Академический Документы
Профессиональный Документы
Культура Документы
Access to this document was granted through an Emerald subscription provided by emerald-
srm:232872 []
For Authors
If you would like to write for this, or any other Emerald publication, then please use our Emerald
for Authors service information about how to choose which publication to write for and submission
guidelines are available for all. Please visit www.emeraldinsight.com/authors for more information.
About Emerald www.emeraldinsight.com
Emerald is a global publisher linking research and practice to the benefit of society. The company
manages a portfolio of more than 290 journals and over 2,350 books and book series volumes, as
well as providing an extensive range of online products and additional customer resources and
services.
Emerald is both COUNTER 4 and TRANSFER compliant. The organization is a partner of the
Committee on Publication Ethics (COPE) and also works with Portico and the LOCKSS initiative for
digital archive preservation.
*Related content and download information correct at time of download.
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
The current issue and full text archive of this journal is available on Emerald Insight at:
www.emeraldinsight.com/1741-038X.htm
is a major problem that impacts the performance of a company and its supply chain. The purpose of
this paper is to analyze the cause of delays and to understand the role of coordination to mitigate them.
Design/methodology/approach – An in-depth case study was conducted to identify problems
that delay a project and to examine such problems from a systemic perspective. Based on data from
interviews, group meetings, field observations and documentation, a pattern is proposed to explain the
relation between coordination and lead time.
Findings – Conceptually, to reduce the project lead time a higher level of concurrency is necessary.
However, more concurrency increases the interdependencies between activities, something which
demands more coordination effort. Since the coordination mechanisms applied are not appropriate to
cope with the increasing coordination effort, a number of problems appear causing reworks and
delays which increase the lead time.
Research limitations/implications – The main limitation is that the authors are not able to
distinguish which particular project characteristic influences the adoption of a specific coordination
mechanism. Further research is required to examine the effect of various coordination mechanisms
across a higher number of projects.
Practical implications – Practitioners can benefit from discussions in this study to comprehend
how coordination can improve the delivery performance in ETO supply chains.
Originality/value – This study contributes to a better understanding of coordination in ETO supply
chains by making sense of problems that delay the project. Matching the coordination mechanisms
with the required coordination effort, which is based on the project characteristics, is a way to avoid
delays and reduce the lead time.
Keywords Coordination, Complex projects, Concurrent project development,
Interface engineering-production, Shipbuilding industry
Paper type Research paper
1. Introduction
In engineer-to-order (ETO) supply chains, companies are responsible for performing
different activities during a project, such as: design, engineering, procurement,
logistics, manufacturing, assembling and commissioning (Hicks et al., 2000; McGovern
The authors acknowledge the Research Council of Norway (Norges forskningsråd) and companies
that are supporting and financing us (first and fourth authors) through the project Innovation in
Global Maritime Production 2020 (IGLO-MP). A special acknowledgement is dedicated to all the
managers, engineers and project members who provided the relevant insights and valuable
discussions throughout this study. Yet, this paper reflects and presents the authors’ viewpoints and Journal of Manufacturing
the respective companies involved are not responsible for any statements made or use that may be Technology Management
Vol. 26 No. 3, 2015
made of the information contained in this paper. pp. 429-454
The authors want to thank the anonymous reviewers for their relevant contribution for © Emerald Group Publishing Limited
1741-038X
improving this paper. DOI 10.1108/JMTM-03-2013-0021
JMTM et al., 1999). In such companies, the product differentiation occurs at the design
26,3 stage (Hoekstra and Romme, 1992). This means that each product is designed to satisfy
specific needs which vary from one customer to another. ETO companies are mainly
dedicated to produce capital goods (Hicks et al., 2001). Shipbuilding, heavy equipment,
offshore oil and gas, and construction are typical examples of sectors which operate as
ETO supply chains (Gosling and Naim, 2009). Such type of supply chain typically
430 serves niche markets, which have none or few competitors, and customers, who may
accept to pay a higher price for a product that perfectly fits their needs (Stavrulaki and
Davis, 2010). ETO companies do not have a stock of finished products to immediately
satisfy a specific customer need (Bertrand and Muntslag, 1993). Consequently, the
customer is exposed to the total product lead time (Amaro et al., 1999; McGovern et al.,
1999; Bertrand and Muntslag, 1993).
The occurrence of delays is a major problem that impacts the performance of a
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
company and its supply chain (Stavrulaki and Davis, 2010; Hicks et al., 2001). Long
delays and reworks are common in the development of large engineering projects
because these projects require several refinements during the implementation stage
that increase lead times and costs (Caron and Fiore, 1995). In particular, engineering
and production activities involve a reciprocal interdependence which demands
considerable coordination effort (Konijnendijk, 1994). For example, a high number of
engineering revisions need to be handled through manufacturing because engineering
work is not finalized before production takes place (Hicks et al., 2001). Furthermore, due
to increasing levels of outsourcing, engineering and production need to be coordinated
when these activities are not performed at the same company (Hicks et al., 2000).
Considering this context, competitive advantage emerges from the ability of coordinating
internal and external processes (i.e. Caron and Fiore, 1995; Konijnendijk, 1994; Hicks et al.,
2001; McGovern et al., 1999).
