Вы находитесь на странице: 1из 57

O'NIRE ELECTRICAL ENTERPRISE (7TH APRIL, 2017.

PRICE OF NEW DISTRIBUTION TRANSFORMERS.

PRODUCTS/MAKERS: MALETEC, ABB OR EQUIVALENT


S/NO. RATING (KVA) VOLTAGE LEVEL WINDING UNIT PRICE (N) REMARK
1 200 33/0.415KV CU 2,400,000.00 1-YEAR WARRANTY
2 300 33/0.415KV CU 3,700,000.00
3 500 33/0.415KV CU 5,270,000.00
4 200 11/0.415KV CU 2,250,000.00
5 300 11/0.415KV CU 3,250,000.00
6 500 11/0.415KV CU 3,850,000.00
33KV ELECTRIFICATION PROJECT TITLE:

DATE: DATE:

Description
Sr. No. of Items Unit price Qty Total Price
Sr. No.

=N= =N=

PRELIMINA
A RIES A

Provision For
Supervising
Engineers,
Vehicle, office
stations,
office
1 equipment Lot Sum ### 1
Provision For
Supervising
Engineers
travel and
transport
through out
2 project period Lot sum ### 2

Assistance to
contractor for
3 site take-over Lot Sum ### 3

Assistance to
employer for
payment of
engineere
allowances
and Sundry
4 reinbureables Lot sum ### 4
Provision of
site office and
store
constructed
to engineers
5 specifications Lot Sum ### 5

Provision of
pre-
installation
inspection,
post
installation
test and
commissionin
g of project
by client
supervising
engineers or
6 consultants Lot sum ### 6

Sub-Total ###
EXCEPTION
AL
B PROVISION B

Allow for tree


cutting along
1 network route No 1,500.00 - 1

Allow for
bottom
beaming of
HT / LT poles
in swamps
using 300 x
300 x 600mm
high concrete
2 in site No 1,800.00 - 2

Allow for
clearing of
thick forest
along network
3 route M 200.00 - 3
Allow for
bottom
beaming of
HT / LT poles
in rocky
terrain using
600 x 600 x
4 1200mm high No 3,600.00 - 4

Allow for long


distance
transportation
of men &
5 materials Km 500.00 - 5

Sub-Total -

Description of
Sr. No. Items Unit price Qty Total PriceSr. No.

=N= =N=
Transform
er Sub
C Station C

33KV Gang
1 Isolator No. 100,000.00 1 ### 1

33KV Lighting
Arrestor
2 Complete No. 40,000.00 1 ### 2

33KV
Expulsion
J&P fuse
3 complete No. 30,000.00 1 ### 3

4-way 400A,
TP&N Feeder
Pillar compl
4 with HRC fuse set 80,000.00 1 ### 4

Cable
Lugs,Bolts
and
Nuts,Linetap,
5 Caloric Tape Lot Sum ### 5
8ft galvanised
earth
6 rod(thick) No. 2,500.00 24 ### 6

1X35mm^2
bare copper
for thick earth
7 rod m 450.00 100 ### 7

Allow for
treament of
8 earth pit Lot Sum ### 8

Raychem kits
9 complete set 20,000.00 2 ### 9

9ft Angle
10 Channel No. 4,000.00 4 ### 10

33KV pin
Insulator&pilo
t spindle
11 complete set 2,200.00 3 ### 11
Transfo Plinth
made with
concrete,gran
12 ite chiping Lot Sum ### 12

High tension
stay
complete,
block,wire,ins
13 ulator,clamp No. 4,000.00 4 ### 13

1 by 35mm^2
by Xlpe cable
from d fuse to
xmer
14 complete M 2,000.00 30 ### 14
Fencing of
xmer
substation
with dwarf
wall.the fence
should be
600mm of
block work
above ground
level and
600mm of
iron Mongany
and Iron Gate
not less than
2.4m x 2.4m
width and
15 graveled Lot Sum ### 15

1 by
300mm^2
pvc/swa/pvcu
g Nigerchin
16 cable M 15,000.00 30 ### 16
4 by
150mm^2
pvc/swa/pvcu
g Nigerchin
cable for
17 500KVA M 12,000.00 45 17

4 by 95mm^2
pvc/swa/pvcu
g Nigerchin
cable for
300KVA or
18 200KVA M 8,500.00 45 18

Feeder pillar
plinth 225mm
above normal
19 ground. Lot Sum ### 19

Sub-Total ###

H.T.
D NETWORK D
10.3m HT
concrete
1 poles No 25,000.00 - 1

Danger Plate
with anti-
2 climbing wire No 5,500.00 - 2

HT Stay
complete with
wire rod,
block,insulato
3 r bracket No 5,000.00 - 3

33KV Pilot
4 Spindle No 600.00 - 4

33KV Pin
5 insulator No 1,700.00 - 5

cross arm tie


6 strap M 800.00 - 6

U-Channel
7 Iron 9" No. 5,000.00 - 7

8 Steel X-Arm NO 4,800.00 - 8

Sectional
9 Steel 9" No 5,500.00 - 9
33KV Disc
10 Insulator No 1,800.00 - 10

150mm^2
Alluminium
11 Conductor m 250.00 - 11

Earthing of X-
Arms on
12 poles Points 5,500.00 - 12

Nuts and
Bolts (various
13 sizes) Lots sum 13

Six bolt
clamp, j-
hook,socket
tongue,
14 tension clamp Set 1,900.00 - 14

Sub-Total -

L.T.
E NETWORK E
8.3m concrete
low tension
1 pole Nos 23,000.00 - 1

LT Stay
complete with
wire rod,
block,
insulator
bracket
2 thimble etc Nos 4,000.00 - 2

D Iron
complete with
3 spindle Nos 370.00 - 3

Shackle
4 Insulator Nos 120.00 - 4

5 Binding wire M 65.00 - 5

70mm^2
overhead
Alluminium
6 conductor M 130.00 - 6
Earthing of
angles &
terminal poles
(to include
cable &
galvanized
7 rod) points 5,000.00 - 7

Bimetal
8 linetap Nos 600.00 - 8

Allow for
nuts, washer,
9 bolts etc. Lots Sum 9

Sub-Total -

Test
Certification
&
Commissioni
F ng F
PHCN
1 Logistics Lots ### 1

PHCN
Headquarters
2 Charges Lots ### 2
Power & Steel
Statutory
3 Fees Lots ### 3

Sub-Total ###

SUMMARY OF
BQ
Nos. Items Cost Nos.
N

A Preliminaries ### A

Exceptional
B Provision - B

Transformer
C Sub Station ### C

High Tension
D Materials - D

Low Tension
E Materials - E

Test
Certification
&
Commissioni
F ng ### F
Sub-Total ###

Overhead
1 Charge (30%) ### 1

Contingency
2 (5%) ### 2

Adm. Charges
3 (1%) ### 3

4 TOTAL COST ### 4

VAT (5%) ###

INSTALLATIO
N COST ###

TRANSFORM
G ER G

500KVA,
33/0.415KV,
VAT
INCLUSIVE
GRAND
TOTAL
FOR
INSTALLA
TION ###
4 4
PREPARED BY: MURTALA S.
MURTALA S. YUSUF CHECKED BY: ENGR. ABDULYASS YUSUF
33KV ELECTRIFICATION PROJECT TITLE:

DATE:
Descri
ption
of
Items Unit price Qty Total Price

=N= =N=

PRELI
MINAR
IES

Provisi
on For
Supervi
sing
Engine
ers,
Vehicle,
office
station
s,
office
equipm
ent Lot Sum 150,000.00
Provisi
on For
Supervi
sing
Engine
ers
travel
and
transpo
rt
throug
h out
project
period Lot sum 100,000.00
Assista
nce to
contrac
tor for
site
take-
over Lot Sum 25,000.00

Assista
nce to
employ
er for
payme
nt of
engine
ere
allowan
ces and
Sundry
reinbur
eables Lot sum 100,000.00
Provisi
on of
site
office
and
store
constru
cted to
engine
ers
specific
ations Lot Sum 100,000.00
Provisi
on of
pre-
installa
tion
inspect
ion,
post
installa
tion
test
and
commi
ssionin
g of
project
by
client
supervi
sing
engine
ers or
consult
ants Lot sum 150,000.00

Sub-
Total 625,000.00
EXCE
PTION
AL
PROVI
SION

Allow
for tree
cutting
along
networ
k route No ### -

Allow
for
bottom
beamin
g of
HT / LT
poles
in
swamp
s using
300 x
300 x
600mm
high
concret
e in site No ### -
Allow
for
clearin
g of
thick
forest
along
networ
k route M 200.00 -
Allow
for
bottom
beamin
g of
HT / LT
poles
in
rocky
terrain
using
600 x
600 x
1200m
m high No ### -

Allow
for long
distanc
e
transpo
rtation
of men
&
materia
ls Km 500.00 -

Sub-
Total -

Descrip
tion of
Items Unit price Qty Total Price

=N= =N=
Trans
forme
r Sub
Statio
n

33KV
Gang
Isolator No. ### 1 100,000.00
33KV
Lightin
g
Arresto
r
Comple
te No. ### 1 40,000.00
33KV
Expulsi
on J&P
fuse
comple
te No. ### 1 30,000.00
4-way
400A,
TP&N
Feeder
Pillar
compl
with
HRC
fuse set ### 1 80,000.00
Cable
Lugs,B
olts
and
Nuts,Li
netap,
Caloric
Tape Lot Sum 30,000.00
8ft
galvani
sed
earth
rod(thic
k) No. ### 24 60,000.00
1X35m
m^2
bare
copper
for
thick
earth
rod m 450.00 100 45,000.00
Allow
for
treame
nt of
earth
pit Lot Sum 5,000.00
Rayche
m kits
comple
te set ### 2 40,000.00
9ft
Angle
Channe
l No. ### 4 16,000.00
33KV
pin
Insulat
or&pilo
t
spindle
comple
te set ### 3 6,600.00
Transfo
Plinth
made
with
concret
e,granit
e
chiping Lot Sum 50,000.00
High
tension
stay
comple
te,
block,w
ire,insu
lator,cl
amp No. ### 4 16,000.00
1 by
35mm^
2 by
Xlpe
cable
from d
fuse to
xmer
comple
te M ### 30 60,000.00
wall.the
fence
should
be
600mm
of
block
work
above
ground
level
and
600mm
of iron
Monga
ny and
Iron
Gate
not
less
than
2.4m x
2.4m
width
and
gravele
d Lot Sum 150,000.00
1 by
300mm
^2
pvc/sw
a/pvcu
g
Nigerch
in cable M ### 30 450,000.00
4 by
150mm
^2
pvc/sw
a/pvcu
g
Nigerch
in cable
for
500KVA M ### 45

4 by
95mm^
2
pvc/sw
a/pvcu
g
Nigerch
in cable
for
300KVA
or
200KVA M ### 45

Feeder
pillar
plinth
225mm
above
normal
ground. Lot Sum 25,000.00

Sub-
Total ###

H.T.
NETW
ORK
10.3m
HT
concret
e poles No ### -
Danger
Plate
with
anti-
climbin
g wire No ### -

HT Stay
comple
te with
wire
rod,
block,i
nsulato
r
bracket No ### -

33KV
Pilot
Spindle No 600.00 -
33KV
Pin
insulat
or No ### -
cross
arm tie
strap M 800.00 -

U-
Channe
l Iron 9" No. ### -
Steel X-
Arm NO ### -

Section
al Steel
9" No ### -
33KV
Disc
Insulat
or No ### -
150mm
^2
Allumin
ium
Conduc
tor m 250.00 -
Earthin
g of X-
Arms
on
poles Points ### -

Nuts
and
Bolts
(variou
s sizes) Lots sum

Six bolt
clamp,
j-
hook,s
ocket
tongue,
tension
clamp Set ### -

Sub-
Total -

L.T.
NETW
ORK
8.3m
concret
e low
tension
pole Nos ### -

LT Stay
comple
te with
wire
rod,
block,
insulat
or
bracket
thimble
etc Nos ### -
D Iron
comple
te with
spindle Nos 370.00 -
Shackl
e
Insulat
or Nos 120.00 -
Binding
wire M 65.00 -
70mm^
2
overhe
ad
Allumin
ium
conduc
tor M 130.00 -
Earthin
g of
angles
&
termina
l poles
(to
include
cable &
galvani
zed
rod) points ### -

Bimetal
linetap Nos 600.00 -
Allow
for
nuts,
washer,
bolts
etc. Lots Sum

Sub-
Total -

Test
Certific
ation &
Commi
ssionin
g
PHCN
Logisti
cs Lots 100,000.00
PHCN
Headqu
arters
Charge
s Lots 100,000.00
Power
& Steel
Statuto
ry Fees Lots 200,000.00

Sub-
Total ###
SUMM
ARY OF
BQ
Items Cost
N
Prelimi
naries 625,000.00
Excepti
onal
Provisi
on -
Transfo
rmer
Sub
Station ###
High
Tensio
n
Materia
ls -
Low
Tensio
n
Materia
ls -
Test
Certific
ation &
Commi
ssionin
g 400,000.00
Sub-
Total ###

Overhe
ad
Charge
(30%) 668,580.00
Contin
gency
(5%) 111,430.00
Adm.
Charge
s (1%) 22,286.00
TOTAL
COST ###
VAT
(5%) 151,544.80

INSTAL
LATION
COST ###
TRANS
FORME
R
500KVA
,
33/0.41
5KV,
VAT
INCLUS
IVE
GRA
ND
TOTA
L
FOR
INSTA
LLATI
ON ###
MURTALA S.
YUSUF CHECKED BY: ENGR. ABDULY
33KV ELECTRIFICATION PROJECT TITLE:

DATE:
Sr. No. Description of Items Unit price Qty Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

B EXCEPTIONAL PROVISION

1 Allow for tree cutting along network route No ### -


Allo w for bottom beam ing of HT / LT
poles in swamps u sing 300 x 300 x
2 600mm hig h concrete in site No ### -
Allo w for clear ing of thick forest along
3 network r oute M 200.00 -
Allo w for bottom beam ing of HT / LT
poles in rocky terr ain usin g 600 x 600 x
4 1200m m high No ### -
Allo w for lo ng distance tran spo rtation of
5 men & mater ials Km 500.00 -

Sub-Total -

Sr. No. Description of Items Unit price Qty Total Price

=N= =N=

C Transformer Sub Station

1 33KV Gang Isolator No. ### 1 100,000.00


2 33KV Lighting Arrestor Complete No. ### 1 40,000.00
3 33KV Expulsion J&P fuse complete No. ### 1 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse set ### 1 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) No. ### 24 60,000.00
7 1X35mm^2 bare copper for thick earth rod m 450.00 100 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete set ### 2 40,000.00
10 9ft Angle Channel No. ### 4 16,000.00
11 33KV pin Insulator&pilot spindle complete set ### 3 6,600.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p No. ### 4 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete M ### 30 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
16 cable M ### 30 450,000.00
4 by 150mm ^2 pvc/swa/pvcu g Nig er chin
17 cable fo r 500KVA M ### 45
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA or 200KVA M ### 45
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 1,203,600.00

D H.T. NETWORK

1 10.3m HT concrete poles No ### -


2 Danger Plate with anti-climbing wire No ### -
HT Stay com plete with wire rod ,
3 block,in sulator bracket No ### -
4 33KV Pilot Spindle No 600.00 -
5 33KV Pin insulator No ### -
6 cross arm tie strap M 800.00 -
7 U-Channel Iron 9" No. ### -
8 Steel X-Arm NO ### -
9 Sectional Steel 9" No ### -
10 33KV Disc Insulator No ### -
11 150mm^2 Alluminium Conductor m 250.00 -
12 Earthing of X-Arms on poles Points ### -
13 Nuts and Bolts (various sizes) Lots sum
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp Set ### -

Sub-Total -

E L.T. NETWORK

1 8.3m concrete low tension pole Nos ### -


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc Nos ### -
3 D Iron complete with spindle Nos 370.00 -
4 Shackle Insulator Nos 120.00 -
5 Binding wire M 65.00 -
6 70mm^2 overhead Alluminium conductor M 130.00 -
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) points ### -
8 Bimetal linetap Nos 600.00 -
9 Allow for nuts, washer, bolts etc. Lots Sum

Sub-Total -

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries #REF!
B Exceptional Provision -
C Transformer Sub Station 1,203,600.00
D High Tension Materials -
E Low Tension Materials -
F Test Certification & Commissioning 400,000.00

Sub-Total #REF!

1 Overhead Charge (25%) #REF!


2 Contingency (1%) #REF! contingency within town=0%
3 Adm. Charges (1%) #REF!
4 TOTAL COST #REF! contingency outside town=1%
VAT (5%) #REF!
INSTALLATION COST #REF!
G TRANSFORMER
500KVA, 33/0.415KV, VAT INCLUSIVE

GRAND TOTAL FOR INSTALLATION #REF!

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. J. F. DADA

11KV ELECTRIFICATION PROJECT TITLE:

DATE:
Sr. No. Description of Items Unit price Qty Total Price

=N= =N=

A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

B EXCEPTIONAL PROVISION

1 Allow for tree cutting along network route No ### -


Allo w for bottom beam ing of HT / LT
poles in swamps u sing 225 x 225 x
2 600mm hig h concrete in site No ### -
Allo w for clear ing of thick forest along
3 network r oute M 200.00 -
Allo w for bottom beam ing of HT / LT
poles in rocky terr ain usin g 225x
4 225x1200m m h igh No ### -
Allo w for lo ng distance tran spo rtation of
5 men & mater ials Km 500.00 -

Sub-Total -

Sr. No. Description of Items Unit price Qty Total Price

=N= =N=

C Transformer Sub Station

1 11KV Gang Isolator No. ### 1 80,000.00


2 11KV Lighting Arrestor Complete No. ### 1 35,000.00
3 11KV Expulsion J&P fuse complete No. ### 1 25,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse set ### 1 70,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) No. ### 24 60,000.00
7 1X35mm^2 bare copper for thick earth rod m 450.00 100 45,000.00
8 Allow for treatment of earth pit Lot Sum 5,000.00
9 Raychem kits complete set ### 2 40,000.00
10 9ft Angle Channel No. ### 4 16,000.00
11 11KV pin Insulator&pilot spindle complete set ### 3 6,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p No. ### 4 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete M ### 30 60,000.00
4 by 150mm ^2 pvc/swa/pvcu g Nig er chin
15 cable fo r 500KVA M ### 45

16 300mm^2 X 1 pvcl/swa/pvcug Nigerchin cable M ### 30 450,000.00


Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 150,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA or 200KVA M ### 45 382,500.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 1,545,500.00

D H.T. NETWORK

1 10.3m HT concrete poles No ### -


2 Danger Plate with anti-climbing wire No ### -
HT Stay com plete with wire rod ,
3 block,in sulator bracket No ### -
4 11KV Pilot Spindle No 600.00 -
5 11KV Pin insulator No ### -
6 cross arm tie strap M 800.00 -
7 U-Channel Iron 9" No. ### -
8 Steel X-Arm NO ### -
9 Sectional Steel 9" No ### -
10 11KV Disc Insulator No ### -
11 100mm^2 Alluminium Conductor m 250.00 -
12 Earthing of X-Arms on poles Points ### -
13 Nuts and Bolts (various sizes) Lots sum
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp Set ### -

Sub-Total -

E L.T. NETWORK

1 8.3m concrete low tension pole Nos ### -


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc Nos ### -
3 D Iron complete with spindle Nos 370.00 -
4 Shackle Insulator Nos 120.00 -
5 Binding wire M 65.00 -
6 70mm2 overhead alluminium conductor M 130.00 -
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) points ### -
8 Bimetal linetap Nos 600.00 -
9 Allow for nuts, washer, bolts etc. Lots sum

Sub-Total -

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00
SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries #REF!
B Exceptional Provision -
C Transformer Sub Station 1,545,500.00
D High Tension Materials -
E Low Tension Materials -
F Test Certification & Commissioning 400,000.00

Sub-Total #REF!

