Вы находитесь на странице: 1из 37

TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES

Ayala Blvd., Ermita, Manila

COLLEGE OF ENGINEERING
Civil Engineering Department

PROJECT TITLE: 4-STOREY SCHOOL BUILDING WITH ROOF DECK


OWNER/S: ST. THERESE SCHOOL OF ROSE SCHOOL
LOCATION: CALOOCAN CITY

ITEM DESCRIPTION OF WORKS QUANTITY UNIT UNIT COST


I. CONCRETE WORKS
Number of Cement 6050 bags ₱ 240.00
Volume of Sand 174 cu. m ₱ 800.00
Volume of Gravel 328 cu. m ₱ 1,200.00
Volume of Water 22205 US gal. ₱ 0.10
SUBTOTAL:
II. MASONRY WORKS
Number of CHB (6" CHB) 9972 pcs. 14.00
Number of CHB (4" CHB) 5340 pcs. 12.00
Number of Cement 3104 cu. m 240.00
Volume of Sand 986 cu. m 800.00
SUBTOTAL:
Prepared By: Approved:

Allen Edward S. Tutol ENGR. MARJUN B. MACASILH


BSCE-4C INSTRUCTOR
AL UNIVERSITY OF THE PHILIPPINES
Ayala Blvd., Ermita, Manila

LLEGE OF ENGINEERING
vil Engineering Department

WITH ROOF DECK


OOL

TOTAL COST

₱ 1,452,000.00
₱ 139,200.00
₱ 393,600.00
₱ 2,220.50
₱ 1,987,020.50

₱ 139,608.00
₱ 64,080.00
₱ 744,960.00
₱ 788,800.00
₱ 1,737,448.00
ENGR. MARJUN B. MACASILHIG
INSTRUCTOR
TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
Ayala Blvd., Ermita, Manila

