Name of Work : Type the name of work:Reconstruction of Bridge at Km 0/8 of

Uranipuram - Kariyaviduthy Road

Estimate Amount : Rs.175 Lakhs Job Code : NABARD RIDF XXIII

Basic Data Adopted in this Estimate for the above Work


Schedule of Rates adopted in this estimate for the year : 2017-18 (Revised)
Bitumen / Emulsion
DATA of Bitumen DATA of Emulsion
VG10 : Rs.27350.00/MT Emulsion SS1 : Rs.42620.00/MT
VG30 : Rs.28150.00/MT Emulsion RS1 : Rs.26730.00/MT
VG40 : Rs.28860.00/MT Drum Deduction : Rs.1500.00/MT
Source : Manali Source : Irungur
C.G.S.T. in % : C.G.S.T. in % :
S.G.S.T. in % : S.G.S.T. in % :
Storage Charges : 5 %
Storage Charges : 5 % Deduct Drum Cost(-) : 1500/-
Conveyance Factor : 0.99924 Conveyance Factor : 1.690
Lead to Mid of Project Road: 365 Km Lead to Mid of Project Road: 365 Km

Terrian Classification (for conveyance) : Plains


Lead to CMP site Plains Hills
Metal Lead : 55 Km
Bitumen Lead : 345 Km CMP to Work Site (GSB) : 31 Km

Cost of Fuel Details


Diesel : 65.22 /Lit
Furnace oil : 29890.00 /MT
Kerosene : 54.69 /Lit

Details of other allowances.


Night work : No Area Type : Normal
Area Details : 9m Paver involved: No

Road Data - Rev-17.5 1 Revised during - OCT. 2017


Metal lead to Site Metal lead
Chainage Name/ location of quarry Plain Hll
Km 0/8 Mathiyathuparai 61

Gravel lead to site Gravel lead


Chainage Name/ location of quarry Plain Hll
Km 0/8 6/2 AA Road 38

Sand lead to site Sand lead


Chainage Name/ location of quarry Plain Hll
Km 0/8 Vittalapuram 66

Road Data - Rev-17.5 2 Revised during - OCT. 2017


Carted Earth lead to site Carted Earth Lead
Name/ location of quarry Plain Hills
Km 0/8 Earth 2

Road Data - Rev-17.5 3 Revised during - OCT. 2017


Highways Schedule of Rates for 2017-18 (Revised)
IRC HBG Metal Rates for 2017-18 (Revised)
Area : Normal, Location : , Locally Quarried Materials: Yes
Size Rate
90mm 384.76/Cum
75mm 429.52/Cum
63mm 556.19/Cum
53mm 676.19/Cum
46.50mm 907.62/Cum
45mm 907.62/Cum
37.50mm 926.67/Cum
26.50mm 875.24/Cum
25mm 875.24/Cum
22.40mm 1270.48/Cum
13.20mm 1178.10/Cum
11.20mm 800.00/Cum
6.70mm 593.33/Cum
6mm 593.33/Cum
5.60mm 593.33/Cum
4.75mm & Below 524.76/Cum

Labour Charges
Description Rate
Bitumen Sprayer Man 423.30/Day
Bitumen Raker Man 441.29/Day
Heat Master Operator 441.29/Day
Mini Hot Mix Plant Operator 441.29/Day
Gunnuting Plant Operator 369.32/Day
Gunnuting Gun Operator 401.52/Day
Road Mazdoor Gr.- I 364.58/Day
Road Mazdoor Gr.-II 326.70/Day
Head Mazdoor 375.95/Day

Road Data - Rev-17.5 4 Revised during - OCT. 2017


Hire charges for machinery
Hire Charges for Power Roller 788.57
Fuel For Roller per Hour 2.50
Hire Charges for Water Sprinkler per Day 1103.81
Fuel For Water Sprinkler per Hour (WBM) 3.50
Hire Charges for Mini Hot Mix Plant per Day 1594.29
Fuel for Mini Hot Mix Plant per Hour 15.00
Hire Charges for Bitumen Boiler per Day 192.38
Fuel for Bitumen Boiler per Day 25.00
Hire Charges for Vibrator Roller/ Hr 646.19
Water / KL 130.00
Fuel For Water Sprinkler per Hour (others) 3.25
Fuel For heating aggregate 45.00
Central Hot Mixing Plant-per day 9234.29
Vibratory Roller-per day 5169.52
Paver Finisher-per day 2330.48
Tipper Trucks-per day (10 Tonnes) 1041.90
Loader 5 cum capacity-per day 1147.62
Water tanker -per day 814.29
Motor grader-per day (110 HP) 12888.57
Pug mill-per day 6360.95
Generator-per day 4932.38
Tractor per hour 336.19
Tipper Trucks-per tonne /km 2.00
Fuel for water tanker per day 25.00
Rotovator per hour 17.00
Wet Mix Plant 75 tonne capacity/ day 8507.62
Bitumen emulsion sprayer / 10 sqm 15.00
Paver Finisher (9m)-per hour -including fuel 2546.67
Pneumatic tyred roller including fuel per hr 1183.81
Tractor - Rotovator (including fuel per day) 2689.52
Water tanker for Mix in place method (GSB) 1909.52

Road Data - Rev-17.5 5 Revised during - OCT. 2017


Rate of Materials (Other than Stones) PWD RATES 2017-18 (Revised)
Description Rate
Gravel 174.29/Cum
Well Gravel 142.86/Cum
Quarry Rubbish 85.14/Cum
Stone Dust 108.95/Cum
Crushed Stone Sand (M-Sand) 434.29/Cum
Sand for Mortar 168.00/Cum
Sand for Filling 168.00/Cum
Shell Lime (Slaked & Screened) 1223.81/Cum
Binding Wire (Black 18G) 39.11/Kg
Binding Wire (Galvanised - 18G) 39.11/Kg
Cost of Cement (including storage 5%) 5575.53/MT
Cost of Steel (including storage 5%) 38657.88/MT
Cost of Earth (as per GO (D) 107 Industries 100.00/Cum
(MMC.2) Department dated 06.07.2017)
Rates of Works
Description Rate
Clearing Heavy Jungle 4.21/Sqm
Clearing Light Jungle 3.17/Sqm
Clearing Scrub Jungle 2.89/Sqm
Earth Work Excavation SS 20A 61.65/Cum
Earth Work Excavation SS 20B 57.86/Cum
Earth Work Excavation SS 20B for Foundation 115.72/Cum
Refilling with excavated Sand 17.80/Cum
Refilling with excavated soil (other than Sand ) 20.27/Cum
Vibrator Charges for PCC rate per Cum. 36.17/Cum
Vibrator Charges for RCC rate per Cum. 48.67/Cum
Mixing Mortar Cement by Manual 59.94/Cum
Mixing Mortar Cement by Machine 79.55/Cum
Conveyance Charges for Plains and Hills
Rough Stone, Jelly,Sand,Gravel (Rs. Per Km )
Km Plain Hills
0 - 10 Km 9.16 18.32
10-20 Km 7.84 15.68
20-40 Km 6.75 13.50
40-80 Km 6.33 12.66
80 & Above 5.31 10.62

Road Data - Rev-17.5 6 Revised during - OCT. 2017


Cement Rate With Storage 2017-18 (Revised)

Cost of Cement as per PWD Schedule of Rates Rs.5318.00

Deduct loading and unloading charges (-) Rs.167.42


Rs.5150.58
Basic Cement Rate = 5150.58

Add Storage Charges at 5% of Basic Cost = 5150.58 X 5.00


= 257.53
100.00

Cost of Cement including Storage at 5% of Basic Rate= 5318 + 257.53

=Rs.5575.53/MT

Steel Rate with Storage Charges 2017-18 (Revised)

Cost of Steel as per PWD Schedule of Rates Rs.36825.00

Deduct loading and unloading charges (-) Rs.167.42


Rs.36657.58
Basic Steel Rate = 36657.58

Add Storage Charges at 5 % of Basic Cost = 36657.58 X 5.00 = 1832.88


100.00

Cost of Steel including Storage Charges at 5% of Basic


= Rate
36825 + 1832.88

=Rs.38657.88/MT

Road Data - Rev-17.5 7 Revised during - OCT. 2017


Name of Work : Type the name of work:Reconstruction of Bridge at Km 0/8 of Uranipuram - Kariyaviduthy Road

Job Code : NABARD RIDF XXIII Estimate Amount : 175.00 Lakhs


DATA ABSTRACT

Sl
Description Unit Rate
No.
GENERAL RATES (As Per Schedule of Rates)