1 Overhead Charge (25%) #REF!


2 Contingency (1%) #REF! contingency within town=0%
3 Adm. Charges (1%) #REF!
4 TOTAL COST #REF! contingency outside town=1%
VAT (5%) #REF!
INSTALLATION COST #REF!
G TRANSFORMER
500KVA, 11/0.415KV, VAT INCLUSIVE

GRAND TOTAL FOR


INSTALLATION #REF!

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. J. F. DADA

BEMES WITH NEW FORMAT BEGINS ON 19TH MAY, 2014.

33KV ELECTRIFICATION PROJECT TITLE:

DATE:
Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

B EXCEPTIONAL PROVISION

1 Allow for tree cutting along network route No 1,500.00 -


Allo w for bottom beam ing of HT / LT
poles in swamps u sing 300 x 300 x
2 600mm hig h concrete in site No 1,800.00 -
Allo w for clear ing of thick forest along
3 network r oute M 200.00 -
Allo w for bottom beam ing of HT / LT
poles in rocky terr ain usin g 600 x 600 x
4 1200m m high No 3,600.00 -
Allo w for lo ng distance tran spo rtation of
5 men & mater ials Km 500.00 -

Sub-Total -

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

C Transformer Sub Station

1 33KV Gang Isolator 1 No. 100,000.00 100,000.00


2 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00
3 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
11 33KV pin Insulator&pilot spindle complete 3 set 2,300.00 6,900.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
16 cable 30 M 15,000.00 450,000.00
4 by 150mm ^2 pvc/swa/pvcu g Nig er chin
17 cable fo r 500KVA 45 M 12,000.00 540,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA or 200KVA 45 M 8,500.00 382,500.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 2,126,400.00

D H.T. NETWORK

1 10.3m HT concrete poles No 25,000.00 -


2 Danger Plate with anti-climbing wire No 5,500.00 -
HT Stay com plete with wire rod ,
3 block,in sulator bracket No 4,000.00 -
4 33KV Pilot Spindle No 600.00 -
5 33KV Pin insulator No 1,700.00 -
6 cross arm tie strap M 800.00 -
7 U-Channel Iron 9" No. 5,000.00 -
8 Steel X-Arm NO 4,800.00 -
9 Sectional Steel 9" No 5,500.00 -
10 33KV Disc Insulator No 1,800.00 -
11 150mm^2 Alluminium Conductor m 250.00 -
12 Earthing of X-Arms on poles Points 5,500.00 -
13 Nuts and Bolts (various sizes) Lots sum
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp Set 1,900.00 -

Sub-Total -

E L.T. NETWORK

1 8.3m concrete low tension pole Nos 23,000.00 -


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc Nos 4,000.00 -
3 D Iron complete with spindle Nos 370.00 -
4 Shackle Insulator Nos 120.00 -
5 Binding wire M 65.00 -
6 70mm^2 overhead Alluminium conductor M 130.00 -
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) points 5,000.00 -
8 Bimetal linetap Nos 600.00 -
9 Allow for nuts, washer, bolts etc. Lots Sum

Sub-Total -

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Exceptional Provision -
C Transformer Sub Station 2,126,400.00
D High Tension Materials -
E Low Tension Materials -
F Test Certification & Commissioning 400,000.00

Sub-Total 3,601,400.00

1 Overhead Charge (25%) 900,350.00


2 Contingency (1%) 36,014.00
3 Adm. Charges (1%) 36,014.00
4 TOTAL COST 4,573,778.00 contingency within town=0%
VAT (5%) 228,688.90
INSTALLATION COST 4,802,466.90 contingency outside town=1%
G TRANSFORMER
500KVA, 33/0.415KV, VAT INCLUSIVE

GRAND TOTAL FOR INSTALLATION 4,802,466.90

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

11KV ELECTRIFICATION PROJECT TITLE:

DATE:
Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=

A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies

Sup er vising Engin eers fuelling allowan ce


ii through out the perio d of the p roject

Pr ovision o f Pr e-in stallation inspection,


post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

B EXCEPTIONAL PROVISION

1 Allow for tree cutting along network route No 1,500.00 -


Allo w for bottom beam ing of HT / LT
poles in swamps u sing 225 x 225 x
2 600mm hig h concrete in site No 1,800.00 -
Allo w for clear ing of thick forest along
3 network r oute M 200.00 -
Allo w for bottom beam ing of HT / LT
poles in rocky terr ain usin g 225x
4 225x1200m m h igh No 3,600.00 -
Allo w for lo ng distance tran spo rtation of
5 men & mater ials Km 500.00 -

Sub-Total -

Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=

C Transformer Sub Station

1 11KV Gang Isolator 1 No. 80,000.00 80,000.00


2 11KV Lighting Arrestor Complete 1 No. 35,000.00 35,000.00
3 11KV Expulsion J&P fuse complete 1 No. 25,000.00 25,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 70,000.00 70,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treatment of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
11 11KV pin Insulator&pilot spindle complete 3 set 1,800.00 5,400.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete 30 M 2,000.00 60,000.00
4 by 150mm ^2 pvc/swa/pvcu g Nig er chin
15 cable fo r 500KVA 45 M 12,000.00 540,000.00

16 300mm^2 X 1 pvcl/swa/pvcug Nigerchin cable 30 M 15,000.00 450,000.00


Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 150,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA or 200KVA 45 M 8,500.00 382,500.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 2,084,900.00

D H.T. NETWORK

1 10.3m HT concrete poles No 25,000.00 -


2 Danger Plate with anti-climbing wire No 5,500.00 -
HT Stay com plete with wire rod ,
3 block,in sulator bracket No 4,000.00 -
4 11KV Pilot Spindle No 600.00 -
5 11KV Pin insulator No 1,200.00 -
6 cross arm tie strap M 800.00 -
7 U-Channel Iron 9" No. 5,000.00 -
8 Steel X-Arm NO 4,800.00 -
9 Sectional Steel 9" No 5,500.00 -
10 11KV Disc Insulator No 1,500.00 -
11 100mm^2 Alluminium Conductor m 250.00 -
12 Earthing of X-Arms on poles Points 5,500.00 -
13 Nuts and Bolts (various sizes) Lots sum
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp Set 1,900.00 -

Sub-Total -

E L.T. NETWORK

1 8.3m concrete low tension pole Nos 23,000.00 -


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc Nos 4,000.00 -
3 D Iron complete with spindle Nos 370.00 -
4 Shackle Insulator Nos 120.00 -
5 Binding wire M 65.00 -
6 70mm2 overhead alluminium conductor M 130.00 -
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) points 5,000.00 -
8 Bimetal linetap Nos 600.00 -
9 Allow for nuts, washer, bolts etc. Lots sum

Sub-Total -

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00
SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Exceptional Provision -
C Transformer Sub Station 2,084,900.00
D High Tension Materials -
E Low Tension Materials -
F Test Certification & Commissioning 400,000.00

Sub-Total 3,559,900.00

1 Overhead Charge (25%) 889,975.00


2 Contingency (1%) 35,599.00 contingency within town=0%
3 Adm. Charges (1%) 35,599.00
4 TOTAL COST 4,521,073.00 contingency outside town=1%
VAT (5%) 226,053.65
INSTALLATION COST 4,747,126.65
G TRANSFORMER
500KVA, 11/0.415KV, VAT INCLUSIVE

GRAND TOTAL FOR INSTALLATION 4,747,126.65

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

CHECKING POINT COMMUNITY, OPP. AVIATION COLLEGE, OFF AIRPORT ROAD, IL/WEST LGA.

DATE: 19TH MAY, 2014.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

Tr ansform er Sub Station: RELIEF SIDE A


B (i) (i.e. PAIRED ZONE 5 & 6)

1 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00


2 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
3 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
4 Caloric Tape Lot Sum 30,000.00
5 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
6 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
7 Allow for treatment of earth pit Lot Sum 5,000.00
8 Raychem kits complete 2 set 20,000.00 40,000.00
9 9ft Angle Channel 4 No. 4,000.00 16,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
10 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
11 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
12 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
13 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
14 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
15 cable fo r 300KVA 45 M 8,500.00 382,500.00
Feeder pillar plinth 225m m ab ove n ormal
16 groun d. Lot Sum 25,000.00

Sub-Total 1,429,500.00

Tr ansform er Sub Station: RELIEF SIDE B


B (ii) (i.e. PAIRED ZONE 3 & 4)

1 33KV Gang Isolator 1 No. 100,000.00 100,000.00


2 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00
3 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
11 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
12 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
13 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
14 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
15 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
16 cable fo r 300KVA 30 M 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
17 groun d. Lot Sum 25,000.00

Sub-Total 1,402,000.00

B (TOTAL= B(i)+B(ii)) 2,831,500.00

H.T. NETWORK: FOR RELIEF SIDE A (i.e.


C (i) PAIRED ZONE 5 & 6)

1 10.3m HT concrete poles 8 No 25,000.00 200,000.00


2 Danger Plate with anti-climbing wire 2 No 5,500.00 11,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 4 No 4,000.00 16,000.00
4 33KV Pilot Spindle 18 No 600.00 10,800.00
5 33KV Pin insulator 18 No 1,700.00 30,600.00
6 cross arm tie strap 12 M 800.00 9,600.00
7 U-Channel Iron 9" 3 No. 5,000.00 15,000.00
8 Steel X-Arm 6 NO 4,800.00 28,800.00
9 Sectional Steel 9" - No 5,500.00 -
10 33KV Disc Insulator 27 No 1,800.00 48,600.00
11 150mm^2 Alluminium Conductor 1,050 m 250.00 262,500.00
12 Earthing of X-Arms on poles - Points 5,500.00 -
13 Nuts and Bolts (various sizes) Lots sum 5,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 6 Set 1,900.00 11,400.00

Sub-Total 649,300.00

H.T. NETWORK: FOR RELIEF SIDE B (i.e.


C (ii) PAIRED ZONE 3 & 4)

1 10.3m HT concrete poles 10 No 25,000.00 250,000.00


2 Danger Plate with anti-climbing wire 4 No 5,500.00 22,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 5 No 4,000.00 20,000.00
4 33KV Pilot Spindle 18 No 600.00 10,800.00
5 33KV Pin insulator 18 No 1,700.00 30,600.00
6 cross arm tie strap 12 M 800.00 9,600.00
7 U-Channel Iron 9" 7 No. 5,000.00 35,000.00
8 Steel X-Arm 6 NO 4,800.00 28,800.00
9 Sectional Steel 9" 2 No 5,500.00 11,000.00
10 33KV Disc Insulator 36 No 1,800.00 64,800.00
11 150mm^2 Alluminium Conductor 1,350 m 250.00 337,500.00
12 Earthing of X-Arms on poles - Points 5,500.00 -
13 Nuts and Bolts (various sizes) Lots sum 6,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 12 Set 1,900.00 22,800.00

Sub-Total 848,900.00

C (TOTAL= C(i)+C(ii)) 1,498,200.00

D (i) L.T. NETWORK: FOR PAIRED ZONE(1 & 2)

1 8.3m concrete low tension pole 5 Nos 23,000.00 115,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 2 Nos 4,000.00 8,000.00
3 D Iron complete with spindle 20 Nos 370.00 7,400.00
4 Shackle Insulator 20 Nos 120.00 2,400.00
5 Binding wire 25 M 65.00 1,625.00
6 70mm^2 overhead Alluminium conductor 1,000 M 130.00 130,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 1 points 5,000.00 5,000.00
8 Bimetal linetap - Nos 600.00 -
9 Allow for nuts, washer, bolts etc. Lots Sum 2,000.00

Sub-Total 271,425.00

D (ii) L.T. NETWORK: FOR PAIRED ZONE(5 & 6)

1 8.3m concrete low tension pole 10 Nos 23,000.00 230,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 5 Nos 4,000.00 20,000.00
3 D Iron complete with spindle 40 Nos 370.00 14,800.00
4 Shackle Insulator 40 Nos 120.00 4,800.00
5 Binding wire 50 M 65.00 3,250.00
6 70mm^2 overhead Alluminium conductor 2,600 M 130.00 338,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 2 points 5,000.00 10,000.00
8 Bimetal linetap 12 Nos 600.00 7,200.00
9 Allow for nuts, washer, bolts etc. Lots Sum 6,000.00

Sub-Total 634,050.00

D (iii) L.T. NETWORK: FOR PAIRED ZONE(3 & 4)

1 8.3m concrete low tension pole 10 Nos 23,000.00 230,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 5 Nos 4,000.00 20,000.00
3 D Iron complete with spindle 40 Nos 370.00 14,800.00
4 Shackle Insulator 40 Nos 120.00 4,800.00
5 Binding wire 50 M 65.00 3,250.00
6 70mm^2 overhead Alluminium conductor 3,200 M 130.00 416,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 2 points 5,000.00 10,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots Sum 6,000.00

Sub-Total 709,650.00

D (TOTAL= D(i)+D(ii)+D(iii)) 1,615,125.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 200,000.00
2 IBEDC Headquarters Charges Lots 200,000.00
3 Power & Steel Statutory Fees Lots 400,000.00

Sub-Total 800,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station (=B(i)+B(ii)) 2,831,500.00
C High Tension Materials (=C(i)+C(ii)) 1,498,200.00
D Low Tension Materials (=D(i)+D(ii)+D(iii)) 1,615,125.00
E Test Certification & Commissioning 800,000.00

Sub-Total 7,819,825.00

1 Overhead Charge (25%) 1,954,956.25


2 Adm. Charges (1%) 78,198.25
3 TOTAL COST 9,852,979.50
VAT (5%) 492,648.98
INSTALLATION COST 10,345,628.48
F TRANSFORMER
2No s. 300KVA, 33/0.415KV Grou nd
Mounted XFORMER, VAT INCLUSIVE 4,700,000.00

GRAND TOTAL FOR INSTALLATION 15,045,628.48

PREPARED BY: BAYERO YAHAYA CHECKED BY: MURTALA S. YUSUF

AKAJE OLORUNSOGO COMMUNITY VIA AMOYO, IFELODUN L.G.A.

DATE: 19TH MAY, 2014.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

B Transformer Sub Station

1 33KV Gang Isolator 1 No. 100,000.00 100,000.00


2 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00
3 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
11 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
12 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
13 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
14 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
15 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
16 cable fo r 300KVA or 200KVA 45 M 8,500.00 382,500.00
Feeder pillar plinth 225m m ab ove n ormal
17 groun d. Lot Sum 25,000.00

Sub-Total 1,529,500.00

C H.T. NETWORK

1 10.3m HT concrete poles 8 No 25,000.00 200,000.00


2 Danger Plate with anti-climbing wire 4 No 5,500.00 22,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 6 No 4,000.00 24,000.00
4 33KV Pilot Spindle 12 No 600.00 7,200.00
5 33KV Pin insulator 12 No 1,700.00 20,400.00
6 cross arm tie strap 8 M 800.00 6,400.00
7 U-Channel Iron 9" 7 No. 5,000.00 35,000.00
8 Steel X-Arm 4 NO 4,800.00 19,200.00
9 Sectional Steel 9" - No 5,500.00 -
10 33KV Disc Insulator 27 No 1,800.00 48,600.00
11 150mm^2 Alluminium Conductor 6 m 250.00 1,500.00
12 Earthing of X-Arms on poles 2 Points 5,500.00 11,000.00
13 Nuts and Bolts (various sizes) Lots sum 3,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 6 Set 1,900.00 11,400.00
Sub-Total 409,700.00

D L.T. NETWORK

1 8.3m concrete low tension pole 3 Nos 23,000.00 69,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 3 Nos 4,000.00 12,000.00
3 D Iron complete with spindle 12 Nos 370.00 4,440.00
4 Shackle Insulator 12 Nos 120.00 1,440.00
5 Binding wire 15 M 65.00 975.00
6 70mm^2 overhead Alluminium conductor - M 130.00 -
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 3 points 5,000.00 15,000.00
8 Bimetal linetap 12 Nos 600.00 7,200.00
9 Allow for nuts, washer, bolts etc. Lots Sum 2,000.00
Sub-Total 112,055.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00
Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,529,500.00
C High Tension Materials 409,700.00
D Low Tension Materials 112,055.00
E Test Certification & Commissioning 400,000.00

Sub-Total 3,526,255.00

1 Overhead Charge (25%) 881,563.75


2 Contingency (1%) 35,262.55
3 Adm. Charges (1%) 35,262.55
4 TOTAL COST 4,478,343.85
VAT (5%) 223,917.19
INSTALLATION COST 4,702,261.04
F TRANSFORMER
300KVA, 33/0.415KV INCLUSIVE 2,350,000.00

GRAND TOTAL FOR INSTALLATION 7,052,261.04


PREPARED BY: GIDEON S. ELIJAH CHECKED BY: MURTALA S. YUSUF

OLORUNDARA COMMUNITY GANMO IN IFELODUN LGA


DATE:12 JUNE, 2014
Sr. No. Description of Items Qty UNIT Price Total Price
=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00
B EXCEPTIONAL PROVISION
Allo w for bottom beam ing of HT poles in
swamps usin g 225 x 225 x 600mm high
1 co ncr ete in site 14 No 1,800.00 25,200.00

Sub-Total 25,200.00

Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=
C Transformer Sub Station
1 11KV Gang Isolator 1 No. 80,000.00 80,000.00
2 11KV Lighting Arrestor Complete 1 No. 35,000.00 35,000.00
3 11KV Expulsion J&P fuse complete 1 No. 25,000.00 25,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 70,000.00 70,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 Allow for treatment of earth pit Lot Sum 5,000.00
8 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
11 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
12 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
13 xm er comp lete 30 M 2,000.00 60,000.00

14 300mm^2 X 1 pvcl/swa/pvcug Nigerchin cable 30 M 15,000.00 450,000.00


Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 100,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
16 cable fo r 300KVA 45 m 8,500.00 382,500.00
Feeder pillar plinth 225m m ab ove n ormal
17 groun d. Lot Sum 25,000.00
Sub-Total 1,489,500.00

D H.T. NETWORK
1 10.3m HT concrete poles 15 No 25,000.00 375,000.00
2 Danger Plate with anti-climbing wire 6 No 5,500.00 33,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 10 No 4,000.00 40,000.00
4 11KV Pilot Spindle 27 No 600.00 16,200.00
5 11KV Pin insulator 27 No 1,200.00 32,400.00
6 cross arm tie strap 18 m 800.00 14,400.00
7 U-Channel Iron 9" 7 No. 5,000.00 35,000.00
8 Steel X-Arm 9 No. 4,800.00 43,200.00
9 Sectional Steel 9" 2 No 5,500.00 11,000.00
10 11KV Disc Insulator 15 No 1,500.00 22,500.00
11 100mm^2 Alluminium Conductor 1800 m 250.00 450,000.00
12 Earthing of X-Arms on poles 2 Points 5,500.00 11,000.00
13 Nuts and Bolts (various sizes) Lots sum 8,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 12 Set 1,900.00 22,800.00
Sub-Total 1,114,500.00
E L.T. NETWORK
NB: Materials and conductor for du al
network inclusive.
1 8.3m concrete low tension pole 10 Nos 23,000.00 230,000.00
LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 10 Nos 4,000.00 40,000.00
3 D Iron complete with spindle 40 Nos 370.00 14,800.00
4 Shackle Insulator 40 Nos 120.00 4,800.00
5 Binding
70mm wire head allum iniu m cond uctor :
2 over 50 M 65.00 3,250.00
DUAL CONDUCTOR OF 0.3Km
6 INCLUSIVE 3200 M 130.00 416,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 3 points 5,000.00 15,000.00
8 MSY 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots sum 5,000.00
Sub-Total 733,650.00
F Test Certification & Commissioning
1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00
SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Exceptional Provision 25,200.00
C Transformer Sub Station 1,489,500.00
D High Tension Materials 1,114,500.00
E Low Tension Materials 733,650.00
F Test Certification & Commissioning 400,000.00
Sub-Total 4,837,850.00
1 Overhead Charge (25%) 1,209,462.50
2 Contingency (1%) 48,378.50
3 Adm. Charges (1%) 48,378.50
4 TOTAL COST 6,144,069.50
VAT (5%) 307,203.48
INSTALLATION COST 6,451,272.98
G TRANSFORMER
300KVA,11/0.415KV,VAT INCLUSIVE 2,300,000.00
GRAND TOTAL FOR INSTALLATION 8,751,272.98

PREPARED BY GIDEON S. ELIJAH CHECKED BY MURTALA S. YUSUF

YAWU COMMUNITY VIA CHEKO ROAD JUNCTION, EDU L.G.A.

