuá S.A. Corrientes
La Escondida 10 Indunor S.A. Chaco
Kuera Santo Tome 12.92 Norcon SRL Corrientes
Fermosa S.A. 6 Pegni Solutions S.A. Formosa
BIOMASS
Rojas 7 Global Dominion Access S.A. Buenos Aires
Ticino Biomasa S.A. 3 Lorenzati, Ruetsch Y Cia S.A. Córdoba
Capitan Sarmiento 7.2 Granja Tres Arroyos S.A.C.A.F.I Buenos Aires
BM MM Bioenergia 3 Molino Matilde S.A Misiones
Las Lomitas 10 BIOETANOL RIO CUARTO S.A. Formosa
Cogeneración Ingenio 2 Compañía Inversora Industrial Tucuman
Leales S.A.
San Alonso 37 Garruchos Forestación S.A. Corrientes
Lunlunta 6.34 Soledad Vigil Mendoza

Cruz Del Eje 0.5 Empresa Provincial de Energía Córdoba


de Corboda E.P.E.C.
Pichanas 0.5 Empresa Provincial de Energía Córdoba
de Corboda E.P.E.C.
Boca Del Rio 0.5 Empresa Provincial de Energía Córdoba
de Corboda E.P.E.C.
SMALL HYDRO Salto De La Loma 0.7 Latinoamericana de Energía San Juan
S.A.
Salto 7 1.2 Construcciones Electrome- Mendoza
cánicas Del Oeste S.A.
Salto 11 0.51 Maximiliano Llamazares Mendoza
Salto 40 0.52 Maximiliano Llamazares Mendoza

Las Tunas 10 Construcciones Electrome- Mendoza


cánicas Del Oeste S.A.

www .AIRECWEEK. com www.airecweek.com 18


THE RENOVAR PROGRAMME

Phase 2 of Round 2 added the following projects:

Technology Project name Capacity (MW) Bidder name Province Price


(USD/MWh)
Pampa Chubut 100 Enel Green Power Chubut 40.27
San Jorge 100 P.C.R. Buenos Aires 40.27
WIND
El Mataco 100 P.C.R. Buenos Aires 40.27
Diadema II 27.60 Capex S.A. Chubut 40.27
Energia Sustentable
Nonogasta IV 1 La Rioja 41.76
S.A.
Energia Sustentable
Tocota 72 San Juan 40.80
S.A.
SOLAR Latinoamericana De
Los Zorritos 49.50 Catamarca 41.76
Energía S.A
Martifer Renewables
Guañizuil II A 100 San Juan 41.76
SGPS S.A.
Zapata 37 Kuntur Energia Mendoz 41.76
Global Dominion
Venado Tuerto 7 Santa Fe 106.73
BIOMASS Acces
Biomasa La Florida 19 Genneia S.A. Tucuman 106.73
Pacuca Bio Energia 1 Pacuca S.A. Buenos Aires 171.85
Ab Energia 2 Ab Agro S.A. La Pampa 156.85
Enreco 2 Cecilia Debenedetti Córdoba 156.85
Santiago Energías Santiago Del
3 Los Amores S.A. 156.85
Renovables Estero
Biogeneradora Santa Biogeneradora
2 Córdoba 156.85
Catalina Centro S.A
Bio Energia Yan-
BIOGAS Yanquetruz II 0.80 San Luis 177.85
quetruz
Biocaña 3 Sesnich, Nestor Omar Santa Fe 156.85
Pergamino 2.4 Seeds Energy Buenos Aires 156.85
Seeds Energy De
Venado Tuerto 2 Santa Fe 156.85
Venado Tuerto S.A.
Carnes De La Pata-
General Alvear 1 Buenos Aires 171.85
gonia Neuquina S.A.
Carnes De La Pata-
El Mangrullo 2 Buenos Aires 156.85
gonia Neuquina S.A.

After phase two, the average price of Round 2 wind projects inched down to USD
40.91 per MWh, and the price of solar projects to USD 42.84 per MWh. Bidders were
invited to match the average prices of what was awarded under phase one of Round
2. The 88 winning projects under this round are located across 18 provinces. After the
three tenders, the leading province for wind power projects is Buenos Aires, and for
solar power projects - San Juan.

www .AIRECWEEK. com www.airecweek.com 19


THE RENOVAR PROGRAMME

PROJECT PROGRESS

As of May 2018, 41 of the 147 RenovAr projects are under construction or in operation,
representing an investment volume of over USD 2.5 billion and north of 1,600 MW in
terms of capacity, data from the energy ministry shows. Five projects have already
started commercial operations, 36 are under construction.

The signing of the contracts awarded to the 59 projects in the first two RenovAr
rounds was completed in January 2018. An initial set of seven projects under Round 2
got their supply contracts signed in March 2018. A further four contracts were signed
in May. According to a February 2018 World Bank document, 20 projects for 513 MW in
overall capacity, or nearly a third of the 59 projects awarded in Rounds 1 and 1.5, have
reached financial close. A group of 33 projects with a combined capacity of 1.7 GW are
working to meet their contractual deadlines and close financing, while six projects,
representing 204 MW, have missed their deadlines.