1 Clearing Heavy Jungle /Sqm. 4.21

2 Clearing Light Jungle /Sqm. 3.17

3 Clearing Scrub Jungle /Sqm. 2.89

4 Earth Work Excavation SS 20A /Cum. 61.65

5 Earth Work Excavation SS 20B /Cum. 57.86

6 Earth Work Excavation SS 20B For Foundation /Cum. 115.72

7 Refilling With Excavated Sand /Cum. 17.80

8 Refilling With Excavated Soil (Other Than Sand ) /Cum. 20.27

9 Picking the Existing BT Surface /Sqm. 9.84

10 GSB Grade - V Plant Mix /Cum. 1764.71

11 GSB Grade - III Plant Mix /Cum. 1846.40

12 Wet Mix Macadam /Cum. 1955.31

Road Data - Rev-17.5 8 Revised during - OCT. 2017


Sl
Description Unit Rate
No.
13 Crusher Run Macadam 300mm Thick /Cum. 1870.29

14 Prime Coat Over WBM / WMM Surface /Sqm. 52.57

15 Prime Coat Over CRM Surface /Sqm. 61.34

16 Tack Coat Over Primed Non-Bituminous GB /Sqm. 10.26

17 Tack Coat Over Existing BT Surface /Sqm. 13.85

18 Tack Coat Over Dry Lean Cement Surface /Sqm. 11.62

19 Dense Bituminous Macadam 50mm Thick Using CMP /Cum. 6990.38

20 Dense Bituminous Macadam 75mm Thick Using CMP /Cum. 6558.76

21 Bituminous Macadam 50mm Thick Using CMP /Cum. 5990.36

22 Bituminous Macadam 80mm Thick Using CMP /Cum. 6095.03

23 Close Graded Premix Carpet 20mm Thick (CMP) /Sqm. 137.36

24 C.G.P.C. 20mm Thick (CMP) Using Plastic Waste /Sqm. 136.19

25 Bituminous Concrete 30/ 40mm Thick Using CMP /Cum. 7460.80

26 B.C. 30/ 40mm Thick (CMP) Using Plastic Waste /Cum. 7383.45

27 Bituminous Concrete 50mm Thick Using CMP /Cum. 7203.60

Road Data - Rev-17.5 9 Revised during - OCT. 2017


Sl
Description Unit Rate
No.

KM Km 0/8

28 Patch Work Using 45mm IRC Metal /Cum. 2881.90


29 Patch Work Using 13.20mm IRC Metal /Cum. 3152.38
30 Premix Carpet With Seal Coat using Mini Hot Mix Plant /Sqm. 183.77
31 BM 50mm (For Patch Work) using Mini Hot Mix Plant /Cum. 5626.02
32 Dry Lean Cement Concrete for Sub-Base /Cum. 3357.44

KM

28 Patch Work Using 45mm IRC Metal /Cum.


29 Patch Work Using 13.20mm IRC Metal /Cum.
30 Premix Carpet With Seal Coat using Mini Hot Mix Plant /Sqm.
31 BM 50mm (For Patch Work) using Mini Hot Mix Plant /Cum.
32 Dry Lean Cement Concrete for Sub-Base /Cum.

Road Data - Rev-17.5 10 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR GRANULAR SUB BASE

Granular Sub Base Grade - V

Cost of 53mm to 9.50mm Broken Stone

Cost of 53mmMetal @Rs 676.19 /Cum.


Cost of 46.50mmMetal @Rs 907.62 /Cum.
Cost of 45mmMetal @Rs 907.62 /Cum.
Cost of 37.50mmMetal @Rs 926.67 /Cum.
Cost of 26.50mmMetal @Rs 875.24 /Cum.
Cost of 25mmMetal @Rs 875.24 /Cum.
Cost of 22.40mmMetal @Rs 1270.48 /Cum.
Cost of 13.20mmMetal @Rs 1178.10 /Cum.
Cost of 11.20mmMetal @Rs 800.00 /Cum.

Average Rate @Rs 935.24 /Cum.

Cost of 9.50mm to 2.36mm Broken Stone

Cost of 6.70mm Metal @Rs 593.33 /Cum.


Cost of 6mm Metal @Rs 593.33 /Cum.
Cost of 5.60mm Metal @Rs 593.33 /Cum.
Cost of 4.75mm Metal @Rs 524.76 /Cum.
Cost of 2.36mm Metal @Rs 524.76 /Cum.

Average Rate @Rs 565.90 /Cum.

Cost of 2.36mm & Below of Sand

Cost of 4.75mm & BelowMetal @Rs 524.76 /Cum.

Average Rate @Rs 524.76 /Cum.

Road Data - Rev-17.5 11 Revised during - OCT. 2017


METAL RATE FOR GRANULAR SUB BASE (TABLE NO.400.1)

Granular Sub Base Grade - III

Cost of 46.50 - 26.50 mm Broken Stone


Cost of 46.50mmMetal @Rs 907.62 /Cum.
Cost of 45mmMetal @Rs 907.62 /Cum.
Cost of 37.50mmMetal @Rs 926.67 /Cum.
Cost of 26.50mmMetal @Rs 875.24 /Cum.
Average Rate of 46.50 - 26.50 mm @Rs 904.29 /Cum.

Cost of 26.50 - 4.75mm Broken Stone


Cost of 25mmMetal @Rs 875.24 /Cum.
Cost of 22.40mmMetal @Rs 1270.48 /Cum.
Cost of 13.20mmMetal @Rs 1178.10 /Cum.
Cost of 11.20mmMetal @Rs 800.00 /Cum.
Cost of 6.70mmMetal @Rs 593.33 /Cum.
Cost of 6mmMetal @Rs 593.33 /Cum.
Cost of 5.60mmMetal @Rs 593.33 /Cum.
Average Rate of 26.50 - 4.75 mm @Rs 843.40 /Cum.

Cost of 4.75mm & Below of Sand

Cost of 4.75mm & BelowMetal @Rs 524.76 /Cum.


Average Rate of 2.36 & Below @Rs 524.76 /Cum.

Road Data - Rev-17.5 12 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR
WET MIX MACADAM

Cost of 45mm to 22.40mm Broken Stone

Cost of 45mmMetal @Rs 907.62 /Cum.


Cost of 37.50mmMetal @Rs 926.67 /Cum.
Cost of 26.50mmMetal @Rs 875.24 /Cum.
Cost of 25mmMetal @Rs 875.24 /Cum.
Cost of 22.40mmMetal @Rs 1270.48 /Cum.

Average Rate @Rs 971.05 /Cum.

Cost of 22.40mm to 2.36mm Broken Stone

Cost of 22.40mm Metal @Rs 1270.48 /Cum.


Cost of 13.20mm Metal @Rs 1178.10 /Cum.
Cost of 11.20mm Metal @Rs 800.00 /Cum.
Cost of 6.70mm Metal @Rs 593.33 /Cum.
Cost of 6mm Metal @Rs 593.33 /Cum.
Cost of 5.60mm Metal @Rs 593.33 /Cum.
Cost of 4.75mm Metal @Rs 524.76 /Cum.

Average Rate @Rs 793.33 /Cum.

Road Data - Rev-17.5 13 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR
CRUSHER RUN MACADAM

Cost of 53mm to 45 mm Broken Stone


Cost of 53mmMetal @Rs 676.19 /Cum.
Cost of 46.50mmMetal @Rs 907.62 /Cum.
Cost of 45mmMetal @Rs 907.62 /Cum.
Average Rate of 53-45 mm @Rs 830.48 /Cum.

Cost of 45mm - 22.40mm Broken Stone


Cost of 45mmMetal @Rs 907.62 /Cum.
Cost of 37.50mm Metal @Rs 926.67 /Cum.
Cost of 26.50mm Metal @Rs 875.24 /Cum.
Cost of 25.00mm Metal @Rs 875.24 /Cum.
Cost of 22.40mm Metal @Rs 1270.48 /Cum.
Average Rate of 45mm - 22.40mm @Rs 971.05 /Cum.

Cost of 22.40 mm to 5.60mm Broken Stone


Cost of 13.20mm Metal @Rs 1178.10 /Cum.
Cost of 11.20mm Metal @Rs 800.00 /Cum.
Cost of 6.70mm Metal @Rs 593.33 /Cum.
Cost of 6 mm Metal @Rs 593.33 /Cum.
Cost of 5.6 mm Metal @Rs 593.33 /Cum.
Average Rate of 22.40mm - 5.60mm 751.62

Cost of 4.75mm & below @Rs 524.76 /Cum.