DATE: 28/01/2013: RE-REVIEWED ON 31/07/2014


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

B Transformer Sub Station

1 33KV Gang Isolator 1 No. 100,000.00 100,000.00


2 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00
3 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
11 33KV pin Insulator&pilot spindle complete 3 set 2,200.00 6,600.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p 2 No. 4,000.00 8,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
16 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 200KVA 30 M 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 1,450,600.00

C H.T. NETWORK

1 10.3m HT concrete poles 21 No 25,000.00 525,000.00


2 Danger Plate with anti-climbing wire 21 No 5,500.00 115,500.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 5 No 4,000.00 20,000.00
4 33KV Pilot Spindle 57 No 600.00 34,200.00
5 33KV Pin insulator 57 No 1,700.00 96,900.00
6 cross arm tie strap 38 M 800.00 30,400.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 19 NO 4,800.00 91,200.00
9 Sectional Steel 9" 6 No 5,500.00 33,000.00
10 33KV Disc Insulator 45 No 1,800.00 81,000.00
11 150mm^2 Alluminium Conductor 5,700 m 250.00 1,425,000.00
12 Earthing of X-Arms on poles 19 Points 5,500.00 104,500.00
13 Nuts and Bolts (various sizes) Lots sum 15,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 18 Set 1,900.00 34,200.00

Sub-Total 2,655,900.00

D L.T. NETWORK

1 8.3m concrete low tension pole 2 Nos 23,000.00 46,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 2 Nos 4,000.00 8,000.00
3 D Iron complete with spindle 8 Nos 370.00 2,960.00
4 Shackle Insulator 8 Nos 120.00 960.00
5 Binding wire 10 M 65.00 650.00
70m m^2 over head Allum inium cond uctor :
CONDU CTOR F OR AUGMEN TING THE
6 EXISTING ONES TO 3-PHASE EXIST. 715 M 130.00 92,950.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 2 points 5,000.00 10,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots Sum 2,000.00

Sub-Total 168,320.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,450,600.00
C High Tension Materials 2,655,900.00
D Low Tension Materials 168,320.00
E Test Certification & Commissioning 400,000.00

Sub-Total 5,749,820.00

1 Overhead Charge (25%) 1,437,455.00


2 Contingency (1%) 57,498.20
3 Adm. Charges (1%) 57,498.20
4 TOTAL COST 7,302,271.40
VAT (5%) 365,113.57
INSTALLATION COST 7,667,384.97
F TRANSFORMER
300KVA, 33/0.415KV, VAT INCLUSIVE 2,350,000.00

GRAND TOTAL FOR INSTALLATION 10,017,384.97

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

ASUNNARA, AGO AND MEGUN DEVELOPMENT ASSOCIATION MORO L.G.A.

DATE: 18/08/2014
Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

B Transformer Sub Station

1 33KV Gang Isolator 1 No. 100,000.00 100,000.00


2 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00
3 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
11 33KV pin Insulator&pilot spindle complete 3 set 2,200.00 6,600.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p 2 No. 4,000.00 8,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
16 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 200KVA 30 M 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 1,450,600.00

C H.T. NETWORK
1 10.3m HT concrete poles 56 No 25,000.00 1,400,000.00
2 Danger Plate with anti-climbing wire 14 No 5,500.00 77,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 20 No 4,000.00 80,000.00
4 33KV Pilot Spindle 126 No 600.00 75,600.00
5 33KV Pin insulator 126 No 1,700.00 214,200.00
6 cross arm tie strap 84 M 800.00 67,200.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 42 NO 4,800.00 201,600.00
9 Sectional Steel 9" 12 No 5,500.00 66,000.00
10 33KV Disc Insulator 126 No 1,800.00 226,800.00
11 150mm^2 Alluminium Conductor 9,600 m 250.00 2,400,000.00
12 Earthing of X-Arms on poles 10 Points 5,500.00 55,000.00
13 Nuts and Bolts (various sizes) Lots sum 50,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 42 Set 1,900.00 79,800.00
Sub-Total 5,043,200.00

L.T. NETWORK.(NB:materials &


D co nductor for dual network in clusive)
1 8.3m concrete low tension pole 10 Nos 23,000.00 230,000.00
LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 10 Nos 4,000.00 40,000.00
3 D Iron complete with spindle 76 Nos 370.00 28,120.00
4 Shackle Insulator 76 Nos 120.00 9,120.00
5 Binding wire 50 M 65.00 3,250.00

70m m^2 over head Allum inium cond uctor :


6 .Dual con ducto r of 8-spans inclusive 3,600 M 130.00 468,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 4 points 5,000.00 20,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots Sum 5,000.00
Sub-Total 808,290.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00
Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,450,600.00
C High Tension Materials 5,043,200.00
D Low Tension Materials 808,290.00
E Test Certification & Commissioning 400,000.00
Sub-Total 8,777,090.00

1 Overhead Charge (25%) 2,194,272.50


2 Contingency (1%) 87,770.90
3 Adm. Charges (1%) 87,770.90
4 TOTAL COST 11,146,904.30
VAT (5%) 557,345.22
INSTALLATION COST 11,704,249.52
F TRANSFORMER
300KVA, 33/0.415KV, VAT INCLUSIVE 2,350,000.00
S GRAND TOTAL FOR INSTALLATION . 14,054,249.52

PREPARED BY: GIDEON S. ELIJAH CHECKED BY: MURTALA S. YUSUF

EBU IPATA DEVELOPMENT ASSOCIATION,ILORIN WEST LGA


DATE:26 AUGUST, 2014
Sr. No. Description of Items Qty UNIT Price Total Price
=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=
B Transformer Sub Station
1 11KV Gang Isolator 1 No. 80,000.00 80,000.00
2 11KV Lighting Arrestor Complete 1 No. 35,000.00 35,000.00
3 11KV Expulsion J&P fuse complete 1 No. 25,000.00 25,000.00
4-way 600A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 70,000.00 70,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 Allow for treatment of earth pit Lot Sum 5,000.00
8 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
11 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
12 block,wire,insu lato r,clam p 2 No. 4,000.00 8,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
13 xm er comp lete 30 M 2,000.00 60,000.00

14 300mm^2 X 1 pvcl/swa/pvcug Nigerchin cable 30 M 15,000.00 450,000.00


Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 100,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
16 cable fo r 300KVA 30 m 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
17 groun d. Lot Sum 25,000.00
Sub-Total 1,354,000.00

C H.T. NETWORK
1 10.3m HT concrete poles 10 No 25,000.00 250,000.00
2 Danger Plate with anti-climbing wire 4 No 5,500.00 22,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 4 No 4,000.00 16,000.00
4 11KV Pilot Spindle 24 No 600.00 14,400.00
5 11KV Pin insulator 24 No 1,200.00 28,800.00
6 cross arm tie strap 12 m 800.00 9,600.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 6 No. 4,800.00 28,800.00
9 Sectional Steel 9" 2 No 5,500.00 11,000.00
10 11KV Disc Insulator 12 No 1,500.00 18,000.00
11 100mm^2 Alluminium Conductor 1200 m 250.00 300,000.00
12 Earthing of X-Arms on poles 1 Points 5,500.00 5,500.00
13 Nuts and Bolts (various sizes) 12 Lots sum 5,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 1 Set 1,900.00 1,900.00
Sub-Total 761,000.00
D Test Certification & Commissioning
1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00
SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,354,000.00
C High Tension Materials 761,000.00
D Test Certification & Commissioning 400,000.00
Sub-Total 3,590,000.00
1 Overhead Charge (25%) 897,500.00
2 Adm. Charges (1%) 35,900.00
3 TOTAL COST 4,523,400.00
VAT (5%) 226,170.00
INSTALLATION COST 4,749,570.00
G TRANSFORMER
500KVA,11/0.415KV,VAT INCLUSIVE 3,100,000.00
GRAND TOTAL FOR INSTALLATION 7,849,570.00

PREPARED BY GIDEON S. ELIJAH CHECKED BY MURTALA S. YUSUF

ADUAWAGBA COMMUNITY DEVELOPMENT, OGIDI, ILORIN WEST L.G.A.

DATE: 20TH AUGUST, 2014.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

A Transformer Sub Station

1 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00 RASHEED WORK


2 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
3 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
4 Caloric Tape Lot Sum 30,000.00
5 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
6 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
7 Allow for treament of earth pit Lot Sum 5,000.00
8 Raychem kits complete 1 set 20,000.00 20,000.00
9 9ft Angle Channel 4 No. 4,000.00 16,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
10 ch ipin g Lot Sum AVAILABLE
High tensio n stay com plete,
11 block,wire,insu lato r,clam p 3 No. 4,000.00 12,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
12 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
13 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
14 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
15 cable fo r 500KVA 45 M 8,500.00 382,500.00
Feeder pillar plinth 225m m ab ove n ormal
16 groun d. Lot Sum 25,000.00

Sub-Total 1,355,500.00

B H.T. NETWORK
1
2 10.3m HT concrete poles 3 No 25,000.00 75,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 3 No 4,000.00 12,000.00
4 cross arm tie strap 2 M 800.00 1,600.00
5 Steel X-Arm 1 NO 4,800.00 4,800.00
6 33KV Disc Insulator 18 No 1,800.00 32,400.00
7 150mm^2 Alluminium Conductor 200 m 250.00 50,000.00
8 Nuts and Bolts (various sizes) Lots sum 3,000.00
Six bolt clam p, j-hook,socket tongu e,
9 tensio n clamp 6 Set 1,900.00 11,400.00

Sub-Total 190,200.00

C L.T. NETWORK

1 8.3m concrete low tension pole 5 Nos 23,000.00 115,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 3 Nos 4,000.00 12,000.00
3 D Iron complete with spindle 20 Nos 370.00 7,400.00
4 Shackle Insulator 20 Nos 120.00 2,400.00
5 Binding wire 25 M 65.00 1,625.00
6 70mm^2 overhead Alluminium conductor 1,000 M 130.00 130,000.00
7 Bimetal linetap 12 Nos 600.00 7,200.00
8 Allow for nuts, washer, bolts etc. Lots Sum 3,000.00

Sub-Total 278,625.00

D Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Transformer Sub Station 1,355,500.00
B High Tension Materials 190,200.00
C Low Tension Materials 278,625.00
D Test Certification & Commissioning 400,000.00

Sub-Total 2,224,325.00

1 Overhead Charge (25%) 556,081.25


2 Adm. Charges (1%) 22,243.25
3 TOTAL COST 2,802,649.50
VAT (5%) 140,132.48

INSTALLATION COST 2,942,781.98


E TRANSFORMER
500KVA, 33/0.415KV, VAT INCLUSIVE AVAILABLE

GRAND TOTAL FOR INSTALLATION 2,942,781.98

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

ADUAWAGBA COMMUNITY DEVELOPMENT, OGIDI, ILORIN WEST L.G.A.

DATE: 28TH JANUARY, 2014.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES MAIN BEME
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

B Transformer Sub Station

1 33KV Gang Isolator 1 No. 100,000.00 100,000.00


2 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00
3 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 600A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 1 set 20,000.00 20,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
11 33KV pin Insulator&pilot spindle complete 3 set 2,200.00 6,600.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
16 cable 30 M 15,000.00 450,000.00
4 by 150mm ^2 pvc/swa/pvcu g Nig er chin
17 cable fo r 500KVA 45 M 12,000.00 540,000.00
Feeder pillar plinth 225m m ab ove n ormal
18 groun d. Lot Sum 25,000.00

Sub-Total 1,673,600.00

C H.T. NETWORK

1 10.3m HT concrete poles 5 No 25,000.00 125,000.00


2 Danger Plate with anti-climbing wire 5 No 5,500.00 27,500.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 8 No 5,000.00 40,000.00
4 33KV Pilot Spindle 6 No 600.00 3,600.00
5 33KV Pin insulator 6 No 1,700.00 10,200.00
6 cross arm tie strap 2 M 800.00 1,600.00
7 U-Channel Iron 9" 7 No. 5,000.00 35,000.00
8 Steel X-Arm 1 NO 4,800.00 4,800.00
9 Sectional Steel 9" 2 No 5,500.00 11,000.00
10 33KV Disc Insulator 27 No 1,800.00 48,600.00
11 150mm^2 Alluminium Conductor 450 m 250.00 112,500.00
12 Earthing of X-Arms on poles 1 Points 5,500.00 5,500.00
13 Nuts and Bolts (various sizes) Lots sum 5,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 9 Set 1,900.00 17,100.00
Sub-Total 447,400.00

D L.T. NETWORK

1 8.3m concrete low tension pole 15 Nos 23,000.00 345,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 7 Nos 4,000.00 28,000.00
3 D Iron complete with spindle 60 Nos 370.00 22,200.00
4 Shackle Insulator 60 Nos 120.00 7,200.00
5 Binding wire 75 M 65.00 4,875.00
6 70mm^2 overhead Alluminium conductor 3,000 M 130.00 390,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 6 points 5,000.00 30,000.00
8 Bimetal linetap 12 Nos 600.00 7,200.00
9 Allow for nuts, washer, bolts etc. Lots Sum 10,000
Sub-Total 844,475.00

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,673,600.00
C High Tension Materials 447,400.00
D Low Tension Materials 844,475.00
E Test Certification & Commissioning 400,000.00

Sub-Total 4,440,475.00

1 Overhead Charge (25%) 1,110,118.75


2 Contingency (1%) 44,404.75
3 Adm. Charges (1%) 44,404.75
4 TOTAL COST 5,639,403.25
VAT (5%) 281,970.16
INSTALLATION COST 5,921,373.41
F TRANSFORMER
500KVA, 33/0.415KV, VAT INCLUSIVE 3,250,000.00
GRAND TOTAL FOR INSTALLATION 9,171,373.41

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

IFEDAPO COMMUNITY ASSOCIATION, OSIN ITA-ELEPA, ILORIN WEST LGA


DATE: 1ST SEPTEMBER, 2014.
Sr. No. Description of Items Qty UNIT Price Total Price
=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=
B Transformer Sub Station
1 11KV Lighting Arrestor Complete 1 No. 35,000.00 35,000.00
2 11KV Expulsion J&P fuse complete 1 No. 25,000.00 25,000.00
4-way 600A, TP&N F eeder Pillar com pl
3 with HRC fuse 1 set 70,000.00 70,000.00
Cab le Lugs,B olts and Nuts,Linetap,
4 Caloric Tape Lot Sum 30,000.00
5 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
6 Allow for treatment of earth pit Lot Sum 5,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Raychem kits complete 2 set 20,000.00 40,000.00
9 9ft Angle Channel 4 No. 4,000.00 16,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
10 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
11 block,wire,insu lato r,clam p 2 No. 4,000.00 8,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
12 xm er comp lete 30 M 2,000.00 60,000.00

13 300mm^2 X 1 pvcl/swa/pvcug Nigerchin cable 30 M 15,000.00 450,000.00


Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
14 2.4m x 2.4m width and graveled Lot Sum 100,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
15 cable fo r 300KVA 30 m 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
16 groun d. Lot Sum 25,000.00
Sub-Total 1,274,000.00

C H.T. NETWORK
1 10.3m HT concrete poles 1 No 25,000.00 25,000.00
HT Stay com plete with wire rod ,
2 block,in sulator bracket 2 No 4,000.00 8,000.00
3 cross arm tie strap 4 m 800.00 3,200.00
4 Steel X-Arm 2 No. 4,800.00 9,600.00
5 11KV Disc Insulator 3 No 1,500.00 4,500.00
6 100mm^2 Alluminium Conductor 150 m 250.00 37,500.00
7 Earthing of X-Arms on poles 1 Points 5,500.00 5,500.00
8 Nuts and Bolts (various sizes) 1 Lots sum 1,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 1 Set 1,900.00 1,900.00
Sub-Total 96,200.00
D Test Certification & Commissioning
1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00
SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,274,000.00
C High Tension Materials 96,200.00
D Test Certification & Commissioning 400,000.00
Sub-Total 2,845,200.00
1 Overhead Charge (25%) 711,300.00
2 Adm. Charges (1%) 28,452.00
3 TOTAL COST 3,584,952.00
VAT (5%) 179,247.60
INSTALLATION COST 3,764,199.60
G TRANSFORMER
300KVA,11/0.415KV,VAT INCLUSIVE 2,300,000.00
GRAND TOTAL FOR INSTALLATION 6,064,199.60

PREPARED BY GIDEON S. ELIJAH CHECKED BY MURTALA S. YUSUF

OLORUNSOGO LANDLORDS AND TENANTS ASSOCIATION, MAJASURAWAAREA OF OLUNLADE, IFELODUN L.G.A.


