Академический Документы
Профессиональный Документы
Культура Документы
2
Assistant Professor, Faculty of Engineering, Misr University for Science and Technology, Egypt
Abstract: Applications of artificial intelligence have been adopted by construction industry to enhance accuracy and to
save time. The results of these applications are outstanding and encouraged many researchers to seek more of these
applications. Therefore, the aim of this research is to develop a neural network model to estimate site overhead costs as a
percentage from the direct cost. The developed model used 55 residential projects in Egypt as a training data set, and 6 other
projects were used for testing. The model performs the estimation process based on 6 input factors: class of contracting
company, project direct cost, project duration, project location, contract type, and ownership type of the contracting
company. The best model developed shows an accuracy of 84% and consists of 6 input neurons, 2 hidden layers with 6 and 5
hidden neurons respectively, and 1 output layer.
Keywords: Artificial Intelligence, Neural Networks, Cost Estimation, Construction Overheads, Residential.
actual cost either cost over-run or a cost saving. Both cases
can cause a problem for the construction company.
1 Introduction The absence of structured and accurate methods that can
assess site overhead cost for residential projects in Egypt
Cost is considered one of the main three challenges that put construction companies in a risk of inaccurate estimate
face building construction companies, where the success of of bid package that may affect the profit margin of the
any project is measured by its ability to complete it within company.
the allocated budget, according to the planned baseline
schedule, and with the maximum quality [1]. Cost
estimating is an essential element in construction business 2 Literature Review
as supported by many researches. Carty stated that it is a
key function in order to enable companies acquiring new The application of artificial neural networks in the
contracts and projects at the accurate price so as to survive construction management industry goes back to the early
in the market [2]. 1980s’. It was originally developed to enhance the
Construction Company overhead is commonly managers’ ability to make decisions. These applications are
categorized into 2 branches: Site (Project) overhead costs, likes of cost estimation, delay analysis, risk assessment,
and General (Home) overhead costs [3]. prediction of markup, productivity rates.. etc.
Site overhead costs include costs that cannot be In Egypt, Georgy and Barsoum developed an ANN
allocated on a certain work package, but it is essential for model for the parametric cost estimate of schools
activities to be completed, in other words, it serves the construction projects. They used statistical and neural
execution process. General overheads are generally network models for estimating costs; the research finding
considered as costs of conducting business, these are costs was a neural network of a single hidden layer with number
that cannot be allocated on a certain project [4]. of neurons equal to two thirds the number of neurons in the
A study done by Nancy Holland and Dana Hobson input layer would be sufficient [7].
previously identified overhead costs the same as Dagstino Hosny used the AAN modeling to predict the cost
and Feigenbaum did. Also set examples for what may site increase of construction projects in Egypt based on the
overhead costs cover like, site staff, cleaning activities, analysis of several factors influencing project cost such as
temporary services, first aid and safety provisions, project type, contract type, owner behavior, design
transportation of site operatives, and site accommodation completion [8].
[4][5]. In Turkey, Gunaydin and Dogan designed an Artificial
It is difficult for construction companies to estimate the Neural Network model to predict the cost per meter square
optimum percentage for overhead costs, especially through for reinforced concrete structural systems of buildings in an
the unstable environment and construction market that early phase of the design process. The used data for
enable them to acquire a tender and maximize their profit developing the network consists of 30 construction projects
as well. If the overhead costs are not accurately estimated varies from four to eight stories residential buildings. The
prior bid submission, this may lead to a cost overrun and developed ANN architecture consisted of eight input layer
the attempts to recover this overrun can result in a financial (one for each input variable). The resulted model had an
issue and collapse for the construction company [6]. accuracy of 93% in estimating the cost per meter square for
Most of the building construction companies find no reinforced concrete structural residential buildings [9].
hassle in estimating the direct cost of a project, the In Gaza Strip, Arafa & Alqedra developed an Artificial
inaccuracy appears in the estimating of the overhead costs, Neural Network model to predict construction cost at an
causing a clear cost variance between estimated budget and early project phase. The used data base for learning
International Journal of Automation and Computing 00(0), Month 20XX
consisted of 71 construction project from Gaza Strip. The For Construction and Building Contractors.
resulted ANN model architecture consisted of one hidden Then the process of designing the network is ready and
layer with seven neurons. The established model has the main objective of the research; which is developing a
proven to be relatively successful in predicting construction network for estimating the site overhead percentage.
cost at an early stage, and without the need of detailed After reaching the optimum network structure, it is
information about the project [10]. critical to test and validate the network, 6 projects were set
In Philippines, Lyne and Maximinio developed an AAN aside for the validation process to be performed.
