Академический Документы
Профессиональный Документы
Культура Документы
Title Page
I. Introduction
Objectives 2
Importance of Estimates 3
II. Specifications 4
Direct Cost 7
Indirect Cost 7
Computations
Earthworks 8
Concrete Works 9
Masonry 10
Steel Works 11
Tile 13
Painting 14
Truss 15
Roofing 19
1
INTRODUCTION
OBJECTIVES
To give a reasonably accurate idea of the cost
1. Estimating Materials
2. Estimating Labor
The number and kind of workers of different categories who will have to be
employed to complete the work in the specified time can be found from the
estimate.
3. Estimating Plant
4. Estimating Time
The estimate of a work and the past experience enable one to estimate quite
closely the length of time required to complete an item of work or the work as a
whole.
2
IMPORTANCE OF ESTIMATES
management, and the subject deserves the closest attention of one aspiring to a
project for it helps the engineer and the client in setting the budget for the plan.
It also helps the engineer in managing the time for the construction and it also
helps the engineer to determine the equipment and costs (direct or indirect)
3
SPECIFICATIONS
Proportioning of Concrete
4
SUMMARY OF BILL OF MATERIALS
5
Earthworks
Excavation 94.14 cu.m.
Fill Materials 96.46 cu.m. 150.00 14,469.00
Gravel Base 9.41 cu.m. 1200.00 11,292.00
Backfill 77.17 cu.m. 120.00 9,260.00
6
DETAILED ESTIMATES
Direct Costs
Indirect Costs
7
EARTHWORKS
Area of Floor Slab
A. (5m×4m) = 20m²
B. (3.5m×5m) = 17.5m²
C. (8m×4m) = 32m²
D. (6m×3.5m) = 21m²
E. (4.5m×4.5m) = 20.25m²
110.75m²
Column Footing
V = (1m×1m×0.35m×13 columns) = 4.55m3
Column
Wall Footing
V = (0.4m×0.25m×50.1m) = 5.01m3
C.H.B. Wall
V = (0.2m×0.6m×50.1m) = 6.01m3
Total 16.79m3
Space to be filled
Earthfill required
8
CONCRETE WORKS
Column Footing
Column
Wall Footing
V = (0.4m×0.25m×50.1m) = 5.01m3
C.H.B. Walls
V = (0.2m×0.6m×50.1m) = 6.01m3
Slabs
= 72.3m3
9
MASONRY
= [(13×3×2)+(9.5×3×2)+(7.5×3×3)+(11×3×2)+(3×3×2)+(2.6×3×2)+
(5×3)+(3.5×3)] – [(3.2×2.14)+(18×2.2)+(0.9×2.1×3)+(0.7×2.1×3)+
(3×0.5)+(2×0.6×1.2)+(1.2×1.2×2)+(1.8×10×1.2)]
= 327.6m2 – 48.3m2
A = 279.8m2
C.H.B to be used
Mortar
Plaster
V= 279.8m2×0.20m = 11.19m3
10
STEEL REINFORCEMENT
Column Footing
Column
a. 16×12mm = 19.2m
b. 48×10mm = 48cm
38+1 = 39 pcs.
11
STEEL REINFORCEMENT
Beams
For reinforcement
N = 103.6m÷6m = 17.27
Walls
279.8m2×1.6 = 447.68m2
279.8m2×1.72 = 481.26m2
447.68m2+481.26m2 = 928.94m2
12
TILEWORKS
Area = 11=.75m2
Cement Mortar
Area = 11=.75m2
13
PAINTING
A = 279.8
The walls have a fine surface. For fine surface, the total area coverage of a
gallon is 40m2
For neutralizer
14
TRUSS
Truss 1
2049 200
=
2950+k k
k = 319.09
X 2049 X 2049
= =
950+319.09 3269.09 1000+950+319.09 3269.09
X1 = 795.44 X2 =1422.22
Y1 = 1277.78 Y2 = 1738.59
T1=2950+2049+3481.56+795.44+1422.22+1277.78+1738.59
T1=13714.59+200
T1 =13194.50mm
15
Truss 2
2500 200
=
4700+k k
k = 408.7
X 2500
= Y1 = √7252 + 554.792 = 912.92
1133.7 5108.7
X1 = 554.79 Y2 = 1445.77
X2 = 1044.15 Y3 =1830.75
X3 = 1533.51 Y4 = 2256.55
X4 = 2022.87
T2 = 2433.9mm × 2 = 4867.8mm
16
Truss 3
1663 200
=
2325+k k
k = 317.84
X1 = 1033.75
T3 = 9407.03mm × 6 = 56442.18mm
Truss 4
2500 200
=
6667+k k
k = 579.74
X 2500
= Y1 = 1265.2
1667+579.74 2246.74
X1 = 775.07 Y2 = 1501.52
X2 = 1120.07 Y3 =1773.8
X3 = 1465.05 Y4 = 2067.9
X4 = 1810.03 Y5 = 237.73
X5 = 2155.02
T4 = 32128.97mm × 4 = 128,515.88mm
17
Truss 5
2049 200
=
4193+k k
k = 453.54
X1 = 719.55 Y1 = 1231.97
X2 = 1156.56 Y2 =1528.93
X3 = 1593.57 Y3 = 1881.35
T5 = 19593.67mm
Truss 6
2500 200
=
4750+k k
k = 415.04
X1 = 551.05 Y1 = 1141.78
X2 = 1035.26 Y2 =1439.36
X3 = 1519.47 Y3 = 1819
X4 = 2003.68 Y4 = 2239.36
T6 = 46507.66mm×2 = 93015.32mm
TT = T1+T2+T3+T4+T5+T6 = 297995.35mm
18
ROOFING
1
A1 = (5.37) (4.75) (2) = 25.48
2
25.48
N1 = = 7.99 say 8 sheets
3.19
A2 = 44.15
44.15
N2 = = 13.84 say 14 sheets
3.19
A3 = 51.05
51.05
N3 = = 16 sheets
3.19
1
A4&5 = 3 (3.41) (2) = 10.23
2
6.9
N4 = = 2.26 say 3 sheets
3.19
10.23
N5 = = 3.21 say 4 sheets
3.19
A6 = 15.25
15.25
N6 = = 4.8 or 5 sheets
3.19
19
G.I. Rivets
NRivets = NT × Rivets
= 48 × 22 = 1056 pieces
Convert to kg
NWashers = (NRivets × 2)
NAS = 1056
NSheet = 1056 ÷ 342 = 3.09 say 4 pieces 36”x8ft. Plain G.I. Sheet
Convert to kg
20
PRICE QUOTATION AND CANVASS SHEET
21
LABOR COST
Total 6980.00/day
22