Conceptually, coordination is a relevant aspect of the decision-making process that
maintain the order and stability of a system (Malone and Crowston, 1994). To be fully
coordinated, a supply chain requires that all decisions are aligned to accomplish a
global system objective (Shin and Robinson, 2002). The literature has shown that most
companies commonly fail to coordinate activities involving functional interfaces across
multiple business units (i.e. Hui et al., 2008; Pandit and Zhu, 2007; Sherman, 2004; Mihm
et al., 2003). Some common types of coordination problem includes: poor communication,
inadequate initiating structure, inadequate external support, inadequate cooperation,
organizational structure inhibiting coordination, ambiguities in authority relationships,
amongst others (Sherman, 2004). According to Sherman, “While the research literature
is relatively well developed on coordination within teams or functions, research on
coordination across interdependent team, department, or divisional interfaces is not well
developed”. Indeed, coordination has been addressed mainly from a logistics perspective
(Romano, 2003). The requirements of coordination may change according to the nature
of activities performed in the supply chain. Engineering, or product development, which
encompasses concept, basic design and detailed engineering, is an integral element of
the ETO supply chain that typically is a separate business process in other types of
supply chains (Hicks et al., 2000). Nowadays many ETO companies have been sourcing
production to low-labour cost countries, and retained engineering as a core expertise.
This decision has created a barrier between engineering and production that has resulted
in the occurrence of protracted delays leading to poor on time delivery (Hui et al., 2008).
The amount of outsourcing activities have been increasing without considering the
associated risks (Kumar et al., 2009; Hansen et al., 2013).
Considering an ETO supply chain, the purpose of this paper it to analyze the Project delays
cause of project delays and understand the role of coordination in mitigating them. We in an ETO
use the term coordination to designate the inter-functional coordination between
companies. More specifically, the focus is the engineering and production when these
supply chain
activities are not carried out at the same company. Based on an in-depth case study
conducted in a complex project, we identify problems that have delayed the project and
examine such problems from a systemic perspective. The main research question is: 431
RQ1. How can coordination affect the lead time in an ETO supply chain?
This research question is broken down into in three aims that follow:
(1) identify the problems that delay the project;
(2) describe the mechanisms that are causing delays; and
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
2. Background
2.1 ETO supply chain: characteristics and challenges
ETO supply chain produces low volume of a high variety of products and allows
customers to demand products which satisfy exactly their needs. Each customer order
requires some degree of engineering work to adapt an existent design or create a
completely new design. Hence, inventory of finished goods does not exist in ETO
supply chains (Stavrulaki and Davis, 2010). Despite the attempts to incorporate standard
components, products are treated as an individual project (Hicks et al., 2001). Value is
created mainly developing customer-specific solutions and integrating sophisticated
systems (Amaro et al., 1999). Consequently, ETO supply chains need to maintain a highly
flexible production in order to completely customize a product as the customer wants
(Wortmann et al., 1997).
The high degree of product customization required by individual customers has a
direct impact on the project lead time (Konijnendijk, 1994). The greater the degree
of customization the longer the lead time, since more activities are performed after
receiving the order (Amaro et al., 1999). Thus, one of the major challenges for ETO
supply chains is to prevent the lead time from being unacceptably long (Stavrulaki and
Davis, 2010). Hicks et al. (2001) suggests that improving delivery is dependent on both
reducing lead times and increasing the reliability of estimates. Indeed, long delays and
rework are common in the development of complex projects in ETO companies because
such projects require several refinements during the implementation stage that
increase lead times and costs (Caron and Fiore, 1995).
The completion of projects in a timely manner is one of the most important measures
for efficiency that covers the timeliness and amount of resources required during the
project (Brettel et al., 2011). In the project management literature several methods have
JMTM been proposed for completing projects on-time, including: Critical Path Method (CPM),
26,3 Program Evaluation and Review Technique (PERT), Earned Value Management
(EVM), Critical Chain Project Management (CCPM), amongst others (Kerzner, 2009;
PMI, 2004). Despite of the variety of methods available, in practice a project is rarely
completed within the specified time (Assaf and Al-Hejji, 2006). Some researchers
suggest that the underlying theoretical basis of project management is not satisfactory
432 and there is no consensus about which methods to adopt (Koskela and Howell, 2002).
In fact, the project management field is more applied and interdisciplinary than other
management disciplines so it is generally difficult to justify the field as an academic
discipline (Kwak and Anbari, 2009).
In ETO companies, the cause of project delays varies substantially from one project
to another due to existence of various forms of uncertainties (Elfving, 2003; Gosling
et al., 2012). Uncertainty has been recognized as one of the major factors leading to
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
delays in complex projects (i.e. Atkinson et al., 2006; Mihm et al., 2003; Tatikonda and
Rosenthal, 2000 amongst others). Essentially, uncertainty makes it is difficult to predict
the outcome of a project activity hence on-time performance is undermined (i.e. Swink,
2003; Tatikonda and Rosenthal, 2000; Ignatius et al., 2012). A number of studies have
focused on identifying and categorizing the various sources of uncertainty in order
to implement uncertainty reduction techniques (i.e. De Meyer et al., 2002; Atkinson et al.,
2006; Childerhouse and Towill, 2004 amongst others). With reference to ETO supply
chains, coordination has been pointed out as one of the elements of project management
most frequently associated with uncertainties (Gosling et al., 2012).
Basically, the three major phases that require coordination in ETO are: tendering
(sales/marketing), product development (engineering) and product realization
(production) (Hicks et al., 2000). Coordination of these processes requires specific
coordination mechanisms which can be used in a situation of limited standardization
and rarely any repeat orders (Konijnendijk, 1994). High project complexity arises due to
deep product structures, sporadic demand for different items requires various methods
of production, and overlapping of engineering and production activities (McGovern
et al., 1999). In particular, engineering and production activities involves a reciprocal
interdependence which demands considerable coordination effort (Konijnendijk, 1994).
According to Hicks (2001) “Missing information and engineering revisions caused
by the overlapping of manufacturing and design activities are major sources of
uncertainty that complicate the management of ETO manufacturing”.
