Reinforcement detailing of footing is as much important as site investigation for the structural design
of footing. A good detailing reflects the design requirement of the footing for structural stability.
A good detailing of reinforcement covers topics like cover to reinforcement based on environmental
considerations for durability, minimum reinforcement and bar diameters, proper dimensioning of
footing. It is desirable foundation should be detailed in both plan and elevation in drawings.
That is why different aspects of reinforcement detailing of isolated footing is discussed in the
following sections.
If surface levelling is not used, then it is required to specify a cover of 75mm to cover uneven surface
of excavation.
In two-way square footings, the reinforcement extending in both directions is distributed uniformly
across the full width of the footing. But in the case of two-way rectangular footings, reinforcement is
https://theconstructor.org/structural-engg/reinforcement-detailing-isolated-footing/8486/?utm_source=pushengage&utm_medium=pushnotification&utm… 1/4
8/31/2018 Reinforcement Detailing of Isolated Footing
However for short direction, the reinforcement is distributed in the central band as per calculations
below. The rest reinforcement in short direction is distributed equally on both sides of the central
band.
Where y is the long side and x is the short side of the footing.
4. Dowel reinforcement
Dowel reinforcement is used to tie the isolated footing to the above column. with regard to dowel
reinforcement development length, the development length of dowel bars into the column and the
isolated footing shall be provided and clearly shown in the design drawings.
https://theconstructor.org/structural-engg/reinforcement-detailing-isolated-footing/8486/?utm_source=pushengage&utm_medium=pushnotification&utm… 2/4
8/31/2018 Reinforcement Detailing of Isolated Footing
5. Lap splice
Splice length of dowel and column reinforcement shall be clearly shown. Anchorage of both flexural
and dowel reinforcement lengths shall be checked to prevent bond failure of the dowels in the footing
and to prevent failure of the lap splices between the dowels and the column bars.
https://theconstructor.org/structural-engg/reinforcement-detailing-isolated-footing/8486/?utm_source=pushengage&utm_medium=pushnotification&utm… 3/4
8/31/2018 Reinforcement Detailing of Isolated Footing
https://theconstructor.org/structural-engg/reinforcement-detailing-isolated-footing/8486/?utm_source=pushengage&utm_medium=pushnotification&utm… 4/4