ADELANTO PARA MATERIALES N°1

FORMULAS POLINÓMICAS

OBRA : "INSTALACIÓN DEL SISTEMA DE RIEGO TECNIFICADO PARA LAS COMUNIDADES DE PALLA PALLA, VISTA ALEGRE, PARIAHUANCA, QASANCCA, QUINUAS, SUCA, CUYPAMPA, PICHUSPAMPA, CCATUN RUMI Y
LLAQHUAPAMPA DEL DISTRITO DE SAN MIGUEL, PROVINCIA LA MAR – AYACUCHO"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE LA MAR
CONTRATISTA: CONSORCIO SAN ANDRES

FECHA DEL PRESUPUESTO: : abr-18


PRESUPUESTO TOTAL CONTRATADO: S/. 898,877.69 Sin IGV

SUBPRESUPUESTO: 001 CONDUCCION GENERAL

PRESUPUESTO CONTRATADO: S/. 898,877.69 Exonerado del IGV

K= 0.360 Jr/Jo+ 0.156 CAAr/CAAo+ 0.14 Dr/Do+ 0.148 Mr/Mo+ 0.196 Ir/Io

% INCID. COEF. INDICES ABRIL INDICE DIC 2018


No ELEMENTO REPRESENTATIVO IND. UNIF. SIMBOLO MONTO
MONOMIO INCID. 2018 Ib
I k
1 MANO DE OBRA 47 J 3,883.15 1.20% 0.360 #N/A #N/A #N/A
2 ACERO DE CONSTRUCCION CORRUGADO 03 4,494.21 3.205% 0.156 #N/A #N/A #N/A
AGREGADO GRUESO 05 54,832.15 39.103% 0.156 #N/A #N/A #N/A
CEMENTO PORTLAND TIPO I 21 CAA 80,898.56 57.692% 0.156 #N/A #N/A #N/A
3 DÓLAR 28 D 125,842.88 100.00% 0.140 #N/A #N/A #N/A
4 MAQUINARIA Y EQUIPO IMPORTADO 49 M 133,033.90 100.00% 0.148 #N/A #N/A #N/A
5 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 I 176,180.03 100.00% 0.196 #N/A #N/A #N/A

579,164.87 1.000 #N/A

SUBPRESUPUESTO: 002 RIEGO TECNIFICADO PALLA PALLA

PRESUPUESTO CONTRATADO: S/. 397,014.34 Exonerado del IGV

K= 0.396 Jr / Jo+ 0.071 Ar / Ao + 0.109 Mr / Mo+ 0.110 Tr / To+ 0.314 Ir / Io

% INCID. COEF. INDICES ABRIL INDICE DIC 2018


No ELEMENTO REPRESENTATIVO IND. UNIF. SIMBOLO MONTO
MONOMIO INCID. 2018 Ib
I k
1 MANO DE OBRA 47 J 157,217.68 100.00% 0.396 #N/A #N/A #N/A
2 ACERO DE CONSTRUCCION CORRUGADO 03 A 28,188.02 100.000% 0.071 #N/A #N/A #N/A
3 MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA 43 M 43,274.56 100.000% 0.109 #N/A #N/A #N/A
4 TUBERIA DE PVC 72 T 43,671.58 100.000% 0.110 #N/A #N/A #N/A
5 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 I 124,662.50 100.00% 0.314 #N/A #N/A #N/A

397,014.34 1.000 #N/A

SUBPRESUPUESTO: 003 RIEGO TECNIFICADO VISTA ALEGRE

PRESUPUESTO CONTRATADO: S/. 739,672.45 Exonerado del IGV

K= 0.459 Jr / Jo+ 0.068 Mr/Mo+ 0.073 Cr / Co+ 0.132 Tr / To + 0.268 Ir / Io

N° ELEMENTO REPRESENTATIVO IND. SIMBOLO MONTO % INCID. COEF.