In some ETO supply chains, production may also be outsourced with the
corresponded supply chain being controlled by the engineering company (Stavrulaki
and Davis, 2010). For example, in the past, shipbuilding companies were responsible for
performing in-house most of the activities to produce a vessel including the production
of some main equipment. Nowadays, sourcing can cover almost every phase performed
in shipbuilding. The so called “full shipyard” became an “assembly shipyard”
(Andritsos and Perez-Prat, 2000; Held, 2010). With the recent intensification of the
globalization process some shipbuilding companies started to outsource activities
worldwide (Holte et al., 2009). To ensure those projects are delivered on time, shipbuilding
companies have to coordinate a range of activities across several project partners globally
distributed (i.e. Held, 2010, Andritsos and Perez-Prat, 2000; Holte et al., 2009; Mello and
Strandhagen, 2011). In general, ETO companies have increased outsourcing while the
product has become more sophisticated and innovative. Therefore, coordinating
engineering and production activities has considerable scope to improve the supply chain
performance (Hicks et al., 2001; Gosling and Naim, 2009).
2.2 Interface engineering and production Project delays
In ETO supply chains, engineering and production represents the two main flows: in an ETO
non-physical (information flow) and physical (material flow), respectively (Bertrand
and Muntslag, 1993). The interdependency between information and material flows
supply chain
gradually increases as products move from engineering to production, consequently
changes at late stages of engineering have a higher impact on the efficiency of
production (Simchi-Levi et al., 2008). Managing information and material flows requires 433
a systems approach to identify, analyze and coordinate the interactions among the
entities (Shin and Robinson, 2002). Engineering is a central activity in ETO supply
chain that directly influences production (Rahman et al., 2003). Both engineering and
production activities require specific capabilities that should be coordinated to enable
that the final product is delivered on time (Hicks et al., 2001; McGovern et al., 1999;
Konijnendijk, 1994).
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
Table I.
Typology of
mechanisms to
coordinate
engineering and
production Note: (based on Adler, 1995)
•
Project delays
Engineering changes. Coordinates the implementation of changes proposed by
marketing or required by customers. in an ETO
• Transition teams. Design engineers move to manufacturing on temporary supply chain
assignments to perform design revisions.
Other authors addressing coordination mechanisms with focus on the engineering and
production interface, includes: Ettlie (1995), Twigg (2002), Vandevelde and Dierdonck 435
(2003), Terwiesch et al. (2001) and Petersen et al. (2005). In principle, any mechanism
applied to overcome companies’ barriers may contribute to improve coordination. For
example, job rotation and mobility (Ettlie, 1995), sharing preliminary information
(Terwiesch et al., 2001), cross-functional teams (Griffin and Hauser, 1992), etc. In Adler’s
study, the choice of a specific mechanism takes into account the influence of
uncertainty which he represents in the dimensions of novelty and analyzability. While
novelty is solved earlier in the project adopting more interactive mechanisms,
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
3. Research method
3.1 Overview
An in-depth case study was carried out in a shipbuilding project in order to identify
problems delaying the project and to examine their major causes. This method helped
us to collect empirical data and describe causal mechanisms with a richness of details
JMTM that is normally difficult to achieve using other research methods (Yin, 2009).
26,3 While a single-case study is often criticized by not enabling generalization of the
findings (that is true especially in the case of theory testing), it can provide a significant
contribution to knowledge and theory building (Yin, 2009). In theory building and
theory extension, in-depth case study is one of the most applicable methods due to its
extensive qualitative description and contextual analysis (Meredith, 1998).
436 Our study was part of a research project developed in close collaboration with
companies in the shipbuilding industry. The case is a project to design and produce
a special type of vessel known as offshore support vessel (OSV) which is used
to support offshore operations in oil and gas platforms. In general, an OSV is very
sophisticated and customized. Each vessel is designed to fulfill the requirements from a
specific customer order. Such vessels are produced in very low volume, normally small
series of two to six, and each vessel has a set of particular characteristics which
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
To analyze the data, first we sought to highlight the main problems delaying the
project. Based on data from interviews, we were able to identify several coordination
problems (Table III). Documentation analysis and on-site observation helped us to
confirm the occurrence of these problems during the project. Next, we translated these
problems into an influence diagram (Figure 4). Such diagram helped to make sense of
these problems and develop a more comprehensive analysis. The use of influence
diagram was useful for mapping the mess associated with complex projects
(Gharajedaghi, 2006). According to Gharajedaghi (2006), mess is a system of problems
containing elements which are highly interrelated. Through the influence diagram
these complicated linkages between events can be comprehended (i.e. Towill, 1996).
Using the influence diagram we were able to generate a number of insights on potential
cause-effect relationships.
The influence diagram was used as a preliminary step in order to develop a causal
loop diagram (Figure 5). The rationale for using the causal loop diagram was to
understand causal relations between variables. The causal loop diagram helped
to explain how the lack of coordination impacts the project performance. The literature
has highlighted the applicability of causal loop diagram to understand the effects of
delays in complex projects (Williams, 2003). According to Williams (2003), the main
argument for using causal loop diagram is to show the systemic inter-relationships,
which caused the various ramifications of the delays, are build up. Although the causal
loop diagram is a qualitative technique, it can also be used as a preliminary step prior
to the application of other quantitative techniques (e.g. system dynamics model)
(Williams et al., 2003).
Based the on causal loop diagram, a pattern has been proposed to explain potential
cause-effect relationships. This pattern helped to validate the empirical data
and to explain the occurrence of problems delaying the project (internal validation).
We have observed that this pattern is consistent with many other related studies
Department
Planning/ Design/ Procurement/ Production/ Total Group
Company Sales project mgt engineering logistics testing interviews meetings
Table II.
Ship designer 1 2 3 10 1a 17 2 Overview of
Shipyard 0 7 2 4 2 15 1 interviews and
Note: aSite engineer group meetings
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
26,3
438
JMTM
the project
Table III.