Road Data - Rev-17.5 14 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR BM 50mm thick

For 26.50 mm to 13.20 mm IRC


0.180 Cum Cost of 25 & 22.40mm IRC at Rs. 1072.86 /cum. = 193.11
0.820 Cum Cost of 13.20mm IRC at Rs. 1178.10 /cum. = 966.04
Rate of metal 26.50-13.20mm for BM 50mm Rs. 1159.15

For 13.20 mm to 2.36 mm IRC


0.570 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC
at Rs. 620.95 /cum. = 353.94
0.430 Cum Cost of 2.36mm IRC at Rs. 524.76 /cum. = 225.65
Rate of metal 13.20 - 2.36 mm for BM 50mm Rs. 579.59

For 2.36 mm & below


1.000 Cum Cost of 2.36mm IRC at Rs. 524.76 /cum. = 524.76

WORKING OUT METAL RATE FOR DBM 50mm thick

For 26.50mm to 13.20mm IRC


0.160 Cum Cost of 26.50 mm IRC at Rs. 875.24 /cum. = 140.04
0.370 Cum Cost of 25 & 22.40mm IRC at Rs. 1072.86 /cum. = 396.96
0.470 Cum Cost of 13.20mm IRC at Rs. 1178.10 /cum. = 553.71
Rate of metal 26.50-13.20mm for DBM 50mm Rs. 1090.71

For 13.20 mm to 2.36 mm IRC


0.550 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC
at Rs. 620.95 /cum. = 341.52
0.450 Cum Cost of 2.36mm IRC at Rs. 524.76 /cum. = 236.14
Rate of metal 13.20-2.36mm for DBM 50mm Rs. 577.66

For 2.36mm & below


1.000 Cum Cost of 2.36mm IRC at Rs. 524.76 /cum. = 524.76

Road Data - Rev-17.5 15 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR BM 80mm thick

For 37.5 mm to 13.20 mm IRC


0.100 Cum Cost of 37.50 mm IRC at Rs. 926.67 /cum. = 92.67
0.380 Cum Cost of 26.50mm IRC at Rs. 875.24 /cum. = 332.59
0.520 Cum Cost of 25, 22.40 & 13.20 mm IRC at Rs. 1107.94 /cum. = 576.13
Rate of Metal For 37.5 mm to 13.20 mm IRC BM (80mm thick) Rs. 1001.39

For 13.20 mm to 2.36 mm IRC


0.830 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC
at Rs. 620.95 /cum. = 515.39
0.170 Cum Cost of 2.36mm IRC at Rs. 524.76 /cum. = 89.21
Rate of Metal For 13.20 mm to 2.36 mm IRC BM (80mm thick) Rs. 604.60

For 2.36mm & below

1.000 Cum Cost of 2.36mm IRC at Rs. 524.76 /cum. = 524.76


Rate of Metal For 2.36mm & belowBM (80mm thick) Rs. 524.76

WORKING OUT METAL RATE FOR DBM 75mm thick

For 37.50 mm to 13.20 mm IRC


0.140 Cum Cost of 37.50 mm IRC at Rs. 926.67 /cum. = 129.73
0.490 Cum Cost of 26.50mm IRC at Rs. 875.24 /cum. = 428.87
0.370 Cum Cost of 25, 22.40 & 13.20 mm IRC at Rs. 1107.94 /cum. = 409.94
Rate of Metal For 37.50 mm to 13.20 mm IRC DBM (75mm thick) Rs. 968.54

For 13.20 mm to 2.36 mm IRC

0.370 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC


at Rs. 620.95 /cum. = 229.75
0.630 Cum Cost of 2.36mm IRC at Rs. 524.76 /cum. = 330.60
Rate of Metal For 13.20 mm to 2.36 mm IRC DBM (75mm thick) Rs. 560.35

For 2.36mm & below

1.00 Cum Cost of 2.36mm IRC at Rs. 524.76 /cum. = 524.76

Road Data - Rev-17.5 16 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR BC 30/40mm thick

For 19.00 mm to 9.50 mm IRC


0.240 Cum Cost of 13.20mm IRC at Rs. 1178.10 /cum. = 282.74
0.760 Cum Cost of 11.20mm IRC at Rs. 800.00 /cum. = 608.00
Rate of Metal For 19.00 mm to 9.50 mm IRC BC (40mm thick) Rs. 890.74

For 9.50 mm to 2.36 mm IRC


0.660 Cum Cost of 6.70, 6, 5.6 & 4.75 mm IRC at Rs. 576.19 /cum. = 380.29
0.340 Cum Cost of 2.36mm IRC at Rs. 524.76 /cum. = 178.42
Rate of Metal For 9.50 mm to 2.36 mm IRC BC (40mm thick) Rs. 558.71

For 2.36mm & below


1.000 Cum Cost of 2.36mm IRC at Rs. 524.76 /cum. = 524.76

Road Data - Rev-17.5 17 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR
CLOSED GRADED PREMIX CARPET
Cost of 13.20 mm to 11.20mm Broken Stone
Cost of 11.20 mm Metal @Rs 800.00 /Cum.

Average Rate of 13.20 - 11.20mm @Rs 800.00 /Cum.

Cost of 11.20 mm to 5.60 mm Broken Stone


Cost of 6.7 mm Metal @Rs 593.33 /Cum.
Cost of 6 mm Metal @Rs 593.33 /Cum.
Cost of 5.6 mm Metal @Rs 593.33 /Cum.

Average Rate of 11.20-5.6mm @Rs 593.33 /Cum.

Cost of 5.6 mm to 2.80mm Broken Stone

Cost of 4.75mm & below metal @Rs 524.76 /Cum.

Average Rate of 5.60-2.80mm @Rs 524.76 /Cum.

Road Data - Rev-17.5 18 Revised during - OCT. 2017


BITUMEN RATE TO SITE
VG 10 VG 30
VG 10 VG 30 CRMB 55
Basic Rate 27350.00 28150.00 18590.00
C.G.S.T. % 0.00 0.00 #VALUE!
S.G.S.T. % 0.00 0.00 #VALUE!
2974.40
Basic Rate 27350.00 28150.00 #VALUE!
Storage Charges 5% of basic price 1367.50 1407.50 929.50
28717.50 29557.50 929.50

Conveyance at Rs.0.99924 per km for 365 km 729.45 729.45 729.45


140 29446.95 30286.95 1658.95

round 2

EMULSION BITUMEN RATE TO SITE


Slow Setting - Rapid Setting-I
I For Tack for Tack Coat
Coat Application
Application (R/C Drums)
Basic Rate ( R/C42620.00
Drums) 26730.00
C.G.S.T. % 0.00 0.00
S.G.S.T. % 0.00 0.00
Basic Rate 42620.00 26730.00
Storage Charges 5% of basic price 2131.00 1336.50 0.00
Deduct Drum cost -1500.00 -1500.00
Conveyance at Rs.1.69 per km for 365 km 616.85 616.85
43867.85 27183.35

Road Data - Rev-17.5 19 Revised during - OCT. 2017


BITUMEN RATE TO CMP
VG 40 VG 30 VG 10
VG 40 VG 30 VG 10
Basic Rate 28860.00 28150.00 27350.00
C.G.S.T. % 0.00 0.00 0.00
S.G.S.T. % 0.00 0.00 0.00

Basic Rate 28860.00 28150.00 27350.00


Storage Charges 5% of basic price 1443.00 1407.50 1367.50
30303.00 29557.50 28717.50

Conveyance at Rs.0.99924per km for 345 km 689.48 689.48 689.48


30992.48 30246.98 29406.98

Selected Grade of Bitumen for BC VG30 30246.98

Road Data - Rev-17.5 20 Revised during - OCT. 2017


Name of Work Type the name of work:Reconstruction of Bridge at Km 0/8 of Uranipuram - Kariyaviduthy Road

ROAD METAL RATE - SITE


Plains
Lead in Km Kind of Cost of Cost of Stacking
Reach in Km Quarry Total
Plains Hills Materials material Conveyance Charges
Km 0/8 6/2 AA Road 38 Gravel 174.29 291.50 2.89 468.68
Km 0/8 Earth 2 Earth for embankment 177.86 18.32 196.18

Road Data - Rev-17.5 21 Revised during - OCT. 2017


ROAD METAL RATE FOR CMP
CMP Site: Km 7/4 of Vallam - Orathanadu Road
Metal Source: Mathiyathuparai
Lead in Km Cost of Cost of Stacking
Kind of Materials Total
Plains Hills material Conveyance Charges

55 53 - 9.5mm(GSB-V) 935.24 399.95 -- 1335.19


55 9.50-2.36mm(GSB-V) 565.90 399.95 -- 965.85
55 2.36mm & Below(GSB-V) 524.76 399.95 -- 924.71
55 46.5 - 26.5 mm(GSB-III) 904.29 399.95 -- 1304.24
55 26.50 - 4.75 mm(GSB-III) 843.40 399.95 -- 1243.35
55 4.75 mm&below (GSB-III) 524.76 399.95 -- 924.71
55 45 - 22.40mm(WMM) 971.05 399.95 -- 1371.00
55 22.40-2.36mm(WMM) 793.33 399.95 -- 1193.28
55 2.36 & below(WMM) 524.76 399.95 -- 924.71
55 53 - 45 mm(CRM) 830.48 399.95 -- 1230.43
55 45 - 22.40mm(CRM) 971.05 399.95 -- 1371.00
55 22.40 - 5.6 mm(CRM) 751.62 399.95 -- 1151.57
55 26.50-13.20mm(BM) 1159.15 399.95 -- 1559.10
55 13.20-2.36mm(BM) 579.59 399.95 -- 979.54
55 2.36 & below(BM) 524.76 399.95 -- 924.71
55 37.5 - 13.20mm(BM) 1001.39 399.95 -- 1401.34
55 13.20 - 2.36 mm(BM) 604.60 399.95 -- 1004.55
55 2.36 mm & below(BM) 524.76 399.95 -- 924.71
55 26.50-13.20mm(DBM) 1090.71 399.95 -- 1490.66
55 13.20-2.36mm(DBM) 577.66 399.95 -- 977.61
55 2.36 & below(DBM) 524.76 399.95 -- 924.71
55 Stone Dust(DBM) 108.95 399.95 -- 508.90
55 37.50-13.20mm(DBM) 968.54 399.95 -- 1368.49
55 13.20-2.36mm(DBM) 560.35 399.95 -- 960.30
55 2.36 & below(DBM) 524.76 399.95 -- 924.71
55 13.20mm-11.20mm(CGPS) 800.00 399.95 -- 1199.95
55 11.20mm-5.60mm (CGPS) 593.33 399.95 -- 993.28
55 5.60mm-2.8mm (CGPS) 524.76 399.95 -- 924.71
55 2.80mm and below (CGPS) 524.76 399.95 -- 924.71
55 2.36 & below (BC) 524.76 399.95 -- 924.71
55 19.00-9.50mm(BC) 890.74 399.95 -- 1290.69
55 9.50-2.36mm(BC) 558.71 399.95 -- 958.66