INDICES ABRIL INDICE DIC 2018
UNIF. MONOMIO INCID.
2018 Ib
I k
1 MANO DE OBRA 47 J 339,509.65 100.00% 0.459 #N/A #N/A #N/A
2 MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA 43 A 50,297.73 100.000% 0.068 #N/A #N/A #N/A
3 CEMENTO PORTLAND TIPO I 21 M 53,996.09 100.000% 0.073 #N/A #N/A #N/A
4 TUBERIA DE PVC 72 T 97,636.76 100.000% 0.132 #N/A #N/A #N/A
5 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 I 198,232.22 100.00% 0.268 #N/A #N/A #N/A

739,672.45 1.000 #N/A


ADELANTO PARA MATERIALES N°1

FORMULAS POLINÓMICAS

OBRA : "INSTALACIÓN DEL SISTEMA DE RIEGO TECNIFICADO PARA LAS COMUNIDADES DE PALLA PALLA, VISTA ALEGRE, PARIAHUANCA, QASANCCA, QUINUAS, SUCA, CUYPAMPA, PICHUSPAMPA, CCATUN RUMI Y
LLAQHUAPAMPA DEL DISTRITO DE SAN MIGUEL, PROVINCIA LA MAR – AYACUCHO"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE LA MAR
CONTRATISTA: CONSORCIO SAN ANDRES

SUBPRESUPUESTO: 004 RIEGO TECNIFICADO PARIAHUANCA

PRESUPUESTO CONTRATADO: S/. 1,421,271.74 Exonerado del IGV

K= 0.493 Jr / Jo+ 0.051 Cr / Co + 0.064 Mr/Mo + 0.156 Tr / To + 0.236 Ir/Io

N° ELEMENTO REPRESENTATIVO IND. SIMBOLO MONTO % INCID. COEF.


INDICES ABRIL INDICE DIC 2018
UNIF. MONOMIO INCID.
2018 Ib
I k
1 MANO DE OBRA 47 J 700,686.97 100.00% 0.493 #N/A #N/A #N/A
2 CEMENTO PORTLAND TIPO I 21 C 72,484.86 100.000% 0.051 #N/A #N/A #N/A
3 MAQUINARIA Y EQUIPO IMPORTADO 49 M 90,961.39 100.000% 0.064 #N/A #N/A #N/A
4 TUBERIA DE PVC 72 T 221,718.39 100.000% 0.156 #N/A #N/A #N/A
5 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 I 335,420.13 100.00% 0.236 #N/A #N/A #N/A

1,421,271.74 1.000 #N/A

SUBPRESUPUESTO: 005 RIEGO TECNIFICADO QASANCCA

PRESUPUESTO CONTRATADO: S/. 566,165.28 Exonerado del IGV

K= 0.442 Jr / Jo+ 0.065 Mr / Mo+ 0.087 Cr / Co + 0.129 Tr / To + 0.277 Ir/Io

N° ELEMENTO REPRESENTATIVO IND. SIMBOLO MONTO % INCID. COEF.


INDICES ABRIL INDICE DIC 2018
UNIF. MONOMIO INCID.
2018 Ib
I k
1 MANO DE OBRA 47 J 628,202.11 100.00% 0.442 #N/A #N/A #N/A
2 MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA 43 C 92,382.66 100.000% 0.065 #N/A #N/A #N/A
3 CEMENTO PORTLAND TIPO I 21 M 123,650.64 100.000% 0.087 #N/A #N/A #N/A
4 TUBERIA DE PVC 72 T 123,650.64 100.000% 0.129 #N/A #N/A #N/A
5 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 I 393,692.27 100.00% 0.277 #N/A #N/A #N/A

1,361,578.32 1.000 #N/A

SUBPRESUPUESTO: 006 RIEGO TECNIFICADO QUINUAS

PRESUPUESTO CONTRATADO: S/. 434,146.14 Exonerado del IGV

K= 0.427 Jr / Jo+ 0.060 Mr / Mo+ 0.078 Cr / Co + 0.136 Tr / To + 0.299 Ir/Io

N° ELEMENTO REPRESENTATIVO IND. SIMBOLO MONTO % INCID. COEF.