Summary of
problems during
Problem Quotation Confirmation
Delay to deliver drawings “Deliver the drawings in the right time is the most difficult thing for Documentation: project planning scheduling
us because we are missing information [from equipment suppliers]” (Ship designer)
Project Manager (Ship designer)
Poor quality of “Many of these shipyards are not making drawings themselves, On-site observation: little specification was
documentation and they do not have a good understanding of what is really needed provided by an engine supplier (Ship
for the engineering department to do good drawings. They don’t designer)
understand at all our need for documentation” Project Manager
(Ship designer)
Product changes after “Drawings from all the blocks were updated. I start to build, and Documentation: drawings from structure
production starts then they [ship design & engineering] start to replace the drawings were in the version G (Shipyard)
for updated versions. For example, they [ship design &
engineering] say that ‘the inspection door cannot be placed there
anymore, close it and open a new one in another place’” Planning
Manager (Shipyard)
Long time to find and “So the big killer for us is HVAC [Heating, Ventilation and Air On-site observation: the participation in a
correct errors Condition] system that is the area where we do the biggest mistakes meeting has shown the difficulties of project
and it cost the biggest money and we don’t find out about the partners to agree on a solution (Shipyard)
mistakes until very late in the project. That is the major problem”
Engineer Manager (Ship designer)
High number of quality “There is a well-know standard defining that the maximum Documentation: hour allocation reports (Ship
problems capacity of transportation for certain products is 800 m3. But, they design and engineering)
[ship design and engineering] sent us a design where the total
capacity of the tanks was 900 m3. I realized the mistake and
informed my team, but the tank was already built” Application
Engineer (Shipyard)
Information flow is not “Sometimes we make a notification to someone of the structure On-site observation: 3D CAD model was
integrated design, but this information does not go through other disciplines showing a beam crossing a bedroom that was
such as accommodation. And now we [at the shipyard] are not visualized in the 2D drawing (Shipyard)
struggling because there is a beam crossing a furnished
compartment” Design Engineer (Shipyard)
(continued )
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
Table III.
supply chain
439
in an ETO
JMTM (i.e Hui et al., 2008; Terwiesch et al., 2002; Loch et al., 2003 amongst others). This
26,3 indicates the potential for extending our findings to other types of ETO supply chains
(external validation). The use of a pattern supported by the literature is recognized
as one of the most desirable techniques for case study analysis (Yin, 2009).
designer to discuss potential projects. To develop a conceptual design, the ship designer
carried out an interactive tendering process to understand the shipowner’s needs and
requirements. Such requirements supported the ship designer in defining the main
parameters of the design (i.e. power, speed, gross tonnage). Each design is based on
vessels previously developed to other customers. The work of the ship designer in the
design phase is performed under the risk of not reaching a contract with the shipowner.
When the chances of winning the contract are higher, then the ship designer work more
closely with the shipowner in order to develop a completely new concept taking into
account more specific requirements of the operation.
Throughout the tendering, the ship designer had to contact equipment suppliers
and shipyards to evaluate the costs, technical specifications and delivery slots. These
companies had to interact and to agree on technical and commercial issues. For each
equipment at least two suppliers are technically validated to the bidding process where
delivery and price are negotiated. When the shipowner agreed with the conditions
offered to produce a vessel, the shipowner signed a contract with the shipyard to build
the vessel, the shipyard signed a contract with the ship designer to develop the
engineering package (drawings and technical specifications) and the shipyard signed
a contract with the main equipment suppliers to deliver the equipment based on the
specifications provided. The project represented a significant investment, thus contracts
are established to secure the companies involved from the uncertainties in the business
and regulate relationship between them. Before ordering a vessel, the shipowner
had already a contract with an oil and gas company. This contract defined among other
things when the vessel shall start operating and included penalties in case of delays and
bonus for early delivery.
The project started as an adaptation to an existing design. However, due to the
number of changes and their impact on other systems, the project ended up
as a customer-specific design. From the ship designer perspective, just a small change
in the size of the vessel had a significant influence on the selection of main engines,
electrical generators, structural components, etc. Besides, the project had a number
of innovative systems hence main equipment suppliers had to provide specifications
for systems that they had never produced before. Lastly, the shipyard had never
produced a similar vessel in terms of size and number of systems, and there were
uncertainties regarding the shipyard’s experience and technology to build the vessel.
In many ways, the uniqueness of the project situation contributed to increase the risks
of delays.
The shipbuilding project comprised nearly 3,000 activities which were organized in Project delays
different phases. The production of the hull was the longest activity. In order to reduce in an ETO
this long lead time, the engineering and production were performed concurrently.
The ship designer prioritized the work in the structure engineering in order to enable
supply chain
the shipyard start producing the hull as soon as possible. Due to long lead times to
deliver raw materials, the shipyard had to buy a large amount of steel plates and
profiles all at once to build the hull based on preliminary specifications. However, as 441
these specifications changed during the engineering, additional raw materials were
needed and the hull had to be modified. The perception is that this situation had also
generated reworks and delays.
Delays were a critical issue during the shipbuilding project due to high costs
involved. To prevent delays, the shipowner followed the project execution closely and
monitored the progress of several phases with his own personnel at the shipyard.
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
When delays happened in critical activities, the shipowner increased the pressure on
both the ship designer and the shipyard to deliver the vessel on time. Nevertheless, due
to the high number of uncertainties regarding the product and the project activities,
these companies could not guarantee that delays will not happen again.