Road Data - Rev-17.5 22 Revised during - OCT. 2017


CONSTRUCTION OF EARTHEN EMBANKMENT (Only for new formation of subgrade)
Formation of embankment with earth from quarrying place and compaction by power roller
(100% compaction) including cost and conveyance of the earth to worksite, including all labour
charges for laying, spreading etc, including all hire and fuel charges all tools and plants

Hire charges for Machineries

Power Roller8-10 tonne


Hire charges excluding fuel charges per day =Rs. 788.57
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 65.22 /lit =Rs. 1304.40
Total Hire charges per day including Fuel =Rs. 2092.97
Daily Out turn 425 Cum.

Hire charges of Power Roller per 10 sqm. 2092.97 =Rs. 4.92 /Cum
425
Water Sprinklers
Hire charges excluding fuel charges per day =Rs. 1103.81
Fuel charges per day (Diesel) 3.25 lit/Hr x 8.00 Hrs. x 65.22 /lit =Rs. 1695.72
Total Hire charges per day including Fuel =Rs. 2799.53
Daily Out turn 1000 Cum.

Hire charges of Water Sprinklers per 10 sqm. 2799.53 =Rs. 2.8 /Cum
1000

Total Hire charges for Machineries per10sqm = 4.92 + 2.80 =Rs. 7.72 /Cum
Labour charges for Laying Earth for 100cum

2.00 Nos. of Mazdoor Ist Class @Rs. 364.58 /E =Rs. 729.16


Total Labour charges for laying earth per 100cum =Rs. 729.16

Total Labour charges for laying earth per Cum 729.16 =Rs. 7.29 /Cum
100
Total Hire and Labour charges = 7.72 + 7.29 =Rs. 15.01 /Cum

Cost of Earth (as per GO (D) 107 Industries (MMC.2) =Rs. 100.00 /Cum
Department dated 06.07.2017)
Excavation Charges as per PWD rates (SS 20 B) =Rs. 57.86 /Cum
Seigniorage fee per cum ( GO (Ms) No. 6, Industries =Rs. 20.00 /Cum
(MMB1) Department dated 11.1.2001)
Cost of earth per cum at quarrying place =Rs. 177.86 /Cum

Road Data - Rev-17.5 23 Revised during - OCT. 2017


Earth work for formation of embankment (100% compaction)
(For new formation of subgrade)
Km 0/8
1.16 Cum. Cost of Earth incl. conveyanceat Rs. 196.18 /Cum. = 227.57
1.00 Cum. Hire and Labour charges at Rs. 15.01 /cum. = 15.01
Rate for 1.00 cum. Rs. 242.58

1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /cum. =
Rate for 1.00 cum. Rs.

Road Data - Rev-17.5 24 Revised during - OCT. 2017


Earth work for formation of embankment (100% compaction)

1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /cum. =
Rate for 1.00 cum. Rs.

Road Data - Rev-17.5 25 Revised during - OCT. 2017


Granular Sub-Base with Close Graded Material (Table:- 400-1)

Description Unit Quantity Rate (Rs) Cost (Rs)


A Plant Mix Method
Construction of granular sub-base by providing close graded Material, mixing in a
mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in
uniform layers with motor grader on prepared surface and compacting with vibratory
power roller to achieve the desired density, complete as per clause 401
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 375.95 150.38
Mazdoor skilled day 2.000 364.58 729.16
Mazdoor day 8.000 326.70 2613.60
3493.14
b) Machinery
Wet Mix Plant 75 tonne capacity/ hr hour 6.000 1063.45 6380.70
Electric generator 125 KVA hour 6.000 616.55 3699.30
Water tanker 6 KL capacity 5 km lead with hour 4.500 305.60 1375.20
one trip per hour
Front end loader 1 cum bucket capacity hour 6.000 795.65 4773.90
Tipper 10 tonne; conveyance: 31 km tonne.km 450 x L 2.00 27900.00
Add 10 per cent of cost of carriage to cover 2790.00
loading and unloading
Motor Grader 110 HP hour 6.000 1611.07 9666.42
Vibratory roller 8-10 t hour 6.000 809.24 4855.44
61440.96
c) Material as per table 400-1
For Grading-V Material (Drainage/ Top Layer)
Cost of 53mm to 9.50mm Broken Stone cum 144.000 1335.19 192267.36
Cost of 9.50mm to 2.36mm Broken Stone cum 100.000 965.85 96585.00
Cost of 2.36mm & Below of Sand cum 43.000 924.71 39762.53
Cost of water KL 27.000 130.00 3510.00
332124.89
For Grading-III Material (Bottom Layer if thickness more than 300mm)
46.5 mm to 26.50 mm cum 101.000 1304.24 131728.24
26.5 mm to 4.75 mm cum 130.000 1243.35 161635.50
4.75 mm below cum 58.000 924.71 53633.18
Cost of water KL 27.000 130.00 3510.00
350506.92
(i) Rate per cum for grading-V Material
Cost for 225 cum = a+b+c 397058.99
Rate per cum = (a+b+c)/225 Rs.1764.71/Cum.

(ii) Rate per cum for grading-III Material


Cost for 225 cum = a+b+c 415441.02
Rate per cum = (a+b+c)/225 Rs.1846.40/Cum.

Road Data - Rev-17.5 26 Revised during - OCT. 2017


WET MIX MACADAM
Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam
250 mm thick specification including premixing the materials with water at OMC in mechnanical
mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub
Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the
desired density including cost of material, labour charges, rentals for machinery, fuel and all
other incidental charges etc., complete as per clause 406 of MORTH Rev-5
Hire Charges for Machineries
Loader 5 Cum. Capacity
Hire charges excluding fuel charges per day =Rs. 1147.62
Fuel charges per day 80 lit.of diesel 65.22 /lit =Rs. 5217.60

Total Hire charges per day including Fuel =Rs. 6365.22


Total Hire charges per Hour including Fuel =Rs. 795.65

Tipper
Hire charges excluding fuel charges per day =Rs. 1041.90
Fuel charges per day 3.25lit.of diesel x 8hrs 65.22 /lit =Rs. 1695.72
Total Hire charges per day including Fuel =Rs. 2737.62
Total Hire charges per Hour including Fuel =Rs. 342.20

Water Tankers
Hire charges excluding fuel charges per day =Rs. 814.29
Fuel charges per day 25lit.of diesel 65.22 /lit =Rs. 1630.50
Total Hire charges per day including Fuel =Rs. 2444.79
Total Hire charges per Hour including Fuel =Rs. 305.60
Vibratory Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 5169.52
Fuel charges per day 3.00lit.of diesel x 8hrs 65.22 /lit =Rs. 1565.28
Total Hire charges per day including Fuel =Rs. 6734.80
Total Hire charges per Hour including Fuel =Rs. 841.85

Motor Grader including fuel per Hour (Local Rate) =Rs. 1611.07
Base Mix Plant (pug mill) including fuel per hour (local rate) =Rs. 795.12

Total Hire Charges for machineries for 100 Cum of WMM


1. Loader for 6 Hours 795.65 /hr. =Rs. 4773.90
2. Base Mix Plant (Pug Mill) for 6 Hours 795.12 /hr. =Rs. 4770.72
3. Tipper for 24 Hours 342.20 /hr. =Rs. 8212.80
4. Water Tanker for 24 Hours 305.60 /hr. =Rs. 7334.40
5. Motor Grader for 4 Hours 1611.07 /hr. =Rs. 6444.28
6. Vibratory Roller for 6 Hours 841.85 /hr. =Rs. 5051.10
Total Hire Charges for machineries for 100 Cum of WMM =Rs. 36587.20

Total Hire Charges for machineries for 1.00 Cum of WMM =Rs. 365.87 /Cum.

Road Data - Rev-17.5 27 Revised during - OCT. 2017


Labour Charges for 100 cum of WMM
0.50 Nos. of Head Mazdoor @ Rs. 375.95 /E =Rs. 187.98
8.63 Nos. of Mazdoor Ist Class @ Rs. 364.58 /E =Rs. 3146.33
2.00 Nos. of Mazdoor IIst Class @ Rs. 326.70 /E =Rs. 653.40
Total Labour Charges of 100 cum of WMM =Rs. 3987.71

Total Labour Charges of 1.00 cum of WMM =Rs. 39.88 /Cum.