DATE: 22ND AUGUST, 2014.
Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=

A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=

B Transformer Sub Station

1 11KV Lighting Arrestor Complete 1 No. 35,000.00 35,000.00


2 11KV Expulsion J&P fuse complete 1 No. 25,000.00 25,000.00
4-way 400A, TP&N F eeder Pillar com pl
3 with HRC fuse 1 set 70,000.00 70,000.00
Cab le Lugs,B olts and Nuts,Linetap,
4 Caloric Tape Lot Sum 30,000.00
5 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
6 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
7 Allow for treatment of earth pit Lot Sum 5,000.00
8 Raychem kits complete 2 set 20,000.00 40,000.00
9 9ft Angle Channel 4 No. 4,000.00 16,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
10 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
11 block,wire,insu lato r,clam p 2 No. 4,000.00 8,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
12 xm er comp lete 30 M 2,000.00 60,000.00

13 300mm^2 X 1 pvcl/swa/pvcug Nigerchin cable 30 M 15,000.00 450,000.00


Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
14 2.4m x 2.4m width and graveled Lot Sum 100,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
15 cable fo r 300KVA 30 M 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
16 groun d. Lot Sum 25,000.00

Sub-Total 1,274,000.00

C H.T. NETWORK

1 10.3m HT concrete poles 7 No 25,000.00 175,000.00


2 Danger Plate with anti-climbing wire 2 No 5,500.00 11,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 3 No 4,000.00 12,000.00
4 11KV Pilot Spindle 18 No 600.00 10,800.00
5 11KV Pin insulator 18 No 1,200.00 21,600.00
6 cross arm tie strap 10 M 800.00 8,000.00
7 U-Channel Iron 9" 6 No. 5,000.00 30,000.00
8 Steel X-Arm 5 NO 4,800.00 24,000.00
9 Sectional Steel 9" - No 5,500.00 -
10 11KV Disc Insulator 6 No 1,500.00 9,000.00
11 100mm^2 Alluminium Conductor 900 m 250.00 225,000.00
12 Earthing of X-Arms on poles 2 Points 5,500.00 11,000.00
13 Nuts and Bolts (various sizes) Lots sum 3,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 6 Set 1,900.00 11,400.00

Sub-Total 551,800.00

D L.T. NETWORK
NB: Materials and conductor for the
DUAL Networ k inclusive.

1 8.3m concrete low tension pole 9 Nos 23,000.00 207,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 6 Nos 4,000.00 24,000.00
3 D Iron complete with spindle 56 Nos 370.00 20,720.00
4 Shackle Insulator 56 Nos 120.00 6,720.00
5 Binding wire 70 M 65.00 4,550.00
70m m2 overhead allum inium con ductor :
6 DUAL CONDUCTOR INCL USIVE 2800 M 130.00 364,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 5 points 5,000.00 25,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots sum 5,000.00

Sub-Total 661,790.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00
SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,274,000.00
C High Tension Materials 551,800.00
D Low Tension Materials 661,790.00
E Test Certification & Commissioning 400,000.00

Sub-Total 3,962,590.00

1 Overhead Charge (25%) 990,647.50


2 Adm. Charges (1%) 39,625.90
3 TOTAL COST 4,992,863.40
VAT (5%) 249,643.17

INSTALLATION COST 5,242,506.57

F TRANSFORMER
300KVA, 11/0.415KV, VAT INCLUSIVE 2,300,000.00

GRAND TOTAL FOR INSTALLATION 7,542,506.57

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

KWARA STATE GOVERNMENT CHALET (ALIMI ROAD), ILORIN SOUTH L.G.A.

DATE: 18TH DECEMBER, 2014.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

A Transformer Sub Station

1 11KV Lighting Arrestor Complete 1 No. 35,000.00 35,000.00


2 11KV Expulsion J&P fuse complete 1 No. 25,000.00 25,000.00
4-way 400A, TP&N F eeder Pillar com pl
3 with HRC fuse 1 set 70,000.00 70,000.00
Cab le Lugs,B olts and Nuts,Linetap,
4 Caloric Tape Lot Sum 20,000.00
5 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
6 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
7 Allow for treatment of earth pit Lot Sum 5,000.00
8 Raychem kits complete 1 set 20,000.00 20,000.00
9 9ft Angle Channel 3 No. 4,000.00 12,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
9 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
10 block,wire,insu lato r,clam p 2 No. 4,000.00 8,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
11 xm er comp lete 30 M 2,000.00 60,000.00

12 300mm^2 X 1 pvcl/swa/pvcug Nigerchin cable 30 M 15,000.00 450,000.00


4 by 95m m^2 pvc/swa/pvcug Nigerchin
14 cable fo r 300KVA 30 M 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
15 groun d. Lot Sum 25,000.00

Sub-Total 1,140,000.00
B Test Certification & Commissioning
1 IBEDC Logistics Lots 50,000.00
2 IBEDC Headquarters Charges Lots 50,000.00
3 Power & Steel Statutory Fees Lots 100,000.00

Sub-Total 200,000.00
SUMMARY OF BQ
Nos. Items Cost
N
A Transformer Sub Station 1,140,000.00
B Test Certification & Commissioning 200,000.00

Sub-Total 1,340,000.00

1 Overhead Charge (20%) 268,000.00


2 Adm. Charges (1%) 13,400.00
3 TOTAL COST 1,621,400.00
VAT (5%) 81,070.00

INSTALLATION COST 1,702,470.00


C TRANSFORMER
300KVA, 11/0.415KV, VAT INCLUSIVE AVAILABLE
GRAND TOTAL FOR INSTALLATION 1,702,470.00
PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

GBA'AKO COMMUNITY DEVELOPMENT ASSOCIATION, OKO-OLOWO AREA, IL/SOUTH L.G.A

DATE: 14TH JANUARY, 2015.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

B Transformer Sub Station

1 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00


2 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
3 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
4 Caloric Tape Lot Sum 30,000.00
5 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
6 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
7 Allow for treament of earth pit Lot Sum 5,000.00
8 Raychem kits complete 2 set 20,000.00 40,000.00
9 9ft Angle Channel 4 No. 4,000.00 16,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
10 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
11 block,wire,insu lato r,clam p 2 No. 4,000.00 8,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
12 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
13 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
14 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
15 cable fo r 300KVA 45 M 8,500.00 382,500.00
Feeder pillar plinth 225m m ab ove n ormal
16 groun d. Lot Sum 25,000.00

Sub-Total 1,421,500.00

C H.T. NETWORK

1 10.3m HT concrete poles 8 No 25,000.00 200,000.00


2 Danger Plate with anti-climbing wire 4 No 5,500.00 22,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 4 No 4,000.00 16,000.00
4 33KV Pilot Spindle 12 No 600.00 7,200.00
5 33KV Pin insulator 12 No 1,700.00 20,400.00
6 cross arm tie strap 8 M 800.00 6,400.00
7 U-Channel Iron 9" 6 No. 5,000.00 30,000.00
8 Steel X-Arm 4 NO 4,800.00 19,200.00
9 Sectional Steel 9" - No 5,500.00 -
10 33KV Disc Insulator 27 No 1,800.00 48,600.00
11 150mm^2 Alluminium Conductor 900 m 250.00 225,000.00
12 Earthing of X-Arms on poles Points 5,500.00 5,500.00
13 Nuts and Bolts (various sizes) Lots sum 3,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 6 Set 1,900.00 11,400.00
Sub-Total 614,700.00

D L.T. NETWORK

1 8.3m concrete low tension pole 30 Nos 23,000.00 690,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 10 Nos 4,000.00 40,000.00
3 D Iron complete with spindle 120 Nos 370.00 44,400.00
4 Shackle Insulator 120 Nos 120.00 14,400.00
5 Binding wire 150 M 65.00 9,750.00
6 70mm^2 overhead Alluminium conductor 6,000 M 130.00 780,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 5 points 5,000.00 25,000.00
8 Bimetal linetap 12 Nos 600.00 7,200.00
9 Allow for nuts, washer, bolts etc. Lots Sum 10,000.00
Sub-Total 1,620,750.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,421,500.00
C High Tension Materials 614,700.00
D Low Tension Materials 1,620,750.00
E Test Certification & Commissioning 400,000.00

Sub-Total 5,131,950.00

1 Overhead Charge (25%) 1,282,987.50


2 Adm. Charges (1%) 51,319.50
3 TOTAL COST 6,466,257.00
VAT (5%) 323,312.85
INSTALLATION COST 6,789,569.85
F TRANSFORMER
300KVA, 33/0.415KV, VAT INCLUSIVE 2,350,000.00

GRAND TOTAL FOR INSTALLATION 9,139,569.85


PREPARED BY: ABDULRAFIU S. ASUNKERE CHECKED BY: MURTALA S. YUSUF

OPP. SYNERGY FILLING STATION COMMUNITY, AKEREBIATA AREA, IL/EAST L.G.A.

DATE: 11TH FEBRUARY, 2015.


Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=

A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=

B Transformer Sub Station

1 11KV Gang Isolator 1 No. 80,000.00 80,000.00


2 9ft Angle Channel 2 No. 4,000.00 8,000.00
High tensio n stay com plete,
3 block,wire,insu lato r,clam p 2 No. 4,000.00 8,000.00
Sub-Total 96,000.00

C H.T. NETWORK

1 10.3m HT concrete poles 8 No 25,000.00 200,000.00


2 Danger Plate with anti-climbing wire 4 No 5,500.00 22,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 8 No 4,000.00 32,000.00
4 11KV Pilot Spindle 51 No 600.00 30,600.00
5 11KV Pin insulator 51 No 1,200.00 61,200.00
6 cross arm tie strap 30 M 800.00 24,000.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 15 NO 4,800.00 72,000.00
9 Sectional Steel 9" 2 No 5,500.00 11,000.00
10 11KV Disc Insulator 12 No 1,500.00 18,000.00
11 100mm^2 Alluminium Conductor 2550 m 250.00 637,500.00
12 Earthing of X-Arms on poles 3 Points 5,500.00 16,500.00
13 Nuts and Bolts (various sizes) Lots sum 5,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 12 Set 1,900.00 22,800.00

Sub-Total 1,202,600.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00
SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 96,000.00
C High Tension Materials 1,202,600.00
D Test Certification & Commissioning 400,000.00

Sub-Total 2,773,600.00

1 Overhead Charge (25%) 693,400.00


2 Adm. Charges (1%) 27,736.00
3 TOTAL COST 3,494,736.00
VAT (5%) 174,736.80

INSTALLATION COST 3,669,472.80

E TRANSFORMER
300KVA, 11/0.415KV, VAT INCLUSIVE AVAILABLE

GRAND TOTAL FOR INSTALLATION 3,669,472.80

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

TEMIDIRE COMMUNITY, OPP. WAEC OFFICE, OKO-OLOWO, ILORIN

DATE: 24/02/2015
Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=

A Transformer Sub Station

1 11KV Lighting Arrestor Complete 1 No. 35,000.00 35,000.00


2 11KV Expulsion J&P fuse complete 1 No. 25,000.00 25,000.00
4-way 400A, TP&N F eeder Pillar com pl
3 with HRC fuse 1 set 70,000.00 70,000.00
Cab le Lugs,B olts and Nuts,Linetap,
4 Caloric Tape Lot Sum 30,000.00
5 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
6 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
7 Allow for treatment of earth pit Lot Sum 5,000.00
8 Raychem kits complete 2 set 20,000.00 40,000.00
9 9ft Angle Channel 4 No. 4,000.00 16,000.00
10 11KV pin Insulator&pilot spindle complete 3 set 2,000.00 6,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
11 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
12 block,wire,insu lato r,clam p 2 No. 4,000.00 8,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
13 xm er comp lete 30 M 2,000.00 60,000.00

14 300mm^2 X 1 pvcl/swa/pvcug Nigerchin cable 30 M 15,000.00 450,000.00


Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 150,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
16 cable fo r 300KVA 30 M 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
17 groun d. Lot Sum 25,000.00
Sub-Total 1,330,000.00

B H.T. NETWORK

1 10.3m HT concrete poles 5 No 25,000.00 125,000.00


2 Danger Plate with anti-climbing wire 2 No 5,500.00 11,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 2 No 4,000.00 8,000.00
4 11KV Pilot Spindle 9 No 600.00 5,400.00
5 11KV Pin insulator 9 No 1,200.00 10,800.00
6 cross arm tie strap 6 M 800.00 4,800.00
7 U-Channel Iron 9" 6 No. 5,000.00 30,000.00
8 Steel X-Arm 3 NO 4,800.00 14,400.00
9 Sectional Steel 9" - No 5,500.00 -
10 11KV Disc Insulator 6 No 1,500.00 9,000.00
11 100mm^2 Alluminium Conductor 1000 m 250.00 250,000.00
12 Earthing of X-Arms on poles 1 Points 5,500.00 5,500.00
13 Nuts and Bolts (various sizes) Lots sum 2,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 6 Set 1,900.00 11,400.00
Sub-Total 487,300.00

C L.T. NETWORK

1 8.3m concrete low tension pole 2 Nos 23,000.00 46,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 1 Nos 4,000.00 4,000.00
3 D Iron complete with spindle 8 Nos 370.00 2,960.00
4 Shackle Insulator 8 Nos 120.00 960.00
5 Binding wire 10 M 65.00 650.00
6 70mm2 overhead alluminium conductor 400 M 130.00 52,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) - points 5,000.00 -
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots sum 1,000.00

Sub-Total 112,370.00

D Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00
SUMMARY OF BQ
Nos. Items Cost
N
A Transformer Sub Station 1,330,000.00
B High Tension Materials 487,300.00
C Low Tension Materials 112,370.00
D Test Certification & Commissioning 400,000.00

Sub-Total 2,329,670.00

1 Overhead Charge (25%) 582,417.50


2 Adm. Charges (1%) 23,296.70
3 TOTAL COST 2,935,384.20
VAT (5%) 146,769.21
INSTALLATION COST 3,082,153.41
E TRANSFORMER
300KVA, 11/0.415KV, VAT INCLUSIVE 2,300,000.00

GRAND TOTAL FOR INSTALLATION 5,382,153.41

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

SAI BUKOLA, SAI MAIGIDA, EGBE AFENIFERE, REAL OPTION COLLEGE AREA, GAA-ODOTA, IL/WEST LGA.

DATE: 23rd March, 2015.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

B Transformer Sub Station

1 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00


2 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
3 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
4 Caloric Tape Lot Sum 30,000.00
5 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
6 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
7 Allow for treament of earth pit Lot Sum 5,000.00
8 Raychem kits complete 2 set 20,000.00 40,000.00
9 9ft Angle Channel 4 No. 4,000.00 16,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
10 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
11 block,wire,insu lato r,clam p 2 No. 4,000.00 8,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
12 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
13 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
14 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
15 cable fo r 300KVA 30 M 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
16 groun d. Lot Sum 25,000.00

Sub-Total 1,294,000.00

C H.T. NETWORK

1 10.3m HT concrete poles 8 No 25,000.00 200,000.00


2 Danger Plate with anti-climbing wire 2 No 5,500.00 11,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 3 No 4,000.00 12,000.00
4 33KV Pilot Spindle 18 No 600.00 10,800.00
5 33KV Pin insulator 18 No 1,700.00 30,600.00
6 cross arm tie strap 12 M 800.00 9,600.00
7 U-Channel Iron 9" 6 No. 5,000.00 30,000.00
8 Steel X-Arm 6 NO 4,800.00 28,800.00
9 Sectional Steel 9" - No 5,500.00 -
10 33KV Disc Insulator 18 No 1,800.00 32,400.00
11 150mm^2 Alluminium Conductor 1,050 m 250.00 262,500.00
12 Earthing of X-Arms on poles 2 Points 5,500.00 11,000.00
13 Nuts and Bolts (various sizes) Lots sum 3,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 6 Set 1,900.00 11,400.00

Sub-Total 653,100.00

D L.T. NETWORK

1 8.3m concrete low tension pole 3 Nos 23,000.00 69,000.00


L.T. Stay comp lete with wire rod, block,
2 insulator bracket thim ble etc 3 Nos 4,000.00 12,000.00
3 D Iron complete with spindle 12 Nos 370.00 4,440.00
4 Shackle Insulator 12 Nos 120.00 1,440.00
5 Binding wire 15 M 65.00 975.00
6 70mm^2 overhead Alluminium conductor 600 M 130.00 78,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) - points 5,000.00 -
8 Bimetal linetap 12 Nos 600.00 7,200.00
9 Allow for nuts, washer, bolts etc. Lots Sum 1,000.00

Sub-Total 174,055.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,294,000.00
C High Tension Materials 653,100.00
D Low Tension Materials 174,055.00
E Test Certification & Commissioning 400,000.00

Sub-Total 3,596,155.00

1 Overhead Charge (25%) 899,038.75


2 Adm. Charges (1%) 35,961.55
3 TOTAL COST 4,531,155.30
VAT (5%) 226,557.77
INSTALLATION COST 4,757,713.07
F TRANSFORMER
300KVA, 33/0.415KV, VAT INCLUSIVE 2,350,000.00

GRAND TOTAL FOR INSTALLATION 7,107,713.07

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

ADAMA BOLA SAADU HOUSE, 10 AHMADU BELLO WAY, ILORIN.