At present, project developers in Argentina can mainly tap financing from domestic
banks (which is relatively short-term), as well as development finance institutions and
export credit agencies. For example, the province of Jujuy raised funds for a 300 MW
solar development via a green bond sale.

ROUND 3.0

A new round of the RenovAr programme is planned for later in 2018. Energy minister
Juan Jose Aranguren was cited by local media as saying that Round 3 would be
launched between September and October. The size would be similar to Rounds 1 and
2, or around 1 GW.

www .AIRECWEEK. com www.airecweek.com 20


SOLAR PV DEVELOPMENT IN ARGENTINA

SOLAR IRRADIATION AND GEOGRAPHICAL RESOURCE

The Argentine Northwest region (Noroeste


Argentino), which encompasses La Rioja,
Salta and Jujuy, and the mountainous area of
central-west Argentina known as Cuyo, where
the provinces of Mendoza, San Juan and San
Luis are located, has the best solar irradiation
in the country.

In these two regions, the solar irradiation


ranges from about 1,800 kWh/sq m to 2,200
kWh/sq m per year.

CURRENT INSTALLED CAPACITY &


POWER GENERATION

Argentina’s first solar photovoltaic systems


were installed as part of the Renewable Energy
in the Rural Market Project (PERMER) between
1999 and 2012. The first grid-connected
solar plant, a pilot 1.2-MW project in Ullum
department, was built in 2010. There has been
no significant progress in seven years -- at the end of 2017, the country had just 9
MW of large solar power plants, according to a report by the International Renewable
Energy Agency (IRENA), released in March 2018. Neighbours Chile, Brazil and Uruguay
are several hundred megawatts ahead of Argentina with installed solar capacities of
2,183 MW, 1,097 MW and 239 MW, respectively, at end-2017.

On the other hand, the RenovAr tenders in 2016 and 2017 awarded contracts to 1.73
GW of solar projects, which, once completed, will help Argentina catch up. In 2017,
solar PV plants in Argentina produced 16.4 GWh, which represented just 0.012% of
MEM demand. In the first quarter of 2018, the solar power output arrived at 5 GWh
and its contribution, still negligible, was equal to 0.014% of MEM demand (CAMMESA,
Informe Renovables ABR 2018).
Data on solar power generation in Argentina since 2011 is available in the table below.
All in GWh 2011 2012 2013 2014 2015 2016 2017 Jan Feb Mar
2018 2018 2018
Solar
generation 1.76 8.1 15 15.7 14.7 14.3 16.4 1.6 1.4 2.0

MEM
demand 116,349 121,293 125,166 126,467 132,107 132,961 132,413 12,318 11,339 11,227

www .AIRECWEEK. com www.airecweek.com 21


SOLAR PV DEVELOPMENT IN ARGENTINA

PROJECT LANDSCAPE AND CONSTRUCTION TIMELINES

Four solar projects with a combined capacity of 400 MW won contracts in the first
RenovAR tender round in the autumn of 2016, and another 20 solar schemes with a
combined capacity of 516.2 MW were successful in round 1.5.

PROJECTS FROM RENOVAR 1.0 AND 1.5

The Cauchari solar complex in Jujuy province accounted for 300 MW of the 400
MW awarded in round 1.0. It is a project of the Jujuy State Energy and Mining Society
(JEMSE), with an 80% stake, and Chinese partners Shanghai Electric and Zhongli
Talesun Solar. JEMSE announced the start of work on the complex, comprising three
separate solar parks, in the autumn of 2017. The installation schedule, however,
was changed because of delays with the construction of the needed electrical
infrastructure.

A JEMSE official in March told local media that a key substation would be ready to
start work by February 2019. A new contract with CAMMESA has been agreed because
of the delay, extending the deadline for the start of solar power supply to March 2019
from the previous date in May 2018. Under the revised project schedule, the solar
panels will be arriving at the site in the second half of 2018.

The other big solar power project awarded in Round 1 has also been delayed. It was
won by Isolux and FieldFare and later sold to French energy company Neoen. The
company said in April it plans to start construction in November 2018 with the aim
to have the La Puna Solar farm completed by end-2019 and operational in 2020.
Isolux and FieldFare have also sold a solar project won in RenovAr 1.5, of 97.6 MWp
in Cafayate, Salta province to Canadian Solar. The latter has announced plans to
start construction in July. The park is to start feeding power to the grid by the second
quarter of 2019.

Five solar projects of Empresa Mendocina de Energia SA (EMESA) in Mendoza were


also in the RenovAr 1.5 list of awards and in January 2018 signed their contracts
with CAMMESA. With a combined capacity of 72.5 MW, the solar parks have to start
operation in 12 to 30 months from the signing. According to renewable energy firm
360 Energy, the 35 MW Nonogasta solar park was up and ready to run in April this
year. More projects awarded in the 2016 rounds are progressing and, unless there are
more delays, Argentina will grow its solar capacity significantly by the end of 2018.

www .AIRECWEEK. com www.airecweek.com 22


SOLAR PV DEVELOPMENT IN ARGENTINA

PROJECTS FROM RENOVAR 2.0

In November 2017 it was announced that 556.8 MW of solar projects have been
successful in round 2.0 of the RenovAr programme. In the second phase of the tender,
completed in December, there were five winning solar bids with a combined capacity
of 259.5 MW.

At the end of March 2018 the signing of contracts with the successful round 2 projects
started with seven contracts, four of which were allocated to solar projects. The 72-
MW Tocota in San Juan, 6.96-MW Tinogasta II in Catamarca, and the 1-MW Nonogasta
IV and 20.04-MW Nonogasta II, both in La Rioja, have been won by 360 Energy SA.
The contracts are crucial for the start of preparations, but even before these are in
place, developers are drawing and presenting their plans. Martifer Renewables, for
example, presented to authorities in the province of San Juan its design for the 100-
MW Guanizuil II PV park before the first contracts were signed.

In early April French firm Neoen informed government officials in Salta that it plans to
start construction of a 100-MW solar farm in Altiplano in November and complete it by
the end of 2019. The schedule is similar to that for the delayed La Puna Solar project.
Financing for both projects, located in the same municipality, is being negotiated.

www .AIRECWEEK. com www.airecweek.com 23


WIND POWER DEVELOPMENT IN ARGENTINA

WIND SPEEDS AND GEOGRAPHICAL RESOURCE

The southern provinces of Argentina in the


region of Patagonia, including Neuquén,
Chubut, Rio Negro, Santa Cruz and Tierra
del Fuego, have some of the richest wind
resources on the planet (Gerlach et al. 2011).
Central provinces such as Buenos Aires, La
Pampa and Santa Fe also have sites with very
good conditions. Wind speeds average 10 m/s
in Patagonia and the central areas. Capacity
factors are estimated to be around 45%-55%.

CURRENT INSTALLED CAPACITY & POWER


GENERATION

So far, the enormous potential for wind power


generation in Argentina remains largely
untapped. The first large-scale wind farm
connected directly to the SIN in Argentina was
the 25.2-MW Arauco I project. It came online in
2011 and since then has expanded into a much
larger project, expected to reach 400 MW.

At the end of 2017, Argentina had 228 MW of


installed wind power capacity (GWEC, February 2018), after adding 24 MW in the year.
The International Renewable Energy Agency (IRENA) put the figure at 257 MW in a
recently published report. The country is lagging significantly behind Latin America’s
wind leaders Brazil (12.8 GW), Chile (1.54 GW) and Uruguay (1.5 GW). This, however, is
about to change when projects secured in the RenovAr tenders are fully realised.

In 2017, wind farms in Argentina produced a total of 615.8 GWh, which could cover less
than 0.5% of MEM demand. In the first quarter of 2018 that share was 0.44% with 152
GWh produced by wind turbines. (CAMMESA, Informe Renovables ABR 2018)
Details of wind power generation in Argentina are available in the table..

All in GWh 2011 2012 2013 2014 2015 2016 2017 Jan Feb Mar
2018 2018 2018
Wind
generation 16 348.4 446.9 613.3 593.0 546.8 615.8 56.2 45.7 50.2

MEM
demand 116,349 121,293 125,166 126,467 132,107 132,961 132,413 12,318 11,339 11,227

www .AIRECWEEK. com www.airecweek.com 24


WIND POWER DEVELOPMENT IN ARGENTINA

PROJECT LANDSCAPE AND CONSTRUCTION TIMELINES

Argentina’s wind energy capacity is expanding mainly thanks to the RenovAr awards.
Back in 2009, there was also the GENREN tender, which got 1.4 GW in offers and
resulted in 895 MW of contracts signed, but only 128 MW of commissioned capacity.
The GENREN experiment failed due to investor concerns over the credit-worthiness of
CAMMESA, and the overall risk perceived to be present in Argentina.

Wind capacity in the country is also growing through power purchase agreements with
large energy consumers and wind projects for own use.

KEY PROJECTS FROM RENOVAR 1.0 AND 1.5

The first tender round of the RenovAR programme in the autumn of 2016 contracted
12 wind projects with a combined capacity of 708 MW. The government immediately
launched an additional auction, round 1.5, in which it awarded contracts to 10 more
wind projects, representing 765.4 MW of capacity.

One of the big wind farms being built under round 1.0 is the 97.2-MW Los Hercules
wind farm in Deseado department, Santa Cruz province. The developer -- Total Eren,
has to complete the plant by December 2018. Financing for the project was secured at
the end of 2017 and the turbine supplier -- Senvion of Germany, said in December 2017
its contract for the supply and delivery of the 27 turbines for the park has become
firm. It was later announced that the turbines would start arriving at the site in May
this year.

Argentina-based power producer Central Puerto SA also secured financing, about USD
119 million, for the 100-MW La Castellana wind project in Buenos Aires province near
the end of 2017. The wind turbine supplier, German firm Nordex, expects to complete
the wind park in the summer of 2018.

Several phases of the Arauco expansion project in La Rioja province were also
successful in the 2016 RenovAr rounds. Round 1.0 awarded a PPA for 100 MW of
additional capacity at Arauco, while a further 95 MW were secured in round 1.5 of the
programme. Parque Eolico Arauco SAPEM, 75% owned by the La Rioja government, is
the company behind the expanding project. The 195 MW new capacity will be up and
running by 2019.