Total Hire and Labour charges = 365.87 + 39.88 =Rs. 405.75 /Cum.

WET MIX MACADAM 250 mm thick

0.396 Cum. Cost of 45-22.40mm IRC at Rs. 1371.00 /cum. = 542.92


0.528 Cum. Cost of 22.40-2.36mm IRC at Rs. 1193.28 /cum. = 630.05
0.396 Cum. Cost of 2.36mm IRC at Rs. 924.71 /cum. = 366.19
0.08 KL Cost of water at Rs. 130.00 / KL = 10.40
1.00 cum. Hire & Labour charges at Rs. 405.75 /cum. = 405.75
Rate for 1.00 cum. Rs. 1955.31

Road Data - Rev-17.5 28 Revised during - OCT. 2017


CRUSHER RUN MACADAM
Providing and laying, spreading and compacting graded stone aggregates to Crusher
Run Macadam specification including premixing the materials with water at OMC in
mechnanical mix plant carriage of mixed material by tipper to site laying in uniform
layers with pavers in Sub Base/ Base course on well prepared surface and compacting
with vibratory roller to acheive the desired density including cost of material, labour
charges, rentals for machinery, fuel and all other incidental charges etc., complete as
Hire charges for Machineries
Loader 5 Cum. Capacity
Hire charges excluding fuel charges per day =Rs. 1147.62
Fuel charges per day 80 lit.of diesel 65.22 /lit =Rs. 5217.60

Total Hire charges per day including Fuel =Rs. 6365.22


Total Hire charges per Hour including Fuel =Rs. 795.65

Tipper
Hire charges excluding fuel charges per day =Rs. 1041.90
Fuel charges per day 3.25lit.of diesel x 8hrs 65.22 /lit =Rs. 1695.72
Total Hire charges per day including Fuel =Rs. 2737.62
Total Hire charges per Hour including Fuel =Rs. 342.20

Water Tankers
Hire charges excluding fuel charges per day =Rs. 814.29
Fuel charges per day 25lit.of diesel 65.22 /lit =Rs. 1630.50
Total Hire charges per day including Fuel =Rs. 2444.79
Total Hire charges per Hour including Fuel =Rs. 305.60
Vibratory Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 5169.52
Fuel charges per day 3.00lit.of diesel x 8hrs 65.22 /lit =Rs. 1565.28
Total Hire charges per day including Fuel =Rs. 6734.80
Total Hire charges per Hour including Fuel =Rs. 841.85

Motor Grader including fuel per Hour =Rs. 1611.07

Total Hire Charges for machineries for 100 Cum of CRM


1. Loader for 6 Hours 795.65 /hr. =Rs. 4773.92
2. Tipper for 24 Hours 342.20 /hr. =Rs. 8212.86
3. Water Tanker for 24 Hours 305.60 /hr. =Rs. 7334.40
4. Motor Grader for 4 Hours 1611.07 /hr. =Rs. 6444.28
5. Vibratory Roller for 6 Hours 841.85 /hr. =Rs. 5051.10
Total Hire Charges for machineries for 100 Cum of CRM =Rs. 31816.56

Total Hire Charges for machineries for 1.00 Cum of CRM =Rs. 318.17

Road Data - Rev-17.5 29 Revised during - OCT. 2017


Labour Charges for 100 cum of CRM
0.50 Nos. of Head Mazdoor @ Rs. 375.95 /E =Rs. 187.98
8.63 Nos. of Mazdoor Ist Class @ Rs. 364.58 /E =Rs. 3146.33
2.00 Nos. of Mazdoor IIst Class @ Rs. 326.70 /E =Rs. 653.40
Total Labour Charges of 100 cum of CRM =Rs. 3987.71

Total Labour Charges of 1.00 cum of CRM =Rs. 39.88


Total Hire and Labour charges per cum. = 318.17 + 39.88 =Rs. 358.05

CRUSHER RUN MACADAM 300mm THICK

0.09 Cum Cost of 53-45mm IRC 0.090 @Rs 1230.43 /cum 110.74
0.46 Cum. Cost of 45-22.40mm IRC 0.460 @Rs 1371.00 /cum 630.66
0.30 Cum. Cost of 22.40-5.6mm IRC 0.300 @Rs 1151.57 /cum 345.47
0.46 Cum. Cost of 900mm Micron and below 0.460 @Rs 924.71 /cum 425.37
1.00 Cum Hire & Labour charges 1.00 @Rs 358.05 /cum 358.05
Rate for 1.00 cum. Rs. 1870.29

Road Data - Rev-17.5 30 Revised during - OCT. 2017


BITUMINOUS MACADAM 50MM THICK USING CMP
Providing and laying 50mm consolidated thick bituminous macadam using 0.20 cum fo 26.50-
13.20mm, 0.43 cum of 13.20-2.36mm and 0.08 cum of 2.36mm & below size IRC metal with 37
Kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all
materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them
in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper
trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the
specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to
the required density etc., including labour for attending to paver to site etc., including hire charges
and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver
finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all
other incidental charges etc., complete as per specification using CMP as per clause 504 of
MORTH Rev-5

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9234.3 /8 =Rs. 1154.29
Fuel charges per Hour
For running the Plant :30 litres of diesel 65.22 /lit =Rs. 1956.60
For heating the bitumen 25 litres of furnace oil 28.67 /lit =Rs. 716.75
For heating the aggregates : 170 litres of furnace oil 28.67 /lit =Rs. 4873.90
Hire Charges including fuel charges per hour Rs. 8701.54
Out turn of CMP per Hour for BM = 135sqm. of 50 mm thick

Hire Charges for CMP per 10sqm. = 8701.54 X 10 =Rs. 644.56


135
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is
not necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5169.52/8 =Rs. 646.19
Fuel charges per day 2.50 litres x 65.22 /lit =Rs. 163.05
Hire Charges including fuel charges per hour Rs. 809.24
Out turn of Vibrator Roller per hour= 350sqm. of 50 mm thick

Hire Charges for Vibrator roller per 10sqm. = 809.24 X 10 =Rs. 23.12
350
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2330.48 /8 =Rs. 291.31
Fuel charges per hour 6 litres per hour X 65.22 /lit =Rs. 391.32
Hire Charges including fuel charges per hour Rs. 682.63
Out turn of Paver Finisher per hour = 135 sqm. of 50 mm thick

Hire Charges for paver finisher per 10sqm. = 682.63 X 10 =Rs. 50.57
135

Road Data - Rev-17.5 31 Revised during - OCT. 2017


4. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1041.90 /8 =Rs. 130.24
Fuel charges per hour 3.25 litres per hour X 65.22 /lit =Rs. 211.97
Hire Charges including fuel charges per hour Rs. 342.21
Out turn of Tipper Truck per hour = 135 sqm. of 50 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 342.21 x6x10 =Rs. 152.09
135

Total hire charges for machineries per 10 sqm =644.56+ 23.12+ 50.57+ 152.09
= 870.34 /10sqm
LABOUR CHARGES PER 1200SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 364.58 /each = 12031.14
25.00 Nos Mazdoor IInd Class @Rs. 326.70 /each = 8167.50
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 364.58 /each = 3645.80
Total Labour Charges per 1200sqm = 23844.44

Labour Charges per 10sqm. = 23844.44 X 10 =Rs. 198.70


1200

RATE PER CUM OF 50MM THICK BITUMINOUS MACADAM

0.200 Cum Cost of 26.5-13.20mm IRC at Rs. 1559.10 /cum. = 311.82


0.430 Cum Cost of 13.20-2.36mm IRC at Rs. 979.54 /cum. = 421.20
0.080 Cum Cost of 2.36mm & below IRC at Rs. 924.71 /cum. = 73.98
37.00 Kg Cost of VG 30 Bitumen at Rs. 30246.98 /MT = 1119.14
10.00 Sqm Hire charges at Rs. 870.34 /10sqm = 870.34
10.00 Sqm Labour charges at Rs. 198.70 /10sqm = 198.70
Rate for 10 sqm =Rs. 2995.18

Rate per cum of 50 mm thick = 2995.18 = Rs. 5990.36


0.50

Road Data - Rev-17.5 32 Revised during - OCT. 2017


DENSE BITUMINOUS MACADAM 50MM THICK USING CMP
Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.24 cum of 26.50-
13.20mm, 0..25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below and with 53.20 Kgs of VG30/
VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site,
heating the bitumen and aggregate to required temperature and mixing them in required temperature in
central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the
mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted
by Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver at
site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks,
Paver Finisher / 9m paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required,
including fuel and all other incidental charges etc., complete as per specification using CMP as per
clause 505 MORTH Rev-5

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9234.29 /8 =Rs. 1154.29
Fuel charges per Hour
For running the Plant :30 litres of diesel 65.22 /lit =Rs. 1956.60
For heating the bitumen 25 litres of furnace oil 28.67 /lit =Rs. 716.75
For heating the aggregates : 170 litres of furnace oil 28.67 /lit =Rs. 4873.90
Hire Charges including fuel charges per hour Rs. 8701.54
Out turn of CMP per Hour for BM = 135sqm. of 50 mm thick

