RATE ANALYSIS

1) Supply and fixing of 75mm dia PVC pipes 6kg/pressure including all specials such as bends, tees
reducers etc.,
CODE DESCRIPTION UNIT QTY RATE AMOUNT
Details of cost for 10 metre.
MATERIAL:
8644 PVC pipe 75 mm inner dia Mtr 10.00 121.00 1210.00
2321 Add 30% for fittings and wastage etc. 363.00
9999 Cement, sand and grit etc. L.S 5.33 2.48 13.22
LABOUR
0116 Fitter day 0.33 750.00 247.50
0117 Assistant Fitter or 2nd class Fitter day 1.31 650.00 851.50
0114 Beldar day 1.31 500.00 655.00
TOTAL 3340.22
Add Water Charges @ 1% 33.40
TOTAL 3373.62
Add CPOH @ 15% 506.04
Cost of 10 meter 3879.66
Cost of each 387.97
Say 388.00

2) Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot &
cold water supply, including all CPVC plain & brass threaded fittings, including fixing the pipe with
clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement
and
40 mm nominal outer dia Pipes
CODE DESCRIPTION UNIT QTY RATE AMOUNT
Details of cost for 10 metre.
MATERIAL:
Chlorinated Polyvinyl - chloride (CPVC)
8640 Mtr 10.00 265.00 2650.00
pipe 40 mm outer dia.
Add 30% for fittings and wastage etc. on (X)
795.00
30 * X / 100
9999 Cement, sand and grit etc. L.S 5.33 2.48 13.22
LABOUR
0116 Fitter day 0.33 750.00 247.50
0117 Assistant Fitter or 2nd class Fitter day 1.31 650.00 851.50
0114 Beldar day 1.31 500.00 655.00
TOTAL 5212.22
Add Water Charges @ 1% 52.12
TOTAL 5264.34
Add CPOH @ 15% 789.65
Cost of 10 meter 6053.99
Cost of each 605.40
Say 605.00
3) Providing and fixing hand rail of approved size by welding etc. to steel ladder
railing, balcony railing, staircase railing and similar works, including applying
priming coat of approved steel primer.
Code Description Unit Quantity Rate Amount
Detail of cost for 19.49 kg
MATERIAL:
M.S. tube 40mm nominal bore (medium) =
19.49kg
Add wastage @ 5% =0.097
Total = 20.46 kg
kilogram 20.46 63.00 1288.98
4009 Mild steel tubes hot finished welded type
2205 Carriage of steel tonne 0.0205 92.24 1.89
Priming coat
ready mixed red oxide zinc chromate
13.50.3 sqm 0.82 50.70 41.57
primer

1215 Welding by electric plant 18x4x1.00 = 72cm L.S 72.00 2.48 178.85

LABOUR:
Labour for cutting assembling & erection
0102 Blacksmith 1 st class day 0.24 750.00 180.00
0114 Beldar day 0.90 600.00 540.00
0100 Bandhani day 0.12 650.00 78.00
9999 Sundries L.S 12.48 2.48 30.95
TOTAL 2340.24
Add Water Charges @ 1% except on A i.e
22.99
on (2278.86 - 41.57 =) 2237.29
TOTAL 2363.23
Add CPOH @ 15% except on A i.e on
348.25
(2301.24-41.57 =) 2259.67
Cost of 19.49 kg 2711.48
Cost of 1 kg 139.12
round off 0.88
Say 140.00