COLLEGE OF ENGINEERING
Civil Engineering Department

PROJECT TITLE: 4-STOREY SCHOOL BUILDING WITH ROOF DECK


OWNER/S: ST. THERESE SCHOOL OF ROSE SCHOOL
LOCATION: CALOOCAN CITY

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT UNIT AMOUNT


I. Mobilization
Site Clearing 1 lot ₱ 45,000.00
Temporary Facilities 1 lot ₱ 90,000.00
Subtotal
II. Earth Works
Excavation 16 cu. m ₱ 40,000.00
Backfill 16 cu. m ₱ 25,000.00
Subtotal
III. Concrete Works
Number of Cement 6050 bags ₱ 240.00
Volume of Sand 174 cu. m ₱ 800.00
Volume of Gravel 328 cu. m ₱ 1,200.00
Volume of Water 22205 US gal. ₱ 0.10
Subtotal
IV. Steel Works
Number of 10mm Ø bars 1151 pcs. @ 6.00m ₱ 128.00
Number of 12mm Ø bars 1604 pcs. @ 6.00m ₱ 185.00
Number of 20mm Ø bars 1597 pcs. @ 6.00m ₱ 495.00
Number of 25mm Ø bars 722 pcs. @ 7.50m ₱ 1,237.50
Number of #16 Tie Wires 5197 Kgs ₱ 39.00
Subtotal
V. Carpentry Works
Number of Plywood (4' x 8' x 1/4") 77 sheets ₱ 900.00
Number of Lumber (2" x 2") 99 pcs. ₱ 200.00
Number of 8d Common Nail 2 Kgs ₱ 65.00
Number of 2d Common Nail 6 Kgs ₱ 65.00
Subtotal
VI. Form Works
Number of Plywood (4' x 8' x 1/4") 532 sheets ₱ 900.00
Number of Lumber (2" x 2") 15969 pcs. ₱ 200.00
Number of 4d Common Nail 52 Kgs ₱ 65.00
Subtotal
VII. Scaffolding & Staging
Number of Lumber (2" x 2") 10360 pcs. ₱ 280.00
Number of Lumber (2" x 2") 7816 pcs. ₱ 200.00
Number of 4d Common Nail 341 Kgs ₱ 65.00
Subtotal
VIII. Masonry Works
Number of CHB (6" CHB) 9972 pcs. ₱ 14.00
Number of CHB (4" CHB) 5340 pcs. ₱ 12.00
Number of Cement 3104 cu. m ₱ 240.00
Volume of Sand 986 cu. m ₱ 800.00
Subtotal
IX. Roofing Works
G.I. Sheet 42 sheets ₱ 8,500.00
Rivets 6 Kgs ₱ 100.00
G.I. Washer 15 Kgs ₱ 100.00
Plain G.I. Strap 3 pcs. ₱ 320.00
Lead Washer 13 Kgs ₱ 125.00
Gutter 5 pcs. ₱ 340.00
Subtotal
X. Plumbing Works
Water Closet 5 pcs. ₱ 6,200.00
Lavatory 4 pcs. ₱ 3,000.00
Stainless Faucet 6 pcs. ₱ 280.00
Stainless Floor Drain 8 pcs. ₱ 240.00
100mm Ø x 3m PVCSP 30 pcs. ₱ 420.00
100mm Ø PVC Elbow 12 pcs. ₱ 80.00
100mm Ø PVC Wye 35 pcs. ₱ 95.00
100mm Ø PVC Coupling 15 pcs. ₱ 75.00
100mm Ø PVC Tee 2 pcs. ₱ 90.00
100mm Ø PVC C.O. 9 pcs. ₱ 90.00
100mm Ø x 75mm Ø PVC P-Trap 9 pcs. ₱ 85.00
75mm Ø x 3m PVCDS 24 pcs. ₱ 340.00
75mm Ø PVC Elbow 45° 24 pcs. ₱ 63.00
75mm Ø PVC Elbow 45° 4 pcs. ₱ 66.00
75mm Ø PVC Coupling 10 pcs. ₱ 55.00
50mm Ø x 3m PVCSS 18 pcs. ₱ 280.00
50mm Ø PVC Elbow 35 pcs. ₱ 55.00
50mm Ø PVC Tee 15 pcs. ₱ 70.00
50mm Ø PVC Coupling 15 pcs. ₱ 55.00
200mm Ø x 1m CDP 20 pcs. ₱ 350.00
150mm Ø x 1m CDP 45 pcs. ₱ 300.00
Septic Tank (3.45m x 1.50m x 2.00m) 1 unit ₱ 80,000.00
Catch Basin (0.60m x 0.60m) 12 unit ₱ 350.00
Subtotal
XI. Electrical Works
Lighting Fixtures & Accessories
Ceiling Light 72 set ₱ 300.00
Pin light 62 set ₱ 500.00
Duplex Convenience Outlet 50 pcs. ₱ 180.00
Range Convenience Outlet 2 pcs. ₱ 200.00
Water Heater Outlet 4 pcs. ₱ 135.00
Weather Proof Convenience Outlet 9 pcs. ₱ 200.00
Heavy Duty Convenience Outlet 2 pcs. ₱ 220.00
Window Type ACU Outlet 5 pcs. ₱ 150.00
Junction Box 75 pcs. ₱ 30.00
Utility Box 94 pcs. ₱ 20.00
One Way Wall Switch 35 pcs. ₱ 175.00
Wires & Wiring Accessories
22 sq. mm THW 12 meters ₱ 100.00
14 sq. mm THW 20 meters ₱ 85.00
8 sq. mm THW 80 meters ₱ 70.00
5.5 sq. mm THW 100 meters ₱ 30.00
3.5 sq. mm THW 9 rolls ₱ 3,000.00
40 mmø x 3.0 m RSC with Locknut and Bushing 5 pcs. ₱ 250.00
25 mmø x 3.0 m RSC with Locknut and Bushing 7 pcs. ₱ 175.00
20 mmø x 3.0 m RSC with Locknut and Bushing 5 pcs. ₱ 150.00
15 mmø x 3.0 m RSC with Locknut and Bushing 465 pcs. ₱ 120.00
40 mmø RSC Elbow 2 pcs. ₱ 35.00
25 mmø RSC Elbow 2 pcs. ₱ 30.00
20 mmø RSC Elbow 2 pcs. ₱ 25.00
15 mmø RSC Elbow 70 pcs. ₱ 20.00
Plastic Tape 20 rolls ₱ 22.00
Rubber Tape 20 rolls ₱ 55.00
Service Entrance 1 pcs. ₱ 350.00
20 mmø x 3.0 m Grounding Rod Copper Wire 1 pcs. ₱ 400.00
Panel Boards
Main Distribution Panel Board (MDP) 1 set ₱ 8,000.00
Distribution Panel Board (DPA) 1 set ₱ 5,000.00
Distribution Panel Board (DPB) 1 set ₱ 4,000.00
Subtotal
XII. Finishing Works
Number of Cement 1752 bags ₱ 240.00
Volume of Sand 60 cu. m ₱ 800.00
Subtotal
XIII. Paint Works
Acrylic Semi-gloss Latex Paint (Yellow) 68 Liters ₱ 700.00
Acrylic Semi-gloss Latex Paint (Beige) 68 Liters ₱ 800.00
Neutralizer 57 Liters ₱ 300.00
Subtotal
XIV. Tile Works
Granite tiles 60 x 60 cm 132 pcs. ₱ 165.00
Tile Adhesive 7 bags ₱ 200.00
White Cement 20 Kgs ₱ 580.00
Subtotal
XV. Doors & Windows
Aluminum Framed Fixed Swing Type Door 2 pcs. ₱ 7,000.00
Solid Wood Double Panel Door 23 pcs. ₱ 4,300.00
PVC Flush Door 7 pcs. ₱ 1,500.00
Aluminum Framed Fixed and Sliding Window 17 pcs. ₱ 4,000.00
Subtotal
XVI. Demobilization
Clearing 1 lot ₱ 40,000.00
Subtotal