Hire Charges for CMP per 10sqm. = 8701.54 X 10 =Rs. 644.56


135
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5169.52/8 =Rs. 646.19
Fuel charges per day 2.50 litres x 65.22 /lit =Rs. 163.05
Hire Charges including fuel charges per hour Rs. 809.24
Out turn of Vibrator Roller per hour= 320sqm. of 50 mm thick

Hire Charges for Vibrator roller per 10sqm. = 809.24 X 10 =Rs. 25.29
320
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2330.48 /8 =Rs. 291.31
Fuel charges per hour 6 litres per hour X 65.22 /lit =Rs. 391.32
Hire Charges including fuel charges per hour Rs. 682.63
Out turn of Paver Finisher per hour = 135 sqm. of 50 mm thick

Hire Charges for paver finisher per 10sqm. = 682.63 X 10 =Rs. 50.57
135

Road Data - Rev-17.5 33 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1041.90 /8 =Rs. 130.24
Fuel charges per hour 3.25 litres per hour X 65.22 /lit =Rs. 211.97
Hire Charges including fuel charges per DAY Rs. 342.21
Out turn of Tipper Truck per hour = 135 sqm. of 50 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 342.21 x6x10 =Rs. 152.09
135

Total hire charges for machineries per 10 sqm = 644.56+ 25.29+ 50.57+ 152.09
= 872.51 /10sqm
LABOUR CHARGES PER 1200SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 364.58 /each = 12031.14
25.00 Nos Mazdoor IInd Class @Rs. 326.70 /each = 8167.50
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 364.58 /each = 3645.80
Total Labour Charges per 1200sqm = 23844.44

Labour Charges per 10sqm. = 23844.44 X 10 =Rs. 198.70


1200

RATE PER CUM OF 50MM THICK DENSE BITUMINOUS MACADAM

0.240 Cum Cost of 26.50 - 13.20mm IRC at Rs. 1490.66 /cum. = 357.76
0.250 Cum Cost of 13.20-2.36mm IRC at Rs. 977.61 /cum. = 244.40
0.230 Cum Cost of 2.36mm & below IRC at Rs. 924.71 /cum. = 212.68
0.000 Cum Cost of Stone Dust (Filling mat.) at Rs. 508.90 /cum. = 0.00
53.20 Kg Cost of VG 30 Bitumen at Rs. 30246.98 /MT = 1609.14
10.00 Sqm Hire charges at Rs. 872.51 /10sqm = 872.51
10.00 Sqm Labour charges at Rs. 198.70 /10sqm = 198.70
Rate for 10 sqm =Rs. 3495.19

Rate per cum of 50 mm thick = 3495.19 = Rs. 6990.38


0.50

Road Data - Rev-17.5 34 Revised during - OCT. 2017


BITUMINOUS MACADAM 80MM THICK USING CMP
Providing and laying 80mm consolidated thick bituminous macadam using 0.64 cum fo 37.5 -
13.20mm, 0.44 cum of 13.2 - 2.36mm and 0.13 cum of 2.36mm and below size IRC metal with 62
Kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all
materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them
in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper
trucks to paver site, spreading the mix to uniform thickness of 80mm with mechanical paver to the
specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to
the required density etc., including labour for attending to paver to site etc., including hire charges
and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks,Paver Finisher / 9m paver
finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all
other incidental charges etc., complete as per specification using CMP as per clause 504 of
MORTH Rev-5.
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9234.29 /8 =Rs. 1154.29
Fuel charges per Hour
For running the Plant :30 litres of diesel 65.22 /lit =Rs. 1956.60
For heating the bitumen 25 litres of furnace oil 28.67 /lit =Rs. 716.75
For heating the aggregates : 170 litres of furnace oil 28.67 /lit =Rs. 4873.90
Hire Charges including fuel charges per hour Rs. 8701.54
Out turn of CMP per Hour for BM = 90sqm. of 75 mm thick

Hire Charges for CMP per 10sqm. = 8701.54 X 10 =Rs. 966.84


90
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is
not necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5169.52/8 =Rs. 646.19
Fuel charges per day 2.50 litres x 65.22 /lit =Rs. 163.05
Hire Charges including fuel charges per hour Rs. 809.24
Out turn of Vibrator Roller per hour= 250sqm. of 80 mm thick

Hire Charges for Vibrator roller per 10sqm. = 809.24 X 10 =Rs. 32.37
250

4.PAVER FINISHER
Hire charges excluding fuel charges per day 2330.48 /8 =Rs. 291.31
Fuel charges per hour 6 litres per hour X 65.22 /lit =Rs. 391.32
Hire Charges including fuel charges per hour Rs. 682.63
Out turn of Paver Finisher per hour = 90 sqm. of 80 mm thick

Hire Charges for paver finisher per 10sqm. = 682.63 X 10 =Rs. 75.85
90

Road Data - Rev-17.5 35 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1041.90 /8 =Rs. 130.24
Fuel charges per hour 3.25 litres per hour X 65.22 /lit =Rs. 211.97
Hire Charges including fuel charges per DAY Rs. 342.21
Out turn of Tipper Truck per hour = 90 sqm. of 75 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 342.21 x6x10 =Rs. 228.14
90

Total hire charges for machineries per 10 sqm 966.84


= +32.37 +75.85 +228.14
= 1303.20 /10sqm
LABOUR CHARGES PER 1000SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 364.58 /each = 12031.14
25.00 Nos Mazdoor IInd Class @Rs. 326.70 /each = 8167.50
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 364.58 /each = 3645.80
Total Labour Charges per 1000sqm = 23844.44

Labour Charges per 10sqm. = 23844.44 X 10 =Rs. 238.44


1000

RATE PER CUM OF 80MM THICK BITUMINOUS MACADAM

0.640 Cum Cost of 37.50-13.20mm IRC at Rs. 1401.34 /cum. = 896.86


0.440 Cum Cost of 13.20-2.36mm IRC at Rs. 1004.55 /cum. = 442.00
0.130 Cum Cost of 2.36mm & below at Rs. 924.71 /cum. = 120.21
62.00 Kg Cost of VG 30 Bitumen at Rs. 30246.98 /MT = 1875.31
10.00 Sqm Hire charges at Rs. 1303.20 /10sqm = 1303.20
10.00 Sqm Labour charges at Rs. 238.44 /10sqm = 238.44
Rate for 10 sqm =Rs. 4876.02

Rate per cum of 80 mm thick = 4876.02 = Rs. 6095.03


0.80

Road Data - Rev-17.5 36 Revised during - OCT. 2017


DENSE BITUMINOUS MACADAM 75MM THICK USING CMP
Providing and laying 75mm consolidated thick Dense Bituminous macadam using 0.40 cum fo 37.50-
13.20mm, 0.35 cum of 13.20-2.36mm and 0.36 cum of 2.36mm & below size IRC metal with 71.30 kgs
of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to
CMP site, heating the bitumen and aggregate to required temperature and mixing them in required
temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site,
spreading the mix to uniform thickness of 75mm with mechanical paver to the specified grades and
cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to the required density etc.,
including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t
CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller
and all other tools and plant required, including fuel and all other incidental charges etc., complete as
per specification using CMP as per clause 505 of MORTH rev-5.

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9234.29 /8 =Rs. 1154.29
Fuel charges per Hour
For running the Plant :30 litres of diesel 65.22 /lit =Rs. 1956.60
For heating the bitumen 25 litres of furnace oil 28.67 /lit =Rs. 716.75
For heating the aggregates : 170 litres of furnace oil 28.67 /lit =Rs. 4873.90
Hire Charges including fuel charges per hour Rs. 8701.54
Out turn of CMP per Hour for DBM = 90sqm. of 75 mm thick

Hire Charges for CMP per 10sqm. = 8701.54 X 10 =Rs. 966.84


90
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5169.52/8 =Rs. 646.19
Fuel charges per day 2.50 litres x 65.22 /lit =Rs. 163.05
Hire Charges including fuel charges per hour Rs. 809.24
Out turn of Vibrator Roller per hour= 220sqm. of 75 mm thick

Hire Charges for Vibrator roller per 10sqm. = 809.24 X 10 =Rs. 36.78
220

4.PAVER FINISHER
Hire charges excluding fuel charges per day 2330.48 /8 =Rs. 291.31
Fuel charges per hour 6 litres per hour X 65.22 /lit =Rs. 391.32
Hire Charges including fuel charges per hour Rs. 682.63
Out turn of Paver Finisher per hour = 90 sqm. of 75 mm thick

Hire Charges for paver finisher per 10sqm. = 682.63 X 10 =Rs. 75.85
90

Road Data - Rev-17.5 37 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1041.90 /8 =Rs. 130.24
Fuel charges per hour 3.25 litres per hour X 65.22 /lit =Rs. 211.97
Hire Charges including fuel charges per DAY Rs. 342.21
Out turn of Tipper Truck per hour = 90 sqm. of 75 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 342.21 x6x10 =Rs. 228.14
90

