Commissioning Form East Timor Trading PV System

PV Array
PV Array Checklist

Building: A Facing East Check Date

1 No visible damage to any equipment √

2 Confirm no shadow obstruction on the panels during 9am to 4pm √

3 Safe access to all necessary equipment for inspection and maintenance √

4 Label (name/number) clearly visible on string cable √

5 Warning notices and labels installed properly and made of durable materials √

6 All metal parts protected adequately against corrosion √

7 All bolts and screws are torqued to specification (Rail and PV) √

All installed equipment locations comply with the engineering drawings and
8
documentations √

9 The array (ROOF) is properly weather-sealed against water leakage. √

10 All mechanical mounting devices are secure and level √

Inside & outside is clean and orderly, with no trash or construction waste. Vegetation
11
is appropriately cleared. √

12 All cable not touching sharp edges protected from direct sunlight by conduit √

13 Tilt/slope properly 15 degree facing north x

Solar PV mounting system was installed to manufacturer's specification and safety


14
codes √

Notes:
PV Array Checklist

Building: A Facing West Check Date

1 No visible damage to any equipment √

2 Confirm no shadow obstruction on the panels during 9am to 4pm √

3 Safe access to all necessary equipment for inspection and maintenance √

4 Label (name/number) clearly visible on string cable √

5 Warning notices and labels installed properly and made of durable materials √

6 All metal parts protected adequately against corrosion √

7 All bolts and screws are torqued to specification (Rail and PV) √

All installed equipment locations comply with the engineering drawings and
8
documentations √

9 The array (ROOF) is properly weather-sealed against water leakage. √

10 All mechanical mounting devices are secure and level √

Inside & outside is clean and orderly, with no trash or construction waste. Vegetation
11
is appropriately cleared. √

12 All cable not touching sharp edges protected from direct sunlight by conduit √

13 Tilt/slope properly 15 degree facing north x

Solar PV mounting system was installed to manufacturer's specification and safety


14
codes √

Notes:
PV Array Checklist

Building: B Facing North Check Date

1 No visible damage to any equipment √

2 Confirm no shadow obstruction on the panels during 9am to 4pm √

3 Safe access to all necessary equipment for inspection and maintenance √

4 Label (name/number) clearly visible on string cable √

5 Warning notices and labels installed properly and made of durable materials √

6 All metal parts protected adequately against corrosion √

7 All bolts and screws are torqued to specification (Rail and PV) √

All installed equipment locations comply with the engineering drawings and
8
documentations √

9 The array (ROOF) is properly weather-sealed against water leakage. √

10 All mechanical mounting devices are secure and level √

Inside & outside is clean and orderly, with no trash or construction waste. Vegetation
11
is appropriately cleared. √

12 All cable not touching sharp edges protected from direct sunlight by conduit √

13 Tilt/slope properly 15 degree facing north x

Solar PV mounting system was installed to manufacturer's specification and safety


14
codes √

Notes:
PV Array Checklist

Building: C Facing South Check Date

1 No visible damage to any equipment √

2 Confirm no shadow obstruction on the panels during 9am to 4pm √

3 Safe access to all necessary equipment for inspection and maintenance √

4 Label (name/number) clearly visible on string cable √

5 Warning notices and labels installed properly and made of durable materials √

6 All metal parts protected adequately against corrosion √

7 All bolts and screws are torqued to specification (Rail and PV) √

All installed equipment locations comply with the engineering drawings and
8
documentations √

9 The array (ROOF) is properly weather-sealed against water leakage. √

10 All mechanical mounting devices are secure and level √

Inside & outside is clean and orderly, with no trash or construction waste. Vegetation
11
is appropriately cleared. √

12 All cable not touching sharp edges protected from direct sunlight by conduit √

13 Tilt/slope properly 15 degree facing north x

Solar PV mounting system was installed to manufacturer's specification and safety


14
codes √

Notes:
PV Array Checklist

Building: D Facing East Check Date

1 No visible damage to any equipment √

2 Confirm no shadow obstruction on the panels during 9am to 4pm √

3 Safe access to all necessary equipment for inspection and maintenance √

4 Label (name/number) clearly visible on string cable √

5 Warning notices and labels installed properly and made of durable materials √

6 All metal parts protected adequately against corrosion √

7 All bolts and screws are torqued to specification (Rail and PV) √

All installed equipment locations comply with the engineering drawings and
8
documentations √