Following a summary of the main characteristics of the shipbuilding project:
• there was a need to handle specific customer requirements;
• the project involved multiple companies;
• interaction between project partners was needed as the project evolved;
• companies shared incomplete specifications of the product;
• there was a high number of project activities;
• the product had a deep structure which embeds several systems;
• the product had sophisticated systems which had few suppliers;
• the product had several innovative systems that had not been used before;
• there was a high level of interdependence between different systems;
• the engineering and production was not performed in the same company;
• the relationship between companies was driven by contractual agreements;
• on time delivery was a very important issue to customer satisfaction;
• the engineering and production were performed concurrently; and
• significant product changes had occurred during the project.
continually demanded technical documentation from the main equipment suppliers. Some
of these suppliers had agreements with the ship designer while others with the shipyard.
In general, the ship designer had difficulties to obtain technical documentation from
equipment suppliers associated with the shipyard. Such suppliers did not have
contractual obligations with the ship designer consequently they were not committed to
deliver documentation on time.
Throughout the project, there was a massive back and forth flow of information.
The project partners did not have an integrated database. Each company was using a
different ERP and CAD systems which were not compatible. In general, e-mail was the
most common way of sharing project data. As a result, there was little visibility of
the processes and decisions going on across different project partners. When a problem
was found, normally it was too late to avoid delays. In many cases, delays during the
project were related with the poor quality of documentation. For example, even when
the equipment suppliers sent the equipment on time, the delivery of the equipment
at the shipyard was delayed because the documentation to release the equipment at the
customs was incomplete. In some situations, delays were also related to unexpected
events (i.e. absence of workers or weather condition) but there was no mitigation
plan previously developed.
Product changes occurred relatively frequent, and they were complicated to
manage. When the ship designer updated a drawing because an error was found or a
change was made, there were also many other related drawings that had to be updated.
As many systems of the vessel are interdependent, changes in one of them ended up
affecting many others. Moreover, a number of customer changes occurred by the end
of the project when parts of the vessel were already built.
Although both companies in this case study have experience from other shipbuilding
projects, such experience had not being used to avoid delays. Somehow, each project had
Launching of
the project
Delivery of
Engineering Delay the project
Figure 1.
Baseline for Production Delay
Time
engineering and [Months]
production
0 3 10 12 19 22
its own challenges which were not highlighted in the early phases. For example, the ship Project delays
designer ended up using more man-hours than initially planned because the amount in an ETO
of rework was underestimated. Furthermore, the shipyard had little experience and
knowledge to produce the vessel hence it was necessary more interaction with ship
supply chain
designer in order to understand drawings and specifications. Such interaction consumed
a considerable amount of main-hours from the ship designer.
Conflicts between the ship designer and the shipyard arose as the shipyard did not 443
agree on paying for additional man-hours of the ship designer. The shipyard argued
that more interaction was required due to the lack of design specifications and
design errors. From the ship designer perspective, the shipyard did not have enough
production capability to cope with incomplete design specifications and design issues.
The shipyard’s production constraints were not considered by the ship designer in the
beginning of the project consequently a number of adaptations had to be performed
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
on site.
A number of quotations from interviews were selected to illustrate the problems
described above (Table III).
The project documentation helped us to clarify the information gathered and to
confirm the problems pointed out during the interviews. The occurrence of these
problems created delays that have increased the lead time. An evidence of such
delay is clear in the progress reported provided by the shipyard (Figure 2). Remaining
four months to delivery, the project was still delayed approximately 30 per cent,
and the costs for both the ship design and shipyard were considerably higher
than expected.
On-site observations have been employed to check in loco some of the evidence from
the interviews. For example, the vessel was designed to have six tanks to transport
different types of material. This type of tank was very innovative and had been never
used before. When these tanks were built and assembled into the vessel, there was not
enough space to assemble the pumps due to design errors (Figure 3). The ship designer,
equipment supplier and shipyard had great difficulties to find a solution that would fit
both technical and operational criteria. It took almost nine months for the companies to
agree on a solution. Visiting the shipyard, we had the opportunity to attend, as an
observer, one the meetings to discuss this problem. It was possible to notice that rework
not only cause delays but also a conflicts, disappointments and distrust between
project partners.
100
90 Progress of
the Project Planned
80 Delay
70
60
Real
% 50
40
30
20
Figure 2.
10
The progress
0 of the project
Fev Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Fev Mar Apr May Jun Jul Aug Sep
at the shipyard
Chronological time [Months]
JMTM 4.4 Coordination mechanisms used during the project
26,3 Various coordination mechanisms have been used to coordinate the activities between
ship designer and shipyard, as show in the Table IV. To compare the extent to which
these coordination mechanisms were used, we estimated the relative frequency they
were applied during the project. Based on case study data, we rated the coordination
mechanisms as “Not at all”, “Very little”, “Somewhat” or “To a great extent”. The range
444 between the highest frequency and lowest varies from 0 to 6 times. Basically the
intention was to improve our perception of how coordination was done in practice.
In essence, the coordination throughout the project was fundamentally based on
standards and plans. There was little or no use of mutual adjustments and teams.
A description that follows explains the usage of the coordination mechanisms applied:
• Compatibility standards. Some basic information regarding the production
resources has been considered, for example the lifting capacity of cranes in the
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
shipyard was considered to define the number of blocks to divide the vessel.
• Coordination committees. Project managers from both companies have been in
contact one another throughout the project execution, but they role was follow up
activities rather than problem solving.
Tank
63 mm
Figure 3.
An example
of problem that
delayed the project
Pump
• Transition teams. The ship designer had allocated a field engineer at the shipyard
to support problems solving. Still, a single field engineer was not enough given the
number of project problems.
26,3
446
JMTM
situations
Figure 4.
Contractual
Delays to deliver penalties
Delay to deliver equipments
drawings
Product changes
after production
starts Pressure to reduce Deep product
the lead time structure
Occurrence of
Occurrence of
unpredictable Innovative product
delays
events
Increasing level
of concurrency
Separation of
engineering and
production
activities
missing then all these problems tend to increase the rework even more. For example, Project delays
the structure drawings were changed after production had taken place but production in an ETO
people were not notified of these changes until it was too late to avoid the structural
components from being produced. The same rationale applies to explain delays. Due to
supply chain
lack of coordination, delays spread over other activities. Consequently the cumulative
impact of delays was amplified.