Argentine thermal and renewable energy group Genneia SA secured several projects
in the round 1.0 and 1.5 auctions, including the 100 MW Pomona wind farm.

www .AIRECWEEK. com www.airecweek.com 25


WIND POWER DEVELOPMENT IN ARGENTINA

The turbines for it will be installed in early 2019, according to the supplier Nordex.
Construction works started in the spring of 2018 at the 38 MW Necochea Wind Park,
Buenos Aires province, also secured by Genneia.

Danish wind turbine manufacturer Vestas is to start equipment delivery in the third
quarter of 2018 for the 40 MW project Parques Eolicos Vientos del Sur SA, a unit of
Grupo Frali SA. The contract for the La Banderita project in La Pampa was won in the
RenovAr 1.5 renewable energy auction. The first turbine foundation was completed in
April and the park is set to go on stream in the first quarter of 2019.

KEY PROJECTS FROM RENOVAR 2

The Argentine government in November 2017 awarded 1,408.7 MW of renewable


energy capacity under round 2 of its renewable energy programme. This includes
eight wind projects, representing 665.8 MW of capacity. A second auction in December
2017 awarded 634 MW, of which 328 MW were wind contracts.

Argentina signed the first seven contracts with successful projects in round 2 of its
RenovAr renewable energy auction programme at the end of March 2018. The list
did not include any wind. Updates regarding the financing, equipment orders and
construction of the winning wind projects are expected after they sign firm contracts
with CAMMESA.

WIND POWER PROJECTS OUTSIDE RENOVAR

There are a number of wind projects in Argentina that are being built outside the
renewable energy auctions programme. This market is driven by companies in
Argentina which want or need to buy wind power to cover some of their demand.

Aluminum producer Aluar Aluminio Argentino SAIC in the first quarter of 2018 started
receiving components for 14 Vestas wind turbines of a 50-MW wind farm. It will help
the company meet requirements for large electricity users to source a portion of their
demand from renewables. The company has announced plans to install a total of 200
MW of wind power generation capacity in Chubut province.

Argentine state-run oil company YPF also built a wind farm -- the 100-MW Manantiales
Behr, to meet a portion of its needs.

In early 2018, Argentina-based power company Pampa Energia announced the start of
construction of two wind farms with a combined capacity of 100 MW, whose power will
be sold to private large-scale consumers. The Pampa Energia and De la Bahia wind
parks have been granted dispatch priority for 50 MW and 28 MW of their respective
capacities.

www .AIRECWEEK. com www.airecweek.com 26


FORECASTED INSTALLED CAPACITY OF WIND AND
SOLAR POWER PROJECTS BY 2025

Demand for electricity in Argentina is expected to increase to 170 TWh in 2025 from
135 TWh in 2015. (Ministry of Energy and Mining, June 2017). Renewables will play a
major role in meeting the additional demand with 10 GW of new capacity planned to
be put online in the period. Thermal power, large hydro and nuclear power are to add
6 GW, 3 GW and 1 GW respectively.

According to market estimates, Argentina could have 5 to 6 GW of wind power


capacity at the end of the year 2025. At least 2.5 GW have already been secured in the
RenovAr tenders and a new one is coming up in the second half of 2018. For solar, the
expectation is that the country could reach up to 2 GW of capacity by 2025.

The energy ministry has also released two scenarios to 2030. The “Trend+Investment”
scenario envisaged total of 34.3 GW of new power capacity, including 18.2 GW from
renewable energy sources. Capacity additions under the “Efficient+Investment”
scenario stand at 26.4 GW, including 14.3 GW of renewables.

Estimated Investment (in US$ billions)


5 Bill. US$

TRANSMISSION 5 >5K km
THERMAL POWER 4.8 +6 GW
NUCLEAR POWER 6 +1 GW
HYDROPOWER 10.2 +3 GW
RENEWABLES 15 +10 GW
DEMAND 2015 - 135 TWh DEMAND 2025 - 170 TWh

Source: Ministry of Energy and Mining, June 2017

According to market estimates, Argentina could have 5 to 6 GW of wind power


capacity at the end of the year 2025. At least 2.5 GW have already been secured in the
RenovAr tenders and a new one is coming up in the second half of 2018. For solar, the
expectation is that the country could reach up to 2 GW of capacity by 2025.

The energy ministry has also released two scenarios to 2030. The “Trend+Investment”
scenario envisaged total of 34.3 GW of new power capacity, including 18.2 GW from
renewable energy sources. Capacity additions under the “Efficient+Investment”
scenario stand at 26.4 GW, including 14.3 GW of renewables.

www .AIRECWEEK. com www.airecweek.com 27


FINANCING RENEWABLE ENERGY PROJECTS
IN ARGENTINA

Renewable energy projects in Argentina still mainly seek financing from domestic
banks and for relatively short-term loans. Development finance institutions (DFIs) and
export agencies can also be approached as well as the green bond market.

Though international banks are increasingly interested in the Argentine power sector,
they have not yet fully re-entered the market, so projects in the country rely on equity
more than is common in other markets, the World Bank observes. Via its FODER
guarantees, the international institution is a key actor on the renewable energy stage
in Argentina, offering guarantees to projects competing in the tenders.

