Академический Документы
Профессиональный Документы
Культура Документы
1.INTRODUCTION
1|Page
Eng. Waqar Ali Khan
1.1 INTRODUCTION
The purpose of this Method statement is to outline the erection procedure to be implemented
and maintained by SPECTRUM to ensure that all project activities and services are in
conformity with the client’s specifications and requirements.
In order to maintain a proper Method statement and to make sure this method is strictly
followed, the Site Engineer shall monitor the work keeping in view objectives and procedures
stated in this report and report directly to the Project Manager.
The Quality System to be followed for the MEP works shall meet the project specifications/
requirements.
2|Page
Eng. Waqar Ali Khan
3|Page
Eng. Waqar Ali Khan
2.1.1 GENERAL
After completion of the Electrical work, the complete systems shall be tested thoroughly before
commissioning.
The tests outlined herein shall be in addition to, and not substitution for, the tests of the
individual items at the manufacturer’s plant. Insulation and grounding resistance test shall be
made before operating tests. Proper rotation shall determine before permanent connections
are made.
The tests shall be conducted in the presence of the Consultant Engineer and local power
(ADWEA/ADDC) authority’s representative.
Certificates when so required shall be submitted for any equipment installed under this
contract originating by an authorized inspecting body in the country of the manufacturer.
Test shall include the following:-
4|Page
Eng. Waqar Ali Khan
5|Page
Eng. Waqar Ali Khan
6|Page
Eng. Waqar Ali Khan
7|Page
Eng. Waqar Ali Khan
(d) Result :
It’s observed that;
For healthy insulation of wires/cables, the insulation resistance value is 0.5 Mohm or
more in LV system.
For healthy insulation of wires/cables, the insulation resistance value is 0.25 Mohm or
more in SELV & PELV system.
For weak insulation of wires/cables, the insulation resistance value is less than
0.5Mohm in LV system.
(e) Quality Test Report/Specimen Form :
Please find the Test Report form in the section: 3
Polarity test is carried out to ensure that all load points (lights, sockets, etc.) which are
controlled by switches are properly connected with switches through live/phase wires
and neutral wires are directly connected to load point. In case of earth fault, RCD will
not operate if load points are connected directly to Phase/live wires and neutral wires
through switches.
(b) Instrument to be used :
The polarity test should be carried out with an instrument having a no load voltage
between 4V to 24V DC or AC and short circuit current not less than 200mA.
8|Page
Eng. Waqar Ali Khan
(e) Result :
It’s found that the single pole devices are only being connected with the live conductor
and the neutral conductors of all circuits are directly connected and continuous up to
end.
This test is carried out to ensure maximum safety against electric shock in case of direct
or indirect contact with exposed metallic parts of Electric Devices.
9|Page
Eng. Waqar Ali Khan
10 | P a g e
Eng. Waqar Ali Khan
7. Sufficient time should be allowed if special chemicals or salts are added to the
ground to improve the earth resistance values.
(e) Result :
The Earth Electrode Resistance value should be less than 1 ohm.
If a value more than 1ohm is observed, then take necessary action to achieve the
required value.
11 | P a g e
Eng. Waqar Ali Khan
12 | P a g e
Eng. Waqar Ali Khan
Earth Fault Loop Impedance Test is to be carried out to ensure that the Earth Fault Loop
Impedance is low enough to ensure enough current can flow through the circuit to
operate the protective devices(Incoming Supply) in required time.
13 | P a g e
Eng. Waqar Ali Khan
6. Matchthe EFLI value for protective devices in the circuit being tested from the below
table. As the EFLI value should not exceed the rated EFLI value tabulated in the
below table, for the safe instantaneous tripping of the protective devices (MCCBs) in
required time.
7. Select the Protective device as per the Earth Fault Loop Impedance.
(e) Result :
Please find the Earth Fault Loop Impedance Table and verify the result from the table.
For 160A MCCB, EFLI value is 0.17ohms
(f) Quality Test Report/Specimen Form :
Please find the Test Report form in the section : 3
Polarity test is carried out to ensure that all load points (lights, sockets, etc.) which are
controlled by switches are properly connected with switches through live/phase wires
and neutral wires are directly connected to load point. In case of earth fault, RCD will
not operate if load points are connected directly to Phase/live wires and neutral wires
through switches. And reverse polarity also effects the life span of electrical devices.
(b) Instrument to be used :
The polarity test should be carried out with the special instrument, Polarity Tester.