INDICES ABRIL INDICE DIC 2018
UNIF. MONOMIO INCID.
2018 Ib
I k
1 MANO DE OBRA 47 J 606,883.03 100.00% 0.427 #N/A #N/A #N/A
2 MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA 43 MMA 85,276.30 100.000% 0.060 #N/A #N/A #N/A
3 CEMENTO PORTLAND TIPO I 21 C 110,859.20 100.000% 0.078 #N/A #N/A #N/A
4 TUBERIA DE PVC 72 T 110,859.20 100.000% 0.136 #N/A #N/A #N/A
5 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 I 424,960.25 100.00% 0.299 #N/A #N/A #N/A

1,338,837.98 1.000 #N/A

SUBPRESUPUESTO: 007 RIEGO TECNIFICADO SUCA

PRESUPUESTO CONTRATADO: S/. 880,120.10 Exonerado del IGV

K= 0.460 Jr / Jo+ 0.059 Cr / Co + 0.082 Mr / Mo + 0.140 Tr / To + 0.259 Ir/Io

N° ELEMENTO REPRESENTATIVO IND. SIMBOLO MONTO % INCID. COEF.


INDICES ABRIL INDICE DIC 2018
UNIF. MONOMIO INCID.
2018 Ib
I k
1 MANO DE OBRA 47 J 404,855.25 100.00% 0.460 #N/A #N/A #N/A
2 CEMENTO PORTLAND TIPO I 21 C 51,927.09 100.000% 0.059 #N/A #N/A #N/A
3 MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA 43 M 72,169.85 100.000% 0.082 #N/A #N/A #N/A
4 TUBERIA DE PVC 72 T 123,216.81 100.000% 0.140 #N/A #N/A #N/A
5 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 I 227,951.11 100.00% 0.259 #N/A #N/A #N/A

880,120.10 1.000 #N/A


ADELANTO PARA MATERIALES N°1

FORMULAS POLINÓMICAS

OBRA : "INSTALACIÓN DEL SISTEMA DE RIEGO TECNIFICADO PARA LAS COMUNIDADES DE PALLA PALLA, VISTA ALEGRE, PARIAHUANCA, QASANCCA, QUINUAS, SUCA, CUYPAMPA, PICHUSPAMPA, CCATUN RUMI Y
LLAQHUAPAMPA DEL DISTRITO DE SAN MIGUEL, PROVINCIA LA MAR – AYACUCHO"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE LA MAR
CONTRATISTA: CONSORCIO SAN ANDRES

SUBPRESUPUESTO: 008 RIEGO TECNIFICADO CUYPAMPA

PRESUPUESTO CONTRATADO: S/. 396,412.19 Exonerado del IGV

K= 0.426 Jr / Jo+ 0.134 Cr / Co + 0.079 Mr / Mo + 0.133 Tr / To + 0.307 Ir/Io

N° ELEMENTO REPRESENTATIVO IND. SIMBOLO MONTO % INCID. COEF.


INDICES ABRIL INDICE DIC 2018
UNIF. MONOMIO INCID.
2018 Ib
I k
1 MANO DE OBRA 47 J 137,555.03 100.00% 0.347 #N/A #N/A #N/A
2 CEMENTO PORTLAND TIPO I 21 C 53,119.23 100.000% 0.134 #N/A #N/A #N/A
3 MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA 43 M 31,316.56 100.000% 0.079 #N/A #N/A #N/A
4 TUBERIA DE PVC 72 T 52,722.82 100.000% 0.133 #N/A #N/A #N/A
5 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 I 121,698.54 100.00% 0.307 #N/A #N/A #N/A

396,412.19 1.000 #N/A

SUBPRESUPUESTO: 009 RIEGO TECNIFICADO PISCHUSPAMPA

PRESUPUESTO CONTRATADO: S/. 615,600.80 Exonerado del IGV

K= 0.458 Jr / Jo+ 0.055 Cr / Co + 0.079 Mr / Mo + 0.131 Tr / To + 0.277 Ir/Io

N° ELEMENTO REPRESENTATIVO IND. SIMBOLO MONTO % INCID. COEF.


INDICES ABRIL INDICE DIC 2018
UNIF. MONOMIO INCID.
2018 Ib
I k
1 MANO DE OBRA 47 J 281,945.17 100.00% 0.458 #N/A #N/A #N/A
2 CEMENTO PORTLAND TIPO I 21 C 33,858.04 100.000% 0.055 #N/A #N/A #N/A
3 MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA 43 M 48,632.46 100.000% 0.079 #N/A #N/A #N/A
4 TUBERIA DE PVC 72 T 80,643.70 100.000% 0.131 #N/A #N/A #N/A
5 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 I 170,521.42 100.00% 0.277 #N/A #N/A #N/A

615,600.80 1.000 #N/A

SUBPRESUPUESTO: 010 RIEGO TECNIFICADO CCATUM RUMI

PRESUPUESTO CONTRATADO: S/. 290,614.38 Exonerado del IGV

K= 0.396 Jr / Jo+ 0.055 Cr / Co + 0.089 Mr / Mo + 0.121 Tr / To + 0.339 Ir/Io

N° ELEMENTO REPRESENTATIVO IND. SIMBOLO MONTO % INCID. COEF.


INDICES ABRIL INDICE DIC 2018
UNIF. MONOMIO INCID.
2018 Ib
I k
1 MANO DE OBRA 47 J 115,083.29 100.00% 0.396 #N/A #N/A #N/A
2 CEMENTO PORTLAND TIPO I 21 C 15,983.79 100.000% 0.055 #N/A #N/A #N/A
3 MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA 43 M 25,864.68 100.000% 0.089 #N/A #N/A #N/A
4 TUBERIA DE PVC 72 T 35,164.34 100.000% 0.121 #N/A #N/A #N/A
5 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 I 98,518.27 100.00% 0.339 #N/A #N/A #N/A

290,614.38 1.000 #N/A

SUBPRESUPUESTO: 011 RIEGO TECNIFICADO LLAQHUAPAMPA

PRESUPUESTO CONTRATADO: S/. 1,463,472.65 Exonerado del IGV

K= 0.472 Jr / Jo+ 0.055 Cr / Co + 0.072 Mr / Mo + 0.159 Tr / To + 0.242 Ir/Io

N° ELEMENTO REPRESENTATIVO IND. SIMBOLO MONTO % INCID. COEF.


INDICES ABRIL INDICE DIC 2018
UNIF. MONOMIO INCID.
2018 Ib
I k
1 MANO DE OBRA 47 J 690,759.09 100.00% 0.472 #N/A #N/A #N/A
2 CEMENTO PORTLAND TIPO I 21 C 80,491.00 100.000% 0.055 #N/A #N/A #N/A
3 MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA 43 M 105,370.03 100.000% 0.072 #N/A #N/A #N/A
4 TUBERIA DE PVC 72 T 232,692.15 100.000% 0.159 #N/A #N/A #N/A
5 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 I 354,160.38 100.00% 0.242 #N/A #N/A #N/A

1,463,472.65 1.000 #N/A


ADELANTO PARA MATERIALES N°1

CALCULO DE ADELANTOS MAXIMOS POR ELEMENTO REPRESENTATIVO A DICIEMBRE 2018


( SEGÚN D.S. N° 011-79-VC)

OBRA : "INSTALACIÓN DEL SISTEMA DE RIEGO TECNIFICADO PARA LAS COMUNIDADES DE PALLA PALLA, VISTA ALEGRE, PARIAHUANCA, QASANCCA, QUINUAS, SUCA, CUYPAMPA, PICHUSPAMPA, CCATUN
RUMI Y LLAQHUAPAMPA DEL DISTRITO DE SAN MIGUEL, PROVINCIA LA MAR – AYACUCHO"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE LA MAR
CONTRATISTA: CONSORCIO SAN ANDRES

INSUMOS: TUBERIA DE PVC IU


72

COEFICIENTE DE INDICE A
PRESUPUESTO DE MONTO MONTO POR INDICE BASE A MONTO MAXIMO
N° INSUMOS INCIDENCIA ELEMENTO DICIEMBE
COMPONENTE VALORIZADO VALORIZAR ABRIL 2018 PARA ADELANTO
REPRESENTATIVO 2018
01 CONDUCCION GENERAL 0.000 0.000 0.00 0.00 429.31 437.54 0.00
02 RIEGO TECNIFICADO PALLA PALLA 0.110 43,671.577 0.00 43,671.58 429.31 437.54 44,508.77
03 RIEGO TECNIFICADO VISTA ALEGRE 0.132 97,636.763 0.00 97,636.76 429.31 437.54 99,508.49
04 RIEGO TECNIFICADO PARIAHUANCA 0.156 221,718.391 78,925.76 142,792.63 429.31 437.54 145,530.01
05 RIEGO TECNIFICADO QASANCCA 0.129 73,035.321 3,693.28 69,342.04 429.31 437.54 70,671.34
06 RIEGO TECNIFICADO QUINUAS 0.136 59,043.875 0.00 59,043.88 429.31 437.54 60,175.76
07 RIEGO TECNIFICADO SUCA 0.140 123,216.814 37,314.24 85,902.58 429.31 437.54 87,549.35
08 RIEGO TECNIFICADO CUYPAMPA 0.133 52,722.821 17,300.74 35,422.08 429.31 437.54 36,101.14
09 RIEGO TECNIFICADO PICHUSPAMPA 0.131 80,643.705 22,760.57 57,883.13 429.31 437.54 58,992.77
10 RIEGO TECNIFICADO CCATUN RUMI 0.121 35,164.340 8,666.46 26,497.88 429.31 437.54 27,005.85
11 RIEGO TECNIFICADO LLAQHUAPAMPA 0.159 232,692.151 57,829.20 174,862.95 429.31 437.54 178,215.13
TOTALES 1,019,545.76 226,490.25 793,055.51 808,258.61
ADELANTO PARA MATERIALES N°1

CALCULO DE ADELANTOS MAXIMOS POR ELEMENTO REPRESENTATIVO A DICIEMBRE 2018


( SEGÚN D.S. N° 011-79-VC)

OBRA : "INSTALACIÓN DEL SISTEMA DE RIEGO TECNIFICADO PARA LAS COMUNIDADES DE PALLA PALLA, VISTA ALEGRE, PARIAHUANCA, QASANCCA, QUINUAS, SUCA, CUYPAMPA, PICHUSPAMPA, CCATUN
RUMI Y LLAQHUAPAMPA DEL DISTRITO DE SAN MIGUEL, PROVINCIA LA MAR – AYACUCHO"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE LA MAR
CONTRATISTA: CONSORCIO SAN ANDRES
INSUMOS: CEMENTO IU
21

COEFICIENTE DE INDICE A
PRESUPUESTO DE MONTO MONTO POR INDICE BASE A MONTO MAXIMO
N° INSUMOS INCIDENCIA ELEMENTO DICIEMBE
COMPONENTE VALORIZADO VALORIZAR ABRIL 2018 PARA ADELANTO
REPRESENTATIVO 2018
01 CONDUCCION GENERAL 0.156 140,224.920 174.04 140,050.88 449.56 449.56 140,050.88
02 RIEGO TECNIFICADO PALLA PALLA 0.000 0.000 0.00 0.00 449.56 449.56 0.00
03 RIEGO TECNIFICADO VISTA ALEGRE 0.073 53,996.089 0.00 53,996.09 449.56 449.56 53,996.09
04 RIEGO TECNIFICADO PARIAHUANCA 0.051 72,484.859 25,802.65 46,682.21 449.56 449.56 46,682.21
05 RIEGO TECNIFICADO QASANCCA 0.087 49,256.379 2,490.82 46,765.56 449.56 449.56 46,765.56
06 RIEGO TECNIFICADO QUINUAS 0.078 33,863.399 0.00 33,863.40 449.56 449.56 33,863.40
07 RIEGO TECNIFICADO SUCA 0.059 51,927.086 15,725.29 36,201.80 449.56 449.56 36,201.80
08 RIEGO TECNIFICADO CUYPAMPA 0.134 53,119.233 17,430.82 35,688.42 449.56 449.56 35,688.42
09 RIEGO TECNIFICADO PICHUSPAMPA 0.055 33,858.044 9,555.97 24,302.08 449.56 449.56 24,302.08
10 RIEGO TECNIFICADO CCATUN RUMI 0.055 15,983.791 3,939.30 12,044.49 449.56 449.56 12,044.49
11 RIEGO TECNIFICADO LLAQHUAPAMPA 0.055 80,490.996 20,003.81 60,487.19 449.56 449.56 60,487.19
TOTALES 585,204.80 95,122.69 490,082.10 490,082.12
ADELANTO PARA MATERIALES N°1

Comparativo de Adelanto Para Adquisición de Materiales e Insumos ( Según D.S. N° 011-79-VC)

"INSTALACIÓN DEL SISTEMA DE RIEGO TECNIFICADO PARA LAS COMUNIDADES DE PALLA PALLA, VISTA ALEGRE, PARIAHUANCA, QASANCCA, QUINUAS, SUCA, CUYPAMPA, PICHUSPAMPA, CCATUN RUMI Y LLAQHUAPAMPA DEL
Obra:
DISTRITO DE SAN MIGUEL, PROVINCIA LA MAR – AYACUCHO"
Lugar: MUNICIPALIDAD PROVINCIAL DE LA MAR

1) CHEQUEO POR PORCENTAJE


FORMULA DESCRIPCION MONTO S/.
01 CONDUCCIÓN GENERAL 898,877.69
02 RIEGO TECNIFICADO PALLA PALLA 397,014.34
03 RIEGO TECNIFICADO VISTA ALEGRE 739,672.38
04 RIEGO TECNIFICADO PARIAHUANCA 1,421,271.74
05 RIEGO TECNIFICADO QASANCCA 566,165.28
06 RIEGO TECNIFICADO QUINUAS 434,146.14
07 RIEGO TECNIFICADO SUCA 880,120.10
08 RIEGO TECNIFICADO CUYPAMPA 396,412.19
09 RIEGO TECNIFICADO PICHUSPAMPA 615,600.80
10 RIEGO TECNIFICADO CCATUN RUMI 290,614.38
11 RIEGO TECNIFICADO LLAQHUAPAMPA 1,463,472.65

COSTO DIRECTO S/. 8,103,367.69


GASTOS GENERALES FIJOS 10.00% S/. 810,336.77
UTILIDAD 6.00% S/. 486,202.06
SUB TOTAL S/. 9,399,906.52

SALDO BRUTO POR VALORIZAR - SIN IGV S/. 9,399,906.52 CON IGV
% ADELANTO SOLICITADO>>>>>>> 10.00% S/. 939,990.65 S/. 1,109,188.97