In November 2017, long-term international project finance returned to the power


sector in Argentina, where it had not been available since the early 2000s, with the
financial close of Central Puerto’s 100-MW La Castellana wind project. It was led by
the International Finance Corporation (IFC), which is also assessing options to extend
debt financing to other IPPs in the country. It is working in close collaboration with
the International Bank for Reconstruction and Development (IBRD), both being World
Bank Group members. The Multilateral Investment Guarantee Agency (MIGA), another
member of the group, is also contemplating its reengagement in the energy sector of
Argentina.

FODER AND WORLD BANK GUARANTEES

Law 27.191, which in 2016 set the 20% renewable power target by 2025, also created
the Trust Fund for the Development of Renewable Energies (FODER) and offered
a VAT tax rebate and accelerated depreciation in order to boost investments in
renewables. The government’s plan was to make it possible for RenovAr winners to
get better financial conditions by getting access to guarantees by FODER, through
escrow accounts (Cuenta de Garantía), and the World Bank, through the IBRD.

The risk mitigation instruments provided by FODER were welcomed by potential


financiers, but these were not sufficient to attract the required investments. The
political risk and the lack of experience financing renewable energy projects in
Argentina were major concerns for financiers. Here is where the IBRD stepped in and
announced a guarantee of USD 480 million for renewable energy IPPs in RenovAr
rounds 1.0 and 1.5. The Indemnity and Guarantee Agreements were signed in August
2017 and the guarantee became effective in December 2017. A total of 27 projects with
a combined capacity of 1,033 MW, out of 2,424 MW awarded in the 2016 rounds, opted
for the IBRD guarantee.

www .AIRECWEEK. com www.airecweek.com 28


FINANCING RENEWABLE ENERGY PROJECTS
IN ARGENTINA

In March 2018, the World Bank approved a new USD-250-million guarantee for
RenovAr 2 projects. Fifteen projects with a combined capacity of 605 MW, out of
2,043 MW awarded in that round, have requested the guarantee. Overall, the World
Bank observes increasing confidence in investing in the Argentinian renewable energy
market, as the percentage of bidders requesting the guarantee has been decreasing
in the three tenders. It stood at 52% in Round 1.0, at 35% in round 1.5, and at 19% in
Round 2.0.

Wind and solar developers are more interested in the IBRD guarantee as 37% to
39% of the solar and wind capacity awarded has received it. In contrast, about 19% of
bioenergy and small hydro projects have the guarantee. The difference is consistent
with the greater size, financing needs and international profile of wind and solar
projects, the World Bank explains.

The pie charts below show the origin of bidders with or without the guarantee.

RenovAr Program - Awarded bidders' origin with or without IBRD Guarantee

With IBRD Guarantee Without IBRD Guarantee

3% 2%
15% 2%
15%
Argentina
5%
Europe
Usa / Canada
China
Brazil 77%
29%
51%

As a whole, 48% of bidders that opted for the IBRD guarantee included foreign
investors. In rounds 1.0 and 1.5 the percentage of international investors that
requested the IBRD guarantee stood at 56%, while in round 2 it increased to 67%.

www .AIRECWEEK. com www.airecweek.com 29


FINANCING RENEWABLE ENERGY PROJECTS
IN ARGENTINA

GREEN BONDS

Argentina was one of 10 new entrants to the green bond market in 2017, according
to the Climate Bonds Initiative (CBI). La Rioja province announced the issuance of a
USD-200-million green bond due 2025 to support the expansion of the Arauco wind
farm. The bond has an amortizing structure bearing a semi-annual coupon of 9.75%.
The CBI recognised La Rioja’s issuance at its 3rd Annual Green Bond Pioneer Awards
(GBPA) in 2018, in the “New Countries Taking Green Bonds Global” category. GBPA
recognize organisations, financial institutions and government bodies and individuals
who have led the development of green finance and green bond markets in the past
year, providing positive examples of climate resilient and low carbon investment.

Jujuy province issued a USD-210-million green bond several months after La Rioja,
raising financing for the 300-MW Cauchari solar project. It was several times
oversubscribed, attracting offers for a total of USD 744 million. The term is of five
years and the coupon is 8.62%.

Argentina’s Banco Galicia in March 2018 announced that the IFC has subscribed to its
USD-100-million green bond. The proceeds will be used to support climate change
mitigation projects, including energy efficiency, renewable energy, and sustainable
construction projects. Argentina’s Banco Galicia in March 2018 announced that the
IFC has subscribed to its USD-100-million green bond. The proceeds will be used to
support climate change mitigation projects, including energy efficiency, renewable
energy, and sustainable construction projects.

PROJECT FINANCING

The table shows details on financing secured for some of the bigger wind and solar
projects in Argentina.
Project Capacity Project owners Debt Lenders/Backers
financing
IDB Invest, international commercial
San Juan Solar 80 MW JinkoSolar USD 60.15m entities, Canadian Climate Fund for the
Power Project Private Sector in the Americas (C2F)
Vientos los Hércu- KfW IPEX-Bank, DEG, FMO, Euler
97.2 MW Total Eren USD 167m
les Wind Farm Hermes
La Castellana Wind 100 MW Central Puerto USD 119m IFC, MCPP, IDB, Banco Galicia
Project
El Corti Wind Greenwind SA (owned by Pam-
100 MW USD 104m IIC, Banco Santander, ICBC
Project pa Energia & Castlelake LP)
Cauchari solar JEMSE, Shanghai Electric,
300 MW USD 331.5m China Exim Bank
complex Zhongli Talesun Solar
Manantiales Behr 100 MW YPF USD 200m IIC, BBVA, Citibank, Banco Santander
Wind Farm

www .AIRECWEEK. com www.airecweek.com 30


PROCURING RENEWABLE ENERGY FOR COMMERCIAL
AND INDUSTRIAL ENERGY USERS

Industrial and commercial users account for about 60% of the electricity consumption
in Argentina, as illustrated by data for the first quarter of 2018, provided by CAMMESA.

