DETAIL AKTIVITAS ENGINEERIN

Penanggung jawab : Totok Harianto


Bagian : Maintenance Utility
Periode aktivitas : Juni - Nov 2019

No Deskripsi Detail Aktifitas OUTPUT PIC Status Due date Schedule Jun
1 2 3
Project kelengkapan power 1-Jul-19 Plan
Power supply &
1 supply dan compressor mesin Totok H on progress
compressor Actual
Geo 2
Project kelengkapan power 1-Jul-19 Plan
Power supply &
2 supply dan compressor mesin Totok H on progress
compressor Actual
Woven

Rekondisi panel instrumen Instrumen panel 1-Jul-19 Plan


3 Totok H on progress
chiller 4 & 5 ged C & N19, N20 baru chiller Actual

Persiapan cooling system Cooling system 31-Jul-19 Plan


4 Totok H on progress
woven baru woven Actual

Persiapan cooling system Geo Cooling system 31-Jul-19 Plan


5 Totok H on progress
2 baru Geo2 Actual

Pendingin chiller 12-Jul-19 Plan


6 Overhoul Chiller C05 Totok H on progress
C05 ready produksi Actual

Kompressor ready 25-Oct-19 Plan


7 Overhoul comproses kaeser 01 Totok H on progress
produksi Actual

Kompressor ready 22-Nov-19 Plan


8 Overhoul comproses kaeser 02 Totok H on progress
produksi
Kompressor ready
8 Overhoul comproses kaeser 02 Totok H on progress
produksi Actual

Kompressor ready 15-Nov-19 Plan


9 Overhoul comproses kaeser 03 Totok H on progress
produksi Actual

Pendingin chiller 30-Nov-19 Plan


10 Overhoul Chiller N20 Totok H on progress
N20 ready produksi Actual

Pendingin chiller 15-Aug-19 Plan


11 Rekondisi chiller N19 Totok H on progress
N19 ready produksi Actual

Pendingin chiller 31-Aug-19 Plan


12 Overhoul Chiller C04 Totok H on progress
C04 ready produksi Actual

Kompressor ready 15-Sep-19 Plan


13 Overhoul Kompressor sullair 02 Totok H on progress
produksi Actual
Kontrol & cheklist semua
kondisi utility (chiller, kondisi utility ready continue Plan
14 Totok H On Time
kompressor, listrik) dalam untuk produksi continue Actual
kontrol harian
KPI

Penanggung Jawab : Mengetahui,

Totok Harianto Eko Prayitno


Maintenance Utility Engineering SPV
TAS ENGINEERING TEAM

Tahun : 2019
Jun Jul Aug Sep Oct Nov Keterangan
4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Mengetahui,

Andy Mustofah
Engineering Manager
DETAIL AKTIVITAS ENGINEERING
Penanggung jawab : Agus Efendi
Bagian : Maintenance Utility
Periode aktivitas : Juni - Nov 2019

No Deskripsi Detail Aktifitas OUTPUT PIC Status Due date Schedule Jun
1 2 3 4
Project kelengkapan power 1-Jul-19 Plan
Power supply &
1 supply dan compressor mesin Agus E on progress
compressor Actual
Geo 2
Project kelengkapan power 1-Jul-19 Plan
Power supply &
2 supply dan compressor mesin Agus E on progress
compressor Actual
Woven

Rekondisi panel instrumen Instrumen panel 1-Jul-19 Plan


3 Agus E on progress
chiller 4 & 5 ged C & N19, N20 baru chiller Actual

Persiapan cooling system Cooling system baru 31-Jul-19 Plan


4 Agus E on progress
woven woven Actual

Persiapan cooling system Geo Cooling system baru 31-Jul-19 Plan


5 Agus E on progress
2 Geo2 Actual

Pendingin chiller 12-Jul-19 Plan


6 Overhoul Chiller C05 Agus E on progress
C05 ready produksi Actual

Kompressor ready 25-Oct-19 Plan


7 Overhoul comproses kaeser 01 Agus E on progress
produksi Actual

Kompressor ready 22-Nov-19 Plan


8 Overhoul comproses kaeser 02 Agus E on progress
produksi
Kompressor ready
8 Overhoul comproses kaeser 02 Agus E on progress
produksi Actual

Kompressor ready 15-Nov-19 Plan


9 Overhoul comproses kaeser 03 on progress
produksi Actual

Pendingin chiller 30-Nov-19 Plan


10 Overhoul Chiller N20 on progress
N20 ready produksi Actual

Pendingin chiller 15-Aug-19 Plan


11 Rekondisi chiller N19 on progress
N19 ready produksi Actual

Pendingin chiller 31-Aug-19 Plan


12 Overhoul Chiller C04 on progress
C04 ready produksi Actual

Kompressor ready 15-Sep-19 Plan


13 Overhoul Kompressor sullair 02 on progress
produksi Actual
Kontrol & cheklist semua
kondisi utility (chiller, kondisi utility ready continue Plan
14 On Time
kompressor, listrik) dalam untuk produksi continue Actual
kontrol harian
KPI

Penanggung Jawab : Mengetahui,

Agus Efendi Eko Prayitno


Maintenance Utility Engineering SPV
VITAS ENGINEERING TEAM

Tahun : 2019
Jul Aug Sep Oct Nov Keterangan
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Mengetahui,

Andy Mustofah
Engineering Manager
DETAIL AKTIVITAS ENGINEERING T
Penanggung jawab : Iman Santoso
Bagian : Maintenance Preventive
Periode aktivitas : Juni - Nov 2019

No Deskripsi Detail Aktifitas OUTPUT PIC Status Due date Schedule Jun Jul
1 2 3 4 1 2 3

Mesin ready 14-Jun-19 Plan


1 Overhoul NP04 Iman S on progress
produksi Actual

Mesin ready 28-Jun-19 Plan


2 Overhoul AB2 Iman S on progress
produksi Actual

Mesin ready 12-Jul-19 Plan


3 Rekondisi panel winder N21 Iman S on progress
produksi Actual

Mesin ready 30-Jul-19 Plan


4 Rekondisi panel winder N22 Iman S on progress
produksi Actual

Mesin ready 23-Aug-19 Plan


5 Overhoul DBST-01 Iman S on progress
produksi Actual

Mesin ready 30-Sep-19 Plan


6 Overhoul slitter F01 Iman S on progress
produksi Actual

Mesin ready 15-Sep-19 Plan


7 Overhoul QP02 Iman S on progress
produksi Actual

Penggantian clutch brake Penurunan DT SHF 19-Jul-19 Plan


8 Iman S on progress
SHF 4%
Penggantian clutch brake Penurunan DT SHF
8 Iman S on progress
SHF 4% Actual

Mesin ready 18-Oct-19 Plan


9 Rekondisi panel winder C01 Iman S on progress
produksi Actual

Mesin ready 30-Oct-19 Plan


10 Rekondisi panel winder C02 Iman S on progress
produksi Actual

Mesin ready 18-Nov-19 Plan


11 Rekondisi panel winder C03 Iman S on progress
produksi Actual

Cheklist & monitoring kondisi update kondisi continue Plan


12 Iman S On Time
elektrikal mesin ged C, N, K mesin continue Actual

13

KPI

Penanggung Jawab : Mengetahui,

Iman Santoso Eko Prayitno


Maintenance Preventive Engineering SPV
AS ENGINEERING TEAM

Tahun : 2019
Jul Aug Sep Oct Nov Keterangan
4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Mengetahui,

Andy Mustofah
Engineering Manager
DETAIL AKTIVITAS ENGINEERING
Penanggung jawab : Nur Cholis
Bagian : Maintenance Preventive
Periode aktivitas : Juni - Nov 2019

No Deskripsi Detail Aktifitas OUTPUT PIC Status Due date Schedule Jun
1 2 3 4

Mesin ready 14-Jun-19 Plan


1 Overhoul electrical varia K12 Nur Cholis on progress
produksi Actual

Mesin ready 10-Jun-19 Plan


2 Overhoul electrical KS P05 Nur Cholis on progress
produksi Actual

Mesin ready 28-Jun-19 Plan


3 Overhoul electrical KS P06 Nur Cholis on progress
produksi Actual

Mesin ready 15-Aug-19 Plan


4 Overhoul electrical K08 Nur Cholis on progress
produksi Actual

Mesin ready 30-Aug-19 Plan


5 Overhoul electrical YDN 01 Nur Cholis on progress
produksi Actual

Mesin ready 5-Aug-19 Plan


6 Overhoul eletrical roto NP08 Nur Cholis on progress
produksi Actual

Mesin ready 20-Sep-19 Plan


7 Overhoul electrical C02 Nur Cholis on progress
produksi Actual

Mesin ready 27-Sep-19 Plan


8 Overhoul electrical YDN 02 Nur Cholis on progress
produksi
Mesin ready
8 Overhoul electrical YDN 02 Nur Cholis on progress
produksi Actual

Mesin ready 25-Oct-19 Plan


9 Overhoul electrical N22 Nur Cholis on progress
produksi Actual

Mesin ready 15-Nov-19 Plan


10 Overhoul electrical N20 Nur Cholis on progress
produksi Actual

Cheklist & monitoring kondisi update continue Plan


11 Nur Cholis On Time
elektrikal mesin ged C, N, K kondisi mesin continue Actual

Plan
12 Nur Cholis on progress
Actual

Plan
13 Nur Cholis on progress
Actual

Plan
14 Nur Cholis on progress
Actual

KPI

Penanggung Jawab : Mengetahui,

Nur Cholis Eko Prayitno


Maintenance Preventive Engineering SPV
TAS ENGINEERING TEAM

Tahun : 2019
Jul Aug Sep Oct Nov Keterangan
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Mengetahui,

Andy Mustofah
Engineering Manager
DETAIL AKTIVITAS ENGINEERING T
Penanggung jawab : Mokhamad Sodiq
Bagian : Maintenance Preventive
Periode aktivitas : Juni - Nov 2019

No Deskripsi Detail Aktifitas OUTPUT PIC Status Due date Schedule Jun Jul
1 2 3 4 1 2

Mesin ready 14-Jun-19 Plan


1 Overhoul mekanikal varia K12 M Sodiq on progress
produksi Actual

Mesin ready 10-Jun-19 Plan


2 Overhoul mekanikal KS P05 M Sodiq on progress
produksi Actual

Mesin ready 28-Jun-19 Plan


3 Overhoul mekanikal KS P06 M Sodiq on progress
produksi Actual

Mesin ready 15-Aug-19 Plan


4 Overhoul mekanikal K08 M Sodiq on progress
produksi Actual

Mesin ready 30-Aug-19 Plan


5 Overhoul mekanikal YDN 01 M Sodiq on progress
produksi Actual

Mesin ready 5-Aug-19 Plan


6 Overhoul mekanikal roto NP08 M Sodiq on progress
produksi Actual

Mesin ready 20-Sep-19 Plan


7 Overhoul mekanikal C02 M Sodiq on progress
produksi Actual

Mesin ready 27-Sep-19 Plan


8 Overhoul mekanikal YDN 02 M Sodiq on progress
produksi
Mesin ready
8 Overhoul mekanikal YDN 02 M Sodiq on progress
produksi Actual

Mesin ready 25-Oct-19 Plan


9 Overhoul mekanikal N22 M Sodiq on progress
produksi Actual

Mesin ready 15-Nov-19 Plan


10 Overhoul mekanikal N20 M Sodiq on progress
produksi Actual
Cheklist & monitoring mesin continue Plan
update
11 ekstrusi N20, 21, 22, YDN01,02 M Sodiq On Time
kondisi mesin continue Actual
dan Geomembrane

Mesin ready Plan


12 Overhoul mesin cast K09 M Sodiq on progress
produksi Actual

Mesin ready Plan


13 Overhoul mesin Cast kecil M Sodiq on progress
produksi Actual

Plan
14 on progress
Actual

KPI

Penanggung Jawab : Mengetahui,

Mokhamad Sodiq Eko Prayitno


Maintenance Preventive Engineering SPV
AS ENGINEERING TEAM

Tahun : 2019
Jul Aug Sep Oct Nov Keterangan
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Mengetahui,

Andy Mustofah
Engineering Manager
DETAIL AKTIVITAS ENGINEERING T
Penanggung jawab : Nasimin
Bagian : Maintenance Preventive
Periode aktivitas : Juni - Nov 2019

No Deskripsi Detail Aktifitas OUTPUT PIC Status Due date Schedule Jun Jul
1 2 3 4 1 2

Mesin ready 14-Jun-19 Plan


1 Overhoul mekanikal varia K12 Nasimin on progress
produksi Actual

Mesin ready 10-Jun-19 Plan


2 Overhoul mekanikal KS P05 Nasimin on progress
produksi Actual

Mesin ready 28-Jun-19 Plan


3 Overhoul mekanikal KS P06 Nasimin on progress
produksi Actual

Mesin ready 15-Aug-19 Plan


4 Overhoul mekanikal K08 Nasimin on progress
produksi Actual

Mesin ready 30-Aug-19 Plan


5 Overhoul mekanikal YDN 01 Nasimin on progress
produksi Actual

Mesin ready 5-Aug-19 Plan


6 Overhoul mekanikal roto NP08 Nasimin on progress
produksi Actual

Mesin ready 20-Sep-19 Plan


7 Overhoul mekanikal C02 Nasimin on progress
produksi Actual

Mesin ready 27-Sep-19 Plan


8 Overhoul mekanikal YDN 02 Nasimin on progress
produksi
Mesin ready
8 Overhoul mekanikal YDN 02 Nasimin on progress
produksi Actual

Mesin ready 25-Oct-19 Plan


9 Overhoul mekanikal N22 Nasimin on progress
produksi Actual

Mesin ready 15-Nov-19 Plan


10 Overhoul mekanikal N20 Nasimin on progress
produksi Actual
Cheklist & monitoring mesin continue Plan
update
11 ekstrusi N20, 21, 22, YDN01,02 Nasimin On Time
kondisi mesin continue Actual
dan Geomembrane

Mesin ready Plan


12 Overhoul mesin cast K09 M Sodiq on progress
produksi Actual

Mesin ready Plan


13 Overhoul mesin Cast kecil M Sodiq on progress
produksi Actual

Plan
14 on progress
Actual

KPI

Penanggung Jawab : Mengetahui,

Nasimin Eko Prayitno


Maintenance Preventive Engineering SPV
AS ENGINEERING TEAM

Tahun : 2019
Jul Aug Sep Oct Nov Keterangan
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Mengetahui,

Andy Mustofah
Engineering Manager
DETAIL AKTIVITAS ENGINEERING T
Penanggung jawab : Anasyah Ari Jaka
Bagian : Maintenance Preventive
Periode aktivitas : Juni - Nov 2019

No Deskripsi Detail Aktifitas OUTPUT PIC Status Due date Schedule Jun Jul
1 2 3 4 1 2

Mesin ready 14-Jun-19 Plan


1 Overhoul mekanikal varia K12 Anasyah on progress
produksi Actual

Mesin ready 10-Jun-19 Plan


2 Overhoul mekanikal KS P05 Anasyah on progress
produksi Actual

Mesin ready 28-Jun-19 Plan


3 Overhoul mekanikal KS P06 Anasyah on progress
produksi Actual

Mesin ready 15-Aug-19 Plan


4 Overhoul mekanikal K08 Anasyah on progress
produksi Actual

Mesin ready 30-Aug-19 Plan


5 Overhoul mekanikal YDN 01 Anasyah on progress
produksi Actual

Mesin ready 5-Aug-19 Plan


6 Overhoul mekanikal roto NP08 Anasyah on progress
produksi Actual

Mesin ready 20-Sep-19 Plan


7 Overhoul mekanikal C02 Anasyah on progress
produksi Actual

Mesin ready 27-Sep-19 Plan


8 Overhoul mekanikal YDN 02 Anasyah on progress
produksi
Mesin ready
8 Overhoul mekanikal YDN 02 Anasyah on progress
produksi Actual

Mesin ready 25-Oct-19 Plan


9 Overhoul mekanikal N22 Anasyah on progress
produksi Actual

Mesin ready 15-Nov-19 Plan


10 Overhoul mekanikal N20 Anasyah on progress
produksi Actual
Cheklist & monitoring mesin continue Plan
update
11 ekstrusi N20, 21, 22, YDN01,02 Anasyah On Time
kondisi mesin continue Actual
dan Geomembrane

Mesin ready 15-Jul-19 Plan


12 Overhoul mesin cast K09 Anasyah on progress
produksi Actual

Mesin ready 30-Jul-19 Plan


13 Overhoul mesin Cast kecil Anasyah on progress
produksi Actual

Plan
14
Actual

KPI

Penanggung Jawab : Mengetahui,

Anasyah Ari Jaka Eko Prayitno


Maintenance Preventive Engineering SPV
AS ENGINEERING TEAM

Tahun : 2019
Jul Aug Sep Oct Nov Keterangan
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Mengetahui,

Andy Mustofah
Engineering Manager
DETAIL AKTIVITAS ENGINEERING T
Penanggung jawab : Samadi
Bagian : Maintenance Preventive
Periode aktivitas : Juni - Nov 2019

No Deskripsi Detail Aktifitas OUTPUT PIC Status Due date Schedule Jun Jul
1 2 3 4 1 2

Mesin ready 14-Jun-19 Plan


1 Overhoul NP04 Samadi on progress
produksi Actual

Mesin ready 28-Jun-19 Plan


2 Overhoul AB2 Samadi on progress
produksi Actual

Mesin ready 15-Jul-19 Plan


3 Overhoul flexiloop 01 Samadi on progress
produksi Actual

Mesin ready 30-Jul-19 Plan


4 Overhoul flexiloop 02 Samadi on progress
produksi Actual

Mesin ready 30-Jul-19 Plan


5 Overhoul Fasto D26 Samadi on progress
produksi Actual

Mesin ready 23-Aug-19 Plan


6 Overhoul DBST-01 Samadi on progress
produksi Actual

Mesin ready 30-Sep-19 Plan


7 Overhoul slitter F01 Samadi on progress
produksi Actual

Mesin ready 14-Sep-19 Plan


8 Overhoul QP02 Samadi on progress
produksi Actual
Cheklist & control mesin update contonue Plan
9 Samadi On Time
konverter & gusset kondisi mesin continue Actual

Mesin ready 14-Oct-19 Plan


10 Overhoul mesin gusset F21 Samadi on progress
produksi Actual

Mesin ready 30-Oct-19 Plan


11 Overhoul DBL05 Samadi on progress
produksi Actual

Mesin ready 15-Nov-19 Plan


12 Overhoul mesin gulung mulsa Samadi on progress
produksi Actual

Mesin ready 30-Nov-19 Plan


13 Overhoul mesin srink Samadi on progress
produksi Actual
Plan
on progress
Actual

Plan
on progress
Actual
KPI 100
Penanggung Jawab : Mengetahui,

Samadi Eko Prayitno


Maintenance Preventive Engineering SPV
AS ENGINEERING TEAM

Tahun : 2019
Jul Aug Sep Oct Nov Keterangan
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
100 87.5 100
Mengetahui,

Andy Mustofah
Engineering Manager
DETAIL AKTIVITAS ENGINEERING T
Penanggung jawab : Agus Condro
Bagian : Maintenance Preventive
Periode aktivitas : Juni - Nov 2019

No Deskripsi Detail Aktifitas OUTPUT PIC Status Due date Schedule Jun Jul
1 2 3 4 1 2

Mesin ready 14-Jun-19 Plan


1 Overhoul NP04 Condro on progress
produksi Actual

Mesin ready 28-Jun-19 Plan


2 Overhoul AB2 Condro on progress
produksi Actual

Mesin ready 15-Jul-19 Plan


3 Overhoul flexiloop 01 Condro on progress
produksi Actual

Mesin ready 30-Jul-19 Plan


4 Overhoul flexiloop 02 Condro on progress
produksi Actual

Mesin ready 30-Jul-19 Plan


5 Overhoul Fasto D26 Condro on progress
produksi Actual

Mesin ready 23-Aug-19 Plan


6 Overhoul DBST-01 Condro on progress
produksi Actual

Mesin ready 30-Sep-19 Plan


7 Overhoul slitter F01 Condro on progress
produksi Actual
Mesin ready 14-Sep-19 Plan
8 Overhoul QP02 Condro on progress
produksi Actual

Cheklist & control mesin update contonue Plan


9 Condro On Time
konverter & gusset kondisi mesin continue Actual

Mesin ready Plan


10 Overhoul mesin gusset F21 Condro on progress
produksi Actual

Mesin ready Plan


11 Overhoul DBL05 Condro on progress
produksi Actual

Mesin ready Plan


12 Overhoul mesin gulung mulsa Condro on progress
produksi Actual

Mesin ready Plan


13 Overhoul mesin srink Condro on progress
produksi Actual

KPI

Penanggung Jawab : Mengetahui,

Agus Condro Eko Prayitno


Maintenance Preventive Engineering SPV
AS ENGINEERING TEAM

Tahun : 2019
Jul Aug Sep Oct Nov Keterangan
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Mengetahui,

Andy Mustofah
Engineering Manager