Owner: Mr.

John Orven Verdote


Project: Proposed Split Residential House
Location: Maharlika Village, Taytay Rizal
Subject: Percentage Completion

To Date As of July '18


ITEM MATERIAL DESCRIPTION SCOPE OF WORKS

1 General Requirements
Permits
Mobilization/Demobilization
Management and Supervision
Supply and install
Site Enclosure
Temporary Facilities/Utilities
Bonds/Insurances

2 Site works
- excavation works
- compaction works/anchor levelling

- removal of trees/ball out Supply and install


- gravel bedding

- deliverables

3 Concrete works
- Formwork & Scaffoldings
- septic vault works
- Column and Column Footings
- Footing Tie Beam
- retaining wall
- Slab on Grade Supply and install
- Roof Deck Beam
- Second Floor Slab
- Second Floor Beam
- Roof Deck Slab
- Terrace Slab
- deliverables

4 Masonry works
- concreting works (ramps)
- 150mm CHB Wall
Supply and install
- 100mm CHB Wall
- Concrete Plastering
- deliverables

5 Metal works
- glass works and framing accessories

Supply and install


- roof framing works, steel trusses
- roof panels, insulation ,supply and install
Supply and install
- Steel Railings & Baluster
- Welding Works and masonry
- deliverables

6 Architectural works
- exterior wall works
- interior wall works
- door jambs, door and windows
Supply and install
- ceiling works paint finish
- floor finishing finish
- deliverables

7 Plumbing works
- lay out of storm drains and DS
- sewerline provisions
Supply and install
- waterline provisions
- waterproofing works
- deliverables

8 Electrical works
- riser column post
- roughing ins
- wires and cables
Supply and install
- lighting fixtures
- accessories
- deliverables

To Date Total Percentage Completion


Project Duration: target completion date December 2018
To date: 68 working days

Prepared by:

Engr. Sherwin Glenn G. Saraza


UNIT QUANTITY PREVIOUS TO DATE REMARKS

lot 1 0.0% 100.0% completed


lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% on going
lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% Manpower Group insurance

cu.m. 366.1 0.0% 30.0% on going works

cu.m. on going works


145 0.0% 15.0%
lot 1 0.0% 35.0% on going works
cu.m. 55 0.0% 5.0% on going works
lot 1 0.0% 5.0%

lot 1 0.0% 10.0% on going works


lot 1 0.0% 10.0% on going works
sq.m. 40.5 0.0% 38.0% preparation works
sq.m. 19.2 0.0% 25.0% on going works
sq.m. 63.9 0.0% 10.0% on going works
sq.m. 52.5 0.0% 10.0% on going works
sq.m. 20.4 0.0% 0.0%
sq.m. 33.5 0.0% 0.0%
sq.m. 23.2 0.0% 0.0%
sq.m. 127.5 0.0% 0.0%
sq.m. 16.7 0.0% 0.0%
lot 1 0.0% 25.0%

sq.m. 88.5 0.0% 5.0% on going works


sq.m. 9.72 0.0% 5.0% on going works
sq.m. 279.2 0.0% 0.0%
sq.m. 379.2 0.0% 0.0%
lot 1 0.0% 5.0%

lot 1 0.0% 0.0%


lot 1 0.0% 0.0%

lot 1 0.0% 0.0%

sq.m. 48.4 0.0% 0.0%


sq.m. 182.5 0.0% 0.0%
lot 1 0.0% 0.0%
sq.m. 173.8 0.0% 0.0%
sq.m. 252.5 0.0% 0.0%
lot 1 0.0% 0.0%

lot 1 0.0% 0.0%


lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%

lot 1 0.0% 90.0%


lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%

0.0% 24.3%

Noted by:

Ebeth B. Betonio
Owner: Mr. John Orven Verdote
Project: Proposed Split Residential House
Location: Maharlika Village, Taytay Rizal
Subject: Percentage Completion

To Date As of August '18


ITEM MATERIAL DESCRIPTION SCOPE OF WORKS

1 General Requirements
Permits
Mobilization/Demobilization
Management and Supervision
Supply and install
Site Enclosure
Temporary Facilities/Utilities
Bonds/Insurances

2 Site works
- excavation works
- compaction works/anchor levelling

- removal of trees/ball out Supply and install


- gravel bedding

- deliverables

3 Concrete works
- Formwork & Scaffoldings
- septic vault works
- Column and Column Footings
- Footing Tie Beam
- retaining wall
- Slab on Grade Supply and install
- Roof Deck Beam
- Second Floor Slab
- Second Floor Beam
- Roof Deck Slab
- Terrace Slab
- deliverables

4 Masonry works
- concreting works (ramps)
- 150mm CHB Wall
Supply and install
- 100mm CHB Wall
- Concrete Plastering
- deliverables

5 Metal works
- glass works and framing accessories

Supply and install


- roof framing works, steel trusses
- roof panels, insulation ,supply and install
Supply and install
- Steel Railings & Baluster
- Welding Works and masonry
- deliverables

