Outside Pump Station (Equipment Structure (RWI Head Structure) )

Activity ID New Activity Name Value Weight Value

RWI-845 Coffer dam 14% 29,038,058.00


RWI-846 Demolition the Coffer dam 5% 10,370,735.00
RWI-847 Intake Pipiline Inc.(Excavation , Concrete Rock & Crushed Stone) 18% 37,334,646.00
RWI-848 Stone Pitching 13% 26,963,911.00
RWI-849 Lining Concrete for Slope Protection 5% 10,370,735.00
RWI-850 Asphalt Road 4% 8,296,588.00
RWI-851 HDD and Burrowing 30% 62,224,410.00
RWI-852 Piping Works 10% 20,741,470.00
RWI-853 BRC Fence 1% 2,074,147.00
Total 207,414,700.00

Activity ID Old Actvites Name Value Weight Value


RWI-846 Excavation 8% 7,016,800
RWI-847 Coffer dam & Backfilling 10% 8,771,000
RWI-848 Lean Concrete 4% 3,508,400
RWI-849 Rebar 26% 23,681,700
RWI-850 Formwork 20% 17,542,000
RWI-851 Concrete Pouring 26% 23,681,700
RWI-852 Bitumen Coating/ Backfilling 6% 5,508,400

RWI-854 Sheets Piles Works 100% for Suction Pipes 75% 87,819,600
RWI-855 Excavation(including dewatering) of around Sheet Pile Area Work for 100% for Suction Pipes 20% 23,418,560
RWI-856 Demolition and restoration of Sheet Pile Work for 100% for Suction Pipes 5% 5,854,640
Total 207,414,700.00