Total hire charges for machineries per 10 sqm = 966.84 36.78 75.85 228.14
= 1307.61 /10sqm
LABOUR CHARGES PER 1000SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 364.58 /each = 12031.14
25.00 Nos Mazdoor IInd Class @Rs. 326.70 /each = 8167.50
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 364.58 /each = 3645.80
Total Labour Charges per 1000sqm = 23844.44

Labour Charges per 10sqm. = 23844.44 X 10 =Rs. 238.44


1000

RATE PER CUM OF 75MM THICK DENSE BITUMINOUS MACADAM

0.400 Cum Cost of 37.50-13.20mm IRC at Rs. 1368.49 /cum. = 547.40


0.350 Cum Cost of 13.20-2.36mm IRC at Rs. 960.30 /cum. = 336.11
0.360 Cum Cost of 2.36mm & Below IRC at Rs. 924.71 /cum. = 332.90
0.000 Cum Cost of Stone Dust (Filling mat.) at Rs. 508.90 /cum. = 0.00
71.30 Kg Cost of VG 30 Bitumen at Rs. 30246.98 /MT = 2156.61
10.00 Sqm Hire charges at Rs. 1307.61 /10sqm = 1307.61
10.00 Sqm Labour charges at Rs. 238.44 /10sqm = 238.44
Rate for 10 sqm =Rs. 4919.07

Rate per cum of 75 mm thick = 4919.07 = Rs. 6558.76


0.75

Road Data - Rev-17.5 38 Revised during - OCT. 2017


Prime Coat Over WBM/ WMM Surface

Providing and laying Prime Coat over WBM/ WMM surface using 7 Kg of Emulsion Bitumen
(SS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of
material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
complete as perClause 502 of MORTH Rev-5
Labour Charges per 500 sqm for preparation of surface
10.00 Nos Mazdoor Ist Grade @Rs 364.58 /each =Rs 3645.80
16.00 Nos Mazdoor IIst Grade @Rs 326.70 /each =Rs 5227.20
For Applying Primer
4.00 Nos Mazdoor IIst Grade @Rs 326.70 /each =Rs 1306.80
Total Labour Charges per 500 sqm =Rs 10179.80

Total Labour Charges per 10 sqm = 10179.80 x10 Rs. 203.60


500
Rate for Prime Coat over WBM/ WMM surface

7.00 Kgs Cost of Bitumen Emulsion - SS1 @Rs 43867.85 /MT =Rs 307.07
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 203.60 /10sqm =Rs 203.60
Rate for 10 sqm =Rs 525.67

Rate per 1.00 sqm =Rs 52.57 /sqm

Prime Coat Over CRM/ Gravel base


Providing and laying Prime Coat over CRM/ Gravel base using 9 Kg of Emulsion Bitumen
(SS1) per 10 sqm for preparatory to another bituminous construction over it including cost of
material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
complete as perClause 502 of MORTH Rev-5
Labour Charges per 500 sqm for preparation of surface
10.00 Nos Mazdoor Ist Grade @Rs 364.58 /each =Rs 3645.80
16.00 Nos Mazdoor IIst Grade @Rs 326.70 /each =Rs 5227.20
For Applying Primer
4.00 Nos Mazdoor IIst Grade @Rs 326.70 /each =Rs 1306.80
Total Labour Charges per 500 sqm =Rs 10179.80

Total Labour Charges per 10 sqm =


10179.80 x10 Rs. 203.60
500
Rate for Prime Coat over Crusher Run Macadam surface

9.00 Kgs Cost of Bitumen Emulsion (SS1) @Rs 43867.85 /MT =Rs 394.81
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 203.60 /10sqm =Rs 203.60
Rate for 10 sqm =Rs 613.41
Rate per 1.00 sqm =Rs 61.34 /sqm

Road Data - Rev-17.5 39 Revised during - OCT. 2017


Tack Coat Over Existing BT Surface

Providing and laying Tack Coat over Existing BT surface using 2 Kg of Bitumen Emulsion
(RS1) per 10 sqm for preparatory to another bituminous construction over it including cost
of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
complete as perClause 503 of MORTH Rev-5

Labour Charges per 500 sqm


5.00 Nos Mazdoor Ist Grade Preparing Surface @Rs 364.58 /each =Rs 1822.90
5.00 Nos Mazdoor IIst Grade(Applying TC)@Rs 326.70 /each =Rs 1633.50
Total Labour Charges per 500 sqm =Rs 3456.40

Total Labour Charges per 10 sqm = 3456.40 x10 Rs. 69.13


500
Rate for Tack Coat over Existing BT surface

2.00 Kgs Cost of RS-I Bitumen emulsion @Rs 27183.35 /MT =Rs 54.37
10.00 Sqm Hire for bitumen boiler @Rs /10sqm =Rs
10.00 sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 sqm Labour Charges @Rs 69.13 /10sqm =Rs 69.13
Rate for 10 sqm =Rs 138.50

Rate per 1.00 sqm =Rs 13.85 /sqm

Tack Coat Over Primed Surface

Providing and laying Tack Coat over WBM/ WMM surface (treated with primer) using
2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous
construction over it including cost of material, labour charges, rentals for machinery, fuel
and all other incidental charges etc., complete as perClause 503 of MORTH Rev-5
Labour Charges per 500 sqm
3.00 Nos Mazdoor IInd Grade(Applying TC)@Rs 326.70 /each =Rs 980.10
Total Labour Charges per 500 sqm =Rs 980.10

Total Labour Charges per 10 sqm =


980.10 x10 Rs. 19.60
500
Rate for Tack Coat over primed WBM / WMM Surface

2.50 Kgs Cost of RS-I Bitumen emulsion @Rs 27183.35 /MT =Rs 67.96
10.00 Sqm Hire for bitumen boiler @Rs /10sqm =Rs
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 19.60 /10sqm =Rs 19.60
Rate for 10 sqm =Rs 102.56

Rate per 1.00 sqm =Rs 10.26 /sqm

Road Data - Rev-17.5 40 Revised during - OCT. 2017


CLOSE GRADED PREMIX SURFACING 20MM COMPACTED THICK
Providing laying and rolling of close graded premix carpet of compacted 20mm thickness using
using 0.0162 cum of 13.20-11.20mm, 0.1404 cum of 11.2-5.6mm, 0.0729 cum of 5.60-
2.80mm, 0.0405 cum of 2.80mm and below (Type B) graded HBG metal using 19kg of VG30
bitumen for 10sqm including premixing at CMP, conveyance by tipper lorry, laying by paver
finisher and rolling by Vibratory Roller including cost and conveyance of all materials, hire
charges of all T&P all labour charges, fuel and and all other incidental charges etc., Complete
as per specification using CMP as per clause 508 of MORTH Rev-5

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9234.29 /8 =Rs. 1154.29
Fuel charges per Hour
For running the Plant :30 litres of diesel 65.22 /lit =Rs. 1956.60
For heating the bitumen 25 litres of furnace oil 28.67 /lit =Rs. 716.75
For heating the aggregates : 170 litres of furnace oil 28.67 /lit =Rs. 4873.90
Hire Charges including fuel charges per hour Rs. 8701.54
Out turn of CMP per Hour for SDBC = 270sqm. of 25 mm thick

Hire Charges for CMP per 10sqm. = 8701.54 X 10 =Rs. 322.28


270
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATORY ROLLERS :
Hire charges excluding fuel charges per Hour 5169.52/8 =Rs. 646.19
Fuel charges per day 2.50 litres x 65.22 /lit =Rs. 163.05
Hire Charges including fuel charges per Hour Rs. 809.24
Out turn of Vibratory Roller per hour= 500sqm. of 25 mm thick

Hire Charges for Vibratory roller per 10sqm. = 809.24 X 10 =Rs. 16.18
500

4. PAVER FINISHER
Hire charges excluding fuel charges per hour 2330.48 /8 =Rs. 291.31
Fuel charges per hour 6 litres per hour X 65.22 /lit =Rs. 391.32
Hire Charges including fuel charges per DAY Rs. 682.63
Out turn of Paver Finisher per hour = 270 sqm. of 25 mm thick

Hire Charges for paver finisher per 10sqm. = 682.63 X 10 =Rs. 25.28
270

Road Data - Rev-17.5 41 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1041.90 /8 =Rs. 130.24
Fuel charges per hour 3.25 litres per hour X 65.22 /lit =Rs. 211.97
Hire Charges including fuel charges per DAY Rs. 342.21
Out turn of Tipper Truck per hour = 270 sqm. of 25 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 342.21 x6x10 =Rs. 76.05
270

Total hire charges for machineries per 10 sqm =322.28 16.18 25.28 76.05
= 439.79 /10sqm
LABOUR CHARGES PER 2000SQM
For loading materials into CMP
26.40 Nos Mazdoor Ist Class @Rs. 364.58 /each = 9624.91
20.00 Nos Mazdoor IInd Class @Rs. 326.70 /each = 6534.00
For attending Paver Finisher
8.00 Nos Mazdoor Ist Class @Rs. 364.58 /each = 2916.64
Total Labour Charges per 2000sqm = 19075.55