3) CHEQUEO DEL MONTO MAXIMO A OTORGAR DE ACUERDO A LAS CANTIDADES DE LOS MATERIALES
CON LOS PRECIOS DEL PRESUPUESTO BASE REFERENCIAL DEL EXPEDIENTE TECNICO
I.U. Descripción Unidad Cantidad Precio Costo Directo Monto Monto Max.
Requerida Base Del Material Solicitado Por Polinomica

TUBERIA DE PVC S/. 768,778.65 S/. 808,258.61


TEE PVC SAP Ø 110 mm x110 mm u 290.00 S/. 39.36 S/. 11,414.40
TUBERIA PVC 1 1/2" C-10 m 26,160.00 S/. 4.67 S/. 122,167.20
TUBERIA PVC 110 MM C/ANILLO C-7.5 m 5,718.00 S/. 21.86 S/. 124,995.48
TUBERIA PVC 110 MM SAP C-7.5 m 10,246.00 S/. 13.66 S/. 139,960.36
72
TUBERIA PVC 160 MM C/ANILLO C-5 m 5,221.00 S/. 36.90 S/. 192,654.90
TUBERIA PVC 63 MM C/ANILLO C-10 m 2,443.00 S/. 8.20 S/. 20,032.60
TUBERIA PVC 63 MM C/ANILLO C-7.5 m 15,087.10 S/. 5.20 S/. 78,452.91
TUBERIA PVC 75 MM C/ANILLO C-7.5 m 10,315.00 S/. 6.40 S/. 66,016.00
TUBERIA PVC 90 MM C/ANILLO C-5 m 1,363.00 S/. 9.60 S/. 13,084.80
21 CEMENTO S/. 171,212.00 S/. 490,082.12
CEMENTO PORTLAND TIPO I (42.5 kg) bls 7,444.00 S/. 23.00 S/. 171,212.00
TOTAL
ADELANTO PARA MATERIALES N°1

Comparativo de Adelanto Para Adquisición de Materiales e Insumos ( Según D.S. N° 011-79-VC)

"INSTALACIÓN DEL SISTEMA DE RIEGO TECNIFICADO PARA LAS COMUNIDADES DE PALLA PALLA, VISTA ALEGRE, PARIAHUANCA, QASANCCA, QUINUAS, SUCA, CUYPAMPA, PICHUSPAMPA, CCATUN RUMI Y LLAQHUAPAMPA DEL
Obra:
DISTRITO DE SAN MIGUEL, PROVINCIA LA MAR – AYACUCHO"
Lugar: MUNICIPALIDAD PROVINCIAL DE LA MAR

MONTO MAXIMO PARA


IU DESCRIPCIÓN ADELANTO SOLICITADO COMPARACIÓN
ADELANTO ADELANTO APROBADO
72 TUBERIA DE PVC S/. 808,258.61 S/. 768,778.65 S/. 768,778.65 CORRECTO
21 CEMENTO PORTLAND TIPO I (42.5 kg) S/. 490,082.12 S/. 171,212.00 S/. 171,212.00 CORRECTO

TOTALES S/. 1,298,340.73 S/. 939,990.65 S/. 939,990.65 10.00%

RESUMEN

Fecha de presupuesto: abr-18 Sin IGV Con IGV


Presupuesto total contratado: S/. S/. 9,399,906.52 S/. 11,091,889.69

CONCLUSIONES Y RECOMENDACIONES:
Monto Directo S/. 939,990.65
Impuesto General a la Ventas (IGV) S/. 169,198.32
Monto Total Aprobado >>>>>>>>> S/. 1,109,188.97
Porcentaje Aprobado >>>>>>>>>> 10.00%

ADELANTO PARA MATERIALES SOLICITADO FECHA DE ENTREGA MONTO S/. % Respecto al Total

Adelanto Para Materiales N°1 dic-18 S/. 1,109,188.97 10.00%


Total Acumulado S/. 1,109,188.97 10.00%

Adelanto Máximo a Otorgar según Art. 157 D.S. N° 056-2017-EF 10.00% 10.00% <= 20% ES PROCEDENTE