to estimate the total structural cost of building construction
projects in Philippines based on six parameters which are:
number of floors, number of basements, area of floor, 4 Data Collection and Analysis
concrete volume, area of formwork, and weight of
reinforcement steel. The data used for the learning process The process of data collection is divided into two stages:
consists of data from 30 different building construction the first stage is identify the factors influencing the site
projects; this data set was divided into 60%, 20%, and 20% overhead costs in the Egyptian residential construction
for training, validation, and testing respectively. The industry and comparing the factors resulted from the
resulted model architecture was a network of six input literature review with those affecting the construction
neurons (one for each input parameter), one hidden layer industry in Egypt.
with seven neurons, and one output neuron representing the The second stage is to collect data for different
structural cost. The model was developed using MatLab residential construction projects in Egypt, with the data and
with a feed forward back propagation technique [11]. factors resulted from the analysis of the first stage of the
Finally, a study was conducted in Egypt to calculate the data collection and analysis.
overhead percentage for construction projects. The model
was developed using N-Connection professional 1997, and 4.1 Site Overhead Factors Questionnaire
used data for 52 projects with different types. The model
This questionnaire is designed to investigate the factors
performs its estimation based on 10 factors. The resulted
affecting site overhead percentage in the residential
model has an accuracy of 80% [12].
building construction projects in Egypt. And participants
The last study has some similarities to the research
were selected to have an experience more than 10 years in
conducted in this paper. However, the data collected for the
residential construction market in Egypt working in
previous study was for different types of projects.
estimation, tendering, control, financial and commercial
However, this research concentrates on the residential
technical office section, procurement, and others.
projects with a variety in contractors’ classes operating in
The first section of the questionnaire consists of thirteen
these types of projects. Also this study taking into
multiple choice questions, where participant was asked to
consideration the high fluctuations in the economic
rate each factor according to its influence on the site
environment occurring in Egypt after the revolution in 2011
overhead percentage and how each factor can affect this
and the devaluation of the Egyptian pound in 2016. For all
percentage. The selected participants are experts in the
these reasons, this study was conducted.
residential construction industry from the pioneer
companies in the field of residential construction in Egypt.
3 Research Methodology In the second part of the questionnaire the participant
was asked if there is any other factor that was not stated in
the first section that may affect site overhead percentage in
For the aim of developing a neural network to predict
the Egyptian residential construction.
the site overhead percentage, this research has to go
The results of the questionnaire as illustrated in Fig. 1
through different phases in order for this neural network to
shows that the top five factors that most affect the site
be accurate and reliable. The extensive literature study in
overhead percentage in residential construction in Egypt
the previous section serves in identification of the factors
are project location, project direct cost, project duration,
that may influence the percentage of site overhead. These
contract Type, class of company
factors mainly include project location, direct cost,
duration, complexity, payment schedule, contract type,
tendering method, class of company, contractor cash
availability, firm need of work, and number of competitors.
A questionnaire survey was conducted to focus on the
factors that influence the site overhead percentage in the
Egyptian industry.
The next step was to collect project data from the past 7
years for the aim of learning the neural network from actual
project data. Project data for 55 Egyptian residential project
was collected from various number of construction
companies in Egypt. A comparative analysis was then
performed on these projects in order to illustrate the
influence of each factor on the percentage of site overhead. Fig. 1: Questionnaire 1 results
The collected project data and the questionnaire survey
were performed upon a calculated sample size according to
the number of contractors enrolled the Egyptian Federation
F. A. Author et al. / Preparation of Papers for International Journal of Automation and Computing
Table 2: Questionnaire 2 factor choice results Table 3: Sensitivity Analysis Run Example
(3)
Where:
n is the number of projects to be evaluated These projects represented new cases for the model to
xi is the model output related to the sample work on, that should test the accuracy of the developed
E is the target output model whether it is within the acceptable range of relative
percentage error or not. If the value of the relative
percentage error exceeds the acceptable range of the model,
5.3 Network Architecture
the prediction would be considered a wrong prediction.
The “Neural Designer” at this stage needs to set the And if the value of the relative percentage error lies within
number of hidden layers, the number of neurons in each the acceptable range, the prediction would be considered
layer, the transfer function for each layer. right. Table 5 shows the test project and their results.
The process of designing the network was done using a
traditional trial and error method in order to reach the best Table 5: Model testing results
possible model. The best model was chosen according to
the lowest root mean square error and the correspondence
error values.
The trial and error of models resulted in a number of 92
models categorized as follows:
International Journal of Automation and Computing 00(0), Month 20XX