9 The array (ROOF) is properly weather-sealed against water leakage. √

10 All mechanical mounting devices are secure and level √

Inside & outside is clean and orderly, with no trash or construction waste. Vegetation
11
is appropriately cleared. √

12 All cable not touching sharp edges protected from direct sunlight by conduit √

13 Tilt/slope properly 15 degree facing north x

Solar PV mounting system was installed to manufacturer's specification and safety


14
codes √

Notes:
PV Array Checklist

Building: E Facing West Check Date

1 No visible damage to any equipment √

2 Confirm no shadow obstruction on the panels during 9am to 4pm √

3 Safe access to all necessary equipment for inspection and maintenance √

4 Label (name/number) clearly visible on string cable √

5 Warning notices and labels installed properly and made of durable materials √

6 All metal parts protected adequately against corrosion √

7 All bolts and screws are torqued to specification (Rail and PV) √

All installed equipment locations comply with the engineering drawings and
8
documentations √

9 The array (ROOF) is properly weather-sealed against water leakage. √

10 All mechanical mounting devices are secure and level √

Inside & outside is clean and orderly, with no trash or construction waste. Vegetation
11
is appropriately cleared. √

12 All cable not touching sharp edges protected from direct sunlight by conduit √

13 Tilt/slope properly 15 degree facing north x

Solar PV mounting system was installed to manufacturer's specification and safety


14
codes √

Notes:
Inverter
Structural / Mechanical Checklist

Check Date

1 No visible damage to any equipment √

2 Inverter mounting meets manufacturer specifications (height, open-space, etc.). √

3 Labels (name/number) on each Inverter & Meter √

4 All metal parts protected adequately against corrosion √

All installed equipment locations comply with the engineering drawings and
5
documentations √

6 Warning notices and labels installed properly and made of durable materials √

7 All equipment is securely fastened. √

8 All bolts and screws are torqued to specification √

9 All mechanical mounting devices are secure and level √

Area is clean and orderly, with no trash or construction waste. Vegetation is


10
appropriately cleared. √

Notes:
Electrical Checklist

Electrical Checklist

Building: Check Date

Cables adequately protected against mechanical damage (including abrasion on


1 rough surfaces) √

Cable color code complies with local regulations


2
(DC side: Red=Positif, Black=Negatif; AC side: Neutral=Blue, Phase=Black/Brown,
Ground: Yellow Green) √

3 DC cabling separated between positive and negative √

All exposed metal parts and enclosures are adequately earthed with approved
4 mechanical bonding √

5 Grounding system installed according to regulations and provided design drawings √

Check grounding resistance, record value (ohms) in separate provided site


6 commissioning sheets √

7 Surge protection devices installed properly √

DC disconnects and AC disconnects installed properly, labeled clearly and easily


8 accessible √

All cables and protection devices sizes & types conform to engineering drawings
9 and documentation √

10 All wiring conforms to engineering drawings and documentation √

Splice from Inverter and Meter into distribution cable is both mechanically secure
11 and electrically appropriate. √

12 Wire routing is in conduit when needed, and all wire routing is neat and orderly. √

13 Check polarity of every connection √

Notes:
Inverter Test Procedure

Inverter 1

Inverter Brand Capacity


Sungrow SG60KTL 38.88 kWp
DC Side Notes
1 Voltage measurement at the string 1 793 VDC
2 Voltage measurement at the string 2 807 VDC
3 Voltage measurement at the string 3 802 VDC
4 Voltage measurement at the string 4 802 VDC
5 Voltage measurement at the string 5 790 VDC
6 Voltage measurement at the string 6 794 VDC
7 Voltage measurement at the string 7 VDC
8 Voltage measurement at the string 8 VDC
9 Voltage measurement at the string 9 VDC
10 Voltage measurement at the string 10 VDC
If there is no voltage due to this test, check the cable
Bad Good
connection from PV panels
AC Side
Notes
1 Voltage measurement at every channel:
Output
Line 1 - N 211 VAC
Line 2 - N 213 VAC
Line 3 - N 211 VAC
Line 1 – Line 2 368 VAC
Line 2 – Line 3 368 VAC
Line 3 – Line 1 365 VAC