Prepared By: Approved:

Allen Edward S. Tutol ENGR. MARJUN B. MACASILH


BSCE-4C INSTRUCTOR
NIVERSITY OF THE PHILIPPINES
Blvd., Ermita, Manila

GE OF ENGINEERING
ngineering Department

OOF DECK

AMOUNT

₱ 45,000.00
₱ 90,000.00
₱ 135,000.00

₱ 640,000.00
₱ 400,000.00
₱ 1,040,000.00

₱ 1,452,000.00
₱ 139,200.00
₱ 393,600.00
₱ 2,220.50
₱ 1,987,020.50

₱ 147,328.00
₱ 296,740.00
₱ 790,515.00
₱ 893,475.00
₱ 202,683.00
₱ 2,330,741.00

₱ 69,300.00
₱ 19,800.00
₱ 130.00
₱ 390.00
₱ 89,620.00

₱ 478,800.00
₱ 3,193,800.00
₱ 3,380.00
₱ 3,675,980.00

₱ 2,900,800.00
₱ 1,563,200.00
₱ 22,165.00
₱ 4,486,165.00

₱ 139,608.00
₱ 64,080.00
₱ 744,960.00
₱ 788,800.00
₱ 1,737,448.00

₱ 357,000.00
₱ 600.00
₱ 1,500.00
₱ 960.00
₱ 1,625.00
₱ 1,700.00
₱ 363,385.00
₱ 31,000.00
₱ 12,000.00
₱ 1,680.00
₱ 1,920.00
₱ 12,600.00
₱ 960.00
₱ 3,325.00
₱ 1,125.00
₱ 180.00
₱ 810.00
₱ 765.00
₱ 8,160.00
₱ 1,512.00
₱ 264.00
₱ 550.00
₱ 5,040.00
₱ 1,925.00
₱ 1,050.00
₱ 825.00
₱ 7,000.00
₱ 13,500.00
₱ 80,000.00
₱ 4,200.00
₱ 190,391.00

₱ 21,600.00
₱ 31,000.00
₱ 9,000.00
₱ 400.00
₱ 540.00
₱ 1,800.00
₱ 440.00
₱ 750.00
₱ 2,250.00
₱ 1,880.00
₱ 6,125.00

₱ 1,200.00
₱ 1,700.00
₱ 5,600.00
₱ 3,000.00
₱ 27,000.00
₱ 1,250.00
₱ 1,225.00
₱ 750.00
₱ 55,800.00
₱ 70.00
₱ 60.00
₱ 50.00
₱ 1,400.00
₱ 440.00
₱ 1,100.00
₱ 350.00
₱ 400.00

₱ 8,000.00
₱ 5,000.00
₱ 4,000.00
₱ 194,180.00

₱ 420,480.00
₱ 48,000.00
₱ 468,480.00
₱ 47,600.00
₱ 54,400.00
₱ 17,100.00
₱ 119,100.00

₱ 21,780.00
₱ 1,400.00
₱ 11,600.00
₱ 34,780.00

₱ 14,000.00
₱ 98,900.00
₱ 10,500.00
₱ 68,000.00
₱ 191,400.00

₱ 40,000.00
₱ 40,000.00

ENGR. MARJUN B. MACASILHIG


INSTRUCTOR
SUMMARY
ITEM NO. DESCRIPTION AMOUNT
I. Mobilization ₱ 135,000.00
II. Earth Works ₱ 1,040,000.00
III. Concrete Works ₱ 1,987,020.50
IV. Steel Works ₱ 2,330,741.00
V. Carpentry Works ₱ 89,620.00
VI. Form Works ₱ 3,675,980.00
VII. Scaffolding & Staging ₱ 4,486,165.00
VIII. Masonry Works ₱ 1,737,448.00
IX. Roofing Works ₱ 363,385.00
X. Plumbing Works ₱ 190,391.00
XI. Electrical Works ₱ 194,180.00
XII. Finishing Works ₱ 468,480.00
XIII. Paint Works ₱ 119,100.00
XIV. Tile Works ₱ 34,780.00
XV. Doors & Windows ₱ 191,400.00
XVI. Demobilization ₱ 40,000.00
Material Cost ₱ 17,083,690.50

Direct Cost
Material Cost ₱ 17,083,690.50
Labor Cost ₱ 7,687,660.73
Equipment Cost ₱ 854,184.53
Total Direct Cost ₱ 25,625,535.75

Indirect Cost
Contractor's Profit ₱ 3,075,064.29
Over Contingency Miscellaneous (OCM) ₱ 3,075,064.29
E-Vat ₱ 3,813,079.72
Total Indirect Cost ₱ 9,963,208.30

Total Contract Amount ₱ 35,588,744.05

Direct Cost
Material Cost x
Labor Cost 0.45x
Equipment Cost 0.05x
Total Direct Cost 1.5x

Indirect Cost
Contractor's Profit 0.12(1.5x) 0.18x
Over Contingency Miscellaneous (OCM) 0.12(1.5x) 0.18x
E-Vat 0.12(1.5x + 0.18x + 0.18x) 0.2232x
Total Indirect Cost 0.18x + 0.18x + 0.2232x 0.5832x

Total Contract Amount 1.5x + 0.5832x 2.0832x


Manpower Schedule
Manpower 30CD 60CD 90CD 120CD 150CD 180CD 210CD 240CD
Engineer 1 1 1 1 1 1 1 1
Architect 1 1 1 1 1 1 1 1
Foreman 1 1 1 1 1 1 1 1
Laborer 6 12 12 20 25 28 26 22
Steelman 3 5 8 2
Welder 2 2 2 2
Plumber 2 2 2
Mason 2 5 5
Painter 5
Electrician 3 5 6
Equipment Operator 2 3 2
Carpenter 5
270CD
1
1
1
20