Back in 2006, the government


launched its Energia Plus 100%
programme, which offered an 27% 28% 30%
80% Industrial
alternative electricity supply
service to large industrial clients 60% Commercial
29% 29% 29%
with a demand higher than 300
kW. Large users were allowed 40% Residential
to contract directly with new 44% 44%
20% 40%
generation and/or generating
agents, co-generators or self- 0%
generators who were not agents January 2018 February 2018 March 2018
of the electricity market.

The renewable energy legislation (Laws 26.190 and 27.191) later introduced a
requirement for the same group of power users to source 8% of their power from
renewable energy sources by 2018, scaling up biannually to 20% by 2025. Following
up, in August 2017, the Argentine Ministry of Energy and Mining published Resolution
No. 281-E/2017, spelling out details of how this requirement should be met and how
the new Renewable Source Electric Power Term Market Regime (or MATER in its
Spanish acronym) will operate.

In a nutshell, to comply with their renewable energy consumption quotas, large power
consumers can choose between 1) the joint purchases system (Compras Conjuntas
through CAMMESA and the RenovAr programme), 2) concluding a private PPA, or 3)
developing a self-generation project or a co-generation project.

Private PPAs are expected to be the preferred form of complying with the renewable
energy consumption quota as the PPA terms and conditions can be freely agreed
between the contracting parties with the only exception that the price cannot exceed
USD 113/MWh.

Before concluding such a PPA, large consumers need to specifically opt out of the
government’s joint purchasing mechanism. The opt-out notification can be done twice
a year, at the beginning of the seasonal schedules of the MEM. The minimum term for
the exclusion is set at 5 years.

www .AIRECWEEK. com www.airecweek.com 31


PROCURING RENEWABLE ENERGY FOR COMMERCIAL
AND INDUSTRIAL ENERGY USERS

A total of 2,287 large electricity consumers with a combined consumption of 33,087


GWh in 2017 will need to meet the renewable energy consumption quota this year,
CAMMESA said in April 2018. The 403 GUMA users account for the largest part of
the demand or 19,961 GWh in 2017. Three GUMA companies – cement and aluminum
producers, have already notified CAMMESA that they wish to opt out of the joint
purchasing mechanisms. Details are given in the table below.
Company name Type of Consumption in Medium capacity Opt-out
user 2017 (MWh) in 2017(MW) from date
Loma Negra (Catamarca) GUMA 137,841.9 15,735 1/2/2018
Loma Negra (Olavarria) GUMA 162,758.7 18,580 1/2/2018
Aluar SA GUMA 2,521,557.3 287,849 1/8/2018

Cement maker Loma Negra was the first to sign a corporate renewable PPA under
Argentina’s new regulatory framework. In October 2017, it announced it will buy wind
power from the 24 MW extension of the Rawson wind farm of Argentine energy
company Genneia SA under an agreement that runs through December 31, 2037.

According to Resolution No. 281-E/2017, to supply energy for the consumption quotas
of large, renewable energy generation, self-generation and cogeneration projects
must meet the following conditions:

1 - Started operation after January 1, 2017;


2 - Have been registered in the National Register for Renewable Energy Power
Generation (RENPER)
3 - Do not qualify as projects committed under a different contractual regime (e.g.
having an existing PPA with CAMMESA).

In the event that more than one project has filed for the same interconnection point,
and the transport capacity is not enough for all of them, the regulation provides for a
dispatch priority depending on: (i) the earliest beginning of the operation; and (ii) the
biggest factor capacity project, fixed in accordance to the updated provisions of the
production of energy, which shall be duly certified by a qualified independent consultant.
Granted such priority, the renewable project will have the same dispatch priority as the
projects in the joint purchasing mechanism.

In January this year, an initial group of nine wind and solar power projects, with
a combined capacity 273.12 MW, was granted dispatch priority within the MATER
framework. These assignments followed the receipt of 38 requests for 2,150 MW of
capacity by the deadline of November 30, 2017.
A total of 44 renewable energy projects with a combined capacity of 2,031 MW have
submitted dispatch priority requests during the first quarter of 2018, CAMMESA said in a
recent report.

www .AIRECWEEK. com www.airecweek.com 32


OPPORTUNITIES IN DISTRIBUTED GENERATION,
OFF-GRID AND MINI-GRID

At the end of December 2017, Argentina’s Ministry of Energy and Mines published Law
No. 27.424, which declares distributed generation from renewable energy sources as
a national interest and establishes legal and contractual conditions for distributed
generation for self-consumption and a net metering scheme for feeding surplus
electricity to the grid.

