AHMEDABAD CITY GAS DISTRIBUTION PROJECT (VATVA)

ID Task Task Name Duration Start Finish Resource Names


02 Dec '18 09 Dec '18 16 Dec '18 23 Dec '18 30 Dec '18 06 Jan '19 13 Jan '19 20 Jan '19 27 Jan '19 03 Feb '19 10 Feb '19 17 Feb '19 24 Feb '19 03 Mar '19 10 Mar '19 17 Mar '19 24 Mar '19 31 Mar '19
Mode TWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMT
1 Project Execution Schedule for Adani Vatva 55 days Wed 02/01/19 Tue 19/03/19

2 Receipt of Purchase Order 1 day Wed 02/01/19 Wed 02/01/19 Project Manager Project Manager

3 Mobilization of Crew, Resources and Site Set Up 1 day Wed 05/12/18 Wed 05/12/18 HR ADMIN HR ADMIN

4 Mainline Construction Works 51 days Fri 04/01/19 Fri 15/03/19

5 Shifting of Pipe from Adani Yard to Sopan Yard 1 day Fri 04/01/19 Fri 04/01/19 Hydra,Trailor,Supervisor & Rigger Hydra,Trailor,Supervisor & Rigger

6 Clearing & Grading 7 days Mon 07/01/19 Tue 15/01/19 Civil Labour & Rigger Civil Labour & Rigger

7 Stringing of Line Pipe in PL Route 7 days Mon 14/01/19 Tue 22/01/19 Hydra & Supervisor Hydra & Supervisor

8 Trenching 35 days Mon 14/01/19 Fri 01/03/19 Hydra & Civil Labour Hydra & Civil Labour

9 Mainline Welding 30 days Mon 14/01/19 Fri 22/02/19 Fitter,Helper,QA/QC,RCM,Rigger,Welder,Welding Electrodes Fitter,Helper,QA/QC,RCM,Rigger,Welder,Welding Electrodes

10 Welding of Tie-In Joints 24 days Tue 22/01/19 Fri 22/02/19 Fitter,QA/QC,RCM,Welder,Welding Electrodes,Helper,Rigger Fitter,QA/QC,RCM,Welder,Welding Electrodes,Helper,Rigger

11 NDT of Mainline Welding & Tie-In Welding 30 days Tue 15/01/19 Mon 25/02/19 NDT Crew & Helper NDT Crew & Helper

12 NDT Retake & Repair 30 days Wed 16/01/19 Tue 26/02/19 NDT Crew & Helper NDT Crew & Helper

13 Field Joint Coating 29 days Thu 17/01/19 Tue 26/02/19 Insulator & Blaster Insulator & Blaster

14 Warning Mat Laying & PL Lowring 30 days Mon 21/01/19 Fri 01/03/19 Hydra,Rigger,QA/QC Hydra,Rigger,QA/QC

15 Pre-Hydrotesting of Crossing Section 2 days Fri 15/02/19 Mon 18/02/19 Rigger,Helper,QA/QC & RCM Rigger,Helper,QA/QC & RCM

16 Crossing: Cased & Uncased 3 days Wed 20/02/19 Fri 22/02/19 HDD Machine,HDD Crew,QA/QC,RCM,Rigger & Helper HDD Machine,HDD Crew,QA/QC,RCM,Rigger & Helper

17 Back Filling of Trench 29 days Wed 23/01/19 Mon 04/03/19 Hydra & Civil Labour Hydra & Civil Labour

18 Hydrotesting of Whole Pipeline Section 4 days Tue 05/03/19 Fri 08/03/19 Hydrotesting Crew,QA/QC & RCM Hydrotesting Crew,QA/QC & RCM

19 Cleaning, Swabbing & Draying 5 days Mon 11/03/19 Fri 15/03/19 Rigger,Helper,Fitter,QA/QC & RCM Rigger,Helper,Fitter,QA/QC & RCM

20 Installation of Route Markers 5 days Thu 28/02/19 Wed 06/03/19 Civil Labour & Rigger Civil Labour & Rigger

21 Pre-Commissioning & Commissioning 1 day Tue 19/03/19 Tue 19/03/19 SOPAN,ICS & ADANI SOPAN,ICS & ADANI

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Manual Progress
CLIENT-ADANI GAS LIMITED
TPIA- INTERNATIONAL CERTIFICATION SERVICES PVT.LTD. Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress

SOPAN O&M CO.PVT.LTD. CLIENT- ADANI GAS LIMITED


TPIA- INTERNATIONAL CERTIFICATION SERVICES PVT.LTD.