Labour Charges per 10sqm. = 19075.55 X 10 =Rs. 95.38


2000

RATE 10SQM OF CLOSE GRADED PREMIX SURFACING 20MM COMPACTED THICK

0.0162 Cum Cost of 13.20mm -11.20mm Metalat Rs. 1199.95 /Cum. = 19.44
0.1404 Cum Cost of 11.20mm-5.6mm Metal at Rs. 993.28 /Cum. = 139.46
0.0729 Cum Cost of 5.60mm-2.80 Metal at Rs. 924.71 /Cum. = 67.41
0.0405 Cum Cost of 2.80mm and below Metal at Rs. 924.71 /Cum. = 37.45
19.00 Kg Cost of VG30 grade Bitumen at Rs. 30246.98 /MT = 574.69
10.00 Sqm Hire charges at Rs. 439.79 /10sqm = 439.79
10.00 Sqm Labour charges at Rs. 95.38 /10sqm = 95.38
Rate for 10 sqm =Rs. 1373.62

Rate per sqm of 20 mm thick = 1373.62 = Rs. 137.36


10

Road Data - Rev-17.5 42 Revised during - OCT. 2017


BITUMINOUS CONCRETE 30/40MM THICK USING CMP
Providing and laying Bituminous Concrete to 40 mm thick using 0.13 cum of 19.00-9.50mm,
0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30 kgs of VG30/ VG40
bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site,
heating the bitumen and aggregate to required temperature and mixing them in required
temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to
paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the
specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic
Roller to the required density etc., including labour for attending to paver to site etc., including
hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver
Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required,
including fuel and all other incidental charges etc., complete as per specification using CMP as
per clause 507 of MORTH Rev-5
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9234.29 /8 =Rs. 1154.29
Fuel charges per Hour
For running the Plant :30 litres of diesel 65.22 /lit =Rs. 1956.60
For heating the bitumen 25 litres of furnace oil 28.67 /lit =Rs. 716.75
For heating the aggregates : 170 litres of furnace oil 28.67 /lit =Rs. 4873.90
Hire Charges including fuel charges per hour Rs. 8701.54
Out turn of CMP per Hour for BC = 170sqm. of 40 mm thick

Hire Charges for CMP per 10sqm. = 8701.54 X 10 =Rs. 511.86


170
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5169.52/8 =Rs. 646.19
Fuel charges per day 2.50 litres x 65.22 /lit =Rs. 163.05
Hire Charges including fuel charges per hour Rs. 809.24
Out turn of Vibrator Roller per hour= 400sqm. of 40 mm thick

Hire Charges for Vibrator roller per 10sqm. = 809.24 X 10 =Rs. 20.23
400
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2330.48 /8 =Rs. 291.31
Fuel charges per hour 6 litres per hour X 65.22 /lit =Rs. 391.32
Hire Charges including fuel charges per hour Rs. 682.63
Out turn of Paver Finisher per hour = 170 sqm. of 40 mm thick

Hire Charges for paver finisher per 10sqm. = 682.63 X 10 =Rs. 40.15
170

Road Data - Rev-17.5 43 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1041.90 /8 =Rs. 130.24
Fuel charges per hour 3.25 litres per hour X 65.22 /lit =Rs. 211.97
Hire Charges including fuel charges per DAY Rs. 342.21
Out turn of Tipper Truck per hour = 170 sqm. of 40 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 342.21 x6x10 =Rs. 120.78
170

Total hire charges for machineries per 10 sqm =511.86+ 20.23+ 40.15+ 120.78
= 693.02 /10sqm
LABOUR CHARGES PER 1200 SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 364.58 /each = 12031.14
25.00 Nos Mazdoor IInd Class @Rs. 326.70 /each = 8167.50
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 364.58 /each = 3645.80
Total Labour Charges per 1200sqm = 23844.44

Labour Charges per 10sqm. = 23844.44 X 10 =Rs. 198.70


1200

RATE PER SQM OF BITUMINOUS CONCRETE 30/40MM THICK

0.130 Cum Cost of 19.00-9.50mm IRC at Rs. 1290.69 /cum. = 167.79


0.170 Cum Cost of 9.50 - 2.36mm IRC at Rs. 958.66 /cum. = 162.97
0.260 Cum Cost of 2.36 mm and below at Rs. 924.71 /cum. = 240.42
50.30 Kg Cost of VG30 Bitumen at Rs. 30246.98 /MT = 1521.42
10.00 Sqm Hire charges at Rs. 693.02 /10sqm = 693.02
10.00 Sqm Labour charges at Rs. 198.70 /10sqm = 198.70
Rate for 10 sqm =Rs. 2984.32

Rate per cum = 2984.32/(10x0.04) = 7460.80

Road Data - Rev-17.5 44 Revised during - OCT. 2017


PROVIDING GRAVEL FOR BERMS INCL. COMPACTION
Providing and laying of Gravel including cost and conveyance of the same to work site
from approved quarry including stacking the same to departemental gauge for
premeasurement including all labour charges for laying, spreading etc., complete and as
directed by the departmental engineers for making up of low berms

Hire charges for Machineries

Power Roller 8-10 tonne


Hire charges excluding fuel charges per day =Rs. 788.57
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 65.22 /lit =Rs. 1304.40
Total Hire charges per day including Fuel =Rs. 2092.97
Daily Out turn 425 Cum.

Hire charges of Power Roller per 10 sqm. 2092.97 =Rs. 4.92


425
Water Sprinklers
Hire charges excluding fuel charges per day =Rs. 1103.81
Fuel charges per day (Diesel) 3.25 lit/Hr x 8.00 Hrs. x 65.22 /lit =Rs. 1695.72
Total Hire charges per day including Fuel =Rs. 2799.53
Daily Out turn 1000 Cum.

Hire charges of Water Sprinklers per 10 sqm. 2799.53 =Rs. 2.8


1000

Total Hire charges for Machineries per10sqm = 4.92 + 2.80 =Rs. 7.72

Labour charges for Laying U.S. Gravel for 100cum


2.00 Nos. Mazdoor Ist Class @Rs. 364.58 /E =Rs. 729.16
Total Labour charges for laying gravel per 100cum =Rs. 729.16

Total Labour charges for laying gravel per Cum 729.16 =Rs. 7.29
100
Total Hire and Labour charges = 7.72 + 7.29 =Rs. 15.01

Road Data - Rev-17.5 45 Revised during - OCT. 2017


Providing gravel for berms including compaction (100 % Compaction)

Km 0/8
1.16 Cum. Cost of Gravel at Rs. 468.68 /Cum. = 543.67
1.00 Cum. Hire and Labour charges at Rs. 15.01 /Cum. = 15.01
Rate for 1.00 cum. Rs. 558.68

1.16 Cum. Cost of Gravel at Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /Cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Gravel at Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /Cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Gravel at Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /Cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Gravel at Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /Cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Gravel at Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /Cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Gravel at Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /Cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Gravel at Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /Cum. =
Rate for 1.00 cum. Rs.

Road Data - Rev-17.5 46 Revised during - OCT. 2017


Providing gravel for berms including compaction (100 % Compaction)

1.16 Cum. Cost of Gravel at Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /Cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Gravel at Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 15.01 /Cum. =
Rate for 1.00 cum. Rs.

Road Data - Rev-17.5 47 Revised during - OCT. 2017


Earthwork for Berms
Earth Work for berms including Cost of earth work and compaction by power roller
(100% compaction)
Hire charges for Machineries
Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 788.57
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 65.22 /lit =Rs. 1304.40
Total Hire charges per day including Fuel =Rs. 2092.97
Daily Out turn 425 Cum.
Hire charges of Power Roller per 10 sqm. 2092.97 =Rs. 4.92 /Cum
425
Water Sprinklers
Hire charges excluding fuel charges per day =Rs. 1103.81
Fuel charges per day (Diesel) 3.25 lit/Hr x 8.00 Hrs. x 65.22 /lit =Rs. 1695.72
Total Hire charges per day including Fuel =Rs. 2799.53
Daily Out turn 1000 Cum.
Hire charges of Water Sprinklers per 10 sqm. 2799.53 =Rs. 2.8 /Cum
1000

Total Hire charges for Machineries per10sqm = 4.92 + 2.80 =Rs. 7.72 /Cum
Labour charges for Laying Earth for 100cum
2.00 Nos. of Mazdoor Ist Class @Rs. 364.58 /E =Rs. 729.16
Total Labour charges for laying earth per 100cum =Rs. 729.16

Total Labour charges for laying earth per Cum 729.16 =Rs. 7.29 /Cum
100
Total Hire and Labour charges = 7.72 + 7.29 =Rs. 15.01 /Cum

1.00 Cum Excavation Charges as per PWD rates Rs.57.86/Cum =Rs. 57.86
1.00 Cum Hire and Labour Charges Rs.15.01/Cum =Rs. 15.01
Cost of earth per cum at worksite =Rs. 72.87 /Cum