iii. Fulltime SHO at project site and one project per SHO
iii. Fulltime SSS at project site and one project per SSS
SUBSTATION
MS provided is complete and comprehensive to cover all work
activities under the scope of project and shall be endorsed by the
i.
Competent Engineer ( Live Apparatus ) / Contractor's Project
Manager ( Dead Apparatus )
14 Safety Communication
Tool Box Talk topic shall cover the work scope of the day and
vii its related MS, HIRADC, MSDS, SWP, PPE and tools /
equipment and current OSH issues (redundant with item ii & iii)
18 Safety Training
Safety training for site supervisor other than CIDB & NTSP
ii.
(e.g. HIRADC, ERP, ERT, WAH, etc ).
20 Working at Height
21 Ladders
22 Scaffolding
All lifting gears and lifts are identified and list of register and
i. checklist available. (cranes, jacks, wire or chain slings, steel
chain blocks, derrick, gin-pole, winch, pulley).
25 Hygiene Facilities
33 Traffic Safety
34 Security System
36 Incident Statistics
i) Reports available.
i) Reports available.
i) Reports available.
4 Safety Corner
5 Environmental Pollution
9 Foot Protection
10 Hearing Protection
13 Safety Communication
15 First-aid facilities
18 Ventilation
19 Working at Height
20 Ladders
a. Condition of scaffolds.
d. Wall ties
Crane shall have valid Permit Mesin Angkat (PMA) and Safe
ii
Working Load (SWL) displayed.
iv. Housekeeping
No superfluous materials at :
iii. Substation / Overhead Lines / Underground Cables/ Storage
area
33 Traffic Safety
34 Security System
36 Machine Guarding