Delays were common throughout the project, in particular delays to deliver 447
engineering drawings and equipments. Such delays were influenced by the quality of
technical documentation. Due to the high degree of uncertainty regarding the final
product it was difficult for the ship designer and the main equipment suppliers to provide
good quality documentation. In addition, there were a number of delays in production
because of the occurrence of unpredictable events (i.e. long periods of rain, absenteeism
and staff turnover). Even though coordination alone may not be enough to completely
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
eliminate such delays, the adoption of more effective coordination mechanisms can
enable a much faster response to problems and therefore to minimize their impact.
Coordination Coordination
effort required effort applied
+
+
R1 +
Pressure on Level of Coordiantion–
delivery concurrency gap
+
B1
Figure 5.
R2 + Pattern that explains
Project Delays + Rework the causal
lead time –
+ relationship
+
JMTM the coordination applied depends on both the ability to coordinate and willingness to
26,3 work together. The lack of proper coordination can affect the project performance in
terms of development time and product quality. For example, Ford and Sterman (2003)
argue that increasing concurrence as a response to delivery pressure aggravates delays
and degrades quality. Valle and Vázquez-Bustelo (2009) mention that in situations
where changes are not predictable or under control, concurrence may generate large
448 problems of communication, integration and rework. Indeed, when activities are carried
out concurrently, changes are often reported as a threat for the performance (Bogus
et al., 2005; Ford and Sterman, 2003). Normally, innovative designs take more time to
converge into a solution since a higher number of configurations are taken into account,
and a higher number of revisions occur that delay production (Terwiesch et al., 2002).
Loch et al. (2003) have shown that overlapping project activities increases the
coordination effort required even when all components and their interactions are
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
very simple. Moreover, the fact that engineering and production are not performed by
the same company increases substantially the coordination effort. Hui et al. (2008) have
demonstrated that outsourcing production of complex products creates coordination
challenges which lead to poor project performance when companies do not maintain
high levels of dominance over the activities performed.
projects in an ETO supply chain (Twigg, 2002). Hence, the learning obtained by the
project team can increase the effectiveness of coordination and progressively reduce
the need for interaction.
6. Conclusion
The literature has shown that improving delivery in ETO supply chains is dependent on
reducing lead times and increasing the reliability of estimates (i.e. Hicks et al., 2001;
McGovern et al., 1999; Gosling and Naim, 2009). In this paper, we examined the
root cause of delays from a coordination perspective. The main research question was
“how can coordination affect the lead time in an ETO supply chain?” To answer this
research question, three aims has been posed. The first aim was to identify the main
problems causing project delay. Through a detailed analysis of data from shipbuilding
project a number of problems have been identified (conf. Table III). Such problems
highlighted the lack of coordination between two companies, a ship designer and a
shipyard responsible for performing engineering and production activities, respectively.
The second aim was proposed to describe the mechanisms that are causing delays.
Based on the influence diagram (conf. Figure 4), it was possible to make sense of
complicated linkages between problems. Although overlapping engineering and
production has been used as a practice to shorten the lead time, such practice increases
the interdependence between these activities and demand more coordination effort.
In addition to that, a number of project characteristics, such as: deep product structure,
substantial product changes, variety of engineering disciplines, incomplete product
information, high number of project activities, use of innovative systems and
disintegration of engineering and production contribute to increase the coordination
effort. In many ways, the coordination effort applied was less than the coordination
effort required (Gerwin, 2004). Due to this lack of coordination, companies were not
able to effectively coordinate the project and a number of problems generated reworks
and delays which increased the lead time (conf. Figure 5).
The third aim was to discuss the role of coordination in avoiding delays. The results
of the case study have shown that the number and nature of interactions increase
the coordination effort in a complex project where engineering and production are not
carried out at the same company. Previous studies (i.e. Novak and Eppinger, 2001;
Ulrich and Eppinger, 2000; Ettlie, 1997) suggests that the need for coordination can be
reduced adopting more standard components, modular systems and manufacturing-
friendly designs. Nevertheless, the application of such approaches is very limited in the
ETO supply chains due to high influence of the customer into the product design.
JMTM Our results suggest that the coordination mechanisms adopted to manage the
26,3 engineering and production interface need to be compatible with the coordination effort
in each project situation. Through more interactive coordination mechanisms, it should
be possible to avoid delays and cope with increasing levels of concurrency to shorten
the lead time. Even though the use of more interactive mechanisms increases the
coordination costs, such costs can be compensated by a lower lead time.
450 Evidently, these findings are limited to the ETO context that we have analyzed.
The main limitation is that we are not able to distinguish which particular project
characteristic influences the adoption of a specific coordination mechanism. In order
to enable generalization, further research is required to examine a higher number of
projects and to compare the effect of various coordination mechanisms against
different project characteristics. More research is also needed to investigate the relation
between project learning and coordination. For instance, the extent to which post-
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
project appraisals can help to reduce the coordination effort is not fully comprehended.
Recapping the main research question, this study contributes to increase the
understanding of coordination in an ETO supply chain by explaining project problems
in the light of coordination theory. Based on findings from an in-depth case study, the
paper has also furthered the understanding of the concept of coordination gap. Our
analysis has shown the relevance of adopting the appropriate coordination mechanisms
to achieve a short and reliable lead time. The context we have investigated provides a rich
source of evidence about problems generated by the lack of coordination. An in-depth
case study often results in a large amount of data which is difficult to analyze,
but following a systemic approach we have provided a comprehensive analysis and
explained complicated causal links. A meaningful pattern based on potential cause-effect
relationships helped to comprehend the occurrence of rework and delays which increase
the lead time. Such pattern is consistent with other references in the literature (i.e Hui
et al., 2008; Gerwin, 2004; Terwiesch et al., 2002; Loch et al., 2003; Caron and Fiore, 1995;
Handfield, 1994). Practitioners can benefit from discussions in this study to comprehend
how coordination can improve the delivery in ETO supply chains.