DATE: 19TH NOVEMBER, 2015.
Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=
B Transformer Sub Station

1 11KV Lighting Arrestor Complete 1 No. 35,000.00 35,000.00


2 11KV Expulsion J&P fuse complete 1 No. 25,000.00 25,000.00
4-way 600A, TP&N F eeder Pillar com pl
3 with HRC fuse 1 set 70,000.00 70,000.00
Cab le Lugs,B olts and Nuts,Linetap,
4 Caloric Tape Lot Sum 10,000.00
5 8ft galvanised earth rod(thick) 12 No. 2,500.00 30,000.00
6 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
7 Allow for treatment of earth pit Lot Sum 5,000.00
Iron Gate not less than 2.4m x 2.4m width
8 an d graveled Lot Sum 10,000.00
Sub-Total 230,000.00

C Test Certification & Commissioning


1 IBEDC Logistics Lots 50,000.00
2 IBEDC Headquarters Charges Lots 50,000.00
3 Power & Steel Statutory Fees Lots 100,000.00
Sub-Total 200,000.00
SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 230,000.00
C Test Certification & Commissioning 200,000.00
Sub-Total 1,505,000.00

1 Overhead Charge (25%) 376,250.00


2 Adm. Charges (1%) 15,050.00
3 TOTAL COST 1,896,300.00
VAT (5%) 94,815.00
INSTALLATION COST 1,991,115.00
D TRANSFORMER
500KVA, 11/0.415KV, VAT INCLUSIVE 3,100,000.00

GRAND TOTAL FOR INSTALLATION 5,091,115.00


PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

BLAMING GESSE OPP. KAIAMA DAM OFF NEW BUSSA ROAD, KAIAMA LGA

DATE: 10TH DECEMBER, 2015.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

B EXCEPTIONAL PROVISION

1 Allow for bush clearing along network route 100 M 200.00 20,000.00

Sub-Total 20,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

C Transformer Sub Station

1 33KV Gang Isolator 1 No. 100,000.00 100,000.00


2 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00
3 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
11 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
12 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
13 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
14 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
15 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
16 cable fo r 300KVA 30 M 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
17 groun d. Lot Sum 25,000.00

Sub-Total 1,402,000.00

D H.T. NETWORK
1 10.3m HT concrete poles 7 No 25,000.00 175,000.00
2 Danger Plate with anti-climbing wire 6 No 5,500.00 33,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 9 No 4,000.00 36,000.00
4 33KV Pilot Spindle 3 No 600.00 1,800.00
5 33KV Pin insulator 3 No 1,700.00 5,100.00
6 cross arm tie strap 2 M 800.00 1,600.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 1 NO 4,800.00 4,800.00
9 Sectional Steel 9" 4 No 5,500.00 22,000.00
10 33KV Disc Insulator 36 No 1,800.00 64,800.00
11 150mm^2 Alluminium Conductor 540 m 250.00 135,000.00
12 Earthing of X-Arms on poles 3 Points 5,500.00 16,500.00
13 Nuts and Bolts (various sizes) Lots sum 3,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 12 Set 1,900.00 22,800.00
Sub-Total 571,400.00

E L.T. NETWORK
NB: Materials & Con ducto r are in clusive
for Du al Network
1 8.3m concrete low tension pole 10 Nos 23,000.00 230,000.00
LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 4 Nos 4,000.00 16,000.00
3 D Iron complete with spindle 44 Nos 370.00 16,280.00
4 Shackle Insulator 44 Nos 120.00 5,280.00
5 Binding wire 55 M 65.00 3,575.00
6 70mm^2 overhead Alluminium conductor 2,540 M 130.00 330,200.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 4 points 5,000.00 20,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots Sum 5,000.00
Sub-Total 631,135.00

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00
Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Exceptional Provision 20,000.00
C Transformer Sub Station 1,402,000.00
D High Tension Materials 571,400.00
E Low Tension Materials 631,135.00
F Test Certification & Commissioning 400,000.00
Sub-Total 4,099,535.00

1 Overhead Charge (25%) 1,024,883.75


2 Contingency (1%) 40,995.35
3 Adm. Charges (1%) 40,995.35
4 TOTAL COST 5,206,409.45
VAT (5%) 260,320.47
INSTALLATION COST 5,466,729.92
G TRANSFORMER
300KVA, 33/0.415KV, VAT INCLUSIVE 2,350,000.00
GRAND TOTAL FOR INSTALLATION 7,816,729.92
PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. I. I. DABARAKO

UBE SCHOOLALONG TENEBO ROAD, KAIAMA LGA.

DATE: 10TH DECEMBER, 2015.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

B Transformer Sub Station

1 33KV Gang Isolator 1 No. 100,000.00 100,000.00


2 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00
3 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
11 33KV pin Insulator&pilot spindle complete 3 set 2,300.00 6,900.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
16 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA 30 M 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 1,408,900.00

C L.T. NETWORK
NB: Materials & Con ducto r are in clusive
for Du al Network
8.3m concrete low tension p ole: As
1 intermediar y dual po les 8 Nos 23,000.00 184,000.00
LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 2 Nos 4,000.00 8,000.00
3 D Iron complete with spindle 32 Nos 370.00 11,840.00
4 Shackle Insulator 32 Nos 120.00 3,840.00
5 Binding wire 40 M 65.00 2,600.00
6 70mm^2 overhead Alluminium conductor 2,880 M 130.00 374,400.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 2 points 5,000.00 10,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots Sum 3,000.00

Sub-Total 602,480.00

D Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,408,900.00
C Low Tension Materials 602,480.00
D Test Certification & Commissioning 400,000.00

Sub-Total 3,486,380.00

1 Overhead Charge (25%) 871,595.00


2 Contingency (1%) 34,863.80
3 Adm. Charges (1%) 34,863.80
4 TOTAL COST 4,427,702.60
VAT (5%) 221,385.13
INSTALLATION COST 4,649,087.73
E TRANSFORMER
300KVA, 33/0.415KV, VAT INCLUSIVE 2,350,000.00

GRAND TOTAL FOR INSTALLATION 6,999,087.73

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. I. I. DABARAKO

KEMANJI BYPASS OFF TENEBO ROAD, KAIAMA LGA.


DATE: 10TH DECEMBER, 2015.
Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

B EXCEPTIONAL PROVISION

1 Allow for bush clearing along network route 10 M 200.00 2,000.00

Sub-Total 2,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

C Transformer Sub Station

1 33KV Gang Isolator 1 No. 100,000.00 100,000.00


2 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00
3 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
11 33KV pin Insulator&pilot spindle complete 3 set 2,300.00 6,900.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
16 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
17 cable fo r 300KVA 30 M 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
18 groun d. Lot Sum 25,000.00

Sub-Total 1,408,900.00

D H.T. NETWORK

1 10.3m HT concrete poles 1 No 25,000.00 25,000.00


2 Danger Plate with anti-climbing wire 2 No 5,500.00 11,000.00
3 U-Channel Iron 9" 4 No. 5,000.00 20,000.00
4 33KV Disc Insulator 18 No 1,800.00 32,400.00
5 150mm^2 Alluminium Conductor 100 m 250.00 25,000.00
6 Nuts and Bolts (various sizes) Lots sum 1,000.00
Six bolt clam p, j-hook,socket tongu e,
7 tensio n clamp 6 Set 1,900.00 11,400.00

Sub-Total 125,800.00

E L.T. NETWORK
NB: Materials & Con ducto r are in clusive
for Inter mediary poles
8.3m concrete low tension p ole: 3nos. of
1 intermediar y dual po les inclusive 8 Nos 23,000.00 184,000.00
LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 2 Nos 4,000.00 8,000.00
3 D Iron complete with spindle 32 Nos 370.00 11,840.00
4 Shackle Insulator 32 Nos 120.00 3,840.00
5 Binding wire 40 M 65.00 2,600.00
6 70mm^2 overhead Alluminium conductor 2,080 M 130.00 270,400.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 2 points 5,000.00 10,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots Sum 3,000.00

Sub-Total 498,480.00

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Exceptional Provision 2,000.00
C Transformer Sub Station 1,408,900.00
D High Tension Materials 125,800.00
E Low Tension Materials 498,480.00
F Test Certification & Commissioning 400,000.00

Sub-Total 3,510,180.00

1 Overhead Charge (25%) 877,545.00


2 Contingency (1%) 35,101.80
3 Adm. Charges (1%) 35,101.80
4 TOTAL COST 4,457,928.60
VAT (5%) 222,896.43
INSTALLATION COST 4,680,825.03
G TRANSFORMER
300KVA, 33/0.415KV, VAT INCLUSIVE 2,350,000.00

GRAND TOTAL FOR INSTALLATION 7,030,825.03

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. I. I. DABARAKO

BA'AGABI JUNCTION, MAIGIRO AREA (BEHIND MOBOLAJI HOTEL), KAIAMA LGA.

DATE: 10TH DECEMBER, 2015.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

B Transformer Sub Station

1 33KV Gang Isolator 1 No. 100,000.00 100,000.00


2 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00
3 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
11 33KV pin Insulator&pilot spindle complete 3 set 2,300.00 6,900.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
16 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA 45 M 8,500.00 382,500.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 1,536,400.00

C H.T. NETWORK

1 10.3m HT concrete poles 15 No 25,000.00 375,000.00


2 Danger Plate with anti-climbing wire 4 No 5,500.00 22,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 5 No 4,000.00
4 33KV Pilot Spindle 30 No 600.00 18,000.00
5 33KV Pin insulator 30 No 1,700.00 51,000.00
6 cross arm tie strap 20 M 800.00 16,000.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 10 NO 4,800.00 48,000.00
9 Sectional Steel 9" 2 No 5,500.00 11,000.00
10 33KV Disc Insulator 45 No 1,800.00 81,000.00
11 150mm^2 Alluminium Conductor 1,800 m 250.00 450,000.00
12 Earthing of X-Arms on poles 2 Points 5,500.00 11,000.00
13 Nuts and Bolts (various sizes) Lots sum 8,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 12 Set 1,900.00 22,800.00
Sub-Total 1,163,800.00

D L.T. NETWORK

1 8.3m concrete low tension pole 8 Nos 23,000.00 184,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 4 Nos 4,000.00 16,000.00
3 D Iron complete with spindle 32 Nos 370.00 11,840.00
4 Shackle Insulator 32 Nos 120.00 3,840.00
5 Binding wire 40 M 65.00 2,600.00
6 70mm^2 overhead Alluminium conductor 1,750 M 130.00 227,500.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 3 points 5,000.00 15,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots Sum 3,000.00
Sub-Total 468,580.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00
Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,536,400.00
C High Tension Materials 1,163,800.00
D Low Tension Materials 468,580.00
E Test Certification & Commissioning 400,000.00
Sub-Total 4,643,780.00

1 Overhead Charge (25%) 1,160,945.00


2 Contingency (1%) 46,437.80
3 Adm. Charges (1%) 46,437.80
4 TOTAL COST 5,897,600.60
VAT (5%) 294,880.03
INSTALLATION COST 6,192,480.63
F TRANSFORMER
300KVA, 33/0.415KV, VAT INCLUSIVE 2,350,000.00

GRAND TOTAL FOR INSTALLATION 8,542,480.63


PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. I. I. DABARAKO

SABON GARI (ZIKO AREA), KAIAMA LGA.

DATE: 10TH DECEMBER, 2015.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

B Transformer Sub Station

1 33KV Gang Isolator 1 No. 100,000.00 100,000.00


2 33KV Lighting Arrestor Complete 1 No. 40,000.00 40,000.00
3 33KV Expulsion J&P fuse complete 1 No. 30,000.00 30,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
11 33KV pin Insulator&pilot spindle complete 3 set 2,200.00 6,600.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 100,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
16 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA or 200KVA 30 M 8,500.00 255,000.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 1,408,600.00

C H.T. NETWORK

1 10.3m HT concrete poles 17 No 25,000.00 425,000.00


2 Danger Plate with anti-climbing wire 4 No 5,500.00 22,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 10 No 4,000.00 40,000.00
4 33KV Pilot Spindle 36 No 600.00 21,600.00
5 33KV Pin insulator 36 No 1,700.00 61,200.00
6 cross arm tie strap 24 M 800.00 19,200.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 12 NO 4,800.00 57,600.00
9 Sectional Steel 9" 2 No 5,500.00 11,000.00
10 33KV Disc Insulator 45 No 1,800.00 81,000.00
11 150mm^2 Alluminium Conductor 2,100 m 250.00 525,000.00
12 Earthing of X-Arms on poles 2 Points 5,500.00 11,000.00
13 Nuts and Bolts (various sizes) Lots sum 10,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 12 Set 1,900.00 22,800.00
Sub-Total 1,357,400.00

D L.T. NETWORK
NB: Materials & Con ducto r are in clusive
for du al networ k
1 8.3m concrete low tension pole 7 Nos 23,000.00 161,000.00
LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 4 Nos 4,000.00 16,000.00
3 D Iron complete with spindle 28 Nos 370.00 10,360.00
4 Shackle Insulator 28 Nos 120.00 3,360.00
5 Binding wire 35 M 65.00 2,275.00
70m m^2 over head Allum inium cond uctor :
6 dual cond uctor of 300Km in clusive 2,600 M 130.00 338,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 4 points 5,000.00 20,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots Sum 3,000.00
Sub-Total 558,795.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00
Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Transformer Sub Station 1,408,600.00
C High Tension Materials 1,357,400.00
D Low Tension Materials 558,795.00
E Test Certification & Commissioning 400,000.00
Sub-Total 4,799,795.00

1 Overhead Charge (25%) 1,199,948.75


2 Contingency (1%) 47,997.95
3 Adm. Charges (1%) 47,997.95
4 TOTAL COST 6,095,739.65
VAT (5%) 304,786.98
INSTALLATION COST 6,400,526.63
F TRANSFORMER
300KVA, 33/0.415KV, VAT INCLUSIVE 2,350,000.00
GRAND TOTAL FOR INSTALLATION 8,750,526.63
PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. I. I. DABARAKO

NEW BEME IN LINE WITH THE NEW PRICE OF MATERIALS AND TRANSFORMERS

33KV ELECTRIFICATION PROJECT TITLE:

DATE:
Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
& soft copies (A3) Bill of Engineering
i Measurement & Evaluation Lot Sum
Allo w for m aintenance /fuelling of project
vehicle th rougho ut the perio d of the
ii project Lot Sum
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer Lot Sum
Sub-Total (Ai+Aii+Aiii)

B EXCEPTIONAL PROVISION

1 Allow for tree cutting along network route No 1,500.00 -


Allo w for bottom beam ing of HT / LT
poles in swamps u sing 300 x 300 x
2 600mm hig h concrete in site No 1,800.00 -
Allo w for clear ing of thick forest along
3 network r oute M 200.00 -
Allo w for bottom beam ing of HT / LT
poles in rocky terr ain usin g 600 x 600 x
4 1200m m high No 3,600.00 -
Allo w for lo ng distance tran spo rtation of
5 men & mater ials Km 500.00 -

Sub-Total -

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

C Transformer Sub Station

1 500KVA, 33/0.415KV Transformer 1 No.


2 33KV Gang Isolator (Silicon type) 1 No. 150,000.00 150,000.00
33KV Lighting Ar restor Comp lete (Silicon
3 type) 1 No. 140,000.00 140,000.00
33KV Expu lsion J&P fuse complete
4 (Silicon type) 1 No. 105,000.00 105,000.00
4-way 400A, TP&N F eeder Pillar com pl
5 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
6 Caloric Tape Lot Sum 30,000.00
7 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00 ABB-TYPE, year 2016 including TF
8 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00 500/33 = 6,950,000.00
9 Allow for treament of earth pit Lot Sum 5,000.00 500/11 = 4,450,000.00
10 Raychem kits complete 2 set 20,000.00 40,000.00 300/33 = 5,450,000.00
11 9ft Angle Channel 4 No. 4,000.00 16,000.00 300/11 = 4,650,000.00
33KV pin In sulator &pilot spindle
12 co mplete (Silico n type) 3 set 7,700.00 23,100.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
13 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
14 block,wire,insu lato r,clam p 4 No. 5,000.00 20,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
15 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
16 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
17 cable 30 M 15,000.00 450,000.00
4 by 150mm ^2 pvc/swa/pvcu g Nig er chin
18 cable fo r 500KVA 45 M 12,000.00 540,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
19 cable fo r 300KVA or 200KVA 45 M 10,000.00 450,000.00
Feeder pillar plinth 225m m ab ove n ormal
20 groun d. Lot Sum 25,000.00

Sub-Total 2,439,100.00

D H.T. NETWORK
1 10.3m HT concrete poles No 25,000.00 -
2 Danger Plate with anti-climbing wire No 5,500.00 -
HT Stay com plete with wire rod ,
3 block,in sulator bracket No 5,000.00 -
4 33KV Pilot Spindle No 600.00 -
5 33KV Pin insulator (Silicon type) No 5,950.00 -
6 cross arm tie strap M 800.00 -
7 U-Channel Iron 9" No. 5,000.00 -
8 Steel X-Arm NO 4,800.00 -
9 Sectional Steel 9" No 5,500.00 -
10 33KV Disc Insulator (Silicon type) No 6,300.00 -
11 150mm^2 Alluminium Conductor m 300.00 -
12 Earthing of X-Arms on poles Points 5,500.00 -
13 Nuts and Bolts (various sizes) Lots sum
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp Set 1,900.00 -

Sub-Total -

E L.T. NETWORK

1 8.3m concrete low tension pole Nos 23,000.00 -


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc Nos 5,000.00 -
3 D Iron complete with spindle Nos 370.00 -
4 Shackle Insulator (Silicon type) Nos 420.00 -
5 Binding wire M 65.00 -
6 100mm^2 overhead Alluminium conductor M 250.00 -
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) points 5,000.00 -
8 Bimetal linetap Nos 600.00 -
9 Allow for nuts, washer, bolts etc. Lots Sum

Sub-Total -

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries -
B Exceptional Provision -
C Transformer Sub Station 2,439,100.00
D High Tension Materials -
E Low Tension Materials -
F Test Certification & Commissioning 400,000.00

Sub-Total 2,839,100.00

1 Overhead Charge (25%) 709,775.00


2 Contingency (5%) 28,391.00
4 TOTAL COST 3,577,266.00
VAT (5%) 178,863.30
INSTALLATION COST 3,756,129.30

GRAND TOTAL FOR INSTALLATION 3,756,129.30

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

11KV ELECTRIFICATION PROJECT TITLE:

DATE:
Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=

A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
i & soft copies
Sup er vising Engin eers fuelling allowan ce
ii through out the perio d of the p roject
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer
Sub-Total (Ai+Aii+Aiii) Lot Sum 1,075,000.00

B EXCEPTIONAL PROVISION

1 Allow for tree cutting along network route No 1,500.00 -


Allo w for bottom beam ing of HT / LT
poles in swamps u sing 225 x 225 x
2 600mm hig h concrete in site No 1,800.00 -
Allo w for clear ing of thick forest along
3 network r oute M 200.00 -
Allo w for bottom beam ing of HT / LT
poles in rocky terr ain usin g 225x
4 225x1200m m h igh No 3,600.00 -
Allo w for lo ng distance tran spo rtation of
5 men & mater ials Km 500.00 -

Sub-Total -

Sr. No. Description of Items Qty UNIT Price Total Price

=N= =N=

C Transformer Sub Station

1 11KV Gang Isolator 1 No. 80,000.00 80,000.00


2 11KV Lighting Arrestor Complete 1 No. 35,000.00 35,000.00
3 11KV Expulsion J&P fuse complete 1 No. 25,000.00 25,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 70,000.00 70,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treatment of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
11 11KV pin Insulator&pilot spindle complete 3 set 1,800.00 5,400.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p 4 No. 4,000.00 16,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete 30 M 2,000.00 60,000.00
4 by 150mm ^2 pvc/swa/pvcu g Nig er chin
15 cable fo r 500KVA 45 M 12,000.00 540,000.00

16 300mm^2 X 1 pvcl/swa/pvcug Nigerchin cable 30 M 15,000.00 450,000.00


Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 150,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA or 200KVA 45 M 8,500.00 382,500.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 2,084,900.00

D H.T. NETWORK

1 10.3m HT concrete poles No 25,000.00 -


2 Danger Plate with anti-climbing wire No 5,500.00 -
HT Stay com plete with wire rod ,
3 block,in sulator bracket No 4,000.00 -
4 11KV Pilot Spindle No 600.00 -
5 11KV Pin insulator No 1,200.00 -
6 cross arm tie strap M 800.00 -
7 U-Channel Iron 9" No. 5,000.00 -
8 Steel X-Arm NO 4,800.00 -
9 Sectional Steel 9" No 5,500.00 -
10 11KV Disc Insulator No 1,500.00 -
11 100mm^2 Alluminium Conductor m 250.00 -
12 Earthing of X-Arms on poles Points 5,500.00 -
13 Nuts and Bolts (various sizes) Lots sum
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp Set 1,900.00 -

Sub-Total -

E L.T. NETWORK

1 8.3m concrete low tension pole Nos 23,000.00 -


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc Nos 4,000.00 -
3 D Iron complete with spindle Nos 370.00 -
4 Shackle Insulator Nos 120.00 -
5 Binding wire M 65.00 -
6 70mm2 overhead alluminium conductor M 130.00 -
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) points 5,000.00 -
8 Bimetal linetap Nos 600.00 -
9 Allow for nuts, washer, bolts etc. Lots sum

Sub-Total -

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,075,000.00
B Exceptional Provision -
C Transformer Sub Station 2,084,900.00
D High Tension Materials -
E Low Tension Materials -
F Test Certification & Commissioning 400,000.00

Sub-Total 3,559,900.00

1 Overhead Charge (25%) 889,975.00


2 Contingency (1%) 35,599.00
3 Adm. Charges (1%) 35,599.00
4 TOTAL COST 4,521,073.00
VAT (5%) 226,053.65
INSTALLATION COST 4,747,126.65
G TRANSFORMER
500KVA, 11/0.415KV, VAT INCLUSIVE

GRAND TOTAL FOR INSTALLATION 4,747,126.65

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

SHAO ILE, OJULOGBO, AGBAA, ELESINLAAND AKIRIBI VIA OYUN-SOBI H.T., MORO LGA.