Notes
Inverter 2

Inverter Brand Capacity


Sungrow SG60KTL 38.88 kWp
DC Side Notes
1 Voltage measurement at the string 1 814 VDC
2 Voltage measurement at the string 2 805 VDC
3 Voltage measurement at the string 3 810 VDC
4 Voltage measurement at the string 4 804 VDC
5 Voltage measurement at the string 5 809 VDC
6 Voltage measurement at the string 6 812 VDC
7 Voltage measurement at the string 7 VDC
8 Voltage measurement at the string 8 VDC
9 Voltage measurement at the string 9 VDC
10 Voltage measurement at the string 10 VDC
If there is no voltage due to this test, check the cable
Bad Good
connection from PV panels
AC Side
Notes
1 Voltage measurement at every channel:
Output
Line 1 - N 213 VAC
Line 2 - N 211 VAC
Line 3 - N 211 VAC
Line 1 – Line 2 369 VAC
Line 2 – Line 3 365 VAC
Line 3 – Line 1 368 VAC

Notes:
1. IEC 60364-7-712 Compliance

712.4 Protection for safety

712.41 Protection against electric shock

1 DC disconnects and AC disconnects installed properly √

PV equipment on the DC side shall be considered to be energized, even when the system is
disconnected from the AC side.

712.411 Protection against both direct and indirect contact

2 Grounding electrode resistance measurement of less than 5 ohms (as tested per regulation) √

712.413 Fault protection

712.413.1 Protection by automatic disconnection of supply

3 Arrester/RCD installed properly √

712.433 Protection against overload on the DC side

4 Photovoltaic (PV) fuse installed properly √

712.434 Protection against short-circuit currents

5 MCB (Miniature Circuit Breaker) installed properly √

712.52 Wiring systems

712.53 Isolation, switching and control

712.522.8.1 PV string cables, PV array cables and PV DC main cables shall be selected and
erected so as to minimize the risk of earth faults and short-circuits

PV string cables, PV array cables and PV DC main cables size according to the calculation
6 design & standard √

712.53 Isolation, switching and control

712.536.2.1.1 To allow maintenance of the PV inverter, means of isolating the PV inverter


from the DC side and the AC side shall be provided.

7 Isolation, switching and control according to the wiring design √


Wiring Check

Pic 1. Inverter 1

Note:
Pic 2. Inverter 2

Notes:
Pic 3. Layout all building

Notes:
Building A
Building B
Building C
Building D
Building E
2. Workmanship checklist

General Checklist
1 No visible damage to any equipment √
2 Safe access to all necessary equipment for inspection and maintenance √
3 All circuit breakers, fuses, switches and disconnects clearly labeled with their ratings √
4 Schematic diagram of the system is posted clearly on a durable material √
5 Each component clearly labeled (fuses, breakers, switches, wires) √
Cable color code complies with local regulations
6 (DC: Red=Positif, Black=Negatif; AC: Neutral=Blue, Phase=Black/Brown, Ground: Yellow Green) √
7 All metal parts protected adequately against corrosion √
8 All joints at metal conduit are mechanically sound and electrically continuous √
9 Metal conduits are adequately earthed √
10 All exposed metal parts and enclosures are adequately earthed with approved mechanical bonding √
11 All mechanical mounting devices are secure and level √
12 Cables adequately protected against mechanical damage (including abrasion on rough surfaces) √
13 DC cabling separated between positive and negative √
14 Grounding system installed according to regulations √
15 Surge protection devices installed properly √
16 Solar PV mounting system was installed to manufacture’s specification and safety codes √
17 All installed equipment complies to the engineering drawings and documentations √
18 All cables and protection devices have been calculated to withstand the electrical current √
19 All cables are protected from damage √
20 Warning notices and labels installed properly and made of durable materials √
21 All bolts and screws are torqued to specification √
22 Solar PV panels are not shaded at any time of the day and in the foreseeable future √