References
Adler, P.S. (1995), “Interdepartmental interdependence and coordination: the case of the design/
manufacturing interface”, Organization Science, Vol. 6 No. 2, pp. 147-167.
Amaro, G., Hendry, L. and Kingsman, B. (1999), “Competitive advantage, customisation and a
new taxonomy for non make-to-stock companies”, International Journal of Operations &
Production Management, Vol. 19 No. 4, pp. 349-371.
Andritsos, F. and Perez-Prat, J. (2000), “The automation and integration of production processes
in shipbuilding”, State-of-the-Art report, Joint Research Centre – Institute for Systems,
Informatics & Safety, European Commission, Brussels.
Assaf, S.A. and Al-Hejji, S. (2006), “Causes of delay in large construction projects”, International
Journal of Project Management, Vol. 24 No. 4, pp. 349-357.
Atkinson, R., Crawford, L. and Ward, S. (2006), “Fundamental uncertainties in projects and the scope
of project management”, International Journal of Project Management, Vol. 24, pp. 687-698.
Bertrand, J.W.M. and Muntslag, D.R. (1993), “Production control in engineer to order firms”,
International Journal of Production Economics, Vol. 30, pp. 3-22.
Bogus, S.M., Molenaar, K.R. and Diekmann, J.E. (2005), “Concurrent engineering approach to
reducing design delivery time”, Journal of Construction Engineering and Management,
Vol. 131 No. 11, pp. 1179-1185.
Brettel, M., Heinemann, F., Engelen, A. and Neubauer, S. (2011), “Cross-functional integration of Project delays
R&D, marketing, and manufacturing in radical and incremental product innovations
and its effects on project effectiveness and efficiency”, Journal of Product Innovation
in an ETO
Management, Vol. 28 No. 2, pp. 251-269. supply chain
Burns, T. and Stalker, G.M. (1961), The Management of Innovation, University of Illinois at
Urbana-Champaign's Academy for Entrepreneurial Leadership Historical Research
Reference in Entrepreneurship, available at: http://ssrn.com/abstract=1496187 451
Caron, F. and Fiore, A. (1995), “Engineer to order’ companies: how to integrate manufacturing
and innovative processes”, International Journal of Project Management, Vol. 13 No. 5,
pp. 313-319.
Childerhouse, P. and Towill, D.R. (2004), “Reducing uncertainty in European supply chains”,
Journal of Manufacturing Technology Management, Vol. 15 No. 7, pp. 585-598.
Clark, K. and Fujimoto, T. (1991), Product Development Performance: Strategy, Organization, and
Management in the World Auto Industry, Harvard Business Press, Boston, MA.
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
De Meyer, A., Loch, C.H. and Pich, M.T. (2002), “Managing project uncertainty: from variation to
chaos”, Engineering Management Review, IEEE, Vol. 30 No. 3, p. 91.
Elfving, J.A. (2003), “Exploration of opportunities to reduce lead times for engineered-to-order
products”, PhD thesis, University of California, Berkeley, CA.
Ettlie, J.E. (1995), “Product-process development integration in manufacturing”, Management
Science, Vol. 41 No. 7, pp. 1224-1237.
Ettlie, J.E. (1997), “Integrated design and new product success”, Journal of Operations
Management, Vol. 15 No. 1, pp. 33-55.
Ford, D.N. and Sterman, J.D. (2003), “Overcoming the 90% syndrome: iteration management in
concurrent development projects”, Concurrent Enginering: Research and Applications,
Vol. 11 No. 3, pp. 177-186.
Galbraith, J.R. (1973), Designing Complex Organizations, Addison-Wesley Longman Publishing
Co. Inc., Reading, MA.
Gerwin, D. (2004), “Coordinating new product development in strategic alliances”, Academy of
Management Review, Vol. 29 No. 2, pp. 241-257.
Gharajedaghi, J. (2006), Systems Thinking: Managing Chaos and Complexity: A Platform for
Designing Business Architecture, Elsevier, Burlington, MA.
Gosling, J. and Naim, M.M. (2009), “Engineer-to-order supply chain management: a literature review
and research agenda”, International Journal of Production Economics, Vol. 122, pp. 741-754.
Gosling, J., Naim, M. and Towill, D. (2012), “Identifying and categorizing the sources of uncertainty
in construction supply chains”, Journal of Construction Engineering and Management,
Vol. 139 No. 1, pp. 102-110.
Griffin, A. and Hauser, J.R. (1992), “Patterns of communication among marketing engineering and
manufacturing – a comparison between two new product teams”, Management Science,
Vol. 38 No. 3, pp. 360-373.
Handfield, R.B. (1994), “Effects of concurrent engineering on make-to-order products”, IEEE
Transactions On Engineering Management, Vol. 41 No. 4, pp. 384-393.
Hansen, Z.N.L., Zhang, Y. and Ahmed-Kristensen, S. (2013), “Viewing engineering offshoring in a
network perspective: addressing and managing risks”, Journal of Manufacturing
Technology Management, Vol. 24 No. 2, pp. 154-173.
Held, T. (2010), “Supplier integration as an improvement driver – an analysis of some recent
approaches in the shipbuilding industry”, in Engelhardt-Nowitzki, C., Nowitzki, O. and
Zsifkovits, H. (Eds), Supply Chain Network Management. Gestaltungskonzepte und Stand
der Praktischen Anwendung, Springer Fachmedien Wiesbaden GmbH, Gabler Verlag,
pp. 369-384.
