Академический Документы
Профессиональный Документы
Культура Документы
2 Receipt of Purchase Order 1 day Wed 02/01/19 Wed 02/01/19 Project Manager Project Manager
3 Mobilization of Crew, Resources and Site Set Up 1 day Wed 05/12/18 Wed 05/12/18 HR ADMIN HR ADMIN
5 Shifting of Pipe from Adani Yard to Sopan Yard 1 day Fri 04/01/19 Fri 04/01/19 Hydra,Trailor,Supervisor & Rigger Hydra,Trailor,Supervisor & Rigger
6 Clearing & Grading 7 days Mon 07/01/19 Tue 15/01/19 Civil Labour & Rigger Civil Labour & Rigger
7 Stringing of Line Pipe in PL Route 7 days Mon 14/01/19 Tue 22/01/19 Hydra & Supervisor Hydra & Supervisor
8 Trenching 35 days Mon 14/01/19 Fri 01/03/19 Hydra & Civil Labour Hydra & Civil Labour
9 Mainline Welding 30 days Mon 14/01/19 Fri 22/02/19 Fitter,Helper,QA/QC,RCM,Rigger,Welder,Welding Electrodes Fitter,Helper,QA/QC,RCM,Rigger,Welder,Welding Electrodes
10 Welding of Tie-In Joints 24 days Tue 22/01/19 Fri 22/02/19 Fitter,QA/QC,RCM,Welder,Welding Electrodes,Helper,Rigger Fitter,QA/QC,RCM,Welder,Welding Electrodes,Helper,Rigger
11 NDT of Mainline Welding & Tie-In Welding 30 days Tue 15/01/19 Mon 25/02/19 NDT Crew & Helper NDT Crew & Helper
12 NDT Retake & Repair 30 days Wed 16/01/19 Tue 26/02/19 NDT Crew & Helper NDT Crew & Helper
13 Field Joint Coating 29 days Thu 17/01/19 Tue 26/02/19 Insulator & Blaster Insulator & Blaster
14 Warning Mat Laying & PL Lowring 30 days Mon 21/01/19 Fri 01/03/19 Hydra,Rigger,QA/QC Hydra,Rigger,QA/QC
15 Pre-Hydrotesting of Crossing Section 2 days Fri 15/02/19 Mon 18/02/19 Rigger,Helper,QA/QC & RCM Rigger,Helper,QA/QC & RCM
16 Crossing: Cased & Uncased 3 days Wed 20/02/19 Fri 22/02/19 HDD Machine,HDD Crew,QA/QC,RCM,Rigger & Helper HDD Machine,HDD Crew,QA/QC,RCM,Rigger & Helper
17 Back Filling of Trench 29 days Wed 23/01/19 Mon 04/03/19 Hydra & Civil Labour Hydra & Civil Labour
18 Hydrotesting of Whole Pipeline Section 4 days Tue 05/03/19 Fri 08/03/19 Hydrotesting Crew,QA/QC & RCM Hydrotesting Crew,QA/QC & RCM
19 Cleaning, Swabbing & Draying 5 days Mon 11/03/19 Fri 15/03/19 Rigger,Helper,Fitter,QA/QC & RCM Rigger,Helper,Fitter,QA/QC & RCM
20 Installation of Route Markers 5 days Thu 28/02/19 Wed 06/03/19 Civil Labour & Rigger Civil Labour & Rigger
21 Pre-Commissioning & Commissioning 1 day Tue 19/03/19 Tue 19/03/19 SOPAN,ICS & ADANI SOPAN,ICS & ADANI
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Manual Progress
CLIENT-ADANI GAS LIMITED
TPIA- INTERNATIONAL CERTIFICATION SERVICES PVT.LTD. Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress