Академический Документы
Профессиональный Документы
Культура Документы
Co nstruc ti o n
Law Journal
Inc. TCLR
INCORPORATING TECHNOLOGY AND CONSTRUCTION LAW REPORTS
Articles
Cases
Copies of articles from the Construction Law Journal, and other articles, cases and related ■■ Balfour Beatty Regional Construction Ltd v Grove Developments Ltd
materials, can be obtained from DocDel at Thomson Reuters Yorkshire office.
■■ Beumer Group UK Ltd v Vinci Construction UK Ltd
Current rates are: £7.50 + copyright charge + VAT per item for orders by post and email
(CLA account number must be supplied for email delivery). Fax delivery is an additional Technology and Construction Law Reports
£1.25 per page (£2.35 per page outside the UK).
■■ Ziggurat (Claremont Place) LLP v HCC International Insurance Company Plc
For full details, and how to order, please contact DocDel on
■ Tel: 01422 888 019.
■ Fax: 01422 888 001.
■ Email: trluki.admincentral@thomsonreuters.com.
■ Go to: http://www.sweetandmaxwell.co.uk/our-businesses/docdel.aspx.
Please note that all other enquiries should be directed to to Customer Support (Email:
TRLUKI.cs@thomsonreuters.com; Tel: 0345 600 9355).
*724547*
Editors Notes for Contributors
General and Articles Editor
1. We welcome the submission of articles for consideration by the Articles Editor with a view to publication.
ANDREW BURR, MA (Cantab), ACI Arb,
Adjudicator, Arbitrator and Barrister Articles to be considered for publication should be sent to The Articles Editor, Andrew Burr (ArbDB
Case Note Editors Chambers, 150 Fleet Street, London EC4A 2DQ), by email to andrew.burr@arbdb.com.
KIM FRANKLIN QC, LLB, FCI Arb, 2. The preferred length for articles is around 5,000 words. However, shorter contributions will be welcomed and
Barrister, Chartered Arbitrator
longer articles may be considered for publication.
SUSAN LINDSEY, RIBA, FCI Arb,
Barrister, Chartered Arbitrator
3. Submission of articles will be held to imply that they contain original unpublished work and are not being
International Case Note Editor submitted for publication elsewhere. No liability is accepted for loss or damage to material submitted.
PAUL BUCKINGHAM, BSc, C Eng FI Chem E,
Barrister 4. All pages should be numbered consecutively. Titles and headings should be short.
Book Reviews and Editorial 5. Footnotes should be kept to a minimum and numbered consecutively throughout the text with superscript
KIM FRANKLIN QC, LLB, FCI Arb, arabic numerals.
Barrister, Chartered Arbitrator
Information Section and Editorial 6. Authors must supply the biographical information which they wish to appear in the Construction Law Journal,
SUSAN LINDSEY, RIBA, FCI Arb, along with an address to which proofs and two complimentary copies of the Journal can be sent.
Barrister, Chartered Arbitrator
7. Cases and statutes, etc. should be cited accurately and in the correct format, preferably in the footnotes.
Construction Act Review
PETER SHERIDAN 8. Proofs will be sent to authors who undertake to check them. They should be clearly corrected and returned to
Partner, Sheridan Gold LLP the email address given thereon without delay.
Technology and Construction Law Reports
9. Authors who would like their article to be peer reviewed should make this known to the Articles Editor when
DARRYL ROYCE, BA
Barrister they submit their article.
Consultant Editor
THE HONOURABLE MR JUSTICE RAMSEY MA, C Eng MICE
Peer Review Editor
PROFESSOR ISSAKA NDEKUGRI BSc (Civil Eng), LLB, MSc, PhD, MCIOB, MRICS
School of Engineering and the Built Environment, University of Wolverhampton
Editorial Board
Editorial 1
Articles
Concurrent Delay: What is All the Fuss About?
Kim Rosenberg 3
Strength from Diversity: A Refined Proposal for Unifying Australian
Security of Payment Laws in Light of the Murray Review
Jeremy Coggins and Stephen Donohoe 19
Cases
Balfour Beatty Regional Construction Ltd v Grove Developments
Ltd 47
Beumer Group UK Ltd v Vinci Construction UK Ltd 68
Technology and Construction Law Reports
Ziggurat (Claremont Place) LLP v HCC International Insurance
Company Plc. T1
ISSN: 0267-2359
This journal should be cited as (2018) 34 Const. L.J. (followed by the page number).
The Construction Law Journal is published by Thomson Reuters, trading as Sweet &
Maxwell. Thomson Reuters is registered in England & Wales, Company No.1679046.
Registered Office and address for service: 5 Canada Square, Canary Wharf, London, E14
5AQ.
For further information on our products and services, visit
http://www.sweetandmaxwell.co.uk
Computerset by Sweet & Maxwell. Printed and bound in Great Britain by Hobbs the Printers
Ltd, Totton, Hampshire.
No natural forests were destroyed to make this product; only farmed timber was used and
replanted.
Each article and case commentary in this issue has been allocated keywords from the Legal
Taxonomy utilised by Sweet & Maxwell to provide a standardised way of describing legal
concepts. These keywords are identical to those used in Westlaw UK and have been used
for many years in other publications such as Legal Journals Index. The keywords provide
a means of identifying similar concepts in other Sweet & Maxwell publications and online
services to which keywords from the Legal Taxonomy have been applied. Keywords follow
the Taxonomy logo at the beginning of each item. The index has also been prepared using
Sweet & Maxwell’s Legal Taxonomy. Main index entries conform to keywords provided
by the Legal Taxonomy except where references to specific documents or non-standard
terms (denoted by quotation marks) have been included. Readers may find some minor
differences between terms used in the text and those which appear in the index. Please send
any suggestions to sweetandmaxwell.taxonomy@tr.com.
Crown copyright material is reproduced with the permission of the Controller of HMSO
and the Queen’s Printer for Scotland.
All rights reserved. No part of this publication may be reproduced or transmitted in any
form or by any means, or stored in any retrieval system of any nature without prior written
permission, except for permitted fair dealing under the Copyright, Designs and Patents Act
1988, or in accordance with the terms of a licence issued by the Copyright Licensing Agency
in respect of photocopying and/or reprographic reproduction. Application for permission
for other use of copyright material including permission to reproduce extracts in other
published works should be made to the publishers. Full acknowledgement of the author,
publisher and source must be given.
Thomson Reuters, the Thomson Reuters Logo and Sweet & Maxwell ® are trademarks of
Thomson Reuters.
Subscriptions £1,422 post free (£1,808 with Bound Volume Service).
Concessionary rate available for members of Committee T.-International Construction
Contracts, I.B.A. (Section on Business Law).
Orders by email to: TRLUKI.orders@thomsonreuters.com.
The Construction Law Journal is tailored for the needs of lawyers, architects, engineers,
surveyors and company officers who require a forum to which they and members of other
professions with an interest in the construction industry can turn for guidance, comment
and informed debate. The Journal will continue, as one of the leading publications in its
field, to provide expert articles, case notes and commentary on all aspects of construction
law. From 2007 the Construction Law Journal was peer reviewed.
In the Technology and Construction Law Report we include Coulson J’s decision
in Ziggurat (Claremont Place) LLP v HCC International Insurance Company plc.
The claimant employer had the benefit of a performance bond from the defendant
guarantor. The bond was a standard Association of British Insurers’ Model Form
which had been amended. The employer terminated their building contract for
lack of progress. The works were completed by others, following which the
employer demanded payment first from the by then insolvent contractor and then
the guarantor. The learned judge decided the employer was entitled to payment
under the bond. The judgment includes reference to Perar BV v General Surety
and Guarantee Co Ltd, and our commentator reviews Perar and related authorities.
*
Kim Rosenberg
Comparative law; Concurrent causes; Construction disputes; Delay
Introduction
Concurrent delay is a topic that evokes passion amongst members of the
construction law community, yet it is an often misunderstood concept. The question
of how concurrent delay is defined is frequently forgotten in favour of debate
around how it should be treated. Concurrent delay is rare, meaning that angst over
its treatment is often a futile exercise. Concurrency gains so much attention, despite
its infrequency, because decision makers at recipients of delay-related claims may
be nervous about accepting such claims absent clarity on whether concurrency
exists. This nervousness arises because of the treatment of concurrent delay:
depending upon the jurisdiction, concurrency can, at least in part, eradicate
responsibility for an extension of time, liquidated damages and/or prolongation
costs.
This paper addresses two key questions regarding concurrent delay.
1) What is it?
2) How is it treated?
These questions cannot be answered in isolation from the relevant governing law
(and the contract if that expressly deals with concurrent delay, although this is rare
with many standard form contracts).2 As a result, the answers to these questions
may be different depending upon the jurisdiction.
To illustrate this point, this paper provides a comparative law overview on the
second question regarding treatment of concurrent delay in various jurisdictions.
This firstly covers the position in England/ Wales and Scotland, where this issue
has received attention (albeit more so from commentators than courts). That is
followed by a consideration of the principles in other common law jurisdictions,
namely the US, Canada, Hong Kong and Australia. Next, this paper provides an
overview of the principles favoured by the courts in civil law jurisdictions, including
Switzerland, Germany, France, Turkey, Egypt, the United Arab Emirates (UAE)
and Qatar (as well as Shari’a-based systems such as Saudi Arabia), where there is
limited (if any) judicial authority on the specific issue of concurrent delay.
1
This paper was first presented at the Istanbul International Construction Law conference in April 2017 (https:/
/construction-law.bilgi.edu.tr/en/conferences/delays-in-international-construction/ [Accessed 9 January 2018]).
*
Kim Rosenberg is Counsel at Freshfields Bruckhaus Deringer LLP, based in Dubai. The author would like to
acknowledge the assistance of various colleagues at Freshfields Bruckhaus Deringer LLP in the production of this
paper, in particular Oliver Sangster, Amr Omran and Patricia Snell.
2
FIDIC standard form contracts do not expressly address concurrent delay, whereas many Australian standard
form contracts do (such as AS 2124-1992, AS 4300-1995, AS 4000-1997 and AS 4902-2000).
3
This definition is consistent with that contained in Guidance Section 10, UK Society of Construction Law, “Delay
and Disruption Protocol”, 2nd edn (February 2017). In the interest of full disclosure, it should be noted that the author
chaired the drafting committee of the Second Edition of the Protocol. This is also the position taken most recently
by the English courts: Saga Cruises BDF Ltd v Fincantieri SPA [2016] EWHC 1875 (Comm); 167 Con. L.R. 29 and
North Midland Building Ltd v Cyden Homes Ltd [2017] EWHC 2414 (TCC); [2017] B.L.R. 605; 174 Con. L.R. 1 at
[23]–[29].
4
Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm); [2011] B.L.R. 384; 136 Con. L.R. 190 at
[277]; Walter Lilly & Co Ltd v Mackay [2012] EWHC 1773 (TCC); [2012] B.L.R. 503; 143 Con. L.R. 79 and [2012]
EWHC 1972 (TCC); 143 Con. L.R. 79; [2012] 6 Costs L.O. 862 at [370]; Galoo Ltd v Bright Grahame Murray
[1994] 1 W.L.R. 1360; [1995] 1 All E.R. 16 at 29; [1994] B.C.C. 319.
5
See A. Al-Sanhouri, Al-Wasit Commentary on the Civil Code: Part I—The Sources of Obligations (2010),
pp.832–833.
Therefore, at least under English law, the mere overlapping of the effects of two
delay events is not sufficient. Both events must cause critical delay. The following
simple bar charts show example scenarios to illustrate that point (note that these
bar charts show the effect of the relevant delay events as opposed to the occurrence
of the events themselves).6
Figure 1
Figure 2
6
These scenarios are based upon the example given in para.10.7 of the UK Society of Construction Law, “Delay
and Disruption Protocol”, 2nd edn (2017).
Figure 3
It is only the third of the above example scenarios where there is concurrent
delay. In the first two examples, there is none, but rather there is one event that is
solely causing critical delay at the relevant times.
In summary, concurrent delay (that is relevant to the allocation of responsibility
between the employer and the contractor) exists when the following criteria are
met7:
1) at least two delay events occur—one the contractual responsibility
of the employer and the other the contractual responsibility of the
contractor;
2) the effects of both delay events either start or end at the same time;
and
3) completion is or will be delayed because of those delay effects—i.e.
both events affect the activities on the critical path.
As to the second point, given the less rigid approach to causation in civil law
jurisdictions, there may be more flexibility around the requirement that the effects
of both delay events start or end at the same time. However, if one event clearly
is not on the critical path because the other event is driving the completion date,
as a matter of causation, there is unlikely to be concurrent delay.
An analysis of the facts is crucial to identifying whether the above criteria have
been met. For anything other than a simple project, that will involve a programming
analysis. Modern programming tools allow the parties (and relevant decision
makers) to more readily distinguish between the effects of different delay events,
rather than assuming concurrency of effect.8 However, it is important to recognise
that a programming analysis, no matter how detailed the programme, can rarely
be precise down to even a few days.9 Therefore, a common sense approach ought
7
There is also the concept of “true concurrent delay” referred to in the UK Society of Construction Law, “Delay
and Disruption Protocol”, 2nd edn (2017). This is a sub-set of concurrent delay, which arises when, in addition to
these criteria, the relevant delay events occur at the same time (see para.10.3 of the Protocol).
8
Essex Electro Engineers v Danzig , 224 F 3d 1283 (Fed Circ 2000), as cited in J. Bidgood, “Cutting the Knot on
Concurrent Delay” (2008) Construction Briefings No 2008-2, pp 6-8; see also K. Pickavance, Delay and Disruption
in Construction Contracts, 3rd edn (London: Sweet & Maxwell, 2005), p.652: “The widespread use and acceptance
of the CPM programmes has, it might be argued, made it progressively easier for parties to differentiate between the
impacts on programmes of individual events and thereby determine the appropriate entitlement.”
9
See para.10.11 of the UK Society of Construction Law, “Delay and Disruption Protocol”, 2nd edn (2017).
to be taken in identifying the start and end dates of the effects of delay events and,
therefore, whether there is concurrent delay.
10
Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd (1999) 70 Con. L.R. 32.
11
Malmaison (1999) 70 Con. L.R. 32 at [13].
12
Royal Brompton Hospital NHS Trust v Hammond (No.7) [2001] EWCA Civ 206; 76 Con. L.R. 148 at [85];
Steria Ltd v Sigma Wireless Communications Ltd [2007] EWHC 3454 (TCC); [2008] B.L.R. 79; 118 Con. L.R. 177;
De Beers UK Ltd (formerly Diamond Trading Co Ltd) v Atos Origin IT Services UK Ltd [2010] EWHC 3276 (TCC);
[2011] B.L.R. 274; 134 Con. L.R. 151; Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm); [2011]
B.L.R. 384; 136 Con. L.R. 190 and Walter Lilly [2012] EWHC 1773 (TCC); [2012] B.L.R. 503; 143 Con. L.R. 79.
13
Steria [2008] B.L.R. 79; 118 Con. L.R. 177 at [130].
14
The Hon Sir Vivian Ramsey and Stephen Furst, QC (eds), Keating on Construction Contracts, 8th edn (London:
Sweet & Maxwell, 2006), p.275. The quotation also appears in substantively similar form in the current 10th edn:
The Hon Sir Vivian Ramsey and Stephen Furst, QC (eds), Keating on Construction Contracts, 10th edn (London:
Sweet & Maxwell, 2016), p.238.
15
J. Marrin QC, “Concurrent Delay Revisited” (2013) SCL, pp.16–17.
16
Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No.2) [2007] EWHC 447 (TCC); [2007]
B.L.R. 195; 111 Con. L.R. 78 at [47].
Case law subsequent to Malmaison and Steria, however, casts doubt on the first
point above. In Jerram Falkus17 the English court concluded that, on the question
of time, the prevention principle is not triggered where there is concurrent delay
in the sense described in the previous section of this article.18 Rather, a better
rationale for the proposition that the contractor is entitled to “time but not money”
may be the application of the “but for” causation test in response to a claim for
monetary compensation: a claimant (whether the contractor or the employer) should
not recover compensation where there is concurrent delay because the claimant
would have suffered the loss even absent the respondent’s offending act or
omission. That means that, where there is concurrent delay, the contractor should
not recover prolongation costs and the employer should not recover liquidated
damages. The only way to prevent the employer recovering liquidated damages
is for the contractor to be given an extension of time, thereby achieving the outcome
of “time but not money” for the contractor where there is concurrent delay.
As an alternative, some commentators have suggested that apportionment
between the relevant delay events may exist under English law amongst other
methods of assessment.19 However, this was firmly rejected by the English court
in the first instance decision of Walter Lilly20:
“In any event, I am clearly of the view that, where there is an extension of
time clause such as that agreed upon in this case and where delay is caused
by two or more effective causes, one of which entitles the Contractor to an
extension of time as being a Relevant Event, the Contractor is entitled to a
full extension of time. … The fact that the Architect has to award a ‘fair and
reasonable’ extension does not imply that there should be some apportionment
in the case of concurrent delays. The test is primarily a causation one”.
Therefore, as a matter of English law, the contractor is entitled to an extension of
time for the full period of any concurrent delay.
There is less judicial authority regarding the treatment of the contractor’s
prolongation costs claims when there is concurrent delay. The UK Society of
Construction Law Delay and Disruption Protocol (the SCL Protocol) provides that
for periods of concurrency the contractor is not entitled to recover prolongation
costs, except to the extent it can separately account for the costs of the employer
delay event that would not have otherwise been incurred as a result of the contractor
delay event (e.g. the costs of the variation itself, but not the prolongation costs for
the period of (concurrent) delay arising from the variation instruction).21 This
guidance framed the approach taken by the industry to prolongation costs in periods
of concurrent delay—i.e. time but not money. The English courts have subsequently
17
Jerram Falkus Construction Ltd v Fenice Investments Inc (No.4) [2011] EWHC 1935 (TCC); [2011] B.L.R.
644; 138 Con. L.R. 21.
18
Jerram Falkus [2011] B.L.R. 644; 138 Con. L.R. 21 at [52], in support of Adyard Abu Dhabi [2011] B.L.R. 384;
136 Con. L.R. 190. See also North Midland Building [2017] B.L.R. 605; 174 Con. L.R. 1 at [23]–[29], approving
these cases obiter.
19
M. Cocklin, “International Approaches to the Legal Analysis of Concurrent Delay: Is there a Solution for English
Law?”(April 2013) SCL, p.8.
20
Walter Lilly [2012] EWHC 1773 (TCC); [2012] B.L.R. 503; 143 Con. L.R. 79 at [370].
21
Section 1.10 of the UK Society of Construction Law, “Delay and Disruption Protocol”, 1st edn (October 2002),
which is materially the same in s.14 of the 2nd edn (2017).
Scotland
The Scottish approach to concurrency represents a marked contrast to the English
approach, in that the courts apportion liability as between the relevant events where
there is concurrent delay. This approach was first advanced in John Doyle
Construction, where the court determined that apportionment may be appropriate
in cases of concurrency based on the evidence and carried out on a basis that is
reasonable in all the circumstances23:
“During the period when both [delay events] operated [i.e. there is concurrent
delay], we are of the opinion that each should normally be treated as
contributing to the loss, with the result that the employer is responsible for
only the part of the delay during that period. Unless there are special reasons
to the contrary, responsibility during that period should probably be divided
on an equal basis, at least where the concurrent cause is not the contractor’s
responsibility”.24
In City Inn, the court endorsed this approach so that, where two causes are
operative, the decision-maker may apportion the period of concurrent delay between
the relevant contractor event and the employer event.25 This decision was upheld
on appeal:
“In such a situation, which could, as a matter of language, be described as
one of concurrent causes, in a broad sense (see para. [48] infra), it will be
open to the decision-maker, whether the architect, or other tribunal,
approaching the issue in a fair and reasonable way, to apportion the delay in
the completion of the works occasioned thereby as between the relevant event
and the other event. In that connection, it must be recognised that the
background to the decision making, in particular, the possibility of a claim
for liquidated damages, as opposed to one for extension of time, must be
borne in mind and approached in a fair and reasonable manner.”26
The Scott law approach of apportioning responsibility for concurrent delay adopts
a rationale similar to the apportionment of liability on account of contributory
negligence, i.e. based on considerations of culpability and causative potency.27
22
De Beers UK [2011] B.L.R. 274; 134 Con. L.R. 151at [177]. This approach is also recognised by other
commentators, for example: Ramsey and Furst (eds), Keating on Construction Contracts, 9th edn (2016), pp.295 and
302.
23
John Doyle Construction Ltd v Laing Management (Scotland) Ltd 2004 SC 713 (Court of Session, Inner House);
2004 S.C.L.R. 872; [2004] B.L.R. 295 at [18] and [19].
24
John Doyle Construction , 2004 SC 713 (Court of Session, Inner House); 2004 S.C.L.R. 872; [2004] B.L.R. 295
at [16].
25
City Inn Ltd v Shepherd Construction Ltd [2007] CSOH 190; [2008] B.L.R. 269; (2008) 24 Const. L.J. 590 at
[167].
26
City Inn Ltd v Shepherd Construction Ltd [2010] CSIH 68 (Court of Session, Inner House); 2011 S.C. 127; 2011
S.C.L.R. 70 at [42].
27
N. Dennys (ed.), Hudson’s Building and Engineering Contracts, 13th edn (London: Sweet & Maxwell, 2015),
p.790; John Doyle Construction Ltd v Laing Management (Scotland) Ltd 2004 S.C. 713 (Court of Session, Inner
House); 2004 S.C.L.R. 872; [2004] B.L.R. 295 at [17]: “This procedure does not, however, seem to us to be
fundamentally different in nature from that used in relation to contributory negligence or contribution among
wrongdoers”.
US
As a general proposition,28 in the US, where concurrent delay arises, the contractor
is entitled to an extension of time for the full period of concurrent delay (and so
the employer is not entitled to liquidated damages), but the contractor is not entitled
to prolongation costs—i.e. time but not money.29 Essentially, neither party can
benefit monetarily from periods of concurrent delay.30 There is no provision for
the courts to engage in apportionment between the different delay events.
Concurrent delay has been described by commentators in the US as a risk allocation
principle to distribute the costs associated with contemporaneous delays on a status
quo basis—with each responsible party bearing its own costs for periods of
concurrent delay.31
Canada
There is a dearth of Canadian commentary and jurisprudence on concurrent delay,
however the Canadian position may be described as a hybrid time-and-cost
procedure. The contractor will be entitled to an extension of time for the full period
of concurrent delay (and so the employer has no entitlement to liquidated damages).
As to prolongation costs, there is a low evidentiary threshold borne by the contractor
in identifying the costs attributable to the employer delay event. As a result, there
is likely to be “an almost indistinguishable exercise of apportionment” when it
comes to prolongation costs.32 One of the rationales for this approach is an extension
of the concept of “contributory negligence” to contractual claims, which some
commentators suggest is evident in the courts in certain provinces.33 Also relevant
to the treatment of concurrent delay in Canada is that the courts exercise a flexible
discretion and apply a “broad brush” or “do the best it can” approach when it
comes to assessing quantum.34 The upshot is that where concurrent delay arises,
the contractor will be entitled to an extension of time for the full period and, likely,
will recover some of its prolongation costs.35
Hong Kong
Concurrent delay is not well-defined in Hong Kong jurisprudence, though the
English approach has traditionally been favoured by commentators, with the SCL
28
Bearing in mind the differing jurisdictions within the US, both among different States and at the federal level.
29
Dennys (ed.), Hudson’s Building and Engineering Contracts, 13th edition (2015), pp.791–792; See RP Wallace,
Inc v US , 63 Fed Cl 401, 410–411 (2004) and also P. O’Connor and P. Bruner, Bruner & O’Connor on Construction
Law (Thomson Reuters, 2016), section 15-67.
30
See Pittman Construction Co, Inc v US , 2 Cl Ct 211 (1983) at [217]: Settled law dictates that, where both parties
contribute to the delay, “neither can recover damage, unless there is in the proof a clear apportionment of the delay
and the expense attributable to each party”.
31
O’Connor and Bruner, Bruner & O’Connor on Construction Law (2016), section 7-195.
32
Dennys (ed.), Hudson’s Building and Engineering Contracts, 13th edn (2015), p.792.
33
M. Cocklin, “International Approaches to the Legal Analysis of Concurrent Delay: Is There a Solution for English
Law?” (April 2013) SCL, p.12.
34
Wood v Grand Valley Railway (1915) 51 SCR 283 (SCC), cited by Cocklin, “International Approaches to the
Legal Analysis of Concurrent Delay: Is There a Solution for English Law?” (April 2013) SCL, p.12; See also A.
Stephenson, “Concurrency Causation Common Sense and Compensation” (2010) 13 Journal of the Canadian College
of Construction Lawyers.
35
G. Grenier, “Evaluating Concurrent Delay—Unscrambling the Egg” (2006) Construction Law Reports, 4.
Protocol being recognised by the industry in Hong Kong.36 However, the first
instance decision in W Hing Construction, in which the court expressly agreed
with the apportionment approach in the Scottish case of City Inn, suggests a shift
of approach in this jurisdiction.37
Australia
Commentators suggest that the position under Australian law reflects that under
English law.38 However, there is limited case law on this topic. This is because
many Australian standard form contracts expressly deal with concurrent delay—and
do so in a manner different from the English approach.39 For those contracts, it is
unnecessary to have regard to the position at law. Instead, the contractual position
prevails.
36
Cocklin, “International Approaches to the Legal Analysis of Concurrent Delay: Is There a Solution for English
Law?” (2013) SCL, p.13. The Protocol’s recommended approach to concurrent delay accords with the position in
England and Wales described above.
37
W Hing Construction Co Ltd v Boost Investments Ltd [2009] 2 HKLRD 501 at [61].
38
Dennys (ed.), Hudson’s Building and Engineering Contracts, 13th edn (2015), p.791.
39
Clause 35.3 of AS 2124-1992 that dictates the contractor has no entitlement to an extension of time for periods
of concurrent delay and clause 34.4 of AS 4000-1997 and AS 4902-2000 provides for apportionment in the event of
concurrent delay.
40
J. Bell, Principles of French Law, 2nd edn (OUP, 2008), p.410.
41
See M. Grose, Construction Law in the United Arab Emirates and the Gulf, 1st edn (Wiley-Blackwell, 2016),
p.133.
Switzerland
There is no clearly prescribed or clear-cut position on dealing with concurrent
delay under Swiss law (and it is unusual for Swiss construction contracts to
expressly deal with this issue). That said, commentators suggest that there appears
to be a tendency by the Swiss courts to follow the “time but not money” approach,
however this will depend on the circumstances of the case.42 An argument remains
though that a form of nuanced apportionment should apply based on general
contractual law principles applicable to the reduction of damages and the
apportionment of liability under art.44(1) of the Swiss Code of Obligations.43
Germany
There is no clear position as to how the German courts will address the treatment
of concurrent delay as the concept is not expressly dealt with in the German Civil
Code (BGB). Commentators suggest that the contractor will be entitled to an
extension of time for the full period of concurrent delay (or “parallel hindrances”).44
On the question of prolongation costs, the courts have a broad discretion (“free
discretion” or “free belief”) when assessing quantum pursuant to s.287 of the BGB.
Despite this, commentators suggest that German courts are unlikely to award
prolongation costs to the contractor for periods of concurrent delay.45 However,
like other civil law jurisdictions, the argument remains that the courts can rely on
the principle of contributory fault (s.254 of the BGB) to apportion liability between
the parties.
France
Similarly to the position in Switzerland and Germany, the French Civil Code does
not address concurrent delay, there is no clear judicial authority and there is no
uniformly-accepted view among practitioners regarding the treatment of concurrent
delay. It is possible that the French courts would apportion liability as between
the employer and the contractor delay events.46 This approach would be premised
on the requirement of good faith in the performance of the contract, as provided
under art.1104 of the French Civil Code47 and the principle of full compensation
(réparation intégrale) as enshrined in arts 1231–2 of the French Civil Code,48
42
N. Voser, “Construction Arbitration 2016: Switzerland (2016)” GAR Know-How.
43
Article 44(1) of the Federal Act on the Amendment of the Swiss Civil Code (Part Five: The Code of Obligations)
of 30 March 1911 (Status as of 1 January 2016): “Where the injured party consented to the action which caused the
loss or damage or circumstances attributable to him helped give rise to or compound the loss or damage or otherwise
exacerbated the position of the party liable for it, the court may reduce the compensation due or even dispense with
it entirely”.
44
The courts must justify this approach under the German good faith obligation, s.242 of the BGB. See C. Ennis,
“Claims for Extensions of Time and Compensation under the FIDIC Red Book: Civil Law and Common Law
Approaches Compared” (October 2013) SCL, pp.6–7.
45
See Ennis, “Claims for Extensions of Time and Compensation under the FIDIC Red Book: Civil Law and
Common Law Approaches Compared” (2013) SCL, p.5; see also S. Osing, “Time and Acceleration Issues Affecting
International Construction Contracts: The German Approach” (2010) International Construction Law Review 282–283.
46
P. Rosher and F. Gillion, “Construction Arbitration 2016: France (2016)” GAR Know-How.
47
Article 1104 of the French Civil Code (consolidated version as of 2 March 2017); Bell, Principles of French
Law, 2nd edn (2008), p.333 (referring to art.1134 under an earlier version of the Code). Other civil law jurisdictions,
such as Italy, similarly proceed on the basis of apportionment of liability and proportional valuation of damages when
faced with concurrent delay where the damage quantification cannot be shown: See L. Di Paola, “Concurrent Delays”
(2006) International Construction Law Review 384.
48
Article 1231-2 of the French Civil Code (consolidated version as of 2 March 2017).
whereby a party is “compensated for the loss he has suffered—no more and no
less—and for the gain of which he has been deprived”.49
Turkey
While the recently enacted Turkish Code of Obligation50 applies to construction
contracts51 it makes no explicit reference to concurrent delay and there is no Turkish
case law that deals with this topic. However, given the Turkish Code of Obligations
is modelled on the Swiss Code of Obligations, Swiss jurisprudence and commentary
on this topic will be persuasive.52 As indicated above, though, there is a paucity of
guidance from Switzerland. Nonetheless, the same leaning towards “time but not
money” may be accepted under Turkish law. Of course, like Switzerland, there
are arguments available for apportionment under the Turkish Code of Obligations
based on the following articles53:
1) Article 51(1):
the judge determines the nature and the amount of the compensation
taking particular account of the degree of fault54;
2) Article 52:
regarding the reduction of damages:
“Where the injured person consented to the action which caused
the damage or circumstances attributable to him helped give
rise to or compound the damage or otherwise exacerbated the
position of the person liable for it, the judge may reduce the
compensation due or even dispense with it entirely”.55
Egypt
The Egyptian Civil Code does not address concurrent delay and there is no judicial
authority or persuasive commentary on this topic. Like French law, the Egyptian
Civil Code emphasises the importance of observing good faith in carrying out
contractual obligations,56 which might support an argument for an extension of
time for full periods of concurrent delay. An argument for apportionment, in
contrast, could be developed based on the principle of “full compensation”,57 along
49
G. Bermann and E. Picard (eds), Introduction to French Law, 1st edn (Kluwer Law International, 2008), p.235
(referring to art.1149 under an earlier version of the Code).
50
Entered into effect on 1 July 2012.
51
Z. Akinci, Arbitration Law of Turkey: Practice and Procedure, 1st edn (Juris, 2011), p.248.
52
See Ennis, “Claims for Extensions of Time and Compensation under the FIDIC Red Book: Civil Law and
Common Law Approaches Compared” (2013) SCL, pp.2–5.
53
E. Buyksagis, “The New Turkish Tort Law” (2012) 3 Journal of European Tort Law 44, 62; see T. Ansay,
Introduction to Turkish Law, 3rd edn (Singer, 1987), pp.200–201; Turkey: Construction & Engineering Law (2016)
International Comparative Law Guide.
54
Translation provided by: E. Buyksagis, “The New Turkish Tort Law” (2012) 3 Journal of European Tort Law
44, 90.
55
Translation provided by: Buyksagis, “The New Turkish Tort Law” (2012) 3 Journal of European Tort Law 44,
91.
56
Article 148(1) of the Egyptian Civil Code, Law No.131 of 1948 (as amended): “A contract must be performed
in accordance with its provisions and in compliance with the requirements of good faith”.
57
Article 221(1) of the Egyptian Civil Code, Law No.131 of 1948 (as amended): “The judge shall assess the amount
of damages, if it has not been fixed in the contract or by a provision of law. Damages include compensation for losses
with art.216 of the Egyptian Civil Code, pursuant to which the judge retains a
discretionary power to either reduce or refuse to award any damages to the injured
party if it had contributed, through its own fault, to the occurrence or increase of
the harm.58
Furthermore, on the question of liquidated damages, where there is concurrent
delay, liquidated damages could be reduced under Egyptian law if the judge is
satisfied that:
1) the agreed amount is “greatly exaggerated” in comparison to the
actual harm sustained by the creditor (the employer); or
2) the original obligation has been partially performed.59
In fact, the debtor (the contractor) may succeed in denying the creditor’s claim to
liquidated damages altogether if it is able to prove that the creditor has suffered
no harm as a result of the breach.60 These provisions may be relied on by a
contractor to support an argument that it ought not be liable for liquidated damages
for periods of concurrent delay given the employer was itself responsible for an
event that caused that delay.
incurred by the creditor and profits foregone, provided that they are the natural result of the failure to perform the
obligation or the delay in such performance. The harm shall be considered a natural result if the creditor is unable to
avoid it by exerting reasonable efforts”.
58
Article 216 of the Egyptian Civil Code, Law No.131 of 1948 (as amended): “The judge may reduce the amount
of damages or award no damages if the creditor, through his own fault, contributed to the occurrence of the harm, or
increased it”.
59
Article 224(2) of the Egyptian Civil Code, Law No.131 of 1948 (as amended): “The judge may reduce the amount
of damages if the debtor proves that the amount fixed [by agreement] was greatly exaggerated, or that the original
obligation has been partially performed”.
60
Article 224(1) of the Egyptian Civil Code, Law No.131 of 1948 (as amended): “Damages fixed by agreement
are not due if the debtor proves that the creditor has suffered no harm”.
61
Articles 296 and 383(2) of the UAE Civil Code, Law No.5 of 1985 (as amended).
62
Grose, Construction Law in the United Arab Emirates and the Gulf, 1st edn (2016), p.131.
1. Article 290 (which is found in the tort section of the UAE Civil
Code but has been found to have application in the context of a
contract claim)63:
if the employer contributes to the occurrence of the harm, the judge
may take into account the level of involvement of the injured party
when assessing compensation, and may reduce or deny compensation
in accordance with the degree of its contribution;
2. Article 246(1):
enshrining the duty of good faith in the performance of a contract;
and
3. Article 106:
sets out the criteria for the unlawful exercise of a right.
However, equally, an argument in favour of an extension of time for the full period
of concurrent delay can be developed based on the same provisions of the UAE
Civil Code.
It is also worth noting that, on the question of liquidated damages, the courts
retain a power to revise the specified amount upwards or downwards pursuant to
art.390(2) of the UAE Civil Code. The court has full discretion to ensure that
compensation reflects the actual loss,64 and this provision may be relied on to adjust
the liquidated damages down where there is concurrent delay.
Qatar
Again, there is no provision for concurrent delay in the Qatari Civil Code. Because
the Qatari Civil Code is closely aligned with its Egyptian counterpart, the same
arguments available in Egypt and the UAE for the treatment of concurrent delay
are likely to apply in Qatar. Indeed art.257 of the Qatari Civil Code regarding
reduction of compensation due to the claimant’s contribution to harm65 is almost
word-for-word the same as art.216 of the Egyptian Civil Code as referred to above.
Similarly, the provisions on liquidated damages in the Egyptian Civil Code have
been reproduced almost verbatim in the Qatari Civil Code.66
Saudi Arabia
The Kingdom of Saudi Arabia is one of few countries in the world to embrace a
legal system derived almost solely from the Islamic Shari’a.67 Saudi Arabia has
not promulgated a civil code, and there are no codified rules in other laws that
63
See, e.g., UAE Union Supreme Court, Petitions Nos 1 and 28 of JY26 (Shar’i), 27 June 2005 (explaining that
the rule on contributory fault in art.290 of the UAE Civil Code applies equally to both contractual and tort liability,
because the rationale for applying it under either theory is the same).
64
Grose, Construction Law in the United Arab Emirates and the Gulf, 1st edn (2016), p.139.
65
Article 257 of the Qatari Civil Code, Law No.22 of 2004 on issuing the Civil Code: “The court may reduce the
amount of damages or award no damages if the creditor, through his own fault, contributed to the occurrence of the
harm, or increased it”.
66
Articles 224 and 225 of the Egyptian Civil Code are almost identical to arts 266 and 267 of the Qatari Civil
Code.
67
Articles 1 and 23 of the Basic Law of Governance, Royal Order No. (A/91) 27 Sha’ban 1412H (1 March 1992),
published in Umm al-Qura Gazette No 3397, 2 Ramadan 1412H (5 March 1992).
Conclusion
The title of this paper queries the fuss about concurrent delay. This is a fair question
given the infrequency of concurrent delay:
• modern programming tools can more readily distinguish between
the effects of different delay events;
• that, coupled with the definition of concurrent delay, namely when
two or more delay events cause completion to be later than it would
have been, demonstrates that concurrent delay is factually rare (albeit
principles of causation vary across jurisdictions, which will impact
the identification of concurrent delay);
• as is evident from the comparative overview of the treatment of
concurrent delay in various jurisdictions, there is hardly an abundance
of cases on this topic; and
• in civil law jurisdictions, concurrent delay is not addressed in the
civil codes and there is scant judicial authority.
That landscape should serve as a significant flag that concurrency is not a usual
feature of construction projects that are in delay. Yet this is an issue that has arisen
in every construction dispute in which the author has been involved, across multiple
jurisdictions, only for the court or the tribunal to usually determine there was no
concurrent delay. Project participants should recognise this situation before
over-emphasising the topic of concurrent delay.
On the rare occasion when concurrent delay does arise, there is no uniform
approach to its treatment across jurisdictions. In fact in many legal systems,
particularly civil law jurisdictions, there is no authority at all regarding concurrent
delay. This creates uncertainty for project participants, particularly given the
differing outcomes on entitlement for extensions of time, liquidated damages and
prolongation costs.
To conclude, below is a summary of the position on the treatment of concurrent
delay in each of the jurisdictions addressed by this paper. As indicated above, if
the relevant contract addresses concurrent delay, that will prevail over the position
at law.
Figure 4
Jurisdiction Treatment of Concurrent Delay
England and Wales Contractor gets time but not money. No liquidated damages for employer.
Scotland Apportionment on time and money.
US Contractor gets time but not money. No liquidated damages for employer.
Canada Contractor gets time and probably some money (depending on the facts).
No liquidated damages for employer.
Hong Kong Traditionally, followed English approach of time but not money. Apportion-
ment may be possible.
Australia Limited case law, but possibly English approach of time but not money.
Switzerland Unclear; arguments can be made either way, but possibly time but not
money depending on the facts.
Germany Unclear; arguments can be made either way, but possibly time but not
money depending on the facts.
France Unclear; arguments can be made either way, but possibly apportionment
depending on the facts.
Turkey Unclear; arguments can be made either way, but possibly time but not
money depending on the facts (in following Switzerland).
Egypt Unclear; arguments can be made either way, but possibly apportionment
depending on the facts.
United Arab Emirates Unclear; arguments can be made either way, but possibly apportionment
depending on the facts.
Qatar Unclear; arguments can be made either way, but possibly apportionment
depending on the facts.
Saudi Arabia Unclear; arguments can be made either way, but possibly apportionment
depending on the facts.
*
Jeremy Coggins
**
Stephen Donohoe
Australia; Comparative law; Construction contracts; Harmonisation; Payments;
Statutory adjudication
I. Introduction
Over the past 20 years, building and construction industry security of payment
legislation (“the legislation”) has come into force in several Commonwealth
jurisdictions.2 In Australia, the first jurisdiction to pass such legislation was New
South Wales (NSW). The NSW Act formed the model upon which most other
Australian jurisdictions, to varying degrees, progressively based their legislation
culminating in the Tasmanian Act which received Royal Assent on 17 December
2009. The consequence of this piecemeal, jurisdiction-by-jurisdiction, approach
to enacting the legislation throughout Australia has been diversity between the
various jurisdictions. Such inconsistency is particularly marked, with respect to
the underlying conceptual frameworks and detail of the drafting, between the
Western Australia (WA) and Northern Territory (NT) Acts on the one hand which
more closely resemble the construction industry payment legislation in the UK
and New Zealand (NZ), and the other Australian Acts on the other which are more
closely modelled on the NSW Act. In recognition that the Australian Acts may be
broadly categorised into one of two models, the WA and NT Acts are widely
referred to as the “West Coast model” (WCM) legislation as opposed to the “East
Coast model” (ECM) tag given to the other Australian Acts. With the ECM
1
This article is dedicated to the memory of the late Dr Stephen Donohoe.
*
BSc (Hons), LLM, Grad Cert BCLaw, PhD in Law (Adelaide); Senior Lecturer, School of Natural and Built
Environments, University of South Australia.
**
BSc, LLB, MSc, EdD, LLM, PhD; Associate Professor, School of Architecture, Design and Environment,
University of Plymouth.
2
Pt II of The Housing Grants, Construction and Regeneration Act 1996 (the UK Act); Building and Construction
Industry Security of Payment Act 1999 (the NSW Act); Building and Construction Industry Security of Payment Act
2002 (the Vic Act); Construction Contracts Act 2002 (the NZ Act); Building and Construction Industry Payments
Act 2004 (the Qld Act); Construction Contracts Act 2004 (the WA Act); Building and Construction Industry Security
of Payment Act 2004 (the Singaporean Act); Construction Contracts (Security of Payments) Act 2004 (the NT Act);
Construction Contracts Act 2004 (The Isle of Man Act); Building and Construction Industry Security of Payment
Act 2009 (the Tasmanian Act); Building and Construction Industry Security of Payment Act 2009 (the Australian
Capital Territory Act); Building and Construction Industry Security of Payment Act 2009 (the South Australian Act);
Construction Industry Payment and Adjudication Act 2012 (the Malaysian Act); Construction Contracts Act 2013
(the Irish Act).
legislation having been in operation for some 18 years and the WCM legislation
for some 13 years, the Australian jurisdictions have collectively amassed a wealth
of experience and adjudication usage data with respect to these two legislative
approaches to security of payment in the building and construction industry.
A common objective of all of the legislation is the eradication of unfair
contractual provisions and practices with regards to payment in order to get cash
flowing in as fair a manner as possible down the hierarchical contractual chains
that exist on most commercial construction projects. A central feature of all the
legislation is the provision for a rapid statutory adjudication scheme, designed to
facilitate quick and inexpensive resolution of contractual payment disputes in the
construction industry. The key differences between the East and West Coast models
have been broadly summarised by Coggins, Fenwick Elliott and Bell3 as follows.
• The ECM Acts provide a detailed statutory payments regime,
overriding any inconsistent contractual provisions, which parties
undertaking “construction work” or “related goods and services”
may choose to engage by submitting a payment claim under the Act
at regular intervals and have it responded to within a certain
timeframe. Conversely, the WCM Acts largely preserve (rather than
override) the parties’ contractual interim payment regimes.
• The ECM Acts only allow for payment claims to be made up the
“contractual stream” (typically by a subcontractor against its head
contractor, or head contractor against its principal). Conversely, the
WCM allows for payment claims both up and down the “contractual
stream”.
• Whilst both models allow for a statutory adjudication scheme to
determine, in the interim, disputed payment claims, they differ with
respect to adjudicator appointment, submissions which may be
considered by an adjudicator, and the approach which an adjudicator
is to adopt in order to arrive at his or her determination. In all of
these respects the East Coast Acts are more restrictive, disallowing
mutual agreement of an adjudicator, consideration of reasons for
withholding payment which have not been duly submitted in
accordance with the statutory payment scheme, and discouraging an
evaluative approach to adjudicators’ determinations.
Since enactment of the legislation in each of the eight Australian state and territory
jurisdictions came to pass, there have been several calls from commentators that
the legislation should be harmonised into a uniform national approach in order to
benefit the construction industry,4 echoing the recommendation of the Cole Royal
3
J. Coggins, R. Fenwick Elliott, and M. Bell, “Towards Harmonisation of Construction Industry Payment Legislation:
A Consideration of the Success Afforded by the East and West Coast Models in Australia”, (2010) 10(3) Australasian
Journal of Construction Economics & Building 15.
4
See, for example, I.H. Bailey, “Harmonisation or Reform of Legislation: Construction Industry and Dispute
Resolution.” Paper delivered at Construction Law Seminar, Melbourne Law School, 10 November 2009; T. Zhang,
“Why national legislation is required for the effective operation of the security of payment scheme”, (2009) 25(6)
Building and Construction Law 376; M. Bell and D. Vella, “From motley patchwork to security blanket: The challenge
of national uniformity in Australian ‘security of payment’ legislation” (2010) Australian Law Journal 84; J.K. Coggins,
“From disparity to harmonisation of construction industry payment legislation in Australia: a proposal for a dual
process of adjudication based upon Size of Progress payment claim” (2011) 11(2) Australasian Journal of Construction
Economics and Building 34–59.
Commission some 15 years ago.5 Towards the end of 2015, the Australian Senate
Economics References Committee report into insolvency in the Australian
construction industry6 made a recommendation to unify the building and
construction industry security of payment legislation by the enactment of a
Commonwealth act. This recommendation was heeded by the Turnbull
Commonwealth Government in December 2016 when it appointed John Murray
AM to conduct a review of security of payments laws in the building and
construction industry, which seeks to identify what measures can be taken to
overcome the current fragmented nature of the security of payment laws around
Australia.7
In his PhD thesis, completed in July 2012,8 the lead author of this article
proposed that unifying Commonwealth building and construction industry security
of payment legislation should be introduced on the basis of a dual process of
adjudication (“Coggins’ dual process proposal”). This proposal essentially
recommended the use of the ECM for “smaller” payment claims and the WCM
for “larger” payment claims. The proposal was derived from an analysis of the
contemporaneous dispute resolution and procedural justice literature, available
adjudication usage data, and judicial review activity with respect to adjudicators’
determinations in the various state courts. The proposal was, amongst other things,
founded upon the observation that the ECM legislation (as compared to the WCM)
was proving to be particularly well used and efficient for the resolution of smaller
payment claims (for which it was originally designed); and the WCM (as compared
to the ECM) was proving to be relatively well used, more economical (in terms
of adjudication fees) and more resilient to applications for judicial review with
respect to the determination of larger payment claims. In other words, it was found
that the enactment of diverse legislation in Australia appeared to have given rise
to a unique opportunity for a unified statute to capitalise on the best of both of the
existing East and West Coast models, with the strengths of each the models being
clearly identifiable through the review of the relevant literature and secondary
data.
Notably, under key reform to the Queensland Act that came into effect on 15
December 2014, a dual scheme for payment and adjudication was introduced into
the Queensland Act based upon size of payment claim.9 The Queensland dual
system establishes two types of payment claim: “standard payment claims” which
are claims up to $750,000 in value, and “complex payment claims” which are
claims greater than $750,000 in value. The Queensland dual scheme, however,
differs from Coggins’ dual process proposal in that it provides an ECM scheme,
5
T. Cole, Final Report of the Royal Commission into the Building and Construction Industry, Commonwealth of
Australia (2003).
6
Senate Economics References Committee, “‘I just want to be paid’—Insolvency in the Australian construction
industry”, Commonwealth of Australia, December 2015.
7
J. Murray, “Review of Security of Payments Laws: Issues Paper”, Department of Employment, Australian
Government, 2017, p.3.
8
J. Coggins, “A Proposal for Harmonisation of Security of Payment Legislation in the Australian Building and
Construction Industry”, 2012, PhD Thesis, Adelaide University.
9
The Qld Act is, at the time of writing, undergoing further key reform although the dual process is retained. The
Building Industry Fairness (Security of Payment) Bill 2017 is currently before the Qld Parliament. Amongst other
things, the bill provides for the mandatory use of project bank accounts on public sector construction contracts between
$1 million and $10 million, as well as some procedural changes to the ECM payment and adjudication mechanisms.
although with differing timescales being prescribed, for both standard and complex
payment claims.
Almost five years on from the publication of the lead author’s PhD thesis, the
publication of an Issues Paper, seeking submissions from stakeholders in the
legislation, by John Murray as part of his review into security of payments laws
has provided the impetus for the authors of this article to revisit Coggins’ dual
process proposal in light of the further developments and experience that has
accrued with respect to the security of payment legislation in the various Australian
jurisdictions, as well as some of the international jurisdictions. As such, the
following key issues raised by John Murray in his Issues Paper (the “Murray
Paper”) have been used as the basis for the structure of this article: two systems
under the one legislation; timeframes on key process steps; endorsement of payment
claims under the ECM; the process for appointment of adjudicators; quality of
adjudication decisions and adjudication for domestic construction.
This article initially presents an up-to-date analysis of adjudication usage and
judicial review data in Australia, which is subsequently used as evidence when
considering the key issues raised by the Murray Paper. Through the adoption of a
systematic and evidence-based approach to addressing the Murray Paper key issues,
the article revisits and refines Coggins’ 2012 unifying dual process proposal. The
article concludes that, conceptually, Coggins’ dual process proposal, refined in
light of a further five years of legislative experience, remains a viable option for
federal building and construction industry security of payment legislation in
Australia.
Adjudication applications
Usage of statutory adjudication in Australia is monitored by the relevant
administering government bodies in each jurisdiction.10 Most of these government
bodies have collated and published, to varying degrees of detail over varying
periods of time, statistical adjudication usage data. It is from these publications
that the data analysed in this section has been drawn.
A statistical analysis of the adjudication data in New South Wales (NSW),
Queensland (Qld), Victoria (Vic) and Western Australia (WA) shows that the
number of adjudication applications in NSW, Qld and Vic for smaller claims (less
than $25,000) is far higher by proportion than in WA—see Table 1.
10
NSW Fair Trading, Department of Finance and Services; Victorian Building Authority; Queensland Building
and Construction Commission; Building Commission, Department of Commerce (WA).
In 2014/15, 42 per cent of all payment claims adjudicated in NSW, 47 per cent
of all payment claims adjudicated in Qld, and 64 per cent of all payment claims
adjudicated in Vic were for less than $25,000. In WA for 2014/15, only 11 per
cent of all adjudicated payment claims lodged were for less than $25,000.
The low rate of adjudication usage for small claims in WA has been recognised
as an issue in the 2015 WA Evans Review,12 which the Review attributes to lack
of education of smaller contractors about the Act.
The data presented in Table 1 also shows that the number of adjudication
applications in WA for larger claims (more than $250,000) is far higher by
proportion than in NSW, Qld and Vic. Forty-nine per cent of all payment claims
adjudicated in WA in 2014/15 were in excess of $250,000, whereas over the same
period only 17 per cent of all payment claims adjudicated in NSW, 19 per cent of
all payment claims adjudicated in Qld, and 9 per cent of all payment claims
adjudicated in Vic were in excess of $250,000.
Adjudication fees
A comparison of adjudication fees between Qld, WA and NSW is shown in Table
2. The last year that the WA Building Commission published adjudication fees by
payment claim size was 2010/11 and, therefore, this is the last year in which a
comparison of adjudication fees by payment claim size can be made between the
relevant states. The first financial year that NSW Fair Trading published average
adjudication fees by claim size was 2011/12.
11
These include applications which were invalid, had a zero amount or were a superseded claim.
12
P. Evans, “Report on the Operation and Effectiveness of the Construction Contracts Act 2004 (WA)”, 2015,
p.31.
The data also shows that mean adjudication fees were significantly lower in
WA than in Qld and NSW for larger payment claims. For payment claims between
$100,000 and $249,999 the mean adjudication fee in WA is 56 per cent of that in
Qld, and 71 per cent of that in NSW. For payment claims over $250,000, the mean
adjudication fee in Qld is generally more than double, and in NSW around double,
of that in WA.
When compared to the 2010/11 and 2011/12 data, 2014/15 adjudication fees in
NSW and Qld (see Table 3) have decreased for claims in the ranges between $1
and $99,999 and, generally, increased slightly for claims in the ranges between
$250,000 and $499,999.
Table 3: Mean adjudication fees reported in Qld, Vic and NSW for 2014/15
Range of claims ($) Mean fees for adjudication ($)
Qld Vic NSW
2014/15 2014/15 2014/15
<5,000 624 525 697
5,000–9,999 950 1,093 986
10,000–24,999 1,503 1,496 1,493
25,000–39,999 2,953 2,075 2,259
40,000–99,999 4,021 3,909 3,177
13
2010/11 was the last year in which the WA Building Commission published adjudication fees by payment claim
size.
14
The 2011/12 adjudication fee statistics were used for NSW in this comparison, as 2011/12 was the first financial
year that NSW Fair Trading published average adjudication fees by claim size.
15
QBCIPA (2011).
16
Construction Contracts Registrar (WA) (2011).
17
NSW Procurement (2012).
18
Society of Construction Law Australia, “Report on Security of Payment and Adjudication in the Australian
Construction Industry”, 2014, Australian Legislative Reform Sub-Committee.
19
Lists of these decisions may be viewed in Appendix 1.
20
A list of these decisions may be viewed in Appendix 1.
21
Only cases which readily identify the adjudication determination amount in the case report have been included
in this analysis, which explains the discrepancies between the numbers reported in Tables 4 and 5. The cases and
their adjudication determination amounts are shown in Appendix 1.
22
According to the Australian Bureau of Statistics, “2011-12 Private Sector Construction Industry Australia”,
8772.0, at the end of June 2012 there were 209,783 businesses in the construction industry, 97.7% of which were
small construction businesses (employment range of 0–19 persons) and only 0.1% of which were large construction
businesses (employment range of 200 persons or more). Of these, small construction businesses accounted for 49%
of total industry income, whereas large businesses accounted for 27%.
The ECM was originally designed to provide security of payment for “small
end of town”. As stated in the Second Reading Speech for the Building and
Construction Industry Security of Payment Bill in the NSW Legislative assembly:
“It is all too frequently the case that small subcontractors—such as bricklayers,
carpenters, electricians and plumbers—are not paid for their work. Many of
them cannot survive financially when that occurs, with severe consequences
for themselves and their families.”23
The focus on small subcontractors and suppliers explains the highly regulatory
nature and short timescales of the ECM.
The original objective of the ECM was to be a quick independent payment
certification mechanism for construction works done and/or goods and services
supplied, as opposed to a dispute resolution method to assess amounts claimed for
damages within the scope of the contract (e.g., contractors’ claims for delay and
disruption costs). However, shortly after the commencement of the ECM legislation,
“mission drift” began to occur in the three ways: the courts found that the ECM
could be used for assessing more complex matters such as delay damages claims24;
the ECM became regularly used to decide very large payment disputes in the order
of millions of dollars; and the courts declared adjudication to be an administrative
tribunal and, therefore, susceptible to judicial review.
Not being originally designed as a dispute resolution process, the ECM is
unsuitable for the determination of larger payment claims as it lacks basic elements
of procedural justice. This can been seen in the following ways:
• the ECM essentially limits the adjudicator to a consideration of
documents only when making their determination;
• the ECM bars respondents from submitting adjudication responses
where no payment schedule has been duly served;
• the ECM’s adjudication process does little to facilitate, or enable the
facilitation, of an ongoing commercial relationship between parties;
and
• The ECM provides short timeframes for respondents to prepare their
adjudication responses and for adjudicators to make their
determinations.
A further issue which has come to light is the lack of perceived procedural justice
afforded by the adjudicator appointment mechanism under the ECM due to the
unilateral selection of an Authorised Nominating Authority (ANA),25 as discussed
in further detail in Part IV of this article.
Simply speaking, the ECM was not designed to cater for the resolution of large
and/or complex payment claims. It is, however, being often used to do so. Hence,
23
M. Iemma, Building and Construction Industry Security of Payment Bill Second Reading Speech, 29 June 1999,
Parliament of NSW Legislative Assembly Hansard Transcript, p.1594.
24
See, for example: Coordinated Construction Co Pty Ltd v JM Hargreaves Pty Ltd [2005] NSWCA 228;
Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229; Minister for Commerce
(formerly Public Works & Services) v Contrax Plumbing (NSW) Pty Ltd [2005] NSWCA 142; and, John Holland
Pty Ltd v Roads & Traffic Authority of New South Wales [2007] NSWCA 19.
25
See further: A. Wallace, “Final Report of the Review of the Discussion Paper—Payment dispute resolution in
the Queensland building and construction industry”, 2013, pp.131–140; B. Collins, “Final Report of the Independent
Inquiry into Construction Industry Insolvency in NSW”, 2012, p.72.
26
Coggins, “A Proposal for Harmonisation of Security of Payment Legislation in the Australian Building and
Construction Industry”, 2012, PhD Thesis, Adelaide University.
article demonstrate that the ECM has been relatively popular for
smaller claims, and that adjudication fees for smaller payment claims
in the ECM jurisdictions are relatively low, when compared to the
WCM. As such by retaining the ECM process for smaller claims,
the proposed dual process capitalises on the successful aspects of
the East Coast process.
2) The West Coast legislative approach—with its respect for primacy
of contract and procedural justice—is more appropriate for deciding
payment claims at the “larger end of town”, producing adjudication
determinations that are more likely to be accepted by the parties as
well as being more resilient to judicial review than determinations
under the ECM. The less regulatory nature of the WCM offers far
less scope for judicial challenge on the basis of jurisdictional error
than does the ECM with its “drop dead” timeframes and prescriptions
for payment claims and payment schedules. Accordingly, the
adjudication data reviewed in Part II of this article shows that the
ECM has generally been more susceptible to judicial challenges and
quashings since commencement of the legislation.
In light of the adjudication data previously reviewed in Part II, it is suggested the
cap value for the proposed dual process should be $100,000 due to the data
revealing this amount to be:
• a demarcation point below which adjudication fees are relatively
lower in the ECM jurisdictions as compared to WA; and
• the threshold below which applications for judicial review of
adjudicators’ determinations are rarely made—nearly all judicial
review applications since the start of 2014 have been for adjudicator
determinations in excess of $50,000, and around 80 per cent of
judicial review applications for adjudicator determinations in excess
of $100,000.
27
It should be noted that SA Act differs from the other ECM Acts in that it allows 15 business days for a payment
schedule to be served from the date of the payment claim, and 15 business days for a claimant to apply for adjudication
after receiving the payment schedule.
28
It should be noted that under the WCM, the time period between submission of payment claim and issuance of
the contractual payment certificate is in accordance with the agreed contractual terms. For the purposes of Figure 2,
10 business days has been used as this timeframe is typically provided by standard forms of construction contract—e.g.,
AS 2124 General Conditions of Contract cl.42.1; and AS 4000 General Conditions of Contract cl.37.2.
29
Except for: the SA Act which allows 15 business days; and the Qld Act which allows 15 business days for
complex payment claims served within 90 days or less, and 30 business days for complex payment claims served
more than 90 days after the reference date.
30
See, for example, cl.42.1 of the AS 2124 General Conditions of Contract, and cl.37.2 of the AS 4000 General
Conditions of Contract.
31
Except for the SA Act which allows 15 business days.
32
WA Act s.26(1).
33
NT Act s.28(1).
34
Evans, “Report on the Operation and Effectiveness of the Construction Contracts Act 2004 (WA)”, 2015, p.23.
35
Evans, “Report on the Operation and Effectiveness of the Construction Contracts Act 2004 (WA)”, 2015, p.23.
36
Evans, “Report on the Operation and Effectiveness of the Construction Contracts Act 2004 (WA)”, 2015, p.23.
37
The Housing Grants, Construction and Regeneration Act 1996.
38
Construction Contracts Act 2013.
39
Construction Industry Payment and Adjudication Act 2012.
40
Except for the ACT Act which allows 7 business days, and the Qld Act which allows 10 business days for
standard payment claims and 15 business days for complex payment claims.
41
Except for the ACT and Tasmanian Acts which allow 5 business days, and the Qld Act which allows 7 business
days for standard payment claims and 12 business days for complex payment claims.
42
See WA Act s.27(1); NT Act s.29(1).
48
Except for the SA Act which allows 15 business days, and the NSW Act as discussed below.
49
This amendment commenced on 21 April 2014.
50
NSW Act ss.11(1A)(a) and 11(1B)(a).
51
See, for example, the Vic Act s.14(2)(e).
52
In their survey, which sought to assess the performance of the NSW Act by surveying the members of two peak
trade associations operating in NSW, Brand and Uher found that around half of the sampled contractor and subcontractor
firms felt that endorsement of payment claims negatively affects to some degree the working relationship between
the parties to a payment claim—see M.C. Brand and T. Uher, “Follow-up empirical study of the performance of the
New South Wales construction industry security of payment legislation”, 2010 2(1) International Journal of Law in
the Built Environment7–25. See also Collins, “Final Report of the Independent Inquiry into Construction Industry
Insolvency in NSW”, 2012, p.73.
53
The ECM only permits one statutory payment claim per reference date—see, for example, NSW Act s.13(5).
54
Kitchen Xchange v Formacon Building Services [2014] NSWSC 1602 at [3].
55
Wallace, “Final Report of the Review of the Discussion Paper—Payment dispute resolution in the Queensland
building and construction industry”, 2013, p.130.
margin charged. The “for profit” ANAs appoint the majority of adjudicators, with
the largest for profit ANA stating on its website that it has managed over 60 per
cent of all applications made nationally.56
There has been much anecdotal evidence submitted regarding apprehended or
perceived bias with respect to appointment of “claimant-friendly” adjudicators by
“for profit” ANAs given the potential for such ANAs to benefit from repeat
business.57 There is also anecdotal evidence with respect to instances of “adjudicator
shopping” and “unhealthy relationships” between ANAs and payment claim
preparers.58
In their defence “for profit” ANAs point out, amongst other things, that the
private sector delivers services more efficiently; ANAs provide training,
professional administrative and mentor support; and ANAs provide advice to
claimants on making claims and submitting applications correctly.59
56
Adjudicate Today website, at http://www.adjudicate.com.au/vic/start/claimant-common-pitfalls [Accessed 10
January 2018].
57
See, for example, Wallace, “Final Report of the Review of the Discussion Paper—Payment dispute resolution
in the Queensland building and construction industry”, 2013, pp.131–140; Collins, Final Report of the Independent
Inquiry into Construction Industry Insolvency in NSW”, 2012, p.72.
58
See, for example, Wallace, “Final Report of the Review of the Discussion Paper—Payment dispute resolution
in the Queensland building and construction industry”, 2013, pp.131–140.
59
See, for example, Wallace, “Final Report of the Review of the Discussion Paper—Payment dispute resolution
in the Queensland building and construction industry”, 2013, p. 145; Adjudicate Today, “Response to Proposed
Changes to Building and Construction Industry Security of Payment Act Consultation Paper”, June 2016, Submission
to South Australian Small Business Commissioner, at https://www.sasbc.sa.gov.au/security_of_payment/review-of
-the-building-and-construction-security-of-payment-act-200 [Accessed 10 January 2018]; Thomas Uher, “Response
to the Consultation Paper”, 2016, Submission to South Australian Small Business Commissioner, at https://www
.sasbc.sa.gov.au/security_of_payment/review-of-the-building-and-construction-security-of-payment-act-200 [Accessed
10 January 2018].
60
Queensland Building and Construction Commission, “Monthly Adjudication Statistics—June 2016”, http://www
.qbcc.qld.gov.au/sites/default/files/BCIPA_overall_statistics_June_2016.pdf [Accessed 10 January 2018].
61
Adjudicate Today, Response to Proposed Changes to Building and Construction Industry Security of Payment
Act Consultation Paper”, June 2016, p.12.
The QBCC statistics do not show how many of the 228 applications withdrawn
concern smaller payment claims. If Adjudicate Today’s opinion is correct, that the
increase in withdrawals is due to the abolishment of the free support structure the
ANAs used to provide to subcontractors, then it could be expected that the vast
majority of withdrawals relate to adjudication applications made by smaller
contractors and suppliers who cannot afford the professional legal advice that
larger claimants often obtain.
62
These statistics extracted from QBCC Monthly Adjudication Reports for November 2014 and June 2015.
63
See Construction Contracts Act 2002 s.33(3).
legislation, then the adjudication applicant would choose which ANA to submit
their adjudication application to.
This proposed appointment process may add a few business days to the
adjudication process, but would go a long way to eliminating any perceptions of
ANAs being claimant friendly, as it will introduce an element of respondent choice
into the ANA selection process.
64
The NSW Act s.18(1)(b) and SA Act s.18(1)(b) state that such qualifications, expertise and experience may be
prescribed by the regulations for the purposes of this Act. The Tasmanian Act s.22(2), states that the qualifications,
expertise and experience required, if any, are to be determined by the Security of Payments Official. The ACT Act
s.20(1)(c), further requires that an adjudicator must have successfully completed a relevant training course.
65
The Building and Construction Industry Security of Payment Regulations 2011 (SA) s.6 requires that a person
has attended a 2 day adjudication course, and either holds a degree, diploma or other qualification in a listed discipline
or is, or is eligible to be, a member of a listed professional body.
66
Building and Construction Industry Payments Act 2004 s.22(1).
67
Building and Construction Industry Payments Act 2004 s.111(2)(b).
68
Building and Construction Industry Payments Regulation 2004 s.3.
69
Building and Construction Industry Payments Regulation 2004 Sch.1 Pt 2.
70
Building and Construction Industry Payments Regulation 2004 Sch.1 Pt 1. The bodies listed comprise 7 out of
the 8 registered ANAs.
71
Construction Contracts Act 2004 s.48(1); Construction Contracts Regulations 2004 reg.9.
72
Construction Contracts Regulations 2004 reg.9.
73
i.e., architecture, engineering, quantity surveying, building surveying, building or construction.
74
The Royal Australian Institute of Architects, Institution of Engineers Australia, Australian Institute of Quantity
Surveyors, Australian Institute of Building Surveyors, The Australian Institute of Building, The Institute of Arbitrators
and Mediators of Australia, Australian Institute of Project Management.
75
Small Business Commissioner (SA), Code of Conduct for Authorised Nominating Authorities, Building and
Construction Industry Security of Payment Act 2009, Government of South Australia, p.3.
76
See Construction Contracts Act 2013 s.6(8).
77
Qld Building Services Authority, “Building and Construction Industry Payments Act 2004”, Discussion Paper,
2010, Brisbane, p.5.
78
With the exception of the Tasmanian Act, which prescribes the same East Coast model type statutory payment
system for home owners as it does for commercial operators. It does, however, make one concession for home owners
in that “a home owner has 20, rather than 10, business days to consider the content of a payment claim” (N. Speranza,
“An evaluation of Australian security of payment and United States construction lien law” (2011) 27 Building and
Construction Law 187).
79
Qld Building Services Authority, “Building and Construction Industry Payments Act 2004”, Discussion Paper,
2010, Brisbane, p.5.
IX. Conclusion
Australia has eight differing acts throughout its states and territories dealing with
security of payment in the building and construction industry. Each of the acts
may broadly be categorised into one of two distinct legislative models. The ECM
provides a highly regulatory process originally designed, in accordance with
parliamentary intent, for the rapid determination of payment claims made by
smaller contractors for construction work carried out or related goods and services
supplied. The WCM provides a process, based upon primacy of contract, designed
for the determination of all payment claims under the contract including those for
damages within the scope of the contract. The scope of both the East and West
Coast models is similarly wide-ranging, covering any contractor or supplier,
regardless of size, who has undertaken construction work or supplied related goods
and services falling within the definition of the legislation.
The application of the ECM to larger and more complex payment claims, for
which it was not originally designed, has led to a considerable amount of
applications for judicial review of adjudicators’ determinations due to the
shortcomings in procedural justice it affords. Despite its problems at the “larger
end of town”, however, adjudication under the ECM has proven to have a
proportionally higher uptake rate, as well as being cheaper and faster, for the
determination of smaller payment claims than its WCM counterpart. Conversely,
the more procedurally just and contract-focused WCM has resulted in a
proportionally higher adjudication uptake rate, as well as an adjudication process
that is more economical and resistant to judicial review, for the determination of
larger payment claims relative to its ECM counterpart since commencement of
the legislation.
The existent diversity in Australia’s security of payment legislation may be
turned to advantage if the wealth of experience now accumulated in both East and
West Coast model jurisdictions is capitalised on, and the contrasting, yet
complimentary, strengths of the existing models are drawn together into a single
harmonised model. In light of the analysis of the available adjudication data
reviewed in this article, and a consideration of the key consultation issues raised
by John Murray AM as part of his federal review of security of payment laws in
Australia, it is proposed that a unifying dual process—where the ECM is used for
payment claims up to $100,000 and the WCM for payment claims above
$100,000—provides a sound starting point for agreement upon such an optimal
harmonised model.
With the construction industry accounting for around seven per cent of
Australia’s gross domestic product, and employing around nine per cent of the
workforce,80 the enactment of harmonised security of payment law is essential if
the Australian construction industry is to realise the concomitant efficiencies of
uniform legislation. It may, indeed, be argued that the precise shape and form of
any eventuating law should be secondary to the act of harmonisation per se. Having
said this, however, it would undoubtedly be preferable and conducive to successful
nationwide adoption, if the shape and form of any harmonising model were to be,
80
Australian Bureau of Statistics, “Feature Article: A Statistical Overview of the Construction Industry.” Retrieved
5 Mar 2012, from http://www.abs.gov.au/AUSSTATS/abs@.nsf/Lookup/1350.0Feature+Article1Oct+2010 [Accessed
10 January 2018].
Qld
Annie Street JV Pty Ltd v MCC Pty Ltd [2016] Failed Challenge N/A
QSC 268; BC201609945
Ostwald Bros Pty Ltd v Jaylon Pacific Pty Ltd Quashed for substantila $424,901.40
[2016] QSC 240; BC201608959 denial of NJ
Sierra Property Qld Pty Ltd v National Construc- Quashed in part due to $264,742.12
tion Management Pty Ltd [2016] QSC 108; JE
BC201603673
Wiggins Island Coal Export Terminal Pty Ltd v Failed Challenge $22,132,839.35
Monadelphous Engineering Pty Ltd [2015] QSC
307; BC201510571
Agripower Australia Ltd v Queensland Engineer- Quashed for JE N/A
ing & Electrical Pty Ltd [2015] QSC 268;
BC201508965
BRB Modular Pty Ltd v AWX Constructions Pty Failed Challenge $3,706,601.88 including
Ltd [2015] QSC 218; BC201507242 GST
Camporeale Holdings Pty Ltd v Mortimer Con- Failed Challenge $90,311.58
struction Pty Ltd [2015] QSC 211; BC201506897
JAG Projects Qld Pty Ltd v Total Cool Pty Ltd Failed Challenge $88,000 including GST
[2015] QSC 229; BC201507431
Sunshine Coast Regional Council v Earthpro Pty Quashed in part for JE $1.4M
Ltd [2015] QSC 168; BC201505768
Lean Field Developments Pty Ltd v E & I Global Failed Challenge $527,783.08
Solutions (Aust) Pty Ltd [2016] 1 Qd R 30; [2014]
QSC 293; BC201410238
McNab Developments (Qld) Pty Ltd v Mak Con- Failed Challenge (QSC $241,441.20
struction Services Pty Ltd [2015] 1 Qd R 350; decision upheld)
[2014] QCA 232; BC201407638
Caltex Refineries (Qld) Pty Ltd v Allstate Access Quashed for denial of 1784299.15 and
(Australia) Pty Ltd [2014] QSC 223; NJ $2,357,796.32
BC201407597
Eco Steel Homes Pty Ltd v Hippo’s Concreting Failed Challenge $29,689.84
Pty Ltd [2014] QSC 135; BC201406984
CMF Projects Pty Ltd v Masic Pty Ltd [2014] Quashed for denial of N/A but Payment Claim
QSC 209; BC201406985 NJ amount was $48.993.60
and Payment Schedule
-$40,445.95
Kaycee Trucking Pty Ltd v M & C Rogers Trans- Failed Challenge $99,813.27 (including
port Pty Ltd [2014] QSC 185; BC201406570 GST)
Ball Construction Pty Ltd v Conart Pty Ltd [2014] Quashed for JE N/A
QSC 124; BC201404388
J Hutchinson Pty Ltd v Cada Formwork Pty Ltd Quashed for denial of $222,625.70, including
& Ors [2014] QSC 063; BC201402398 NJ GST
Conveyor & General Engineering Pty Ltd v Quashed for denial of $121,472.02
Basetec Services Pty Ltd [2015] 1 Qd R 265; NJ
[2014] QSC 030; BC201401245
Vic
Raw Build Pty Ltd v JBK Industries Pty Ltd [2016] Challenge held over to $9115.7+ $81,415.00
VSC 547; BC201609286 a separate hearing
WA
Cooper & Oxley Builders Pty Ltd v Steensma Quashed for JE $182,047.44 +
[2016] WASC 386; BC201610261 $88,626.88
Samsung C&T Corp v Loots [2016] WASC 330; Quashed for JE $333199 +
BC201608995 $49,642,958.72, plus
GST
Laing O’Rourke Australia Construction Pty Ltd Failed challenge $ 2 0 9 6 5 0 7 6 +
v Samsung C&T Corp (2016) 50 WAR 399; (quashing overturned) $8,287,786.01
[2016] WASCA 130; BC201606166
BGC Construction Pty Ltd v Citygate Properties Quashed for JE $402,273.21 (exclusive
Pty Ltd [2016] WASC 88; BC201601865 of GST) + $392,145
(exclusive of GST)
NRW Pty Ltd as Trustee for NRW Unit Trust v Failed Challenge $17,467,884.10
Samsung C & T Corp [2015] WASC 369;
BC201509667
SC Projects Australia Pty Ltd v Field Deployment Failed Challenge $162,625.64
Solutions Pty Ltd [2015] WASC 339;
BC201508785
Laing O’Rourke Australia Construction Pty Ltd Quashed for JE $20965076 +
v Samsung C & T Corp (2015) 31(5) BCL 290; $8,287,786.01
[2015] WASC 237; BC201506037
Delmere Holdings Pty Ltd v Green [2015] WASC Quashed for JE $873,011.87 including
148; BC201503021 GST
Field Deployment Solutions Pty Ltd v SC Projects Failed Challenge N/A
Australia Pty Ltd [2015] WASC 60;
BC201500628
Hamersley Iron Pty Ltd v James [2015] WASC Failed Challenge $2,138,733.05 plus GST
10; BC201500072
Johnson, Re; Ex parte Decmil Australia Pty Ltd Failed Challenge N/A but claimed
[2014] WASC 348; BC201408070 amount $705,586.50
(exclusive of GST)
WQube Port of Dampier v Philip Loots of Kahlia Failed Challenge N/A but claimed
Nominees Ltd [2014] WASC 331; BC201407692 amount $2,830,920.84
Red Ink Homes Pty Ltd v Court [2014] WASC Quashed for JE $65472 + $254,871.77
52; BC201400834 + $11,120.90
Zurich Bay Holdings Pty Ltd v Brookfield Multi- Quashed for JE $1,191,402.84
plex Engineering and Infrastructure Pty Ltd
[2014] WASC 40; BC201400449
Zurich Bay Holdings Pty Ltd v Brookfield Multi- Failed Challenge $522,209.25
plex Engineering and Infrastructure Pty Ltd
[2014] WASC 39; BC201400448
Alexander Nissen QC and William Webb (instructed by Macfarlanes LLP) for the
claimant/respondent.