DATE: 13TH JUNE, 2012.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
& soft copies (A3) Bill of Engineering
i Measurement & Evaluation Lot Sum 250,000.00
Allo w for m aintenance /fuelling of project
vehicle th rougho ut the perio d of the
ii project Lot Sum 400,000.00
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer Lot Sum 300,000.00
Sub-Total (Ai+Aii+Aiii) 950,000.00

B EXCEPTIONAL PROVISION

Allo w for clear ing of thick forest along


1 network r oute 1300 M 200.00 260,000.00
Allo w for lo ng distance tran spo rtation of
2 men & mater ials 80 Km 500.00 40,000.00

Sub-Total 300,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

C Transformer Sub Station

1 300KVA, 33/0.415KV Transformer 1 No. 5,450,000.00 5,450,000.00


2 33KV Gang Isolator (Silicon type) 1 No. 150,000.00 150,000.00
33KV Lighting Ar restor Comp lete (Silicon
3 type) 1 No. 140,000.00 140,000.00
33KV Expu lsion J&P fuse complete
4 (Silicon type) 1 No. 105,000.00 105,000.00
4-way 400A, TP&N F eeder Pillar com pl
5 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
6 Caloric Tape Lot Sum 30,000.00
7 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
8 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
9 Allow for treament of earth pit Lot Sum 5,000.00
10 Raychem kits complete 2 set 20,000.00 40,000.00
11 9ft Angle Channel 4 No. 4,000.00 16,000.00
33KV pin In sulator &pilot spindle
12 co mplete (Silico n type) 3 set 7,700.00 23,100.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
13 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
14 block,wire,insu lato r,clam p 4 No. 5,000.00 20,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
15 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
16 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
17 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA or 200KVA 45 M 10,000.00 450,000.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 7,349,100.00

D H.T. NETWORK

1 10.3m HT concrete poles 23 No 25,000.00 575,000.00


2 Danger Plate with anti-climbing wire 23 No 5,500.00 126,500.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 12 No 5,000.00 60,000.00
4 33KV Pilot Spindle 57 No 600.00 34,200.00
5 33KV Pin insulator (Silicon type) 57 No 5,950.00 339,150.00
6 cross arm tie strap 38 M 800.00 30,400.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 19 NO 4,800.00 91,200.00
9 Sectional Steel 9" 4 No 5,500.00 22,000.00
10 33KV Disc Insulator (Silicon type) 54 No 6,300.00 340,200.00
11 150mm^2 Alluminium Conductor 3,780 m 300.00 1,134,000.00
12 Earthing of X-Arms on poles 19 Points 5,500.00 104,500.00
13 Nuts and Bolts (various sizes) Lots sum 23,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 3 Set 1,900.00 5,700.00

Sub-Total 2,935,850.00

E(i) L.T. NETWORK

1 8.3m concrete low tension pole 9 Nos 23,000.00 207,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 4 Nos 5,000.00 20,000.00
3 D Iron complete with spindle 36 Nos 370.00 13,320.00
4 Shackle Insulator (Silicon type) 36 Nos 420.00 15,120.00
5 Binding wire 45 M 65.00 2,925.00
6 100mm^2 overhead Alluminium conductor 1,600 M 250.00 400,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 3 points 5,000.00 15,000.00
8 Bimetal linetap 12 Nos 600.00 7,200.00
9 Allow for nuts, washer, bolts etc. Lots Sum 9,000.00

Sub-Total 689,565.00

E(ii) L.T. NETWORK

1 8.3m concrete low tension pole 7 Nos 23,000.00 161,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 3 Nos 5,000.00 15,000.00
3 D Iron complete with spindle 28 Nos 370.00 10,360.00
4 Shackle Insulator (Silicon type) 28 Nos 420.00 11,760.00
5 Binding wire 35 M 65.00 2,275.00
6 100mm^2 overhead Alluminium conductor 1,200 M 250.00 300,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 2 points 5,000.00 10,000.00
8 Bimetal linetap Nos 600.00 -
9 Allow for nuts, washer, bolts etc. Lots 7,000.00

Sub-Total 517,395.00

E(iii) L.T. NETWORK

1 8.3m concrete low tension pole 1 Nos 23,000.00 23,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 1 Nos 5,000.00 5,000.00
3 D Iron complete with spindle 4 Nos 370.00 1,480.00
4 Shackle Insulator (Silicon type) 4 Nos 420.00 1,680.00
5 Binding wire 5 M 65.00 325.00
6 100mm^2 overhead Alluminium conductor 1,600 M 250.00 400,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 1 points 5,000.00 5,000.00
8 Bimetal linetap Nos 600.00 -
9 Allow for nuts, washer, bolts etc. Lots Sum 1,000.00

Sub-Total 437,485.00

E(iv) L.T. NETWORK

1 8.3m concrete low tension pole 22 Nos 23,000.00 506,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 11 Nos 5,000.00 55,000.00
3 D Iron complete with spindle 88 Nos 370.00 32,560.00
4 Shackle Insulator (Silicon type) 88 Nos 420.00 36,960.00
5 Binding wire 110 M 65.00 7,150.00
6 100mm^2 overhead Alluminium conductor 4,200 M 250.00 1,050,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 7 points 5,000.00 35,000.00
8 Bimetal linetap Nos 600.00 -
9 Allow for nuts, washer, bolts etc. Lots Sum 22,000.00

Sub-Total 1,744,670.00

E (TOTAL=E(i)+E(ii)+E(iii)+E(iv)) 3,389,115.00

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 950,000.00
B Exceptional Provision 300,000.00
C Transformer Sub Station 7,349,100.00
D High Tension Materials 2,935,850.00
E Low Tension Materials 3,389,115.00
F Test Certification & Commissioning 400,000.00

Sub-Total 15,324,065.00

1 Overhead Charge (25%) 3,831,016.25


2 Contingency (5%) 153,240.65
4 TOTAL COST 19,308,321.90
VAT (5%) 965,416.10
INSTALLATION COST 20,273,738.00

GRAND TOTAL FOR INSTALLATION 20,273,738.00

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

ATIPO COMMUNITY VIAATIPO JUNCTION, MORO LGA.

DATE:14TH JUNE, 2012.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
& soft copies (A3) Bill of Engineering
i Measurement & Evaluation Lot Sum 200,000.00
Allo w for m aintenance /fuelling of project
vehicle th rougho ut the perio d of the
ii project Lot Sum 300,000.00
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer Lot Sum 210,000.00
Sub-Total (Ai+Aii+Aiii) 710,000.00

B EXCEPTIONAL PROVISION

Allo w for lo ng distance tran spo rtation of


1 men & mater ials 80 Km 500.00 40,000.00

Sub-Total 40,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

C Transformer Sub Station

1 300KVA, 33/0.415KV Transformer 1 No. 5,450,000.00 5,450,000.00


2 33KV Gang Isolator (Silicon type) 1 No. 150,000.00 150,000.00
33KV Lighting Ar restor Comp lete (Silicon
3 type) 1 No. 140,000.00 140,000.00
33KV Expu lsion J&P fuse complete
4 (Silicon type) 1 No. 105,000.00 105,000.00
4-way 400A, TP&N F eeder Pillar com pl
5 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
6 Caloric Tape Lot Sum 30,000.00
7 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
8 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
9 Allow for treament of earth pit Lot Sum 5,000.00
10 Raychem kits complete 2 set 20,000.00 40,000.00
11 9ft Angle Channel 4 No. 4,000.00 16,000.00
33KV pin In sulator &pilot spindle
12 co mplete (Silico n type) 3 set 7,700.00 23,100.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
13 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
14 block,wire,insu lato r,clam p 4 No. 5,000.00 20,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
15 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
16 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
17 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
19 cable fo r 300KVA or 200KVA 45 M 10,000.00 450,000.00
Feeder pillar plinth 225m m ab ove n ormal
20 groun d. Lot Sum 25,000.00

Sub-Total 7,349,100.00

D H.T. NETWORK

1 10.3m HT concrete poles 5 No 25,000.00 125,000.00


2 Danger Plate with anti-climbing wire 5 No 5,500.00 27,500.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 4 No 5,000.00 20,000.00
4 33KV Pilot Spindle 3 No 600.00 1,800.00
5 33KV Pin insulator (Silicon type) 3 No 5,950.00 17,850.00
6 cross arm tie strap 2 M 800.00 1,600.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 1 NO 4,800.00 4,800.00
9 Sectional Steel 9" 2 No 5,500.00 11,000.00
10 33KV Disc Insulator (Silicon type) 27 No 6,300.00 170,100.00
11 150mm^2 Alluminium Conductor 900 m 300.00 270,000.00
12 Earthing of X-Arms on poles 1 Points 5,500.00 5,500.00
13 Nuts and Bolts (various sizes) Lots sum 5,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 2 Set 1,900.00 3,800.00

Sub-Total 713,950.00

E L.T. NETWORK

1 8.3m concrete low tension pole 22 Nos 23,000.00 506,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 11 Nos 5,000.00 55,000.00
3 D Iron complete with spindle 88 Nos 370.00 32,560.00
4 Shackle Insulator (Silicon type) 88 Nos 420.00 36,960.00
5 Binding wire 110 M 65.00 7,150.00
6 100mm^2 overhead Alluminium conductor 6,160 M 250.00 1,540,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 7 points 5,000.00 35,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots Sum 22,000.00

Sub-Total 2,239,470.00

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 710,000.00
B Exceptional Provision 40,000.00
C Transformer Sub Station 7,349,100.00
D High Tension Materials 713,950.00
E Low Tension Materials 2,239,470.00
F Test Certification & Commissioning 400,000.00

Sub-Total 11,452,520.00

1 Overhead Charge (25%) 2,863,130.00


2 Contingency (5%) 114,525.20
4 TOTAL COST 14,430,175.20
VAT (5%) 721,508.76
INSTALLATION COST 15,151,683.96

GRAND TOTAL FOR INSTALLATION 15,151,683.96

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

GBODI VIAAIYELEKAN H.T., MORO LGA.

DATE: 13TH JUNE, 2012


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
& soft copies (A3) Bill of Engineering
i Measurement & Evaluation Lot Sum 277,000.00
Allo w for m aintenance /fuelling of project
vehicle th rougho ut the perio d of the
ii project Lot Sum 400,000.00
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer Lot Sum 300,000.00
Sub-Total (Ai+Aii+Aiii) 977,000.00

B EXCEPTIONAL PROVISION

Allo w for clear ing of thick forest along


1 network r oute 2500 M 200.00 500,000.00
Allo w for lo ng distance tran spo rtation of
2 men & mater ials 80 Km 500.00 40,000.00

Sub-Total 540,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

C Transformer Sub Station

1 300KVA, 33/0.415KV Transformer 1 No. 5,450,000.00 5,450,000.00


2 33KV Gang Isolator (Silicon type) 1 No. 150,000.00 150,000.00
33KV Lighting Ar restor Comp lete (Silicon
3 type) 1 No. 140,000.00 140,000.00
33KV Expu lsion J&P fuse complete
4 (Silicon type) 1 No. 105,000.00 105,000.00
4-way 400A, TP&N F eeder Pillar com pl
5 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
6 Caloric Tape Lot Sum 30,000.00
7 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
8 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
9 Allow for treament of earth pit Lot Sum 5,000.00
10 Raychem kits complete 2 set 20,000.00 40,000.00
11 9ft Angle Channel 4 No. 4,000.00 16,000.00
33KV pin In sulator &pilot spindle
12 co mplete (Silico n type) 3 set 7,700.00 23,100.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
13 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
14 block,wire,insu lato r,clam p 4 No. 5,000.00 20,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
15 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
16 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
17 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA or 200KVA 30 M 10,000.00 300,000.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 7,199,100.00

D H.T. NETWORK

1 10.3m HT concrete poles 43 No 25,000.00 1,075,000.00


2 Danger Plate with anti-climbing wire 43 No 5,500.00 236,500.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 22 No 5,000.00 110,000.00
4 33KV Pilot Spindle 108 No 600.00 64,800.00
5 33KV Pin insulator (Silicon type) 108 No 5,950.00 642,600.00
6 cross arm tie strap 72 M 800.00 57,600.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 36 NO 4,800.00 172,800.00
9 Sectional Steel 9" 10 No 5,500.00 55,000.00
10 33KV Disc Insulator (Silicon type) 108 No 6,300.00 680,400.00
11 150mm^2 Alluminium Conductor 7,350 m 300.00 2,205,000.00
12 Earthing of X-Arms on poles 36 Points 5,500.00 198,000.00
13 Nuts and Bolts (various sizes) 36 Lots sum 43,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 6 Set 1,900.00 11,400.00

Sub-Total 5,602,100.00

E L.T. NETWORK

1 8.3m concrete low tension pole 13 Nos 23,000.00 299,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 6 Nos 5,000.00 30,000.00
3 D Iron complete with spindle 52 Nos 370.00 19,240.00
4 Shackle Insulator (Silicon type) 52 Nos 420.00 21,840.00
5 Binding wire 215 M 65.00 13,975.00
6 100mm^2 overhead Alluminium conductor 2,400 M 250.00 600,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 4 points 5,000.00 20,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots Sum 13,000.00

Sub-Total 1,021,855.00

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 977,000.00
B Exceptional Provision 540,000.00
C Transformer Sub Station 7,199,100.00
D High Tension Materials 5,602,100.00
E Low Tension Materials 1,021,855.00
F Test Certification & Commissioning 400,000.00

Sub-Total 15,740,055.00

1 Overhead Charge (25%) 3,935,013.75


2 Contingency (5%) 157,400.55
4 TOTAL COST 19,832,469.30
VAT (5%) 991,623.47
INSTALLATION COST 20,824,092.77

GRAND TOTAL FOR INSTALLATION 20,824,092.77

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

BODE VIA ILESHA BARUBA, BARUTEN LGA.

DATE: 11TH JUNE, 2012.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
& soft copies (A3) Bill of Engineering
i Measurement & Evaluation Lot Sum 300,000.00
Allo w for m aintenance /fuelling of project
vehicle th rougho ut the perio d of the
ii project Lot Sum 700,000.00
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer Lot Sum 300,000.00
Sub-Total (Ai+Aii+Aiii) 1,300,000.00

B EXCEPTIONAL PROVISION

Allo w for clear ing of thick forest along


1 network r oute 17100 M 200.00 3,420,000.00
Allo w for bottom beam ing of HT / LT
poles in rocky terr ain usin g 600 x 600 x
2 1200m m high 327 No 3,600.00 1,177,200.00
Allo w for lo ng distance tran spo rtation of
3 men & mater ials 250 Km 500.00 125,000.00

Sub-Total 4,722,200.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

C Transformer Sub Station

1 300KVA, 33/0.415KV Transformer 1 No. 5,450,000.00 5,450,000.00


2 33KV Gang Isolator (Silicon type) 1 No. 150,000.00 150,000.00
33KV Lighting Ar restor Comp lete (Silicon
3 type) 1 No. 140,000.00 140,000.00
33KV Expu lsion J&P fuse complete
4 (Silicon type) 1 No. 105,000.00 105,000.00
4-way 400A, TP&N F eeder Pillar com pl
5 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
6 Caloric Tape Lot Sum 30,000.00
7 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
8 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
9 Allow for treament of earth pit Lot Sum 5,000.00
10 Raychem kits complete 2 set 20,000.00 40,000.00
11 9ft Angle Channel 4 No. 4,000.00 16,000.00
33KV pin In sulator &pilot spindle
12 co mplete (Silico n type) 3 set 7,700.00 23,100.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
13 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
14 block,wire,insu lato r,clam p 4 No. 5,000.00 20,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
15 xm er comp lete 45 M 2,000.00 90,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
16 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
17 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA 45 M 12,000.00 540,000.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 7,469,100.00

D H.T. NETWORK

1 10.3m HT concrete poles 277 No 25,000.00 6,925,000.00


2 Danger Plate with anti-climbing wire 277 No 5,500.00 1,523,500.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 139 No 5,000.00 695,000.00
4 33KV Pilot Spindle 825 No 600.00 495,000.00
5 33KV Pin insulator (Silicon type) 825 No 5,950.00 4,908,750.00
6 cross arm tie strap 488 M 800.00 390,400.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 244 NO 4,800.00 1,171,200.00
9 Sectional Steel 9" 62 No 5,500.00 341,000.00
10 33KV Disc Insulator (Silicon type) 576 No 6,300.00 3,628,800.00
11 150mm^2 Alluminium Conductor 51,030 m 300.00 15,309,000.00
12 Earthing of X-Arms on poles 244 Points 5,500.00 1,342,000.00
13 Nuts and Bolts (various sizes) Lots sum 100,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 32 Set 1,900.00 60,800.00

Sub-Total 36,940,450.00

E L.T. NETWORK

1 8.3m concrete low tension pole 50 Nos 23,000.00 1,150,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 25 Nos 5,000.00 125,000.00
3 D Iron complete with spindle 200 Nos 370.00 74,000.00
4 Shackle Insulator (Silicon type) 200 Nos 420.00 84,000.00
5 Binding wire 250 M 65.00 16,250.00
6 100mm^2 overhead Alluminium conductor 10,640 M 250.00 2,660,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 17 points 5,000.00 85,000.00
8 Bimetal linetap 12 Nos 600.00 7,200.00
9 Allow for nuts, washer, bolts etc. Lots Sum 50,000.00

Sub-Total 4,251,450.00

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,300,000.00
B Exceptional Provision 4,722,200.00
C Transformer Sub Station 7,469,100.00
D High Tension Materials 36,940,450.00
E Low Tension Materials 4,251,450.00
F Test Certification & Commissioning 400,000.00

Sub-Total 55,083,200.00

1 Overhead Charge (25%) 13,770,800.00


2 Contingency (5%) 550,832.00
4 TOTAL COST 69,404,832.00
VAT (5%) 3,470,241.60
INSTALLATION COST 72,875,073.60

GRAND TOTAL FOR INSTALLATION 72,875,073.60

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

GWASORO VIA GWANE, BARUTEN LGA.