Under the law, all new national public buildings must include distributed generation
systems for self-consumption from renewable energy resources. What is more, all
retail power consumers can now install renewable energy generation systems. No
prior autorisation from the distribution company is required if the capacity of the
system is smaller or equivalent to the user’s consumption. Users that want to install
higher capacity need to request authorization from distribution companies.

Argentina has more or less replicated the successful Brazilian model for remuneration
of surplus electricity of distributed systems, connected to the grid. If users consume
more power than they inject over the month, the difference will be charged in the
monthly bill by the distribution company. If users inject more power than they
consumed during the month, they do not receive money from the retail market, but a
credit in kWh to be compensated in the following month.

A specialized fund - Fondo Para la Generación Distribuida de Energías Renovables


(Fodis), was created to support investments in distributed generation via loans,
guarantees and capital contributions. On the supply side, Argentina-based suppliers
of distributed energy equipment will have access to an array of incentives, including
tax certificates, accelerated amortization on assets, VAT rebate as well as access
to finance with preferential rates. However, secondary legislation still needs to be
published to provide more guidance and clear procedures on the implementation of
the law.

Rural electrification also offers business opportunities for small-scale renewable


energy systems. In 1999, Argentina started its Project for Renewable Energy in Rural
Markets (PERMER). Essentially, it is an off-grid rural electrification plan through the
use of sustainable sources, mainly solar PV. Its first phase, which ended in 2012, was
funded mainly through a loan granted by the International Bank for Reconstruction
and Development (IBRD) for an amount of USD 30 million, supplemented by a USD 10
million donation from the Global Environmental Fund (GEF). In 2008, IBRD approved
a new loan of USD 50 million to provide additional financing. Between 2001 and 2012,
PERMER helped 25,000 families from 15 provinces of the country to get residential
kits while thermal and electrical equipment was installed in 1,800 schools, data of the
National Audit Office shows.

www .AIRECWEEK. com www.airecweek.com 33


OPPORTUNITIES IN DISTRIBUTED GENERATION,
OFF-GRID AND MINI-GRID

On September 21, 2015, IBRD approved a new loan agreement for an amount of
USD 200 million, with the objective of developing PERMER 2. Earlier this year, the
Energy ministry launched PERMER 2 -- a tender for the provision of solar kits for
up to 120,000 rural households in Argentina. Each installation will consists of two
photovoltaic panels with a total power of 120 Wp, a battery, a control board and five
lamps of 18 W. The tender attracted 10 bidders, namely Nokero International Ltd,
IPL – GLP Consortium, D.Light Design Inc, Emprecepar Partipacoes Ltda EPP, Apca
DT Renewit, China National Huachen Energy Group Co.Ltd, Coradir SA, Exo SA, New
San SA – Gamma SL and Dinatech SA. The bids were opened at the end of April and
outcomes will be announced in the coming weeks. Installation processes are expected
to begin in the last quarter of 2018.

Opening of the bids in April 2018, Photo by Argentina.gob.ar. All rights reserved.

www .AIRECWEEK. com www.airecweek.com 34


ENERGY STORAGE

Energy storage is a cornerstone tool for enabling the transition from fossil fuels to
renewable energy supply and it finds application both in front-of-the-meter (utility &
wholesale electricity market) and behind-the-meter (customer) applications. What is
more, since 2010 the cost of batteries has decreased by more than 70% from about
USD 1,000 per kWh to about USD 200 per kWh, at present (Lazard’s Levelized Cost of
Storage Analysis—Version 3.0).

Argentina is already well known with its pumped-storage hydropower. The Los
Reyunos power project has an installed capacity of 224 MW and has been in
operation since 1983. Using the same technology but at a larger scale, the Rio Grande
hydroelectric complex was built in 1986. It has an installed capacity of 750 MW
comprised of four turbines of 187.5-MW each.

Battery-based utility-scale storage systems are also considered for big renewable
projects in Argentina. For example, the governor of Jujuy Province Gerardo Morales
said in March 2017 that Power China, the developer of 300 MW solar power projects
Cauchari 1, 2 and 3, is also thinking about another 1 GW solar power project, coupled
with round-the-clock storage. Morales also noted that Chinese PV maker Talesun,
which is building a PV panel factory in the province, has already signed a contract for
a 5 MW PV plant in La Quiaca, which will include lithium-ion battery storage.

The lithium-based energy storage solutions will be particularly interesting to investors


as Argentina is part of the so-called lithium triangle which also includes Bolivia and
Chile. The Puna Plateau, a region of the Andes Mountains spanning 1,800 km across
Argentina, Bolivia, and Chile, houses the largest proven deposit of lithium on the globe
but, at present, only Chile is a major producer of the white metal. However, as the
investment climate improved in Argentina over the past three years, about 40 foreign
companies began to consider opportunities in Argentina’s mining industry, more than
half of those in lithium, Mining Secretary Daniel Meilan told Bloomberg in an interview
last year.

Industry heavyweights Albemarle Corp., Soc. Quimica y Minera de Chile SA, Eramet
SA and Jiangxi Ganfeng Lithium Co. are among those looking at expanding or building
new lithium operations in Argentina, as part of a USD 20-billion pipeline of mining
projects through 2025, Meilan said.