(c) Manufacture Name : (will be provided during testing)
(d) Model No. : (will be provided during testing)
(e) Calibration Certificate will be provided at the time of testing.
14 | P a g e
Eng. Waqar Ali Khan
(h) Result :
It’s found that the single pole devices are only being connected with the live conductor
and the neutral conductors of all circuits are directly connected.
Earth Fault Loop Impedance Test is to be carried out to ensure that the Earth Fault Loop
Impedance is low enough to ensure enough current can flow through the circuit to
operate the protective devices in required time. The earth fault loop impedance must
be lower than the protection devices MCB or MCCB rated earth fault loop impedance
for instantaneous tripping as shown in the table. Please refer table shown below.
15 | P a g e
Eng. Waqar Ali Khan
Earth Fault Loop Impedance Tester is to be used for calculating the Earth Fault Loop
Impedance.
Manufacture Name : (will be provided during testing)
Model No. : (will be provided during testing)
Calibration Certificate will be provided at the time of testing.
(c) Safety Precautions/Risk Assessments :
1. This test is carried out in live circuit. So necessary precautions to be taken.
2. Follow all site/municipality/PAL HSE guidelines, rules and regulations.
3. Ware proper PPE before entering to the site.
4. Avoid direct/indirect contact with the electrical live conductors and equipments.
5. Before testing, the main equipotential bonding conductors are to be disconnected.
6. Use proper tools and equipment for testing.
16 | P a g e
Eng. Waqar Ali Khan
Note : The above values are given for the conductor’s temperature at 70°C as
measurements are normally taken at room temperature. The measured values must be
approximately 20% less than tabulated values above.
(e) Result :
Earth Fault Loop Impedance value is found out and the Protective device is selected
accordingly.
The EFLI value for 10A MCB(Type B) = 4.80 ohm.
The EFLI value for 20A MCB(Type B) = 2.40 ohm.
The EFLI value for 32A MCB(Type B) = 1.50 ohm.
(f) Quality Test Report/Specimen Form :
Please find the Test Report form in the section : 3
This test is carried out to ensure that the RCDs/ELCB operate correctly on their rated
residual current rating. In this test, actually we inject the specific amount of current like
(30mA/100mA) into the circuit of RCD/ELCB and checks the tripping time of the
RCD/ELCB. A RCD/ELCB should trip within 200ms on its rated residual current in case of
earth fault. RCD devices for final circuits must have a time-current performance
characteristic complying with BS EN 61008 and BS 4293. This requires that the device
17 | P a g e
Eng. Waqar Ali Khan
must operate within 200ms at its residual current rating and within 40ms at 5 times its
residual current rating. And it must not operate below 50% of its residual current rating.
(b) Instrument to be used :
A test instrument to be used which can inject a current 5 times greater than the RCD
devices rated residual current installed and also could inject a current half of the
residual current of the RCDs.
Manufacture Name : (will be provided during testing)
Model No. : (will be provided during testing)
Calibration Certificate will be provided at the time of testing.
1.1 Plug the instrument test lead into any of the power socket of the RCD circuit.
1.2 Select the Residual current rating in the instrument. For example, 30mA or 100mA
depend upon the RCD under test.
1.3 Now set the adjustable knob of the instrument to half times of Rated current (x1/2)
and press the Test button. It will inject a current half of the Rated current selected.
1.4 Check the RCD/ELCB which should not trip on its half of rated residual current.
18 | P a g e
Eng. Waqar Ali Khan
2. Now set the adjustable knob of the instrument to one time of rated current (x1) and
Press the Test button it will trip the RCD. RCD should trip within 200ms. Check the
tripping time from the Display of instrument.
3. Five times rated current test :
3.1 Reset the RCD/ELCB into ON position.
3.2 Repeat the step number 1.1 and 1.2
3.3 Now set the adjustable knob of the instrument to five times of the Rated current
(x5) and press the test button. It will inject a current 5 times greater than the rated
current.
3.4 Now check the RCD/ELCB. It should trip the RCD/ELCB with in 40ms.
4. Manual Test Button Test :
4.1 Reset the ELCB to ON position.
4.2 Press Test button provided on the front panel of RCD. It will immediately trip the
RCD.
(e) Results :
1. RCD should not trip on its half times of rated residual current.
2. RCD must trip on its one times of rated residual current within 200ms.
3. RCD must trip on its five times of rated residual current within 40ms.
19 | P a g e
Eng. Waqar Ali Khan
20 | P a g e