6 Architectural works
- exterior wall works
- interior wall works
- door jambs, door and windows
Supply and install
- ceiling works paint finish
- floor finishing finish
- deliverables

7 Plumbing works
- lay out of storm drains and DS
- sewerline provisions
Supply and install
- waterline provisions
- waterproofing works
- deliverables

8 Electrical works
- riser column post
- roughing ins
- wires and cables
Supply and install
- lighting fixtures
- accessories
- deliverables

To Date Total Percentage Completion


Project Duration: target completion date December 2018
To date: 68 working days

Prepared by:

Engr. Sherwin Glenn G. Saraza


UNIT QUANTITY PREVIOUS TO DATE REMARKS

lot 1 0.0% 100.0% completed


lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% on going
lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% Manpower Group insurance

cu.m. 366.1 0.0% 83.0% on going works

cu.m. on going works


145 0.0% 31.0%
lot 1 0.0% 61.0% on going works
cu.m. 55 0.0% 18.0% on going works
lot 1 0.0% 16.0%

lot 1 0.0% 19.0% on going works


lot 1 0.0% 27.0% on going works
sq.m. 40.5 0.0% 49.0% preparation works
sq.m. 19.2 0.0% 37.0% on going works
sq.m. 63.9 0.0% 17.0% on going works
sq.m. 52.5 0.0% 28.0% on going works
sq.m. 20.4 0.0% 0.0%
sq.m. 33.5 0.0% 0.0%
sq.m. 23.2 0.0% 0.0%
sq.m. 127.5 0.0% 0.0%
sq.m. 16.7 0.0% 0.0%
lot 1 0.0% 25.0%

sq.m. 88.5 0.0% 12.0% on going works


sq.m. 9.72 0.0% 10.0% on going works
sq.m. 279.2 0.0% 0.0%
sq.m. 379.2 0.0% 0.0%
lot 1 0.0% 18.0%

lot 1 0.0% 0.0%


lot 1 0.0% 0.0%

lot 1 0.0% 0.0%

sq.m. 48.4 0.0% 0.0%


sq.m. 182.5 0.0% 0.0%
lot 1 0.0% 0.0%
sq.m. 173.8 0.0% 0.0%
sq.m. 252.5 0.0% 0.0%
lot 1 0.0% 0.0%

lot 1 0.0% 8.0%


lot 1 0.0% 7.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 6.0%

lot 1 0.0% 100.0%


lot 1 0.0% 5.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 17.0%

0.0% 31.4%

Noted by:

Ebeth B. Betonio
Owner: Mr. John Orven Verdote
Project: Proposed Split Residential House
Location: Maharlika Village, Taytay Rizal
Subject: Percentage Completion

To Date As of August '18


ITEM MATERIAL DESCRIPTION SCOPE OF WORKS

1 General Requirements
Permits
Mobilization/Demobilization
Management and Supervision
Supply and install
Site Enclosure
Temporary Facilities/Utilities
Bonds/Insurances

2 Site works
- excavation works
- compaction works/anchor levelling

- removal of trees/ball out Supply and install


- gravel bedding

- deliverables

3 Concrete works
- Formwork & Scaffoldings
- septic vault works
- Column and Column Footings
- Footing Tie Beam
- retaining wall
- Slab on Grade Supply and install
- Roof Deck Beam
- Second Floor Slab
- Second Floor Beam
- Roof Deck Slab
- Terrace Slab
- deliverables

4 Masonry works
- concreting works (ramps)
- 150mm CHB Wall
Supply and install
- 100mm CHB Wall
- Concrete Plastering
- deliverables

5 Metal works
- glass works and framing accessories

Supply and install


- roof framing works, steel trusses
- roof panels, insulation ,supply and install
Supply and install
- Steel Railings & Baluster
- Welding Works and masonry
- deliverables

6 Architectural works
- exterior wall works
- interior wall works
- door jambs, door and windows
Supply and install
- ceiling works paint finish
- floor finishing finish
- deliverables

7 Plumbing works
- lay out of storm drains and DS
- sewerline provisions
Supply and install
- waterline provisions
- waterproofing works
- deliverables

8 Electrical works
- riser column post
- roughing ins
- wires and cables
Supply and install
- lighting fixtures
- accessories
- deliverables

To Date Total Percentage Completion


Project Duration: target completion date December 2018
To date: 68 working days

Prepared by:

Engr. Sherwin Glenn G. Saraza


UNIT QUANTITY PREVIOUS TO DATE REMARKS

lot 1 0.0% 100.0% completed


lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% on going
lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% Manpower Group insurance

cu.m. 366.1 0.0% 90.0% on going works

cu.m. on going works


145 0.0% 65.0%
lot 1 0.0% 72.0% on going works
cu.m. 55 0.0% 35.0% on going works
lot 1 0.0% 39.0%

lot 1 0.0% 42.0% on going works


lot 1 0.0% 100.0% on going works
sq.m. 40.5 0.0% 56.0% preparation works
sq.m. 19.2 0.0% 76.0% on going works
sq.m. 63.9 0.0% 100.0% on going works
sq.m. 52.5 0.0% 49.0% on going works
sq.m. 20.4 0.0% 0.0%
sq.m. curing
33.5 0.0% 72.0%
sq.m. curing
23.2 0.0% 85.0%
sq.m. 127.5 0.0% 0.0%
sq.m. 16.7 0.0% 0.0%
lot 1 0.0% 55.0%

sq.m. 88.5 0.0% 21.0% on going works


sq.m. 9.72 0.0% 22.0% on going works
sq.m. 279.2 0.0% 0.0%
sq.m. 379.2 0.0% 0.0%
lot 1 0.0% 26.0%

lot 1 0.0% 0.0%


lot 1 0.0% 0.0%

lot 1 0.0% 0.0%

sq.m. 48.4 0.0% 0.0%


sq.m. 182.5 0.0% 0.0%
lot 1 0.0% 0.0%
sq.m. 173.8 0.0% 0.0%
sq.m. 252.5 0.0% 0.0%
lot 1 0.0% 0.0%

lot 1 0.0% 15.0%


lot 1 0.0% 12.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 9.0%

lot 1 0.0% 100.0% completed August '18


lot 1 0.0% 5.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 17.0%

0.0% 46.4%

Noted by:

Ebeth B. Betonio
Owner: Mr. John Orven Verdote
Project: Proposed Split Residential House
Location: Maharlika Village, Taytay Rizal
Subject: Percentage Completion

To Date As of October '18


ITEM MATERIAL DESCRIPTION SCOPE OF WORKS

1 General Requirements
Permits
Mobilization/Demobilization
Management and Supervision
Supply and install
Site Enclosure
Temporary Facilities/Utilities
Bonds/Insurances

2 Site works
- excavation works
- compaction works/anchor levelling

- removal of trees/ball out Supply and install


- gravel bedding

- deliverables

3 Concrete works
- Formwork & Scaffoldings
- septic vault works
- Column and Column Footings
- Footing Tie Beam
- retaining wall
- Slab on Grade Supply and install
- Roof Deck Beam
- Second Floor Slab
- Second Floor Beam
- Roof Deck Slab
- Terrace Slab
- deliverables

4 Masonry works
- concreting works (ramps)
- 150mm CHB Wall
Supply and install
- 100mm CHB Wall
- Concrete Plastering
- deliverables

5 Metal works
- glass works and framing accessories

Supply and install


- roof framing works, steel trusses
- roof panels, insulation ,supply and install
Supply and install
- Steel Railings & Baluster
- Welding Works and masonry
- deliverables

6 Architectural works
- exterior wall works
- interior wall works
- door jambs, door and windows
Supply and install
- ceiling works paint finish
- floor finishing finish
- deliverables

7 Plumbing works
- lay out of storm drains and DS
- sewerline provisions
Supply and install
- waterline provisions
- waterproofing works
- deliverables

8 Electrical works
- riser column post
- roughing ins
- wires and cables
Supply and install
- lighting fixtures
- accessories
- deliverables

To Date Total Percentage Completion


Project Duration: target completion date December 2018
To date: 68 working days

Prepared by:

Engr. Sherwin Glenn G. Saraza


UNIT QUANTITY PREVIOUS TO DATE REMARKS

lot 1 0.0% 100.0% completed


lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% on going
lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% completed
lot 1 0.0% 100.0% Manpower Group insurance

cu.m. 366.1 0.0% 95.0% on going works

cu.m. on going works


145 0.0% 75.0%
lot 1 0.0% 85.0% on going works
cu.m. 55 0.0% 45.0% on going works
lot 1 0.0% 43.0%

lot 1 0.0% 52.0% on going works


lot 1 0.0% 100.0% on going works
sq.m. 40.5 0.0% 65.0% preparation works
sq.m. 19.2 0.0% 85.0% on going works
sq.m. 63.9 0.0% 100.0% on going works
sq.m. 52.5 0.0% 52.0% on going works
sq.m. 20.4 0.0% 15.0%
sq.m. curing
33.5 0.0% 75.0%
sq.m. curing
23.2 0.0% 85.0%
sq.m. 127.5 0.0% 0.0%
sq.m. 16.7 0.0% 0.0%
lot 1 0.0% 65.0%

sq.m. 88.5 0.0% 35.0% on going works


sq.m. 9.72 0.0% 55.0% on going works
sq.m. 279.2 0.0% 45.0%
sq.m. 379.2 0.0% 10.0%
lot 1 0.0% 35.0%

lot 1 0.0% 0.0%


lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%

sq.m. 48.4 0.0% 25.0%


sq.m. 182.5 0.0% 5.0%
lot 1 0.0% 0.0%
sq.m. 173.8 0.0% 0.0%
sq.m. 252.5 0.0% 0.0%
lot 1 0.0% 10.0%

lot 1 0.0% 25.0%


lot 1 0.0% 18.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 15.0%

lot 1 0.0% 100.0% completed August '18


lot 1 0.0% 5.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 0.0%
lot 1 0.0% 17.0%

0.0% 53.6%