Outside utility applications, small-scale energy storage solutions – or “community


batteries”, usually 100 kW to 500 kW installations (community storage) and 10 kW to
100 kW (village electrification) in size, can have a viable business case, supporting the
ongoing growth of decentralized generation in Argentina.

www .AIRECWEEK. com www.airecweek.com 35


REFERENCES & PHOTO CREDITS

1. RenovAr Plan de energias renovables Argentina 2016 – 2015, Ministerio de Energia


y Mineria. Republica Argentina. Accessed online on April 24, 2018.

2. Renewable Energy Argentina, December 2016, report by Undersecretariat of


Renewable Energy, Ministry of Energy and Mining, Argentine Republic

3. Electricity Regulation. Argentina. November 2017, Hugo C Martelli and Rogelio


Baratchart, Martelli Abogados and Tecnolatina

4. Ministerio de Energia y Mineria Presidencia de la Nacion, Adjudicciones del


Programa RenovAr, Tableau public, accessed online on May 4, 2018

5. International bank for reconstruction and development (IBRD). Project appraisal


document on a proposed IBRD guarantee on the amount of US$480 million
in support of the fund for the development of renewable energy (FODER) in the
Argentine Republic, Document of the World Bank, February 2, 2017, accessed
online May 4, 2018

6. International bank for reconstruction and development (IBRD). Project appraisal


document on a proposed IBRD guarantee on the amount of US$250 million in
support of the fund for the development of renewable energy (FODER) in the
Argentine Republic, Document of the World Bank, February 22, 2018, accessed online
May 4, 2018

7. World Bank to lend USD 250m to RenovAr projects in Argentina, article by


Renewables Now, accessed online on May 4, 2018

8. Renewable Energy Auctions. Analysing 2016, International Renewable Energy


Agency (IRENA), 2017, accessed online on May 4, 2018

9. Climatescope 2017, Argentina, accessed online on May 4, 2018

10. Genneia to sell renewable energy to private company, 1st in Argentina, article by
Renewables Now, accessed online on May 4, 2018

11. Green projects totalling 2 GW seek dispatch priority in Argentina, article by


Renewables Now, accessed online on May 5, 2018

12. Argentina to launch new RenovAr tender in Sep-Oct , article by Renewables Now,
accessed online on May 5, 2018

13. RÉGIMEN DE FOMENTO A LA GENERACIÓN DISTRIBUIDA DE ENERGÍA

www .AIRECWEEK. com


www.airecweek.com
REFERENCES & PHOTO CREDITS

14. RENOVABLE INTEGRADA A LA RED ELÉCTRICA PÚBLICA, Ley 27424, accessed


online on May 10, 2018

15. Argentina Renewable Energy Distributed Generation Law, Climatescope 2017,


accessed online on May 10, 2018,

16. Kits solares para que todos los argentinos accedan a la energía, accessed online
on May 10, 2018

17. Power Purchase Agreements en Argentina, WBCSD, CEADS, accessed online on


May 10, 2018

18. El panorama de las energias renovables en la Argentina, Telam SE, Agencia


Nacional de Noticias Bolivar, accessed online on April 24,2018

19. Argentina to launch new RenovAr tender in Sep-Oct – report, article by


Renewables Now (March 21, 2018), accessed online on April 24, 2018

20. Argentina signs first RenovAr Round 2 contracts for 112.2 MW, article by
Renewables Now (March 29, 2018), accessed online on April 24, 2018

21. World Bank to lend USD 250m to RenovAr projects in Argentina, article by
Renewables Now (March 20, 2018), accessed online on April 24, 2018

22. Argentina's Santa Fe to extend credit line to solar DG programme, article by


Renewables Now (March 23, 2018), accessed online on April 24, 2018

23. IFC subscribes to USD 100m green bond by Banco Galicia, article by Renewables
Now (March 27, 2018), accessed online on on April 24, 2018

24. IIC mulls loan for 195-MW wind project in Argentina, article by Renewables Now
(March 21, 2018) accessed online on April 24, 2018

25. Argentina eyes cutting energy deficit with renewable power capacity, article by
S&P Global Platts, February 22, 2018, accessed online on April 24, 2018

26. Argentina plans 1 GW solar + storage project, PV Magazine, March 2017

27. https://twitter.com/Renovables_Ar accessed online on on April 24, 2018

28. www.energia.gob.ar accessed online on on April 24, 2018

29. https://www.cnea.gov.ar/es/wp-content/uploads/2018/03/SINTESIS_
MEM_2018_2.pdf accessed online on on April 24, 2018

www .AIRECWEEK. com


www.airecweek.com
22 - 25 OCTOBER 2018 - BUENOS AIRES

ARGENTINA'S LARGEST CLEAN


ENERGY CONGRESS & EXHIBITION

If you enjoyed the content in this report, all of these


areas will be covered at the 2018 edition of
AIREC WEEK, Argentina's largest clean
energy congress & exhibition.

The event will take place over 4 days from


22-25 October in Buenos Aires and will feature
180 speakers delivering expert insights across the
renewable energy market including solar, wind,
grids and storage, finance and the commercial and
industrial sector.

For more information visit www.airecweek.com or


contact jamie.dowswell@greenpowerglobal.com

@AIRECnews | #AIREC www.airecweek.com www .AIRECWEEK. com

Вам также может понравиться