5
4

4
Equipment Schedule
Equipment 30CD 60CD 90CD 120CD 150CD 180CD 210CD 240CD
Back Hoe 1 1 1
Bulldozer 1 1 1
Compactor 1 1
Excavator 1 1
Vibrator 1 1 1 1
Cement Mixer 1 1 2 1
Welding Machine 2 2 2 2
Dump Truck 1 1
Tower Crane 1 1 1 1 1 1 1
Lifter 1 1 1 1 1
270CD

1
1
Cash Flow
ITEM NO. DESCRIPTION AMOUNT PERCENTAGE
I. Mobilization ₱ 281,232.00 0.79%
II. Earth Works ₱ 2,166,528.00 6.09%
III. Concrete Works ₱ 4,139,361.11 11.63%
IV. Steel Works ₱ 4,855,399.65 13.64%
V. Carpentry Works ₱ 186,696.38 0.52%
VI. Form Works ₱ 7,657,801.54 21.52%
VII. Scaffolding ₱ 9,345,578.93 26.26%
VIII. Masonry Works ₱ 3,619,451.67 10.17%
IX. Roofing Works ₱ 757,003.63 2.13%
X. Plumbing Works ₱ 396,622.53 1.11%
XI. Electrical Works ₱ 404,515.78 1.14%
XII. Finishing Works ₱ 975,937.54 2.74%
XIII. Paint Works ₱ 248,109.12 0.70%
XIV. Tile Works ₱ 72,453.70 0.20%
XV. Doors & Windows ₱ 398,724.48 1.12%
XVI. Demobilization ₱ 83,328.00 0.23%
Total Amount ₱ 35,588,744.05 100.00%

Cumulative Amount
% Accomplishment
30CD 60CD 90CD 120CD 150CD
₱ 281,232.00
₱ 216,652.80 ₱ 866,611.20 ₱ 1,083,264.00
₱ 827,872.22 ₱ 1,241,808.33 ₱ 1,655,744.44 ₱ 413,936.11
₱ 971,079.93 ₱ 1,456,619.90 ₱ 1,942,159.86
₱ 37,339.28 ₱ 56,008.92 ₱ 74,678.55
₱ 765,780.15 ₱ 2,297,340.46 ₱ 3,063,120.61
₱ 1,869,115.79 ₱ 2,803,673.68
₱ 723,890.33 ₱ 1,085,835.50
₱ 151,400.73

₱ 497,884.80 ₱ 1,694,483.42 ₱ 4,099,271.69 ₱ 8,058,719.83 ₱ 9,534,805.05


₱ 497,884.80 ₱ 2,192,368.22 ₱ 6,291,639.91 ₱ 14,350,359.75 ₱ 23,885,164.79
1.40% 6.16% 17.68% 40.32% 67.11%
180CD 210CD 240CD 270CD

₱ 485,539.97
₱ 18,669.64
₱ 1,531,560.31
₱ 4,672,789.46
₱ 1,809,725.84
₱ 302,801.45 ₱ 227,101.09 ₱ 75,700.36
₱ 79,324.51 ₱ 158,649.01 ₱ 118,986.76 ₱ 39,662.25
₱ 40,451.58 ₱ 161,806.31 ₱ 121,354.73 ₱ 80,903.16
₱ 585,562.52 ₱ 390,375.01
₱ 99,243.65 ₱ 148,865.47
₱ 28,981.48 ₱ 43,472.22
₱ 199,362.24 ₱ 199,362.24
₱ 83,328.00

₱ 8,940,862.75 ₱ 547,556.41 ₱ 1,229,191.74 ₱ 985,968.35


₱ 32,826,027.54 ₱ 33,373,583.95 ₱ 34,602,775.70 ₱ 35,588,744.05
92.24% 93.78% 97.23% 100.00%
Cash Flow
ITEM NO. DESCRIPTION AMOUNT PERCENTAGE
I. Mobilization ₱ 281,232.00 0.79% 100%
II. Earth Works ₱ 2,166,528.00 6.09%
III. Concrete Works ₱ 4,139,361.11 11.63%
IV. Steel Works ₱ 4,855,399.65 13.64%
V. Carpentry Works ₱ 186,696.38 0.52% 75%
VI. Form Works ₱ 7,657,801.54 21.52%
VII. Scaffolding ₱ 9,345,578.93 26.26%
VIII. Masonry Works ₱ 3,619,451.67 10.17%
IX. Roofing Works ₱ 757,003.63 2.13% 50%
X. Plumbing Works ₱ 396,622.53 1.11%
XI. Electrical Works ₱ 404,515.78 1.14%
XII. Finishing Works ₱ 975,937.54 2.74%
XIII. Paint Works ₱ 248,109.12 0.70% 25%
XIV. Tile Works ₱ 72,453.70 0.20%
XV. Doors & Windows ₱ 398,724.48 1.12%
XVI. Demobilization ₱ 83,328.00 0.23%
Total Amount ₱ 35,588,744.05 100.00%

Cumulative Amount
% Accomplishment
30CD 60CD 90CD 120CD 150CD
₱ 281,232.00
₱ 216,652.80 ₱ 866,611.20 ₱ 1,083,264.00
₱ 827,872.22 ₱ 1,241,808.33 ₱ 1,655,744.44 ₱ 413,936.11
₱ 971,079.93 ₱ 1,456,619.90 ₱ 1,942,159.86
₱ 37,339.28 ₱ 56,008.92 ₱ 74,678.55
₱ 765,780.15 ₱ 2,297,340.46 ₱ 3,063,120.61
₱ 1,869,115.79 ₱ 2,803,673.68
₱ 723,890.33 ₱ 1,085,835.50
₱ 151,400.73

₱ 497,884.80 ₱ 1,694,483.42 ₱ 4,099,271.69 ₱ 8,058,719.83 ₱ 9,534,805.05


₱ 497,884.80 ₱ 2,192,368.22 ₱ 6,291,639.91 ₱ 14,350,359.75 ₱ 23,885,164.79
1.40% 6.16% 17.68% 40.32% 67.11%
180CD 210CD 240CD 270CD

₱ 485,539.97
₱ 18,669.64
₱ 1,531,560.31
₱ 4,672,789.46
₱ 1,809,725.84
₱ 302,801.45 ₱ 227,101.09 ₱ 75,700.36
₱ 79,324.51 ₱ 158,649.01 ₱ 118,986.76 ₱ 39,662.25
₱ 40,451.58 ₱ 161,806.31 ₱ 121,354.73 ₱ 80,903.16
₱ 585,562.52 ₱ 390,375.01
₱ 99,243.65 ₱ 148,865.47
₱ 28,981.48 ₱ 43,472.22
₱ 199,362.24 ₱ 199,362.24
₱ 83,328.00

₱ 8,940,862.75 ₱ 547,556.41 ₱ 1,229,191.74 ₱ 985,968.35


₱ 32,826,027.54 ₱ 33,373,583.95 ₱ 34,602,775.70 ₱ 35,588,744.05
92.24% 93.78% 97.23% 100.00%
PREDECESSO
DESIGNATION ACTIVITY
R
A Construction of Temporary Enclosure -
B Site Excavation A
C Soil Compaction B
D Arrangement of RSB and formworks for Footing C
E Arrangement of RSB and formworks for FTB C
F Pouring of concrete for Footing and FTB D, E
G Curing F
H Arrangement of scaffolding F
I Installation of column RSB and formworks H
J Pouring of Concrete for columns I
K Installation of beam RSB and formworks J
L Pouring of concrete for beams K
M Installation of RSB and formwork for slab L
N Installation of pipes for electrical and plumbing L
O Pouring of concrete for slab M, N
P Arrangement of CHB O
Q Installation of electrical wirings G, P
R Installation of roof P
S Plastering Q, R
T Painting Works S
U Installation of Tiles S
V Installation of Doors and Windows U
W Installation of lighting fixtures V
X Disassembly of scaffoldings T, W
Y Demobilization X
NO. OF DAYS
(n)
2
6 A ES EF
4 n LS LF
4 A =Activity
2 n =No. of days
1 ES =Early Start
35 EF =Early Finish
8 LS =Late Start
18 LF =Late Finish
10
17
10 A 0 2 B 2 8 C
START
14 2 0 2 6 2 8 4
10
10
60
14
2
35
60
14
14
9
3
2
D 12 16 G 17 52
4 12 16 35 129 164

8 12 F 16 17
8 12 1 16 17

E 12 14 H 17 25 I 25 43 J
2 14 16 8 17 25 18 25 43 10
M 80 94
14 80 94

43 53 K 53 70 L 70 80 O 94 104 P
43 53 17 53 70 10 70 80 10 94 104 60

N 80 90
10 84 94
T 213 273
60 213 273

Q 164 178 S 178 213


14 164 178 35 178 213

104 164 U 213 227 V 227 241 W


104 164 14 236 250 14 250 264 9

R 164 166
2 176 178
X 273 276 Y 276 278
FINISH
3 273 276 2 276 278

241 250
264 273
Program Evaluation and Review Technique (P
Critical Path Method (CPM)
DESIGNATION ACTIVITY
A Construction of Temporary Enclosure
B Site Excavation
C Soil Compaction
D Arrangement of RSB and formworks for Footing
E Arrangement of RSB and formworks for FTB
F Pouring of concrete for Footing and FTB
G Curing
H Arrangement of scaffolding
I Installation of column RSB and formworks
J Pouring of Concrete for columns
K Installation of beam RSB and formworks
L Pouring of concrete for beams
M Installation of RSB and formwork for slab
N Installation of pipes for electrical and plumbing
O Pouring of concrete for slab
P Arrangement of CHB
Q Installation of electrical wirings
R Installation of roof
S Plastering
T Painting Works
U Installation of Tiles
V Installation of Doors and Windows
W Installation of lighting fixtures
X Disassembly of scaffoldings
Y Demobilization
ew Technique (PERT)
od (CPM)
PREDECESSO NO. OF DAYS
R (n)
- 1
A 4 A ES EF
B 3 n LS LF
C 3 A =Activity
C 2 n =No. of days
D, E 1 ES =Early Start
F 46 EF =Early Finish
F 7 LS =Late Start
H 20 LF =Late Finish
I 12
J 15
K 8 A 0 1
L 15
START 1 0 1
L 12
M, N 10
O 62
G, P 14
P 2
Q, R 31
S 61
S 12
Critical Path
U 12
V 8
T, W 2
X 1
D 8 11 G 12 58
3 8 11 46 115 161

B 1 5 C 5 8 F 11 12
4 1 5 3 5 8 1 11 12

E 8 10 H 12 19
2 9 11 7 12 19
M 74
15 74

I 19 39 J 39 51 K 51 66 L 66 74
20 19 39 12 39 51 15 51 66 8 66 74

N 74
12 77
T
61

89 Q 161 175 S 175 206


89 14 161 175 31 175 206

O 89 99 P 99 161 U
10 89 99 62 99 161 12

86 R 161 163
89 2 173 175
206 267
206 267

X 267 269 Y 269 270


2 267 269 1 269 270

206 218 V 218 230 W 230 238


235 247 12 247 259 8 259 267
FINISH

Вам также может понравиться