JMTM Hicks, C., Mcgovern, T. and Earl, C.F. (2000), “Supply chain management: a strategic issue in
engineer to order manufacturing”, International Journal of Production Economics, Vol. 65,
26,3 pp. 179-190.
Hicks, C., Mcgovern, T. and Earl, C.F. (2001), “A typology of UK engineer-to-order companies”,
International Journal of Logistics: Research and Applications, Vol. 4 No. 1, pp. 43-56.
Hoekstra, S.J. and Romme, J. (1992), Integral Logistic Structures: Developing Customer-Oriented
452 Goods Flow, Industrial Press, New York, NY.
Holte, E., Rialland, A. and Westvik, M. (2009), Drivers and Trends in Global Maritime Production.
Innovation in Global Maritime Production – 2020 (IGLO-MP), Norwegian University of
Science and Technology (NTNU) – Dep. of Industrial Economics and Technology
Management, Trondheim.
Hui, P.P., Davis-Blake, A. and Broschak, J.P. (2008), “Managing interdependence: the effects of
outsourcing structure on the performance of complex projects”, Decision Sciences, Vol. 39
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
Rahman, A., Rahim, A., Shariff, M. and Baksh, N. (2003), “The need for a new product
development framework for engineer-to-order products”, European Journal of Innovation
Management, Vol. 6 No. 3, pp. 182-196.
Romano, P. (2003), “Co-ordination and integration mechanisms to manage logistics processes
across supply networks”, Journal of Purchasing & Supply Management, Vol. 9, pp. 119-134.
Sarin, S. and O’connor, G.C. (2009), “First among equals: the effect of team leader characteristics
on the internal dynamics of cross-functional product development teams”, Journal of
Product Innovation Management, Vol. 26 No. 2, pp. 188-205.
Senge, P.M. (1990), The Fifth Discipline: The Art and Practice of the Learning Organization,
Random House, London.
Shani, A.B.R., Mohrman, S.A., Pasmore, W.A., Stymne, B. and Adler, N. (2008), Handbook of
Collaborative Management Research, Sage, Thousand Oaks, CA.
Sherman, J.D. (2004), “Optimal modes and levels of integration, and the identification of cross-
functional coordination deficiencies in concurrent engineering”, IEEE Transactions on
Engineering Management, Vol. 51 No. 3, pp. 268-278.
Shin, F. and Robinson, E.P. (2002), “Flow coordination and information sharing in supply
chains: review, implications, and directions for future research”, Decision Sciences, Vol. 33
No. 4, pp. 505-536.
Simchi-Levi, D., Kaminsky, P. and Simchi-Levi, E. (2008), Designing and Managing the Supply
Chain: Concepts, Strategies, and Case Studies, McGraw-Hill/Irwin, New York, NY.
Stavrulaki, E. and Davis, M. (2010), “Aligning products with supply chain processes and
strategy”, International Journal of Logistics Management, Vol. 21 No. 1, pp. 127-151.
Swink, M. (2003), “Completing projects on-time: how project acceleration affects new product
development”, Journal of Engineering and Technology Management, Vol. 20, pp. 319-344.
Takeuchi, H. and Nonaka, I. (1986), “The new product development game”, Harvard Business
Review, Vol. 64 No. 1, pp. 137-146.
Tatikonda, M.V. and Rosenthal, S.R. (2000), “Technology novelty, project complexity, and
product development project execution success: a deeper look at task uncertainty in product
innovation”, IEEE Transactions on Engineering Management, Vol. 47 No. 1, pp. 74-87.
Terwiesch, C., Bohn, R.E. and Chea, K.S. (2001), “International product transfer and production ramp-
up: a case study from the data storage industry”, R&D Management, Vol. 31 No. 4, pp. 435-451.
Terwiesch, C., Loch, C.H. and Meyer, A.D. (2002), “Exchanging preliminary information in
concurrent engineering: alternative coordination strategies”, Organization Science, Vol. 13
No. 4, pp. 402-419.
JMTM Thompson, J.D. (1967), Organizations in Action: Social Science Bases of Administrative Theory,
McGraw-Hill, New York, NY.
26,3
Towill, D.R. (1996), “Time compression and supply chain management-a guided tour”, Supply
Chain Management: An International Journal, Vol. 1 No. 1, pp. 15-27.
Treville, S.D. and Trigeorgis, L. (2010), “It may be cheaper to manufacture at home”, Harvard
Business Review, pp. 84-87.
454 Twigg, D. (2002), “Managing the design/manufacturing interface across firms”, Integrated
Manufacturing Systems, Vol. 13 No. 4, pp. 212-221.
Ulrich, K.T. and Eppinger, S.D. (2000), Product Design and Development, McGraw Hill, New York, NY.
Valle, S. and Vázquez-Bustelo, D. (2009), “Concurrent engineering performance: incremental versus
radical innovation”, International Journal of Production Economics, Vol. 119, pp. 136-148.
Van Der Ven, A.H., Delbecq, A.L. and Koenig, R.J. (1976), “Determinants of coordination modes
within organizations”, American Sociological Review, Vol. 41 No. 2, pp. 322-338.
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: permissions@emeraldinsight.com
This article has been cited by:
1. Mario Henrique Mello, Jan Ola Strandhagen, Erlend Alfnes. 2015. Analyzing the factors affecting
coordination in engineer-to-order supply chain. International Journal of Operations & Production
Management 35:7, 1005-1031. [Abstract] [Full Text] [PDF]
Downloaded by UMEA UNIVERSITY At 13:48 11 February 2016 (PT)