The judgment of Jackson LJ reads as follows:
Part 1—Introduction
2 This is an appeal by a building contractor against a decision that there is no
entitlement to interim payments in the period after the contractual date for practical
completion. The principal issues are (i) how some rather unusual amendments to
the standard form building contract should be construed and (ii) how section 109
of the Housing Grants, Construction and Regeneration Act 1996 (“the 1996 Act”)
applies in the circumstances of this case.
3 The contractor, Mansell Construction Services Limited, had a name change
during the course of the building works and became Balfour Beatty Regional
Construction Limited. I shall refer to the contractor at all stages as “BB”. I shall
refer to the employer, Grove Developments Limited, as “Grove”.
4 Sections 109 and 110 of the 1996 Act provide as follows:
“109.– Entitlement to stage payments.
(1) A party to a construction contract is entitled to payment by
instalments, stage payments or other periodic payments for any
work under the contract unless –
(a) it is specified in the contract that the duration of the
work is to be less than 45 days, or
(b) it is agreed between the parties that the duration of the
work is estimated to be less than 45 days.
(2) The parties are free to agree the amounts of the payments and
the intervals at which, or circumstances in which, they become
due.
(3) In the absence of such agreement, the relevant provisions of
the Scheme for Construction Contracts apply.
(4) References in the following sections to a payment provided for
by the contract include a payment by virtue of this section.
110.– Dates for payment.
(1) Every construction contract shall –
(a) provide an adequate mechanism for determining what
payments become due under the contract, and when,
and
(b) provide for a final date for payment in relation to any
sum which becomes due.
The parties are free to agree how long the period is to be
between the date on which a sum becomes due and the final
date for payment.
…
(3) If or to the extent that a contract does not contain such provision
as is mentioned in subsection (1) […], the relevant provisions
of the Scheme for Construction Contracts apply.”
5 The Scheme for Construction Contracts (England and Wales) Regulations 1998
set out the Scheme for Construction Contracts (“the Scheme”) which applies to
construction contracts, in so far as the provisions of those contracts do not comply
with the requirements of the 1996 Act.
6 Paragraphs 1 to 7 of the Scheme set out rules for monthly interim payments to
the contractor. These provisions are incorporated in any construction contract
which does not comply with Sections 109 and 110 of the 1996 Act.
7 After these introductory remarks, I must now turn to the facts.
amount at the Interest Rate for the period from the final date for
payment until payment is made. Interest under this clause 4.9.5 shall
be a debt due to the Contractor from the Employer.
.6 Acceptance of a payment of interest under clause 4.9.5 shall not in
any circumstances be construed as a waiver of the Contractor’s right
to proper payment of the principal amount due, to suspend performance
under clause 4.11 or to terminate his employment under section 8 .
Payment Notices, Pay Less Notice and general provisions
.1 Each Payment Notice under this Contract shall specify the sum that
the Party giving the notice considers to be or have been due at the due
date in respect of the relevant payment and the basis on which that
sum has been calculated.
.2 A Pay Less Notice:
.1 (where it is to be given by the Employer) shall specify both the
sum that he considers to be due to the Contractor at the date
the notice is given and the basis on which that sum has been
calculated;
.2 (where it is to be given by the Contractor) shall specify both
the sum that he considers to be due to the Employer at the date
the notice is given and the basis on which that sum has been
calculated.
.3 A Payment Notice or a Pay Less Notice to be given by the
Employer may be given on his behalf by the Employer’s Agent
or by any other person who the Employer notifies the Contractor
as being authorised to do so.
.4 In relation to the requirements for the giving of notices under
section 4 and the submission of a Final Statement, it is
immaterial that the amount then considered to be due may be
zero.
.5 Any right of the Employer to deduct or set off any amount
(whether arising under any provision of this Contract or under
any rule of law or equity) shall be exercisable against any
monies due or to become due to the Contractor, whether or not
such monies include or consist of any Retention.
..”
…
Final Statement and final payment
.1 Following practical completion of the Works the Contractor shall
submit the Final Statement to the Employer and supply him with such
supporting documents as he may reasonably require.
.2 The Final Statement shall set out the adjustments to the Contract Sum
to be made in accordance with clause 4.2 and shall state:
.1 the Contract Sum, as so adjusted; and
.2 the sum of amounts already paid by the Employer to the
Contractor,
and the final payment shall be the difference (if any) between the two
sums, which shall be shown as a balance due to the Contractor from
the Employer or to the Employer from the Contractor, as the case may
be. The Final Statement shall state the basis on which that amount has
been calculated, including details of all such adjustments.
…
.5 The due date for the final payment shall be the date one month after
whichever of the following occurs last:
.1 the end of the Rectification Period in respect of the Works or
(where there are Sections) the last such period to expire;
.2 the date stated in the Notice of Completion of Making Good
under clause 2.36 or (where there are Sections) in the last such
notice to be issued; or
.3 the date of submission to the other Party of the Final Statement
or, if issued first, the Employer’s Final Statement (“the relevant
statement”).
…
Ascertainment—Alternative A
4.13 The Gross Valuation shall be the total of the amounts referred to in
clauses 4.13.1 and 4.13.2 less the total of the amounts referred to in
clause 4.13.3, calculated as at completion of the relevant stage.
.1 The following which are subject to Retention shall be included:
.1 the cumulative value at the relevant stage;
.2 the value of any Changes or other work referred to in
clause 5.2 that are relevant to the Interim Payment
(whether agreed pursuant to clause 5.2 or valued under
the Valuation Rules) but excluding any amounts referred
to in clause 4.13.2–4;
3. the value of any Listed Items, when their value is to be
included under clause 4.15;
.4 the amount of any adjustment under Fluctuations Option
C (if applicable);
.5 where Fluctuations Option C is applicable and where
in accordance with the Formula Rules amounts in the
Value of Work are to be allocated to lift installations,
structural steelwork installations or catering equipment
installations, the total value of Site Materials of those
descriptions, provided that their value shall only be
included if they are adequately protected against weather
and other casualties and they are not on the Works
prematurely; and
.6 the amount of any adjustment by Confirmed Acceptance
of an Acceleration Quotation.
.2 The following which are not subject to Retention shall be
included:
.1 any amounts to be included in Interim Payments in
accordance with clause 4.3 by the Employer as a result
“Valu- Val month Mansell Applica- Valuation Date Grove Certificate Payment made by
ation tion Submission Issued (3 work- Grove by (30
no. Date to Grove ing days) days from Val
date)
JUL
AUG
1 SEPT 19/09/2013 20/09/2013 25/09/2013 20/10/2013
2 OCT 17/10/2013 18/10/2013 23/10/2013 22/11/2013
3 NOV 14/11/2013 15/11/2013 20/11/2013 20/12/2013
4 DEC 19/12/2013 19/12/2013 24/12/2013 23/01/2014
5 JAN 23/01/2014 24/01/2014 29/01/2014 25/02/2014
6 FEB 20/02/2014 21/02/2014 26/02/2014 28/03/2014
7 MAR 20/03/2014 21/03/2014 26/03/2014 25/04/2014
8 APR 17/04/2014 18/04/2014 23/04/2014 23/05/2014
9 MAY 22/05/2014 23/05/2014 28/05/2014 27/06/2014
10 JUN 19/06/2014 20/06/2014 25/06/2014 25/07/2014
“Valu- Val month Mansell Applica- Valuation Date Grove Certificate Payment made by
ation tion Submission Issued (3 work- Grove by (30
no. Date to Grove ing days) days from Val
date)
11 JUL 17/07/2014 18/07/2014 23/07/2014 22/08/2014
12 AUG 21/08/2014 22/08/2014 27/08/2014 28/09/2014
13 SEPT 18/09/2014 19/09/2014 24/09/2014 24/10/2014
14 OCT 16/10/2014 17/10/2014 22/10/2014 21/11/2014
15 NOV 20/11/2014 21/11/2014 26/11/2014 26/12/2014
16 DEC 18/12/2014 19/12/2014 24/12/2014 23/01/2015
17 JAN 22/01/2015 23/01/2015 28/01/2015 27/02/2015
18 FEB 19/02/2015 20/02/2015 25/02/2015 27/03/2015
19 MAR 19/03/2015 20/03/2015 25/03/2015 24/04/2015
20 APR 16/04/2015 17/04/2015 22/04/2015 22/05/2015
21 MAY 21/05/2015 22/05/2015 27/05/2015 26/06/2015
22 JUN 18/06/2015 19/06/2015 24/06/2015 24/07/2015
23 JUL 16/07/2015 17/07/2015 22/07/2015 21/08/2015”
On 15th September Grove issued a Pay Less notice in respect of application 24.
This showed that Grove would deduct £2 million, because there was a dispute
about whether BB should give credit for an extra-contractual payment of £2 million
previously made by Grove. The Pay Less notice showed the payment date as 25th
September. On 18th September Grove paid £439,503, which was the sum shown
as due on the Pay Less notice after deducting the £2 million.
19 BB took strong exception to Grove’s calculation of dates. They also took the
view that by reason of Grove’s miscalculations the Pay Less notice was ineffective.
Accordingly on 30th September 2015 BB sent a formal letter to Grove demanding
payment of the £2 million, which Grove had withheld in reliance on the Pay Less
notice. On page 2 of that letter BB wrote:
“Despite efforts on both sides, no agreement has been reached in relation to
the Interim payment process beyond July 2015. For the avoidance of any
doubt, our previous offers to agree the Interim payment process beyond July
2015 are now withdrawn and are no longer capable of acceptance.”
20 During October and November 2015 the parties continued to correspond and
serve notices on the assumption that interim payments were due, but they never
reached agreement about the applicable dates. Grove made no further payments
to BB during that period. This was for two reasons. First, Grove maintained that
their Pay Less notice of 15th September was valid and entitled them to withhold
the disputed £2 million. Secondly, they maintained that liquidated and ascertained
damages for delay exceeded and extinguished any payments due to BB in respect
of work done.
21 On 9th December 2015, after taking independent advice, Grove asserted that
BB had no continuing entitlement to receive payments.
22 BB disputed the proposition that they had no further entitlement to interim
payments. Accordingly, in order to resolve that dispute, Grove commenced the
present proceedings.
payment notices and payments were a matter of detail which could if necessary
be resolved by adjudication or some similar mechanism. I cannot accept that.
Identification of the dates for valuation, payment notices, Pay Less notices and
payments were an essential feature. If Grove served notices out of time, the
consequences would be Draconian (as BB asserted in their letter dated 30th
September 2015). Both parties needed to know with certainty what were the
applicable dates.
38 Mr Walker submits that to interpret the contract in this way creates a commercial
nonsense. The parties cannot have intended that, if practical completion were
delayed, BB would have to wait for payment until the final payment date under
clause 4.12. Therefore the court must construe the contract as amended by the
Tumber schedule as providing a continuing entitlement to interim payments after
July 2015.
39 I reject this submission for three reasons. First, the express words used make it
clear that the parties were only agreeing a regime of interim payments up to the
contractual date for practical completion. See the Tumber email, which referred
to the “agreed schedule of valuation / payment dates for this project”. Neither the
email nor the schedule made any provision for interim payments after July 2015.
Secondly, it is impossible to deduce from the hybrid arrangement what would be
the dates for valuations, payment notices, Pay Less notices and payments after
July 2015. These were essential matters for the reasons previously stated. Thirdly,
this is a classic case of one party making a bad bargain. The court will not, indeed
cannot, use the canons of construction to rescue one party from the consequences
of what that party has clearly agreed. There is no ambiguity in the present case
which enables the court to reinterpret the parties’ contract in accordance with
“commercial common sense”, which Mr Walker seeks to invoke.
40 Mr Walker places reliance on the judgment of Lord Neuberger (with whom
Lord Sumption and Lord Hughes agreed) in Arnold v Britton [2015] UKSC 36;
[2015] AC 1619 at [15] to [23]. I do not think that those principles assist BB. The
language of the contract as amended by the Tumber schedule is clear. It provides
only for interim payments up to valuation 23. As Lord Neuberger said at [19]:
“The mere fact that a contractual arrangement, if interpreted according to its
natural language, has worked out badly, or even disastrously, for one of the
parties is not a reason for departing from the natural language.”
41 Paragraph 20 of Lord Neuberger’s judgment is also apposite:
“Fourthly, while commercial common sense is a very important factor to take
into account when interpreting a contract, a court should be very slow to reject
the natural meaning of a provision as correct simply because it appears to be
a very imprudent term for one of the parties to have agreed, even ignoring
the benefit of wisdom of hindsight. The purpose of interpretation is to identify
what the parties have agreed, not what the court thinks that they should have
agreed. Experience shows that it is by no means unknown for people to enter
into arrangements which are ill-advised, even ignoring the benefit of wisdom
of hindsight, and it is not the function of a court when interpreting an
agreement to relieve a party from the consequences of his imprudence or poor
Part 6—Do the 1996 Act and the Scheme enable BB to recover interim
payments after July 2015?
50 I have set out the relevant provisions of the 1996 Act in Part 1 above. If the
parties’ contract did not comply with sections 109 and 110 of the 1996 Act, then
paragraphs 2-7 of the Scheme would apply.
51 Ms Slow submits that the word “any” in section 109(1) of the 1996 Act means
“all”. Therefore the relevant provisions of the Scheme will apply if a construction
contract fails to provide a regime of interim payments covering the whole of the
work which the contractor performs.
52 Ms Slow prays in aid the decision of Eve J in Clarke-Jervoise v Scutt [1920] 1
Ch 382. That case concerned a tenancy agreement in which the tenant agreed not
to plough “any grass land”. Eve J construed that phrase broadly as meaning all
land covered in grass either at the date of the demise or subsequently. He therefore
treated the word “any” as meaning “all”.
53 I readily understand, and respectfully agree with, the decision in that case. But
the judge arrived at his conclusion specifically by reference to the context in which
the word “any” appeared: see page 388. He was not saying that in every context
“any” means “all”.
54 I now return to section 109(1) of the 1996 Act. In that context I do not think
that “any work” means “every single piece of work”. In my view the subsection
is a more general one saying that work done under construction contracts shall
(except in very short projects) be subject to a regime of interim payments.
55 Section 109(2) gives the parties considerable latitude as to the system of interim
payments which they may agree. They can decide for themselves the frequency
of interim payments and the amounts to be paid. For example, the parties may
agree that interim payments shall be less than the full value of work done. Indeed
parties normally do agree that, so that the Employer holds retention monies, usually
releasing half at practical completion and the other half when all defects have been
made good.
56 We heard some interesting arguments as to whether contracting parties could
frustrate Parliament’s intention by agreeing a pitifully inadequate scheme of interim
payments. Mr Nissen relied upon the following passage in the 10th Edition of
Keating on Construction Contracts :
“18-106 Stage Payments.
Section 109 of the Act states that a party to a construction contract is generally
entitled to payment by instalments, stage payments or other periodic payments
for any work under the contract. The reference to “stage payments” would
seem to permit payment by reference to the achievement of particular elements
of the work. Further, there is no requirement as to when such payments are
to be made; any arrangement which satisfies the definition will be sufficient.
Thus a contract prescribing one periodic payment, even of an insignificant
amount, would, it would seem, meet the requirements.”
57 If the parties are going to exclude the operation of the Scheme, they must draw
up a system of interim payments in good faith. I doubt that a cynical device to
exclude the operation of the Scheme by prescribing one interim payment “of an
insignificant amount” would suffice. But for present purposes, it is not necessary
to decide whether that passage in Keating is correct. Suffice it to say that section
109(2) gives the contracting parties a wide measure of freedom as to the nature of
the regime which they may agree.
58 In the present case the parties agreed a regime of twenty three interim payments
stretching right up to the date specified for practical completion. I am quite satisfied
that the contract, as amended by the Tumber schedule, satisfies the requirements
of section 109.
59 Clause 4.14 of the contract provided an adequate mechanism for quantifying
interim payments. Therefore the parties’ contract, although unusual, satisfied the
requirements of section 110.
60 In those circumstances the Scheme does not apply. BB cannot rely upon the
1996 Act and the Scheme to recover interim payments after July 2015. My answer
to the question posed in this part of the judgment is no. I therefore reject the second
ground of appeal.
61 I must turn finally to the question whether the parties reached a separate
agreement for interim payments after valuation 23.
Part 7—Did the parties reach a separate agreement for interim payments
after valuation 23?
62 The judge has recited very fully the correspondence passing between the parties
in the period May to December 2015. See paragraphs 16 to 21 and 39 of his
judgment. I will not repeat that recitation.
63 The short answer to the third ground of appeal is this. The parties never agreed
the terms upon which interim payments would be made. They did not agree the
dates for valuations, notices and payments. Both parties treated those matters as
essential elements of any contract. BB themselves put this point forcefully in their
letter to Grove dated 30th September 2015, from which I have quoted in Part 2
above.
64 Mr Walker argued that Grove waived the need to agree on dates by issuing
payment notice 24. I do not agree. Grove maintained their position in relation to
dates and contractual terms. Grove issued the payment notice and made a payment
to protect themselves against the risk of losing their right to withhold £2 million,
if it turned out that their interpretation of the contract was wrong. In the event, BB
still maintained that Grove had forfeited the right to withhold £2 million.
65 In agreement with the judge, I find it quite impossible to derive any fresh
agreement between the parties from their conduct or their correspondence between
May and December 2015.
66 Accordingly my answer to the question posed in this part of the judgment is no.
I reject the third ground of appeal.
Part 8—Conclusion
67 For the reasons set out in Parts 5, 6 and 7 above, I would reject all three grounds
of appeal. If either of my Lords agree with me, this appeal will be dismissed.
of the JCT form were specifically applicable to Alternative A, and that clauses
4.8.3 and 4.14 were specifically applicable to Alternative B, so that by their original
choice the parties had excluded the operation of clause 4.8.3 and 4.14. The first
question is, therefore, whether when the parties agreed the Tumber Schedule, the
effect of that agreement was to bring those clauses back into operation (and/or
also, I suppose, to exclude the operation of clauses 4.8.2 and 4.13 that are
specifically applicable to Alternative A). For a number of reasons, I have concluded
that that must have been the result of the amendment that was agreed in the Tumber
Schedule.
71 First, in the language of the JCT form, the Tumber Schedule is only referable
to the agreement of “Periodic Payments” rather than “Stage Payments”. I need not
go into too much detail, but the columns in the Tumber Schedule are all referable
to elements of what is provided for by clause 4.8.3 and 4.14. Alternative B provides
in the period up to Practical Completion for “Interim Applications [to] be made
at monthly dates specified in the Contract” (clause 4.8.3), and column 3 of the
Schedule provides such monthly dates. Alternative B provides for monthly valuation
dates as being the “specified date” which is the same as the date of the interim
application (clause 4.8.3 and 4.14), whilst the Tumber Schedule provides for
valuation dates that were in all but one case the day following the date for the
interim application. The JCT form provides for the issue by the employer of a
“Payment Notice” not later than 5 days after the “due date” (the later of the specified
date and date the employer receives the interim application) (clauses 4.8.3 and
4.9.2), whilst the Tumber Schedule provides for Grove to provide an employer’s
certificate 3 working days after the valuation date (which comes to the same thing
because of the intervention of a week-end in every case). Finally, the JCT form
(as originally varied by the parties) provided for payment of the interim payment
28 days from its due date (clause 4.9.1), whilst the Tumber Schedule provided for
a payment date 30 days from the specified valuation date. The Tumber Schedule
does not specify or contemplate “stages” as envisaged by Alternative A and clauses
4.8.2 and 4.13.
72 Secondly, the valuation of each periodic payment envisaged by the Tumber
Schedule had to be undertaken according to some known process. Neither party
has suggested that any such process was available to the parties, save that contained
in clause 4.14. There was no evidence that any of the 3 adjudications invoked
clause 4.14, but it seems very likely that, had they involved an argument about the
basis of the valuation, they would have done so. Certainly, the process envisaged
by the Tumber Schedule cannot fit within the provisions of clause 4.13.
73 Thirdly, throughout the course of the Contract, it is clear that the parties operated
the process envisaged by the parts of the JCT form that were applicable to both
Alternatives A and B. The best example is the service of “Pay Less notices”
envisaged by clause 4.10. The parties spent much time arguing about one of these
notices and the consequence of it having been served late. They can only have
done so on the basis that they understood that the JCT form applied to the process
they were engaged upon.
74 It, therefore, seems to me that the inevitable consequence of the agreement of
the Tumber Schedule was that the parties must be taken to have reversed the express
decision taken in the original contract to elect for the applicability of Alternative
suggestion from the admissible factual matrix that the financing and security risks
had been intended to pass in that way to BB after the expected completion date.
Grove’s submissions on incentives to complete on time are all pure speculation
when the JCT form has detailed provisions that have that effect.
79 I accept, of course, as Jackson LJ has mentioned, that the Tumber Schedule was
sent to Grove’s representative by BB under cover of an email that recited “[p]lease
find attached agreed schedule of valuation/payment dates for this project”. But I
do not think too much weight can be placed on this document that was apparently
sent after the Tumber Schedule had been agreed. Moreover, the dates in the Tumber
Schedule were the only ones actually specified “for the project”, so those words
cannot outweigh the proper meaning of the Tumber Schedule read together with
the JCT form in the way I have suggested and taken against the background of the
appropriate factual matrix.
80 In these circumstances, I cannot accept the judge’s conclusion that the proper
construction of the Tumber Schedule means that only 23 interim payments were
to be made under the Contract. For the reasons I have given, I take the view that
the Contract is ambiguous.
in construing a Contract that is ambiguous and I would regard that common sense
as pointing clearly to the construction I have reached.
84 A further question arises as to what the Contract provides for interim payments
after practical completion. That does not arise in this case thus far. One may hope
that parties will be able to agree a suitable regime. All I would say is that it is less
obvious that the Contract must be construed as meaning that monthly interim
payments were intended to continue in the same way after practical completion,
when clause 4.8.3 provides for bi-monthly payments and when the Tumber
Schedule ends at expected completion.
85 Since I do not think that, on a proper construction of the Contract, there was
actually a lacuna, section 109 of the 1996 Act will not be applicable. As to the
construction of section 109, I can, however, say that I am inclined to agree with
Jackson LJ. I do not, therefore, think that it would have come to BB’s aid had I
not construed the contract as I have.
86 I have reached these conclusions without feeling the need to repeat the
well-known principles of statutory construction most recently summarised by Lord
Neuberger in Arnold v. Britton [2015] AC 1619. But I should say, perhaps, that I
have had regard to these principles and do not think they are contravened by my
construction. This is a case somewhat akin to Aberdeen City Council v. Stewart
Milne Group Limited [2012] SC (UKSC) 240 referred to by Lord Neuberger at
paragraph 22 in Arnold, where Lord Hope said (also at paragraph 22) that the
context showed that the intention of the parties was as he found it to be, and that
it could be assumed that that was what the parties would have said if they had been
asked about it at the time. The fact that it made good commercial sense was simply
a makeweight. In that case, as in this, the words of the contract itself told the reader
what must have been intended. Here the parties must have intended interim
payments to continue on the same basis up to practical completion. No undue
violence is required to the words the parties actually used to reach that construction.
87 I would allow this appeal.
B which they had expressly agreed not to adopt in the first place. In my judgment,
they made a new agreement and that new agreement covered the matters set out
in the Tumber schedule and no more.
91 The effect of the construction preferred by Vos LJ is (as he is happy to
acknowledge) to treat the schedule as if at the end it had added the rubric “etcetera”.
That effectively adds an important word which is additional to the agreement made
by the parties and is, to my mind, an impermissible construction.
92 For these short reasons I agree with Jackson LJ on the point of construction (as
on all other matters) and concur with him in dismissing this appeal.
JUDGMENT
MR JUSTICE FRASER:
Introduction
1 This is an application by Beumer Group UK Ltd (“Beumer”) against Vinci
Construction UK Ltd (“Vinci”) for certain declarations arising as a result of an
adjudicator’s decision dated 17 June 2016 by Dr Chern. That decision followed a
second adjudication between Beumer and Vinci (which I shall refer to as “BV II”).
Dr Chern was also the adjudicator on the first adjudication between the parties,
the details of which are not relevant to this application.
2 Beumer and Vinci had contracted for certain works to be performed by Beumer
at Gatwick Airport, namely a Works Package that comprised the Baggage Handling
System. That contract was dated 8 November 2012. Vinci was the Main Contractor
and Beumer was the Sub-Contractor. The Main Contract works concerned the
South Terminal Baggage and Pier 1 — Phase 2 works at Gatwick, and the Employer
is Gatwick Airport Ltd (“GAL”). The Main Contract is based upon the NEC 3
Engineering and Construction Contract, Option A. The Sub-Contract, as might be
The facts
6 Put briefly, on the same day that Beumer commenced BV II against Vinci,
namely 18 March 2016, it also commenced a second adjudication (“BL II”) against
Logan. That adjudication was also before Dr Chern. It concerned similar issues,
although within the context of the Logan sub-sub-contract, namely failure by Logan
to complete its works by particular dates and a claim by Beumer for liquidated
damages for delay. It therefore concerned delay. That adjudication was conducted
at the same time as BV II. However, Vinci did not know that there was a
simultaneous adjudication ongoing between Beumer and Logan in which Dr Chern
was the adjudicator, or of the content of the submissions Beumer made to Dr Chern
in that adjudication. Neither Beumer nor Dr Chern notified Vinci of this other
adjudication, and Dr Chern did not disclose to Vinci that he was acting
contemporaneously as an adjudicator in another dispute to which Beumer was a
party (whether on the same project, or at all).
7 Dr Chern had been named by Beumer as the potential adjudicator for the dispute
in BV II, based upon his having been chosen by both Beumer and Vinci to be the
adjudicator for BV I, the first adjudication between the parties, and because he
was one of the three individuals named in Option W2. He was in fact the only one
of those three with availability at the time of BV I. When that had occurred, in
February 2015, Vinci were not told by Beumer that Dr Chern had already been
appointed as the adjudicator in BL I. His involvement in adjudications between
Beumer and Logan was therefore not brought to Vinci’s attention until Beumer’s
solicitors responded to queries from Vinci’s solicitors in July 2016.
The Law
12 It is trite law that adjudication is a speedy process designed only to provide what
is called “interim finality” on construction disputes. Parliament intended that the
parties should be given a quick answer, and that quick answer should be binding
on the parties until the dispute, whatever it may be, is resolved finally either by
litigation or arbitration. It has been said in a case concerning what is called the
statutory Scheme, namely the statutory instrument entitled the Scheme for
Construction Contracts (England and Wales) Regulations 1998 (“the Scheme”),
by Chadwick LJ in paragraph [86] of Carillion Construction Ltd v Devonport
Royal Dockyard Ltd [2005] EWCA Civ 1358 [2006] BLR 15 that:
“The need to have the ‘right’ answer has been subordinated to the need to
have an answer quickly.”
Although made in a case under the Scheme, that statement is of wide application
to adjudications generally, whether under the Scheme or otherwise. Adjudicators’
decisions will be enforced by the court by summary judgment regardless of errors
of fact and/or law by the adjudicator. Aggrieved losing parties can and should
comply with the adjudicator’s decision, as long as that decision was made by an
adjudicator with jurisdiction over the dispute, who has conducted the adjudication
fairly and in accordance with the rules of natural justice.
13 The rules of natural justice have two limbs, and these are firstly, that a party
must have an opportunity to present his own case and meet the case against him,
and secondly, that the matter is decided by an impartial tribunal. It is the second
of those two limbs that concerns bias, both actual and apparent.
14 The submissions concerning natural justice relied upon by Vinci encompass
both limbs of the rules of natural justice, although the first limb is emphasised
more than the second. Chadwick LJ in paragraph [85] of Carillion Construction
Ltd v Devonport Royal Dockyard Ltd [2005] EWCA Civ 1358 [2006] BLR 15
stated that a decision should be enforced:
“…unless it is plain that the question which he has decided was not the
question referred to him or the manner in which he has gone about his task
is obviously unfair”.
In paragraph [87] he continued:
“To seek to challenge the adjudicator’s decision on the ground that he has
exceeded his jurisdiction or breached the rules of natural justice (save in the
plainest cases) is likely to lead to a substantial waste of time and expense….”
The proper course is to comply with the decision — which is after all only an
interim solution — and resolve the dispute with finality if the losing party considers
it is wrong.
15 In Amec Capital Projects Ltd v Whitefriars City Estates Ltd [2004] EWCA Civ
1418 [2005] BLR 1 Dyson LJ (as he then was) stated in paragraphs [20] to [22]
that adjudicators are almost always professionally qualified and, like judges, can
be assumed to be trustworthy and to approach matters with an open mind. In that
case, apparent bias was claimed by the losing party, that plea being based upon
the adjudicator having been previously involved in deciding an issue. The
adjudicator had reached the same decision on a subsequent adjudication, his first
decision having been declared a nullity. The matter was then referred to him again,
and the Court of Appeal held that his second decision was enforceable. His failure
to recuse himself, and the other matters relied upon by the losing party to found
apparent bias, were insufficient to lead the fair minded and informed observer to
conclude that there was a real possibility of bias.
16 It is therefore clear that for breaches of natural justice to be sufficient to justify
the court declining to order summary judgment enforcing an adjudicator’s decision,
they must be the plainest of cases; the adjudication proceedings must have been
obviously unfair. Combing through what has occurred, or concentrating on the
fine detail of the material before the adjudicator, to allege a breach of natural
justice, will neither be encouraged nor permitted by the court. Adjudications are
conducted very quickly, and this speed is part of the process imposed by Parliament
on those who enter into construction contracts. The framework within which
adjudicators have to reach decisions has to be taken into account when complaints
are made by losing parties.
Discussion
17 Putting the identity of the adjudicator to one side for the moment, the first factual
question that arises is whether Beumer did advance factually inconsistent cases in
each of the two adjudications.
18 Beumer’s claim in BL II was for time related damages, stated in Payment
Notices, and calculated in two ways as set out in paragraph 125 of Mr Francis’
witness statement. They were (i) “failure to meet the Key Date AOR estimated
£35,000 per day” and (ii) “failure to meet the section Subcontract Completion
Date 3 (AOR Commencement) £10,000 per day”. These are time related claims,
and the date for AOR forms a clear, central and obvious part of the calculation. If
there were any doubt about that — and in my judgment there cannot sensibly be
such doubt — it is clearly resolved by the findings Dr Chern made in his decision
in BL II, in which (for example) on Issue No.3 he stated on the issue of:
“Whether substantial completion has been achieved. I find that substantial
completion has not been achieved.”
The date of AOR is highly relevant to substantial completion of the works. Also,
on Issue No. 8 he stated on the issue of:
“Whether liquidated damages apply and if so is [Beumer] able to recover
both liquidated damages and costs, I find that [Beumer] is entitled to recover
liquidated damages for delay and reimbursement of its costs in completing
[Logan’s] works consequent to [Logan’s] failure (and which excludes costs
associated with delay)”.
I accept that Mr Francis accurately summarises Beumer’s case in BL II when
he stated in paragraph 144 of his witness statement that:
“In the second Beumer-Logan adjudication, Beumer’s position was that its
sub-sub-contractor, Logan, had not completed all of its works to permit AOR
to commence by 16 December 2015 (and…..Beumer was asserting Logan
had still not reached that stage as at 12 April 2016).”
19 Turning to the case that Beumer was advancing at the same time in its
adjudication against Vinci in BV II, this is most starkly put in paragraph 62 of its
Reply pleading in that adjudication, dated 21 April 2016, which stated the
following:
“It is the case that all the works of [Beumer] to allow AOR to commence had
been completed on 16 December 2015.”
That document in the adjudication was not settled by Mr Curtis QC, who
appeared for Beumer on this application. Mr Curtis QC was not instructed in any
of the adjudications, and did not take any part in them. It was not settled by counsel
at all, but by the solicitors acting for Beumer in BV II. It was put in issue by Vinci,
and again this is not in real doubt, but any doubt would be resolved by the Vinci
Rejoinder in BV II which in paragraph 7.2.2 stated:
“More importantly, the suggestion that Beumer’s sub-contract works were
AOR ready in December 2015 is clearly factually incorrect in any event.”
20 Mr Curtis QC developed an interesting argument that, when looked at in context,
and taking into account the later issue of the three CIs in March 2016, Beumer
was not advancing factually inconsistent cases in the two adjudications. I reject
those submissions. They were an attempt to work around what, in my judgment,
is a stark and inexplicable adoption of two entirely different factual cases advanced
by the same party at the same time, albeit in different adjudications. A central
element of the dispute between Beumer and Vinci in BV II concerned delay, and
this encompassed or included consideration of the date upon which the works had
(or had not) achieved the condition of AOR, a stage in the works important in the
contractual analysis of completion. This judgment does not make any findings
about what that date was, nor could it. However, it is clear that the adjudicator was
being told by Beumer in BV II that the works had reached that condition on 16
December 2015. The same adjudicator was being told by Beumer in BL II that the
works had not reached that condition, even by April 2016.
21 I find, therefore, that the two cases advanced by Beumer in each of the
adjudications were clearly factually inconsistent.
22 Mr Curtis QC submitted that even if they were, nothing flowed from that. He
adopted different routes to the same answer. One was that Beumer could have
argued what it chose, for example, in a mediation leading to a settlement with
Logan, and nobody would have been any the wiser. Whether that is correct or not,
this did not occur in a mediation, which is a consensual confidential process. It
occurred in adjudication, which for all its time pressures and characteristics
concerning enforceability, is still a formal dispute resolution forum with certain
basic requirements of fairness. Although adjudication proceedings are confidential,
decisions by adjudicators are enforced by the High Court and there are certain
rules and requirements for the conduct of such proceedings. Adjudication is not
the Wild West of dispute resolution.
[77], in a section from paragraph [76] to [83] dealing with disclosure generally.
That case was put before me by Mr Curtis QC and concerned a successful
application to remove an arbitrator. Adjudicators are not arbitrators, but in my
judgment are governed broadly by the same principles so far as disclosure is
concerned. Indeed, paragraph [33] of Cofely refers to the case of Eurocom Ltd v
Siemens plc [2014] EWHC 3710 (TCC) [2015] BLR 1 which was a case concerning
adjudication. Adjudicators are acting as impartial tribunals and although
involvement in other adjudications does not of itself constitute a conflict of interest,
that involvement should be disclosed.