DATE: 11TH JUNE, 2012.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
& soft copies (A3) Bill of Engineering
i Measurement & Evaluation Lot Sum 350,000.00
Allo w for m aintenance /fuelling of project
vehicle th rougho ut the perio d of the
ii project Lot Sum 800,000.00
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer Lot Sum 350,000.00
Sub-Total (Ai+Aii+Aiii) 1,500,000.00

B EXCEPTIONAL PROVISION

Allo w for clear ing of thick forest along


1 network r oute 21000 M 200.00 4,200,000.00
Allo w for bottom beam ing of HT / LT
poles in rocky terr ain usin g 600 x 600 x
2 1200m m high 338 No 3,600.00 1,216,800.00
Allo w for lo ng distance tran spo rtation of
3 men & mater ials 250 Km 500.00 125,000.00

Sub-Total 5,541,800.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

C Transformer Sub Station

1 500KVA, 33/0.415KV Transformer 1 No. 6,950,000.00 6,950,000.00


2 33KV Gang Isolator (Silicon type) 1 No. 150,000.00 150,000.00
33KV Lighting Ar restor Comp lete (Silicon
3 type) 1 No. 140,000.00 140,000.00
33KV Expu lsion J&P fuse complete
4 (Silicon type) 1 No. 105,000.00 105,000.00
4-way 600A, TP&N F eeder Pillar com pl
5 with HRC fuse 1 set 100,000.00 100,000.00
Cab le Lugs,B olts and Nuts,Linetap,
6 Caloric Tape Lot Sum 30,000.00
7 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
8 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
9 Allow for treament of earth pit Lot Sum 5,000.00
10 Raychem kits complete 2 set 20,000.00 40,000.00
11 9ft Angle Channel 4 No. 4,000.00 16,000.00
33KV pin In sulator &pilot spindle
12 co mplete (Silico n type) 3 set 7,700.00 23,100.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
13 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
14 block,wire,insu lato r,clam p 4 No. 5,000.00 20,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
15 xm er comp lete 45 M 2,000.00 90,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
16 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
17 cable 30 M 15,000.00 450,000.00
4 by 150mm ^2 pvc/swa/pvcu g Nig er chin
18 cable fo r 500KVA 45 M 12,000.00 540,000.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 8,989,100.00

D H.T. NETWORK

1 10.3m HT concrete poles 340 No 25,000.00 8,500,000.00


2 Danger Plate with anti-climbing wire 340 No 5,500.00 1,870,000.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 200 No 5,000.00 1,000,000.00
4 33KV Pilot Spindle 1014 No 600.00 608,400.00
5 33KV Pin insulator (Silicon type) 1014 No 5,950.00 6,033,300.00
6 cross arm tie strap 600 M 800.00 480,000.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 300 NO 4,800.00 1,440,000.00
9 Sectional Steel 9" 76 No 5,500.00 418,000.00
10 33KV Disc Insulator (Silicon type) 702 No 6,300.00 4,422,600.00
11 150mm^2 Alluminium Conductor 62,790 m 300.00 18,837,000.00
12 Earthing of X-Arms on poles 300 Points 5,500.00 1,650,000.00
13 Nuts and Bolts (various sizes) Lots sum 100,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 39 Set 1,900.00 74,100.00

Sub-Total 45,483,400.00

E L.T. NETWORK

1 8.3m concrete low tension pole 92 Nos 23,000.00 2,116,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 46 Nos 5,000.00 230,000.00
3 D Iron complete with spindle 368 Nos 370.00 136,160.00
4 Shackle Insulator (Silicon type) 368 Nos 420.00 154,560.00
5 Binding wire 460 M 65.00 29,900.00
6 100mm^2 overhead Alluminium conductor 24,640 M 250.00 6,160,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 30 points 5,000.00 150,000.00
8 Bimetal linetap 12 Nos 600.00 7,200.00
9 Allow for nuts, washer, bolts etc. Lots Sum 50,000.00

Sub-Total 9,033,820.00

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,500,000.00
B Exceptional Provision 5,541,800.00
C Transformer Sub Station 8,989,100.00
D High Tension Materials 45,483,400.00
E Low Tension Materials 9,033,820.00
F Test Certification & Commissioning 400,000.00

Sub-Total 70,948,120.00

1 Overhead Charge (25%) 17,737,030.00


2 Contingency (5%) 709,481.20
4 TOTAL COST 89,394,631.20
VAT (5%) 4,469,731.56
INSTALLATION COST 93,864,362.76

GRAND TOTAL FOR INSTALLATION 93,864,362.76

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

BABANE VIA BODE, BARUTEN LGA.

DATE: 11TH JUNE, 2012.


Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
& soft copies (A3) Bill of Engineering
i Measurement & Evaluation Lot Sum 350,000.00
Allo w for m aintenance /fuelling of project
vehicle th rougho ut the perio d of the
ii project Lot Sum 600,000.00
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer Lot Sum 400,000.00
Sub-Total (Ai+Aii+Aiii) 1,350,000.00

B EXCEPTIONAL PROVISION

Allo w for clear ing of thick forest along


1 network r oute 14600 M 200.00 2,920,000.00
Allo w for bottom beam ing of HT / LT
poles in rocky terr ain usin g 600 x 600 x
2 1200m m high 311 No 3,600.00 1,119,600.00
Allo w for lo ng distance tran spo rtation of
3 men & mater ials 250 Km 500.00 125,000.00

Sub-Total 4,164,600.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=

C Transformer Sub Station

1 300KVA, 33/0.415KV Transformer 1 No. 5,450,000.00 5,450,000.00


2 33KV Gang Isolator (Silicon type) 1 No. 150,000.00 150,000.00
33KV Lighting Ar restor Comp lete (Silicon
3 type) 1 No. 140,000.00 140,000.00
33KV Expu lsion J&P fuse complete
4 (Silicon type) 1 No. 105,000.00 105,000.00
4-way 400A, TP&N F eeder Pillar com pl
5 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
6 Caloric Tape Lot Sum 30,000.00
7 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
8 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
9 Allow for treament of earth pit Lot Sum 5,000.00
10 Raychem kits complete 2 set 20,000.00 40,000.00
11 9ft Angle Channel 4 No. 4,000.00 16,000.00
33KV pin In sulator &pilot spindle
12 co mplete (Silico n type) 3 set 7,700.00 23,100.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
13 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
14 block,wire,insu lato r,clam p 4 No. 5,000.00 20,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
15 xm er comp lete 45 M 2,000.00 90,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
16 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
17 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
18 cable fo r 300KVA or 200KVA 45 M 10,000.00 450,000.00
Feeder pillar plinth 225m m ab ove n ormal
19 groun d. Lot Sum 25,000.00

Sub-Total 7,379,100.00
D H.T. NETWORK

1 10.3m HT concrete poles 237 No 25,000.00 5,925,000.00


2 Danger Plate with anti-climbing wire 237 No 5,500.00 1,303,500.00
HT Stay com plete with wire rod ,
3 block,in sulator bracket 119 No 5,000.00 595,000.00
4 33KV Pilot Spindle 705 No 600.00 423,000.00
5 33KV Pin insulator (Silicon type) 705 No 5,950.00 4,194,750.00
6 cross arm tie strap 418 M 800.00 334,400.00
7 U-Channel Iron 9" 10 No. 5,000.00 50,000.00
8 Steel X-Arm 209 NO 4,800.00 1,003,200.00
9 Sectional Steel 9" 52 No 5,500.00 286,000.00
10 33KV Disc Insulator (Silicon type) 486 No 6,300.00 3,061,800.00
11 150mm^2 Alluminium Conductor 43,680 m 300.00 13,104,000.00
12 Earthing of X-Arms on poles 209 Points 5,500.00 1,149,500.00
13 Nuts and Bolts (various sizes) Lots sum 100,000.00
Six bolt clam p, j-hook,socket tongu e,
14 tensio n clamp 27 Set 1,900.00 51,300.00

Sub-Total 31,581,450.00

E L.T. NETWORK

1 8.3m concrete low tension pole 74 Nos 23,000.00 1,702,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 37 Nos 5,000.00 185,000.00
3 D Iron complete with spindle 296 Nos 370.00 109,520.00
4 Shackle Insulator (Silicon type) 296 Nos 420.00 124,320.00
5 Binding wire 370 M 65.00 24,050.00
6 100mm^2 overhead Alluminium conductor 14,880 M 250.00 3,720,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 25 points 5,000.00 125,000.00
8 Bimetal linetap 12 Nos 600.00 7,200.00
9 Allow for nuts, washer, bolts etc. Lots Sum 50,000.00

Sub-Total 6,047,090.00

F Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 1,350,000.00
B Exceptional Provision 4,164,600.00
C Transformer Sub Station 7,379,100.00
D High Tension Materials 31,581,450.00
E Low Tension Materials 6,047,090.00
F Test Certification & Commissioning 400,000.00

Sub-Total 50,922,240.00

1 Overhead Charge (25%) 12,730,560.00


2 Contingency (5%) 509,222.40
4 TOTAL COST 64,162,022.40
VAT (5%) 3,208,101.12
INSTALLATION COST 67,370,123.52

GRAND TOTAL FOR INSTALLATION 67,370,123.52

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

MUHAMMAD KAMAL-DEEN UNIVERSITY (PROPOSED), OGIDI ILORIN AREA, ILORIN WEST LGA

DATE:26/10/2016

Sr. No. Description of Items Qty Unit Price Total Price


=N= =N=
A Preliminaries
Production of all lithographical work
such as detailed working drawing in
hard & soft copies(A3) Bill of
Engineeering Measurement &
i Evaluation Lot Sum 134,000.00
Allow for maintenance / fuelling of
project vehicle throughout the
ii period of the project Lot Sum 200,000.00
Provision of Pre-installation
inspection,post installation test of
the project by the supervising
iii Engineer Lot Sum 150,000.00
Sub-Total (Ai+Aii+Aiii) 484,000.00

B Transformer Sub Station

1 500KVA, 11/0.415KV Transformer 1 No. ### 4,450,000.00


2 11KV Gang Isolator (silicon type) 1 No. ### 130,000.00
11KV Lighting Arrestor Complete
3 (silicon type) 1 No. ### 122,500.00
11KV Expulsion j&p fuse complete
4 (silicon type) 1 No. 87,500.00 87,500.00
4-way 600A, TP&N Feeder Pillar
5 compl with HRC fuse 1 set 90,000.00 90,000.00
Cable Lugs,Bolts and Nuts,Linetap,
6 Caloric Tape Lot Sum 30,000.00
7 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 Allow for treatment of earth pit Lot Sum 5,000.00
8 Raychem kits complete 2 set 20,000.00 40,000.00
9 9ft Angle Channel 4 No. 4,000.00 16,000.00
11KV silicon pin Insulator&pilot
10 spindle complete 3 set 7,000.00 21,000.00
Transfo Plinth made with
11 concrete,granite chiping Lot Sum 50,000.00
High tention stay complete,
12 block,wire,insulator,clamp 4 No. 5,000.00 20,000.00
1 by 35mm^2 by Xlpe cable from d
13 fuse to xmer complete 30 M 2,000.00 60,000.00
4 by 150mm^2 pvc/swa/pvcug
14 Nigerchin cable for 500KVA 30 M 12,000.00 360,000.00
300mm^2 X 1 pvcl/swa/pvcug
15 Nigerchin cable 30 M 15,000.00 450,000.00
Fencing of xmer substation with
dwarf wall using sand crete block of
150by 225 by 450mm^2 provided
iron gate,spraed 1/2 inch granite
16 stone Lot Sum 150,000.00
17 1x35mm bare copper conductor 100 M 450.00 45,000.00
Feeder pillar plinth 225mm above
18 normal ground. Lot 25,000.00
Sub-Total 6,212,000.00

C H.T. NETWORK

1 HT concrete poles 5 No 25,000.00 125,000.00


2 Danger Plate with anti-climbing wire 2 No 5,500.00 11,000.00
HT Stay complete with wire rod,
3 block,insulator bracket 2 No 5,000.00 10,000.00
4 11KV Pilot Spindle 15 No 600.00 9,000.00
5 11KV Pin insulator (silicon type) 15 No 4,200.00 63,000.00
6 cross arm tie strap 6 M 800.00 4,800.00
7 U-Channel Iron 9" 4 No. 5,000.00 20,000.00
8 Steel X-Arm 3 NO 4,800.00 14,400.00
9 Sectional Steel 9" - No 5,500.00 -
10 11KV Disc Insulator (silicon type) 6 No 5,250.00 31,500.00
11 150mm^2 Alluminium Conductor 600 m 300.00 180,000.00
12 Earthing of X-Arms on poles 1 Points 5,500.00 5,500.00
13 Nuts and Bolts (various sizes) Lots sum 2,000.00
Six bolt clamp, j-hook,socket
14 tongue, tension clamp 1 Set 1,900.00 1,900.00
Sub-Total 478,100.00

D Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
Electricity Management Services
3 Fees Lots 200,000.00
Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 484,000.00
B Transformer Sub Station 6,212,000.00
C High Tension Materials 478,100.00
E Test Certification & Commissioning 400,000.00
Sub-Total 7,574,100.00

1 Overhead Charge (25%) 1,893,525.00


2 Contingency (5%) 378,705.00
3 TOTAL COST 9,846,330.00
4 VAT (5%) 492,316.50
TOTAL FOR INSTALLATION ###

PREPARED BY S.A.ASUNKERE CHECKED BY MURTALA S. YUSUF

AGBAKU/ELEPO & AWUYAN/AGBA, MORO LGA.


DATE: 20TH DECEMBER, 2016.
Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
A PRELIMINARIES
Pr oduction of all th e lithog rap hical work
su ch as d etailed wor king dr awing in hard
& soft copies (A3) Bill of Engineering
i Measurement & Evaluation Lot Sum 250,000.00
Allo w for m aintenance /fuelling of project
vehicle th rougho ut the perio d of the
ii project Lot Sum 313,000.00
Pr ovision o f Pr e-in stallation inspection,
post installation test of the p roject by the
iii su per vising Engineer Lot Sum 250,000.00
Sub-Total (Ai+Aii+Aiii) 813,000.00

Sr. No. Description of Items Qty Unit Price Total Price

=N= =N=
Tr ansform er Sub Station: (AWUYAN &
B (i) AGBA VILLAGE)- REPLACEMEN T
1 200KVA, 33/0.415KV Transformer 1 No. 3,950,000.00 3,950,000.00
Tr ansform er Sub Station: (AGBAKU &
(ii) ELEPO VILLAGE)- PROPOSED
1 200KVA, 33/0.415KV Transformer 1 No. 3,950,000.00 3,950,000.00
33KV Lighting Ar restor Comp lete (Silicon
2 type) 1 No. 140,000.00 140,000.00
33KV Expu lsion J&P fuse complete
3 (Silicon type) 1 No. 105,000.00 105,000.00
4-way 400A, TP&N F eeder Pillar com pl
4 with HRC fuse 1 set 80,000.00 80,000.00
Cab le Lugs,B olts and Nuts,Linetap,
5 Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 1X35mm^2 bare copper for thick earth rod 100 m 450.00 45,000.00
8 Allow for treament of earth pit Lot Sum 5,000.00
9 Raychem kits complete 2 set 20,000.00 40,000.00
10 9ft Angle Channel 4 No. 4,000.00 16,000.00
33KV pin In sulator &pilot spindle
11 co mplete (Silico n type) 3 set 7,700.00 23,100.00
Tr ansfo Plinth m ad e with co ncr ete,gr anite
12 ch ipin g Lot Sum 50,000.00
High tensio n stay com plete,
13 block,wire,insu lato r,clam p 2 No. 5,000.00 10,000.00
1 by 35m m^2 by Xlpe cable from d fuse to
14 xm er comp lete 30 M 2,000.00 60,000.00
Fencing o f xm er substatio n with dwarf
wall.the fen ce should be 600mm of b lock
wor k ab ove g round level an d 600m m o f
iron Mongany and Iron Gate not less than
15 2.4m x 2.4m width and graveled Lot Sum 150,000.00
1 by 300mm ^2 pvc/swa/pvcu g Nig er chin
16 cable 30 M 15,000.00 450,000.00
4 by 95m m^2 pvc/swa/pvcug Nigerchin
17 cable fo r 200KVA 30 M 10,000.00 300,000.00
Feeder pillar plinth 225m m ab ove n ormal
18 groun d. Lot Sum 25,000.00

Sub-Total 9,489,100.00

C H.T. NETWORK: AGBAKU VILLAGE

1 10.3m HT concrete poles 2 No 25,000.00 AVAILABLE


2 Danger Plate with anti-climbing wire 2 No 5,500.00 11,000.00

Sub-Total 11,000.00

D L.T. NETWORK: (ELEPO VILLAGE)

1 8.3m concrete low tension pole 25 Nos 23,000.00 575,000.00


LT Stay complete with wire r od, block,
2 insulator bracket thim ble etc 13 Nos 5,000.00 65,000.00
3 D Iron complete with spindle 100 Nos 370.00 37,000.00
4 Shackle Insulator (Silicon type) 100 Nos 420.00 42,000.00
5 Binding wire 125 M 65.00 8,125.00
6 100mm^2 overhead Alluminium conductor 5,000 M 250.00 1,250,000.00
Earthing of ang les & ter min al poles (to
7 includ e cable & galvan ized r od) 3 points 5,000.00 15,000.00
8 Bimetal linetap 8 Nos 600.00 4,800.00
9 Allow for nuts, washer, bolts etc. Lots Sum 10,000.00

Sub-Total 2,006,925.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 Power & Steel Statutory Fees Lots 200,000.00

Sub-Total 400,000.00

SUMMARY OF BQ
Nos. Items Cost
N
A Preliminaries 813,000.00
B Transformer Sub Station 9,489,100.00
C High Tension Materials 11,000.00
D Low Tension Materials 2,006,925.00
E Test Certification & Commissioning 400,000.00