30 It is important that adjudicators should not only act, but be seen to act, fairly.
It is for this reason, as an example, that unilateral telephone conversations should
be avoided. As Dyson LJ (as he then was) stated in paragraph [37] of Amec v
Whitefriars:
“I would accept that conversations between one party and the tribunal in the
absence of the other party should be avoided. Communications should
ordinarily be in writing with copies to all parties.”
Coulson J declined to grant enforcement of an adjudicator’s award for reasons
of apparent bias in Paice and Springall v MJ Harding Contractors [2015] EWHC
661 (TCC) [2015] BLR 345 based partly on a lengthy telephone conversation
between Mr Paice and Ms Springall and the adjudicator’s wife, who acted as his
office manager. In Discain Project Services Ltd v Opecprime Developments Ltd
(No.1) [2000] BLR 402 summary judgment was refused on the basis of apparent
bias, again based upon unilateral telephone conversations between one party and
the adjudicator.
31 If unilateral telephone calls are strongly discouraged (if not verging on
prohibited) due to the appearance of potential unfairness, it is very difficult, if not
in my judgment impossible, for an adjudicator to be permitted to conduct another
adjudication involving one of the same parties at the same time without disclosing
that to the other party. Conducting that other adjudication may not only involve
telephone conversations, but will undoubtedly involve the receipt of
communications including submissions, and may involve a hearing. If all that takes
place secretly, in the sense that the other party does not know it is even taking
place, then that runs an obvious risk in my judgment of leading the fair minded
and informed observer to conclude that there was a real possibility of bias. All of
this can be avoided by disclosing the existence of the appointment at the earliest
opportunity.
32 Mr Lewis relies upon a decision of HHJ Humphrey LLoyd QC in Pring & St
Hill Ltd v CJ Hafner trading as Southern Erectors [2002] EWHC 1775 (TCC). In
that case, the adjudicator had conducted an earlier adjudication between Pring and
the main contractor. Pring had been engaged by Sir Robert McAlpine Ltd
(“McAlpine”) as a glazing sub-contractor on a new building in Cardiff. McAlpine
was the main contractor. The defendant (“SE”) was Pring’s sub-sub-contractor.
SE successfully resisted enforcement, because Pring had not disclosed to it the
earlier decision of the adjudicator in the McAlpine adjudication, which the judge
referred to as Adjudication No.2, and to which SE was not a party. The adjudicator
himself had tried to persuade Pring to disclose this decision to SE, but Pring had
refused. The judge stated in paragraph [29] that SE:
“…was right to infer that there was something in Adjudication No.2 that
might have been relevant to its case in [the relevant] adjudication and of
which [the adjudicator] was aware but which he did not or could not
reveal…..The more material point is whether the information might be relevant
to SE.”
The judge also stated later in the same paragraph that the instant decision may
have been affected by the adjudicator’s prior knowledge which he ought to have
but did not (or could not) disclose, and also that SE had not been treated fairly
because the adjudicator:
“…had in effect communications with [Pring] (via Adjudication No.2) to
which SE was not a party”.
33 Mr Lewis submits that had BL II been conducted slightly early and resulted in
a decision prior to the adjudication in BV II, this authority makes it clear that Vinci
would have been entitled to see the decision in BL II. The test is relevance to the
issue or issues in BV II, and whether it would (or could) have affected how Vinci
chose to put its case. He posed the test as being: would such an earlier decision
have given Vinci the ability to make further, different, or alternative submissions
which the lack of disclosure denied? I accept those submissions. If Vinci would
have been entitled to see any such earlier decision in BL II, had the timing been
different, I turn to consider whether the position is any different because the
adjudications were commenced at the same time. In my judgment, the position is
no different. If, as here, the adjudications took place at exactly the same time, then
the decision cannot be provided because it did not exist. But at the very least, in
my judgment, the Referral document, the Response, and so on — what are
conventionally referred to as the pleadings in the adjudication — should have been
provided to Vinci. This is because the disputes were so closely connected and the
issues so similar. It will be a matter of fact and degree in any case (or more
accurately, two cases) whether this applies, but here in my judgment it clearly
does. It might be that the two adjudications were commenced by Beumer on the
same day deliberately so that neither Logan nor Vinci could see that Beumer was
adopting a contrary position in each adjudication. It might, however, have been
simply coincidence. It is not necessary to speculate.
34 Mr Lewis also relies upon London and Amsterdam Properties Ltd v Waterman
Partnership Ltd [2003] EWHC 3059 (TCC) where HHJ Wilcox stated in paragraph
[89] that:
“It is a fundamental requirement that any reliance upon previously acquired
relevant knowledge by an adjudicator is made known to the parties to the
adjudication, so that both have an opportunity to deal with it, should it be
likely to or if it does in fact affect his decision materially. A professionally
qualified person who is an adjudicator appointed by a body such as the RICS
must be presumed to be aware of such a basic ingredient of any fair hearing
which accords with the requirement of natural justice”.
The requirement of natural justice to which the judge is referring is the first
limb, namely a party’s ability to meet the case against him. Mr Curtis QC argues
that it can be seen from the two decisions in the two adjudications that Dr Chern
scrupulously confined himself to the submissions before him in each adjudication.
However, that submission cannot meet the argument that Vinci must be given a
fair opportunity to put its own case, and an important element of that case (that
Beumer was advancing a case that Logan’s works remained incomplete, which
supported Vinci’s case against Beumer) could not be put.
35 Mr Curtis QC used the Scheme, and in particular paragraph 8(1) and 8(2), by
way of contrast with Option W2.3(3a) and W2.3(3b), to explain the involvement
of Dr Chern in both adjudications at the same time and amplify what he called the
“ Amec default position” in terms of the legal ability of the adjudicator in this
respect to conduct two adjudications at the same time. Option W2.3(3a) and
W2.3(3b) gives the adjudicator the power to conduct adjudications between the
contractor (Vinci), the sub-contractor (Beumer) and the sub-sub-contractor (Logan)
at the same time, and together, if the same matter is disputed under both the
sub-contract and sub-sub-contract. The consent of the sub-sub-contractor is
required. Paragraph 8(1) of the Scheme contains a similar provision if disputes
arise under the same contract. Paragraph 8(2) of the Scheme is relied upon by Mr
Curtis QC principally. This states:
“The adjudicator may, with the consent of all the parties to those disputes,
adjudicate at the same time on related disputes under different contracts,
whether or not one or more of those parties is a party to those disputes.”
Mr Curtis QC also relies, to support his argument on paragraph 8(2) of the
Scheme, on the dicta in HHJ Humphrey LLoyd QC in Pring where at paragraphs
[13] to [15] he considered the different contentions in that case concerning the
effect of simultaneous adjudications and what “related disputes” actually meant.
However, what was decided in that case was set out in paragraph [16] where the
judge stated that paragraph 8(2):
“…is intended to cover all the situations in which there may be related disputes
under different contracts, whether or not the parties are the same and whether
or not there may permissibly be consolidation of the two proceedings”.
This requires consent of all the parties, and is in any event only something that
arises under the Scheme, which did not apply to these adjudications in any event.
I do not consider that this argument concerning paragraph 8(2) assists Mr Curtis
QC at all. Under the terms of Option W2.3(3a) and W2.3(3b), the two adjudications
could have been dealt with together, if the necessary consent had been forthcoming.
However, that is not what happened.
36 Mr Curtis developed his argument by submitting that Vinci are, in effect, seeking
to have a similar provision to paragraph 8(2) of the Scheme implied into Option
W2. In other words, his submission is that Vinci’s case in reality is that because
Vinci did not consent, the adjudicator could not do what he in fact did (conduct
two adjudications at the same time) precisely because he did not have Vinci’s
consent. I do not accept that Vinci are seeking to have an implied term read into
Option W2. Also, with respect to Mr Curtis QC, there is a danger in considering
by analogy what the Scheme does include, and applying it to Option W2 at all.
Option W2 satisfies the requirements of the legislation and as such the Scheme
does not apply at all. Dr Chern was entitled to conduct the two adjudications at
the same time. He should however have disclosed to Vinci that he was acting on
the other one between Beumer and Logan for the reasons that I have explained.
37 Vinci challenges the fundamental fairness of the proceedings before the
adjudicator, based partly upon the fact that he was conducting a parallel adjudication
contemporaneously on similar issues involving the same project, and the same
party (Beumer), and did not disclose this. It is also partly based upon the fact that,
as a result of this, Vinci was not provided with the necessary material to know that
this other adjudication involved Beumer advancing a factually inconsistent case
on the relevant date for AOR in BL II, to that advanced by Beumer in BV II. I
should also say that I would expect the result on enforcement to be the same in
terms of breaches of natural justice, whether an adjudication were conducted under
Option W2 or under the Scheme.
38 It is entirely correct to read Amec v Whitefriars, which is relied upon by Mr
Curtis QC, as stating that adjudicators can be trusted to approach matters with an
open mind, and to decide disputes only on the evidence and material placed before
them on that particular dispute. That is plain, in particular, from the passages in
the leading judgment of Dyson LJ (as he then was) at paragraphs [20] to [22].
Further, in paragraph [21] the following is stated:
“There needs to be something of substance to lead the fair minded and
informed observer to conclude that there is a real possibility that the tribunal
will not bring an open mind and objective judgment to bear.”
That is dicta clearly directed at the second limb of the rules of natural justice,
namely the impartiality of the tribunal. The “something of substance” here is the
appointment of Dr Chern in BL II at the same time, and the conducting of that
adjudication, with all that involved in terms of contact with Beumer, without
notifying Vinci of that fact.
39 The same approach could be said equally to apply to the first limb, namely there
must be “something of substance” to found a complaint of breach of natural justice
generally. That could be just another way of stating that any breach of natural
justice must be material, or plain and obvious. In this case, the “something of
substance” is not only the circumstances of the other adjudication, including the
non-disclosure both of its existence at all, and that Dr Chern was also the
adjudicator. It also includes the consequential keeping from Vinci (as a direct
result of that) of the factually inconsistent case Beumer was advancing in the other
adjudication. In my judgment, the fair minded and informed observer would come
to the conclusion, having considered the matter with the necessary care and only
taking into account relevant matters, that something had gone rather obviously
wrong and that this was a plain case of breach of natural justice.
40 Another important point is that Option W2.3(4) gives the adjudicator the power
both to instruct a party to provide further information related to the dispute within
a stated time, and to instruct a party to take any other action which he considers
necessary to reach a decision. I interpret those powers as including the power to
order (for example) that Beumer disclose documents to Vinci. Vinci were denied
any opportunity of asking the adjudicator to exercise his power to do this in relation
to Beumer’s submissions or pleadings in BL II, because Vinci did not know at the
relevant time that the other adjudication even existed, and so did not know that
such other documents existed. Dr Chern doubtless did not order Beumer to disclose
the relevant documents in the BL II adjudication to Vinci, because Vinci did not
ask him to do so. In my judgment, this made the adjudication proceedings between
Beumer and Vinci unfair.
41 Mr Curtis QC also relied upon lack of materiality were I to find any breach, or
breaches, of natural justice. BV II concerned declarations that the three CIs in
question were compensation events. Paragraph 2.1.1 of Beumer’s Referral states
the following in terms of the subject matter of the adjudication:
“2.1.1 The matter in dispute is in relation to whether certain Contractor’s
Instructions constitute compensation events and their effect on the
Completion Date for the Subcontract Works.”
Clause 62.2 of the Subcontract states:
“62.2 ….compensation events comprise proposed changes to the Prices and
any delay to the Subcontract Completion Date and Key Dates assessed
by the Subcontractor….”
Clause 63.3 of the Subcontract states:
“63.3 A delay to the Subcontract Completion Date is assessed as the length
of time that, due to the compensation event, planned Completion is
later than planned Completion as shown on the Accepted Programme.
A delay to a Key Date is assessed as the length of time that, due to the
compensation event, the planned date when the Condition stated for
a Key Date will be met is later than the planned date shown on the
Accepted Programme”.
There was no current Accepted Programme as at the time of BV II, but the above
clauses show that the question of delay is integral to consideration of compensation
events. The condition of the works therefore, and whether they were AOR ready
in December 2015, was part of the factual matrix being considered by Dr Chern
in considering whether the three CIs in question were compensation events.
42 I fail to see in those circumstances, and given the terms in which Beumer itself
framed the dispute, how it could be said that the date upon which Beumer’s works
were in a condition of AOR was anything other than of relevance. It is not necessary
to predict with certainty what Dr Chern would have done, or what findings he
would have made, had Vinci been given the opportunity to draw his specific
attention to the fact that its case on this point was substantiated by Beumer’s very
own submissions on the very same point in BL II. It is not always easy, and may
on occasion be verging on impossible, to assess the impact of any particular
submission upon the thought processes of the decision making tribunal. It might
very well be the case that the three CIs are compensation events. What is important
is the materiality of the breach of natural justice, and the fact that Vinci was denied
the opportunity of making that submission.
43 Further written submissions were received from Beumer following the hearing,
making the point that the first adjudication between Beumer and Vinci had made
findings that were binding on the parties concerning the operation of the time
machinery in the Sub-Contract. These submissions go to materiality. I therefore
invited a response on this limited point from Vinci. It is clear that the first
Beumer-Vinci adjudication concerned sectional completion dates, not the overall
Sub-Contract completion date. Accordingly, those further submissions do not
affect the materiality of the date for AOR in the second Beumer-Vinci adjudication.
Conclusion
44 In my judgment, therefore, the breach of natural justice was plainly material.
The question of the correct date for AOR was central to considerations of delay,
and delay was central to considerations of whether instructions were indeed
compensation events. The breach of natural justice is sufficiently material that the
decision will not be enforced.
45 Turning therefore to the different issues on this application for summary
judgment set out in paragraph 11 above, the answers are as follows:
Issue 1.
(a) Did Beumer advance factually inconsistent cases in each of the two
adjudications, BV II and BL II?
Answer: Yes
(b) If so, what if any consequences flow from that?
Answer: The consequences that flow are as follows. Beumer’s
advancing of an inconsistent case in the second Beumer-Logan
adjudication could have been specifically relied upon by Vinci as
supporting Vinci’s own case concerning the correct date for AOR.
Vinci was deprived of the opportunity of making submissions to this
effect.
(c) and (d) Was Vinci entitled to be provided with any relevant material
from BL II and if so, what consequences flow from the failure to do
so?
Answer: Vinci was entitled to have sought an order from the
adjudicator for such material. Vinci was deprived of the opportunity
to do so because the other adjudication’s existence was kept from it.
Had such an application been made by Vinci, the adjudicator would
have been likely to have ordered such disclosure in order to conduct
those proceedings fairly.
Issue 2
(a) Should Dr Chern have disclosed to Vinci that he was acting as
adjudicator on another matter, involving Beumer, at the same time as
he was acting as adjudicator in the dispute between Beumer and Vinci?
Answer: Yes
(b) If the answer to that is No, does the fact that the other matter concerned
Beumer and Logan on the same project and Beumer’s works for Vinci
mean he should have disclosed this to Vinci?
Answer: This does not arise
1
Paragraph numbers are as assigned by the court.
guarantor contended that the only trigger for its obligation to pay was a breach
under cl.1, not an insolvency event under cl.2, and there had been no breach because
the validity of the original termination had been disputed by contractor.
H3 Held, granting declarations in terms to be agreed:
(1) If cl.2 were subsidiary to cl.1 in such a way that cl.2 did not operate on the
occurrence of an insolvency event, that would mean that the employer could
never recover against the guarantor for losses due to insolvency, contrary
to the clear purpose and intent of cl.2.
(2) The debt had been asserted but not paid and the contractor was therefore
in breach of the building contract because it had not paid: dictum of Peter
Gibson LJ in Perar applied.2
H4 Alexandra Bodnar appeared for the claimant employer, instructed by Walker
Morris LLP.
Seb Oram appeared for the defendant guarantor, instructed by Clarkslegal LLP.
1. Introduction
1. Pursuant to a building contract incorporating the JCT 2011 standard form, the
claimant employed County Contractors (UK) Limited (“County”) to build blocks
of student studios at 19-26 Claremont Place, Newcastle Upon Tyne (“the site”).
County’s performance was the subject of a Performance Guarantee Bond (“the
Bond”) provided by the defendant to the claimant and dated 28 January 2015.
Following County’s suspension of the works and insolvency, other contractors
were engaged by the claimant to complete the works. The additional costs were
claimed from but not paid by County. A subsequent claim was made on the Bond
which has not been satisfied.
2. By a claim form issued on 3 October 2017, under CPR Part 8, the claimant seeks
three declarations as to the true construction of the Bond. The claims for the first
two declarations are resisted by the defendant, although the third has been belatedly
agreed.
3. I propose to deal with the issues between the parties in this way. In Section 2,
I set out the relevant terms of the building contract and the Bond. In Section 3, I
set out a brief chronology of the relevant events. In Section 4, I set out the
declarations sought by the claimant. In Section 5, I summarise the relevant
principles of interpretation and the applicable authorities relating to performance
bonds of this kind. Then, in Sections 6, 7 and 8, I deal with each of the three
Declarations. I am very grateful to both counsel for their thoughtful skeleton
arguments and concise oral submissions.
2
Perar BV v General Surety & Guarantee Co Ltd (1994) 66 B.L.R. 72.
…
Termination by Employer
8·4 Default by Contractor
·1 If, before practical completion of the Works, the Contractor:
·1 without reasonable cause wholly or substantially
suspends the carrying out of the Works or the design of
the Contractor’s Designed Portion; or
·2 fails to proceed regularly and diligently with the Works
or the design of the Contractor’s Designed Portion; or
·3 refuses or neglects to comply with a notice or instruction
from the Architect/Contract Administrator requiring
him to remove any work, materials or goods not in
accordance with this Contract and by such refusal or
neglect the Works are materially affected; or
·4 fails to comply with clause 3·7 or 7·1; or
·5 fails to comply with clause 3·23;
the Architect/Contract Administrator may give to the Contractor
a notice specifying the default or defaults (the ‘specified default
or defaults’).
·2 If the Contractor continues a specified default for 14 days from
receipt of the notice under clause 8·4·1, the Employer may on,
or within 21 days from, the expiry of that 14 day period by a
further notice to the Contractor terminate the Contractor’s
employment under this Contract.
·3 If the Employer does not give the further notice referred to in
clause 8·4·2 (whether as a result of the ending of any specified
default or otherwise) but the Contractor repeats a specified
default (whether previously repeated or not), then, upon or
within a reasonable time after such repetition, the Employer
may by notice to the Contractor terminate that employment.
8·5 Insolvency of Contractor
·1 If the Contractor is Insolvent, the Employer may at any time
by notice to the Contractor terminate the Contractor’s
employment under this Contract.
·2 The Contractor shall immediately notify the Employer if he
makes any proposal, gives notice of any meeting or becomes
the subject of any proceedings or appointment relating to any
of the matters referred to in clause 8·1.
·3 As from the date the Contractor becomes Insolvent, whether
or not the Employer has given such notice of termination:
·1 clauses 8·7·3 to 8·7·5 and (if relevant) clause 8·8 shall
apply as if such notice had been given;
·2 the Contractor’s obligations under Article 1 and these
Conditions to carry out and complete the Works and the
design of the Contractor’s Designed Portion shall be
suspended; and
8. It should be noted at the outset that the Bond was in standard ABI Model Form
with one important exception: clause 2 was an entirely homemade addition, and
must therefore be taken to have been added by the parties to meet their particular
requirements.
particulars of this dispute were promised, but have never been provided, either by
County or by the defendant.
16. As for the claim on the Bond, in a letter from the defendant dated 12 July 2017,
the defendant’s position was summarised as follows:
“As the bond is a default bond and not a demand instrument, it must be proven
that a breach of contract has taken place and that losses have been incurred
as a result of that breach before a claim can be made upon it.
We are aware that County Contractors (UK) Limited and Ziggurat (Claremont
Place) LLP are in dispute regarding the purported breaches of contract, the
resolution of which needs to be established via the terms and conditions of
the underlying construction contract.
Until a formal decision as to whether County Contractors (UK) Limited has
breached the underlying construction contract and a formal ruling upon the
extent of the losses therefore arising have been established, HCC deny that
any payment is due.”
and/or damages, including any debt or other sums payable (for the purpose
of a claim under paragraph 2 of the bond), in Court proceedings against [the
defendant]. There would be no requirement for [the claimant] to issue
proceedings against [County] first or at all in order to establish these matters.”
20. It is right to note at the outset that, in my view, these declarations are
unnecessarily prolix. More significantly, they do not always reflect the arguments
that were so skilfully advanced by both counsel. Up to a point, this reflects the
uncertain and fluid nature of civil litigation, and no substantive criticism is intended
of either side. But I cannot help feeling that these Part 8 proceedings were not
perhaps the best vehicle for resolving the underlying issues, and that it would have
been much better if the arguments had arisen on an application for summary
judgment under Part 24. Then at least the tramlines introduced by the draft
declarations would have been unneccessary.
21. Following the production of Mr Oram’s skeleton argument, as I have indicated,
Declaration 3 is no longer in issue.
if they were pursuing the contractor. Judge Lloyd rejected that submission. He
said that “the obligation of the surety is relative to the obligation of the contractor
under the terms of the contract; as one might expect in approaching any bond, the
obligation of a surety is simply to stand behind that of the debtor (the contractor)
and not to be under any greater liability than the contractor would have had.”
25. Thirty years ago, there were regular arguments about performance bonds of this
kind provided in support of building contractors. Many of those arguments arose
because the performance bond was only triggered if the contractor was in breach
of contract and so, if the contractor became insolvent, and the contract was
terminated, it was argued that that was not a breach, and that there was therefore
no liability under the bond. In this way, given the unhappy habit of building
contractors becoming insolvent, both then and now, the secondary liability market
was not reflecting the reality of the construction industry.
26. However, those issues were largely resolved by the Court of Appeal in Perar
BV v General Surety and Guarantee Co Limited (1994) 66 BLR 72. In that case
the Court of Appeal held that the automatic termination of the contract following
the insolvency of the contractor did not amount to a breach of contract, with the
result that there was no right to immediate payment under the bond merely because
the contractor did not continue to execute the works. Insolvency alone did not
therefore give rise to any payment entitlement.
27. However, Peter Gibson LJ noted that clause 27.4.5 of the contract under
consideration contained a provision which allowed the calculation of a sum due
under the contract following determination. This provision culminated in a debt
payable by one side to the other. It was a forerunner of the provisions of clause
8.7 in the building contract between County and the claimant. Peter Gibson LJ
went on to say that, in Perar, there had never been a claim under clause 27.4.5,
and that:
“Had a claim been made, as the contract envisaged, it may well be that these
proceedings would have been avoided, as plainly any consequent failure by
the contractor to pay any such demand, if properly made, would have enabled
a claim to be made under the bond…”
In other words, insolvency would lead to a breach (and thus a claim under the
bond) if the employer had followed the provisions of the contract and established
a debt due, and the debt remained unpaid by the contractor.
28. The importance of the contractual ascertainment exercise was restated in
Paddington Churches Housing Association v Technical and General Guarantee
Co Limited [1999] BLR 244. Again, that was a claim on a bond in the absence of
any ascertainment of the debt due under clause 27. Judge Bowsher QC reiterated
both the secondary liability that arose under the bond and the importance of the
contractual mechanism. At paragraph 24 he said:
“The defendants are liable as surety only, and it seems to me to be plain on
the face of the bond that the defendants are liable to pay the amount (if any)
shown to be due to the plaintiffs on a statement made by the employer in
accordance with the terms of the contract. That contract was imported into
the bond by the recitals. Clause 27 of that contract is referred to specifically
in the conditions. Both in case of default and in case of determination on
insolvency (or indeed in any case where it were relevant, for corruption) the
damages are calculated by reference to the code of the contract, which are in
any event unlikely to be different from the damages at general common law.
The accuracy of the employer’s statement might be challenged in the courts,
but the employer’s statement is required before the damages can be said to
be ascertained and there is no liability on the defendants until those damages
are ascertained. The plaintiffs submit that the employer’s statement is only a
mechanism and not a condition precedent to payment, but no other mechanism
for ascertaining the net damages is put forward or relied on by the plaintiffs.”
29. The judge said that the absence of the statement was fatal to the employer’s
claim. At paragraph 30 he said that, “When such a statement is provided, if it
shows a net sum due to the plaintiffs, the defendants will become liable up to the
amount of the bond.”
30. In the present case, the relevant provisions at clauses 8.5 and 8.7 of the 2011
standard form have been the subject of recent consideration by the Court of Appeal
in Wilson and Sharp Investments Limited v Harbour View Developments Limited
[2015] EWCA Civ. 1030. That case was concerned with an appeal against a refusal
by the first instance judge to allow the appellant an injunction to restrain the
defendant from presenting a winding up petition. The issue was whether an accrued
debt could be payable after termination. The judge concluded that clauses 8.5.3
and 8.7.3 could have no application if the contract had already been terminated
prior to the insolvency.
31. The Court of Appeal rejected that conclusion. The critical paragraphs for present
purposes are paragraph 49 and 50 of the judgment of Gloster LJ which were in
the following terms:
“49. First, it is clear that the provisions of clause 8.7.3 are intended to
operate after termination of the contract. Indeed the entire scheme of
clauses 8.7 and 8.8 are directed at setting out the respective rights and
obligations of both parties after the contractor’s employment under
the contract has been terminated by the employer and necessarily the
contract has come to an end: see the opening words of clause 8.7 –“if
the Contractor’s employment is terminated under clause 8.4, 8.5 or
8.6”. To similar effect is clause 8.12 which addresses the consequences
of termination by the contractor under clause 8.9 or by either party
under clause 8.11 upon the happening of certain specified events.
There is no wording in clause 8 which in any way suggests that the
consequential provisions are not to apply after termination, or are not
to apply after a termination by the contractor (pursuant to the saving
provisions of clause 8.3.1) on the grounds of repudiatory breach (as
opposed to pursuant to the express termination provisions contained
in 8.4, 8.5 or 8.6).
50. Second, clause 8.5 (“Insolvency of Contractor”) has a wider ambit
than simply conferring a right of termination on the employer in the
event of the contractor’s insolvency. Thus clause 8.5.2 imposes an
obligation on the contractor immediately to notify the employer if the
contractor makes any proposal, gives notice of any meeting, or
Special Administration) [2013] 1 WLR 903. Mr Oram said that, depending on the
precise nature of the contractor’s insolvency, the measure of damages at common
law might not necessarily be that provided for in clause 8.7, and so clause 2 of the
Bond was making it plain that, irrespective of any theoretical difference in the
measure, the loss recoverable under the Bond would be calculated in accordance
with clause 8.7.
43. In my view this is an unrealistic and convoluted interpretation of clause 2. Under
a building contract, the employer does not care about the precise way in which the
building contractor has become insolvent, or the nice distinctions between
liquidation and administration. All he cares about are the consequences of the
insolvency, which almost always include the abrupt halt to the carrying out of the
works. The employer’s loss in these situations is always the same: the additional
cost of completing the works. That is why the provisions under clause 8.7 are so
clear. So, in my view, clause 2 of the Bond can have had no purpose whatsoever
other than to make it clear that the Bond was to protect the claimant from the
non-payment by County of the debt following the insolvency.
44. There were a number of other minor points as to how, if this was the correct
reading of the Bond, then it would be inconsistent with other references to ‘breach’
alone, such as in clause 5. But in my view, these were simply the consequence of
the parties adding the homemade amendment at clause 2 to cover insolvency, and
then failing to amend the other ABI Model Form provisions at the same time.
These matters cannot affect the proper interpretation of this Bond.
intended to work. Indeed, it is as a result of this that the ABI guidance suggests
that there is no need to amend the model form of the Bond to stipulate that
insolvency or automatic determination will be treated as a breach of contract. On
this basis, the defendant’s stance might be regarded as somewhat surprising because,
on the face of it, it is seeking to undermine the guidance notes of its own
professional body.
6.3 Conclusions
53. For these reasons, I find in favour of the claimant in respect of the interpretation
of the Bond. But I do not grant Declaration 1 as drafted. Declaration 1(a) omits
any reference to the debt and non-payment, and Declaration 1(b) is erroneous
because, even if breach is required, the relevant breach is the non-payment of the
debt, and not the circumstances which led up to the termination.
54. I am sure that counsel can agree a Declaration which succinctly summarises my
conclusions on this topic.
59. In response, Mr Oram said that the judgment in Paddington Churches also noted
that, although a claim could be made in those circumstances, the surety could
defend himself against the claim by advancing any of the arguments as to the
quantum of the debt (a challenge to “the accuracy of the employer’s statement”)
which would have been available to County. He points to the fact that clause 8.7
does not say that the ascertainment and assertion of the debt was in some way
conclusive, and compares that with the provisions relating to, for example, the
Final Certificate, which do contain various conclusivity provisions.
60. In my view, Mr Oram is right on this topic. It is only necessary to consider what
the position would have been under the building contract to see that, as a matter
of principle, the debt figure can be challenged by the defendant. Let us assume
that the debt was asserted by CAG, and that County had then produced a twenty
page critique of the accounting and quantity surveying methodology that had been
adopted, in order to demonstrate that only 20% of the sum asserted was actually
due. County could not be shut out from advancing that defence. There is nothing
in the contract to say that they could not challenge the figure, and there are no
provisions which indicate that, as soon as the figure was asserted, it was due and
payable in the amount asserted, without any ability to challenge. And if County
could have made that challenge, then so too can the defendant.
61. Of course, because these are Part 8 proceedings, I cannot go further than to say
that, as a matter of contractual interpretation, the debt figure of £621,798.38 asserted
on 10 March 2017, is not necessarily conclusive. I cannot go on to reach any other
conclusions. But it is appropriate to observe that, on the facts of this case, the
defendant may be in difficulties in mounting a challenge: other than the general
words of challenge in the latter of 12 April 2017 (“in any event the sums claimed
by Ziggurat are disputed”), County have been entirely silent on how and why the
debt figure may be wrong. The defendant has not set out any case at all on that
topic. In addition, in view of the margin (that is to say, the difference between the
debt asserted of £621,000 odd, and the maximum amount of the Bond of
£382,519.06) any arguments on quantum may not avail the defendant over-much.
62. It follows from all this that the words of Declaration 2 are inapt. They do not
address the actual debate between the parties. It was eventually agreed that the
claimant did not have to pursue County and did not have to reach an agreement
with them. The claimant can rely on the debt in its claim against the defendant
under the Bond but, to the extent that Declaration 2 was seeking to suggest that
the debt was conclusive and could not be challenged by the defendant as a matter
of principle, then I reject that argument.
63. As above, I am sure that counsel can agree a succinct Declaration which
summarises the views expressed on this subject.
Commentary
C1 The proliferation of reported decisions about “on-demand” performance bonds
in the last few years might have led the unwary reader into concluding that the
conditional bond had become, like the telex message and Pears Cyclopaedia,1 a
thing of the past. But it is not so, as the case under consideration demonstrates.
The contractor carrying out the construction of some student accommodation in
Newcastle provided a “performance guarantee bond”, which although it was in
standard Association of British Insurers Model Form, had one important exception:
cl.2 was a bespoke addition. As Coulson J observed (at [23]), a bond of this sort
is an instrument of secondary liability, with the result that the surety cannot be in
a worse position, as against the employer, than the contractor. His Lordship then
referred (at [26]) to the decision of the Court of Appeal in Perar that the automatic
termination of a contract in JCT form following the insolvency of the contractor
did not amount to a breach of contract, with the result that there was no right to
immediate payment under the bond merely because the contractor did not continue
to execute the works. Insolvency alone did not therefore give rise to any payment
entitlement.
C2 The difficulty faced by the plaintiff in Perar was that the bond provided that
any proceedings against the Surety to recover any claim had to be served within
six months after 1 March 1992 and required the employer to give written notice
within 14 days after any breach or default. The contractor went into administrative
receivership on 7 June 1991 before the works were completed, and the works not
been completed within the six-month period specified. Proceedings were issued
on 14 August 1992 on the basis that the contractor had been in breach of its
obligation to carry out and complete the works. At first instance His Honour Judge
Michael Rich QC, raised the point that the contractor that as a result of an automatic
termination of the contractor’s employment upon its insolvency, it had been under
no obligation to continue with or complete the works,2 and the Court of Appeal
upheld this decision.
C3 In doing so, the court had to be deal with the point that the bond referred to
“breach of or default in any of the terms and conditions contained in the said
Contract”. The plaintiff contended that effect had to be given to that wording by
distinguishing between a “default” and a “breach”, with the result that the
contractor’s non-fulfilment of its obligations under the contract amounted to a
default justifying a call on the bond. The Court of Appeal rejected this distinction
and held that “default” meant the same thing as “breach”, leading the late I.N.
Duncan Wallace Q to describe this construction as “flatly contrary to the obvious
business purpose of the bond”3 and to observe:
“This decision robbed the bond of all commercial value and whether on a
contra proferentem or officious bystander or business efficiency basis seems
open to question.”4
1
The final edition was published on 31 August 2017.
2
It should be disclosed that your commentator was counsel for the plaintiff in that case.
3
I. Duncan Wallace, “Loose Cannons in the Court of Appeal: On Demand Per Icuriam?”, (1994) 10 C.L.J. 190,
195.
4
A. Hudson and I.N. Duncan Wallace (eds), Hudson’s Building & Engineering Contracts, 11th edn (London:
Sweet & Maxwell,1995), Vol.II, p.1512, para.17-012.
Nevertheless, Peter Gibson LJ did make the observation relied upon by Coulson
J in the case under consideration that had a claim been made under the express
contractual terms relating to termination
“it may well be that these proceedings would have been avoided, as plainly
any such demand if properly made under the bond, provided such claim was
timeous”.
The obvious problem with that approach was, of course, that the time limit in
the bond for bringing proceedings would have expired before any account could
be drawn up on completion of the works, permitting the plaintiff to make such a
demand. This remains a problem with the JCT forms. Paddington Churches,5
referred to by Coulson J at [28], confirmed that the employer’s statement under
the JCT with Contractor’s Design 1981 edition was required before the damages
could be said to be ascertained and there was no liability under the bond until those
damages had been ascertained. The position is different under the successor to the
Infrastructure Conditions of Contract (which defines insolvency as a default)
where the engineer certifies the appropriate sum whether or not the works are
completed under a separate contract and may issue an interim certificate that
becomes a debt due to the employer.6 It should be added that the real mischief of
thePerar case lay in the adoption of a specific period running from a certain date
during which proceedings claiming on the bond had to be issued. By way of
contrast, the ABI model form of bond contemplates the insertion, as the expiry
date of the bond, of an event such as the issue of a certificate of practical completion
and there is authority to suggest that practical completion of the works by another
contractor would not constitute practical completion under the contract so as to
extinguish the liabilities of the guarantor: see Glasgow City Council7 and De Vere
Hotels.8
C4 The contractual limitation period difficulty did not arise, however, in the case
under consideration because following completion and the making good of defects,
an account was prepared in accordance with the building contract, which indicated
a balance due to the employer, and a demand for that sum was made less than a
year after the act of insolvency ([11] and [12]) and there does not seem to have
been any applicable time limit. Coulson J found (at [34]), under cl.2 of the bond,
that the damages payable by the guarantor to the employer included “any debt or
other sum payable to the Employer under the Contract following the insolvency”,
and on the facts, there was a debt payable under the building contract. In doing so
he rejected the guarantor’s argument that that the only trigger for the obligation
to pay was a breach, not an insolvency event ([40]–[43]). This is consistent with
an inference that could be drawn that the wording of the relevant provision of the
bond had been specially drafted to address the Perar point about an act of
insolvency not being a breach. In the event this amendment of the standard form
proved unnecessary, given the court’s decision that there had been a breach.
5
Paddington Churches Housing Association v Technical and General Guarantee Co Ltd [1999] B.L.R. 244; 65
Con. L.R. 132; (2000) 16 Const. L.J. 216.
6
Infrastructure Conditions of Contract, 2014 edn., cl.15.6.
7
Glasgow City Council v Excess Insurance Co Ltd 1986 S.L.T. 585.
8
De Vere Hotels Ltd v Aegon Insurance Co (UK) Ltd [1997] EWHC Technology 354.
C5 The Tower of Babel is thought to have been a ziggurat, the building of which
gave rise to the confusion of tongues.9 Perhaps we can hope to encounter less
confusion about the effect of insolvency provisions and performance bonds as a
result of this decision.
9
Genesis ix, 1–9.