Sub-Total 12,720,025.00

1 Overhead Charge (25%) 3,180,006.25


2 Contingency (5%) 636,001.25
3 TOTAL COST 16,536,032.50
VAT (5%) 826,801.63
INSTALLATION COST 17,362,834.13

GRAND TOTAL FOR INSTALLATION 17,362,834.13

PREPARED BY: MURTALA S. YUSUF CHECKED BY: ENGR. A. A. ALAGO

KWARA STATE GOVERNMENT


MINISTRY OF ENERGY
P.M.B 1574, ILORIN, KWARA STATE
PROPOSED: INSTALLATION OF TRANSFORMER TO IFESOWAPO BUKOYE AVENUE COMMUNITY
SN DESCRIPTION OF ITEM/WORK QTY UNIT PRICE (N) AMOUNT (N)
(A) PRILIMINARIES
Prod uction o f all lit hogr aph oca l wor k such a s
detaile d wo rking dra wing in har d & so ft co pies
1 (A3) Bill o f Engin eer ing Me arsur men t &
Eva lu ation. 70,000.00
2 Allow f or mainte nance / fu elling of pr oject veh icle
thr ough out the per iod of the pr oject. 100,000.00
Pro vision of p re- inst allation inspection , po st
3 installatio n te st of the pro ject by t he supr visin g
Enginee r. 40,000.00
SUB-TOTAL (A) 210,000.00
(B) TRANSFORMER SUBSTATION
1 500KVA, 11/ O.415KV 1 No 4,450,000.00 4,450,000.00
2 11KV Silicon Gang Isolator 1 No. 150,000.00 150,000.00
3 11KV Silicon Lighting Arrestor Complete 1 SET 140,000.00 140,000.00
4 11KV Silicon Expulsion j&p fuse complete 1 SET 105,000.00 105,000.00
4- way 40 0A, T P&N F eede r Pilla r com plete with
1 No.
5 HRC fu se 80,000.00 80,000.00
6 Cable Lugs,Bolts and Nuts, Linetap, Caloric Tape Lot Sum 30,000.00
7 8ft galvanised earth rod(thick) 24 No. 2,500.00 60,000.00
7 Allow for treament of earth pit Sum 5,000.00 5,000.00
8 Raychem kits complete 2 Set 20,000.00 40,000.00
9 9ft Angle Channel 4 No. 4,000.00 16,000.00
10 11KV Silicon pin Insulator & pilot spindle complete 3 No 7,700.00 23,100.00
Sum
11 Transformer Plinth made with concrete,granite chiping 50,000.00 50,000.00
4 No.
12 High tention stay complete, block,wire,insulator,clamp 5,000.00 20,000.00
Fen cin g of tr ansfor mer subst ation with dwar f wall
using sand cre te b lo ck of 15 0by 22 5 by 45 0mm^ 2 Sum
13 pr ovid ed ir on gate, spra ed 1/ 2 inch gra nite st one 150,000.00 150,000.00
14 1 by 35mm2 bare copper 100 M 500.00 50,000.00
1 by 3 5mm^ 2 by Xlp e cable fr om D fuse t o
15 30 M 2,000.00 60,000.00
tr ansfor mer comple te
16 1 by 300mm^2 pvc/swa/pvcug Nigerchin cable 45 M 15,000.00 675,000.00
4 by 9 5mm^ 2 pvc/swa /pvcug N iger ch in cable for
45 M
18 500KVA 10,000.00 450,000.00
19 Feeder pillar plinth 225mm above normal ground. Sum 25,000.00 25,000.00
SUB-TOTAL (B) 6,579,100.00
C H.T. NETWORK
1 HT concrete poles 10 No 25,000.00 250,000.00
2 Danger Plate with anti-climbing wire 6 No 5,500.00 33,000.00
No
3 HT Stay complete with wire rod, block,insulator bracket 12 5,000.00 60,000.00
4 11KV Pilot Spindle 30 No 800.00 24,000.00
5 33KV Silicon Pin insulator 30 M 5,970.00 179,100.00
6 cross arm tie strap 20 No. 800.00 16,000.00
7 U-Channel Iron 9" 4 NO 5,500.00 22,000.00
8 Steel X-Arm 10 No 4,800.00 48,000.00
9 Sectional Steel 9" 4 No 5,500.00 22,000.00
10 11KV Disc Insulator 30 No 1,800.00 54,000.00
11 150mm Alluminium Conductor 2,100 M 300.00 630,000.00
12 Earthing of Sectional Poles & X-Arms 3 Points 5,500.00 16,500.00
13 Nuts and Bolts (various sizes) Sum 10,000.00 20,000.00
14 Six bolt clamp, j-hook,socket tongue, tension clamp 3 Set 1,900.00 5,700.00
SUB-TOTAL (C) 1,380,300.00

E Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 NEMSA Lots 200,000.00
SUB-TOTAL (E) 400,000.00

SUMMARY OF BQ
ELEMENTS
A PRILIMINARIES 210,000.00
B TRANSFORMER SUBSTATION 6,579,100.00
C HIGH TENSION MATERIALS 1,380,300.00
E TESTING & COMMISSIONING 400,000.00
SUB-TOTAL (A+B+C) 8,569,400.00

CHARGES/DEDUCTIONS
i OVER HEAD CHARGE (30%) 2,570,820.00
ii CONTIGENCY (5%) 428,470.00
TOTAL 11,568,690.00
iii VAT (5%) 578,434.50
GRAND TOTAL 12,147,124.50

PREPARED BY …UMAR ABDULHAMID.............................. CHECKED BY …ENGR IDRIS DABARAKO.....................................

APPROVED BY.....ENGR A Y AHMADU............................. DATE APPROVED..................................

CD/EE

KWARA STATE GOVERNMENT


MINISTRY OF ENERGY
P.M.B 1574, ILORIN, KWARA STATE
PROPOSED: REPLACEM ENT OF BURNT T RANFORMER AT SA LVATI ON COMM UNI TY DE VE LOPME NT ASSOCIATION,
STADI UM ROA D, ILORIN WEST L.G .A.
SN DESCRIPTION OF ITEM/WORK QTY UNIT PRICE (N) AMOUNT (N)
(A) PRILIMINARIES
Prod uction o f all lit hogr aph oca l wor k such a s
detaile d wo rking dra wing in har d & so ft co pies
1 (A3) Bill o f Engin eer ing Me arsur men t &
Eva lu ation. 100,000.00
2 Allow f or mainte nance / fu elling of pr oject veh icle
thr ough out the per iod of the pr oject. 150,000.00
Pro vision of p re- inst allation inspection , po st
3 installatio n te st of the pro ject by t he supr visin g
Enginee r. 122,000.00
SUB-TOTAL (A) 372,000.00
(B) TRANSFORMER SUBSTATION
1 500KVA, 11/ 0.415KV 1 No 4,450,000.00 4,450,000.00
2 11KV Silicon Lighting Arrestor Complete 1 SET 140,000.00 140,000.00
3 11KV Silicon Expulsion j&p fuse complete 1 SET 105,000.00 105,000.00
4- way 60 0A, T P&N F eede r Pilla r com plete with 1 No.
4 HRC fu se 80,000.00 80,000.00
5 Cable Lugs,Bolts and Nuts, Linetap, Caloric Tape Lot Sum 30,000.00
6 8ft galvanised earth rod(thick) 12 No. 2,500.00 30,000.00
7 Allow for treament of earth pit Sum 5,000.00 5,000.00
8 Raychem kits complete 2 Set 20,000.00 40,000.00
9 9ft Angle Channel 4 No. 4,000.00 16,000.00
Sum
10 Transformer Plinth made with concrete,granite chiping 50,000.00 50,000.00
11 2 No.
High tention stay complete, block,wire,insulator,clamp 5,000.00 AVAILABLE
Fen cin g of tr ansfor mer subst ation with dwar f wall
using sand cre te b lo ck of 15 0by 22 5 by 45 0mm^ 2 Sum
12 pr ovid ed ir on gate, spra ed 1/ 2 inch gra nite st one 150,000.00 AVAILABLE
13 1 by 35mm2 bare copper 100 M 500.00 50,000.00
1 by 3 5mm^ 2 by Xlp e cable fr om D fuse t o 30 M
14 tr ansfor mer comple te 2,000.00 60,000.00
15 1 by 300mm^2 pvc/swa/pvcug Nigerchin cable 15 M 15,000.00 225,000.00
16 Feeder pillar plinth 225mm above normal ground. Lot Sum 15,000.00
SUB-TOTAL (B) 5,296,000.00

C L.T. NETWORK:

1 D Iron complete with spindle 24 Nos 370.00 8,880.00


2 Shackle Insulator (Silicon type) 24 Nos 420.00 10,080.00
3 Binding wire 30 M 65.00 1,950.00
4 100mm^2 overhead Alluminium conductor 640 M 250.00 160,000.00
5 Bimetal linetap 12 Nos 600.00 7,200.00
6 Allow for nuts, washer, bolts etc. Lots Sum 10,000.00
SUB-TOTAL (C) 198,110.00

D Test Certification & Commissioning


1 IBEDC Logistics Lots 100,000.00
2 IBEDC Headquarters Charges Lots 100,000.00
3 NEMSA Lots 200,000.00
SUB-TOTAL (D) 400,000.00

SUMMARY OF BQ
ELEMENTS
A PRILIMINARIES 372,000.00
B TRANSFORMER SUBSTATION 5,296,000.00
C LOW TENSION MATERIALS 198,110.00
D TESTING & COMMISSIONING 400,000.00
SUB-TOTAL (A+B+C+D) 6,266,110.00

CHARGES/DEDUCTIONS
i OVER HEAD CHARGE (15%) 939,916.50
ii CONTIGENCY (5%) 313,305.50
TOTAL 7,519,332.00
iii VAT (5%) 375,966.60
GRAND TOTAL 7,895,298.60

PREPARED BY …ABDULMALEEK ABDULLAHI.................... ...CHECKED BY …ENGR. MURTALA S. YUSUF...........

APPROVED BY.....ENGR. A. Y. AHMADU........................ DATE APPROVED..................................

CD/EE
KWARA STATE GOVERNMENT
MINISTRY OF ENERGY
P.M.B 1574, ILORIN, KWARA STATE
OKE AGBO, OPPOSITE TEJUMOLA ESTATE, ILOFFA, OKE ERO LGA
SN DESCRIPTION OF ITEM/WORK QTY UNIT PRICE (N)
(A) TRANSFORMER SUBSTATION
1 300KVA, 33/ O.415KV 1 No AVAILABLE
2 33KV Silicon Gang Isolator 1 No. 150,000.00
4-way 400A, TP&N Feeder Pillar complete
1 No.
3 with HRC fuse 100,000.00
Cable Lugs,Bolts and Nuts, Linetap,
Lot Sum
4 Caloric Tape
5 8ft galvanised earth rod(thick) 24 No. 2,500.00
6 Allow for treament of earth pit Sum 5,000.00
7 Raychem kits complete 2 Set 20,000.00
9 1 by 35mm2 bare copper 45 M 500.00
1 by 300mm^2 pvc/swa/pvcug Nigerchin
30 M
11 cable 10,000.00
1 by 35mm^2 by Xlpe cable from D fuse to
30 M
12 4transformer
by 95mm^2complete
pvc/swa/pvcug Nigerchin 2,000.00
13 cable 45 M 10,500.00
Feeder pillar plinth 225mm above normal
Sum
14 ground. 25,000.00
SUB-TOTAL (B)

B L.T NETWORK
1 8.3m concrete low tension pole 10 Nos 25,000.00
LT Stay complete with wire rod, block,
Nos
2 insulator bracket thimble etc 6 7,500.00
3 D Iron complete with spindle 40 Nos 370.00
4 Shackle Insulator 40 Nos 200.00
5 Binding wire 100 M 100.00
6 100mm2 overhead alluminium conductor 2,000 M 400.00
Earthing of angles & terminal poles(to
points
7 include cable & galvanized rod 4 5,000.00
8 Bimetal linetap 10 Nos 600.00
9 Allow for nuts, washer, bolts etc. Sum
SUB-TOTAL (D)

SUMMARY OF BQ
ELEMENTS
A TRANSFORMER SUBSTATION
B LOW TENSION MATERIALS
GRAND TOTAL

PREPARED BY ENGR ODETOKUN A CHECKED BY ENGR DABARAKO I.I.

APPROVED BY DATE APPROVED..................................

KWARA STATE GOVERNMENT


MINISTRY OF ENERGY
P.M.B 1574, ILORIN, KWARA STATE
COMMUNITY SENIOR SECONDARY SCH, OPPOSITE CENTRAL MOSQUE, EGOSI-ILE, OKE ERO LGA
SN DESCRIPTION OF ITEM/WORK QTY UNIT PRICE (N)
(A) TRANSFORMER SUBSTATION
1 300KVA, 33/ O.415KV 1 No AVAILABLE
2 33KV Silicon Gang Isolator 1 No. 150,000.00
4-way 400A, TP&N Feeder Pillar complete
1 No.
3 with HRC fuse 100,000.00
Cable Lugs,Bolts and Nuts, Linetap,
Lot Sum
4 Caloric Tape
5 8ft galvanised earth rod(thick) 24 No. 2,500.00
6 Allow for treament of earth pit Sum 5,000.00
7 Raychem kits complete 2 Set 20,000.00
8 1 by 35mm2 bare copper 45 M 500.00
1 by 300mm^2 pvc/swa/pvcug Nigerchin
30 M
9 cable 10,000.00
1 by 35mm^2 by Xlpe cable from D fuse to
10 30 M 2,000.00
transformer
4 by 95mm^2complete
pvc/swa/pvcug Nigerchin
11 cable 30 M 10,500.00
Feeder pillar plinth 225mm above normal
Sum
12 ground. 25,000.00
SUB-TOTAL

SUMMARY OF BQ
ELEMENTS
A TRANSFORMER SUBSTATION
GRAND TOTAL

PREPARED BY ENGR ODETOKUN A CHECKED BY ENGR DABARAKO I.I.

APPROVED BY DATE APPROVED..................................

KWARA STATE GOVERNMENT


MINISTRY OF ENERGY
P.M.B 1574, ILORIN, KWARA STATE
OBAJI COMPREHENSIVE HIGH SCH, OPPOSITE EKAN MEJE, OKE ERO LGA
SN DESCRIPTION OF ITEM/WORK QTY UNIT PRICE (N)
(A) TRANSFORMER SUBSTATION
1 AVAILABLE BUT
1 No
300KVA, 33/ O.415KV VANDALISED
2 33KV Silicon Gang Isolator 1 No. 150,000.00
Cable Lugs,Bolts and Nuts, Linetap,
Lot Sum
3 Caloric Tape
4 8ft galvanised earth rod(thick) 24 No. 2,500.00
5 Allow for treament of earth pit Sum 5,000.00
6 Raychem kits complete 2 Set 20,000.00
7 1 by 35mm2 bare copper 45 M 500.00
1 by 300mm^2 pvc/swa/pvcug Nigerchin
45 M
8 cable 15,000.00
1 by 35mm^2 by Xlpe cable from D fuse to
9 30 M 2,000.00
4transformer
by 95mm^2complete
pvc/swa/pvcug Nigerchin
10 cable 45 M 10,000.00
SUB-TOTAL (A)
SUMMARY OF BQ
ELEMENTS
A TRANSFORMER SUBSTATION
GRAND TOTAL

PREPARED BY ENGR ODETOKUN A CHECKED BY ENGR DABARAKO I.I.

APPROVED BY DATE APPROVED..................................

KWARA STATE GOVERNMENT


MINISTRY OF ENERGY
P.M.B 1574, ILORIN, KWARA STATE
ISALE ILALA, ILALA, IREPODUN LGA
SN DESCRIPTION OF ITEM/WORK QTY UNIT PRICE (N)
(A) TRANSFORMER SUBSTATION
AVAILABLE
300/33 TO BE
1 1 No
REPLACED
300KVA, 11/ O.415KV WITH 300/11
2 11KV Silicon Gang Isolator 1 No. 150,000.00
3 11KV Silicon Lighting Arrestor Complete 1 SET 140,000.00
4 11KV Silicon Expulsion j&p fuse complete 1 SET 105,000.00
4-way 400A, TP&N Feeder Pillar complete
1 No.
5 with HRC fuse 100,000.00
Cable Lugs,Bolts and Nuts, Linetap,
Lot Sum
6 Caloric Tape
7 8ft galvanised earth rod(thick) 24 No. 2,500.00
8 Allow for treament of earth pit Sum 5,000.00
9 Raychem kits complete 2 Set 20,000.00
10 9ft Angle Channel 4 No. 4,000.00
11KV Silicon pin Insulator & pilot spindle
3 No
11 complete 7,700.00
High tention stay complete,
4 No.
11 block,wire,insulator,clamp 5,000.00
Fencing of transformer substation with
dwarf wall using sand crete block of 150by
Sum
225 by 450mm^2 provided iron gate,spraed
12 1/2 inch granite stone 150,000.00
13 1 by 35mm2 bare copper 45 M 500.00
1 by 35mm^2 by Xlpe cable from D fuse to
30 M
14 transformer complete 2,000.00
1 by 300mm^2 pvc/swa/pvcug Nigerchin
30 M
15 cable
4 by 95mm^2 pvc/swa/pvcug Nigerchin 10,000.00
16 cable 30 M 10,500.00
Feeder pillar plinth 225mm above normal
Sum
17 ground. 25,000.00
SUB-TOTAL

SUMMARY OF BQ
ELEMENTS
A TRANSFORMER SUBSTATION
GRAND TOTAL

PREPARED BY ENGR. ODETOKUN A. CHECKED BY ENGR DABARAKO I.I.


APPROVED BY DATE APPROVED..................................
KE ERO LGA
AMOUNT (N)

150,000.00

100,000.00

30,000.00
60,000.00
5,000.00
40,000.00
22,500.00

300,000.00

60,000.00
472,500.00

25,000.00
1,265,000.00

250,000.00

45,000.00
14,800.00
8,000.00
10,000.00
800,000.00

20,000.00
6,000.00
10,000.00
1,163,800.00

1,265,000.00
1,163,800.00
2,428,800.00

BY ENGR DABARAKO I.I.

VED..................................
E, EGOSI-ILE, OKE ERO LGA
AMOUNT (N)

150,000.00

100,000.00

30,000.00
60,000.00
5,000.00
40,000.00
22,500.00

300,000.00
60,000.00
315,000.00

25,000.00
1,107,500.00

1,107,500.00
1,107,500.00

BY ENGR DABARAKO I.I.

VED..................................

E, OKE ERO LGA


AMOUNT (N)

150,000.00

30,000.00
60,000.00
5,000.00
40,000.00
22,500.00

675,000.00
60,000.00
450,000.00
1,492,500.00
1,492,500.00
1,492,500.00

BY ENGR DABARAKO I.I.

VED..................................

AMOUNT (N)

150,000.00
140,000.00
105,000.00

100,000.00

30,000.00
60,000.00
5,000.00
40,000.00
16,000.00

23,100.00

20,000.00

150,000.00
22,500.00

60,000.00

300,000.00
315,000.00

25,000.00
1,561,600.00

1,561,600.00
1,561,600.00

BY ENGR DABARAKO I.I.


VED..................................

Вам также может понравиться