Вы находитесь на странице: 1из 5

“MEJORAMIENTO DEL SERVICIO RECREATIVO EN EL PARQUE SAN MARTIN DE PORRES DE LA

PROYECTO URB. LA RINCONADA 2DA ETAPA, DISTRITO DE TRUJILLO, PROVINCIA DE TRUJILLO - LA


LIBERTAD”
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TRUJILLO

UBICACIÓN : DISTRITO: TRUJILLO - PROVINCIA: TRUJILLO - DEPARTAMENTO: LIBERTAD

PLAZO DE EJECUCION : 120 DIAS CALENDARIOS

MES 01 MES 02 MES 03 MES 04 ACUMULADO


Item Descripción Und. MetradoPrecio (S/.) Parcial (S/.)
MET. VAL. % MET. VAL. % MET. VAL. % MET. VAL. % MET. VAL.
01 OBRAS PROVISIONALES S/. 10,914.41
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS GLB 1 3000 S/. 3,000.00 1.00 3,000.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,000.00
01.02 CARTEL DE OBRA DE 6.00x3.60 m. und 1 1867.32 S/. 1,867.32 1.00 1,867.32 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,867.32
01.03 INSTALACION DE CERCO PERIMETRICO CON MALLA RASCHEL m 343 17.63 S/. 6,047.09 343.00 6,047.09 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 343.00 6,047.09
02 VEREDAS Y PISOS S/. 353,893.52
02.01 TRABAJOS PRELIMINARES S/. 24,571.66
02.01.01 DEMOLICION DE VEREDAS Y PISOS DE CONCRETO A PULSO, e=10 cm. m2 1323.4 14.53 S/. 19,229.00 1,323.40 19,229.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,323.40 19,229.00
02.01.02 DEMOLICION DE ESTRUCTURAS DE CONCRETO A PULSO m3 10.92 135.84 S/. 1,483.37 10.92 1,483.37 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.92 1,483.37
02.01.03 TRAZO Y REPLANTEO EN VEREDAS Y PISOS m2 1889.27 0.7 S/. 1,322.49 1,889.27 1,322.49 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,889.27 1,322.49
02.01.04 REUBICACION DE POSTES DE ALUMBRADO PUBLICO und 7 362.4 S/. 2,536.80 7.00 2,536.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 2,536.80
02.02 MOVIMIENTO DE TIERRAS S/. 104,033.54
02.02.01 CORTE EN TERRENO NATURAL PARA VEREDAS Y PISOS, H PROM = 0.35M - MANUAL m2 1838.23 14.53 S/. 26,709.48 1,470.58 21,367.58 80.00% 367.65 5,341.90 20.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,838.23 26,709.48
02.02.02 ELIMINACION MATERIAL EXCEDENTE C/ESPONJAMIENTO, MANUAL., Dist. Min. = 7Km. m3 1114.31 25.69 S/. 28,626.62 557.16 14,313.31 50.00% 557.16 14,313.31 50.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,114.31 28,626.62
02.02.03 PERFILADO, NIVELACION Y COMPACTACION EN SUB-RASANTE PARA PISOS Y VEREDAS. m2 1838.23 3.48 S/. 6,397.04 0.00 0.00 0.00% 1,838.23 6,397.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,838.23 6,397.04
02.02.04 SUB BASE PARA PISOS Y VEREDAS, e=15cm m2 1838.23 12.73 S/. 23,400.67 0.00 0.00 0.00% 1,838.23 23,400.67 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,838.23 23,400.67
02.02.05 BASE PARA PISOS Y VEREDAS, e=10cm m2 1838.23 9.72 S/. 17,867.60 0.00 0.00 0.00% 1,838.23 17,867.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,838.23 17,867.60
02.02.06 CAMA DE ARENA PARA ADOQUIN 0.04 M m2 452.69 2.28 S/. 1,032.13 0.00 0.00 0.00% 226.35 516.07 50.00% 226.35 516.07 50.00% 0.00 0.00 0.00% 452.69 1,032.13
02.03 VEREDAS S/. 33,313.25
02.03.01 VEREDA, e=4" CONCRETO f'c=175 Kg/cm2, a=1.50 m. dos uñas. m2 504.79 64.64 S/. 32,629.63 0.00 0.00 0.00% 504.79 32,629.63 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 504.79 32,629.63
02.03.02 CURADO DE VEREDAS CON CURADOR QUIMICO m2 504.79 0.88 S/. 444.22 0.00 0.00 0.00% 504.79 444.22 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 504.79 444.22
02.03.03 JUNTAS DE DILATACION EN VEREDAS, e=1/2" m 90 2.66 S/. 239.40 0.00 0.00 0.00% 90.00 239.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 90.00 239.40
02.04 PISOS S/. 191,975.07
02.04.01 PISO PORCELANATO S/. 146,639.38
02.04.01.ENCOFRADO Y DESENCOFRADO PARA FALSO PISO m2 178.01 36.16 S/. 6,436.84 0.00 0.00 0.00% 178.01 6,436.84 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 178.01 6,436.84
02.04.01.FALSO PISO CON CONCRETO F'C=175 KG/CM2. m2 931.79 48.61 S/. 45,294.31 0.00 0.00 0.00% 931.79 45,294.31 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 931.79 45,294.31
02.04.01.CONTRAPISO DE 40 mm m2 931.79 28.26 S/. 26,332.39 0.00 0.00 0.00% 931.79 26,332.39 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 931.79 26,332.39
02.04.01.PISO DE PORCELANATO ALTO TRANSITO DE 0.60x0.60 cm. MATE COLOR GRIS m2 319.3 65.52 S/. 20,920.54 0.00 0.00 0.00% 0.00 0.00 0.00% 319.30 20,920.54 100.00% 0.00 0.00 0.00% 319.30 20,920.54
02.04.01.PISO DE PORCELANATO ALTO TRANSITO DE 0.60x0.60 cm. MATE COLOR MARRÓN m2 607.89 66.4 S/. 40,363.90 0.00 0.00 0.00% 0.00 0.00 0.00% 607.89 40,363.90 100.00% 0.00 0.00 0.00% 607.89 40,363.90
02.04.01.PISO DE PORCELANATO ALTO TRANSITO DE 0.60x0.60 cm. MATE COLOR BEIGE m2 4.63 63.45 S/. 293.77 0.00 0.00 0.00% 0.00 0.00 0.00% 4.63 293.77 100.00% 0.00 0.00 0.00% 4.63 293.77
02.04.01.CANTONERA EN PISOS DE PORCELANATO m 395.57 17.69 S/. 6,997.63 0.00 0.00 0.00% 0.00 0.00 0.00% 395.57 6,997.63 100.00% 0.00 0.00 0.00% 395.57 6,997.63
02.04.02 PISO ADOQUIN S/. 45,335.69
02.04.02.SARDINEL 0.15xX0.30 M DE CONCRETO F'C=175 KG/CM2 m 349.51 34.57 S/. 12,082.56 0.00 0.00 0.00% 349.51 12,082.56 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 349.51 12,082.56
02.04.02.ENCOFRADO Y DESENCOFRADO EN SARDINELES m2 209.71 23.35 S/. 4,896.73 0.00 0.00 0.00% 209.71 4,896.73 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 209.71 4,896.73
02.04.02.JUNTAS DE DILATACION EN SARDINELES, e=1/2" m 13.2 4.37 S/. 57.68 0.00 0.00 0.00% 13.20 57.68 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.20 57.68
02.04.02.PISO DE ADOQUIN DE CONCRETO 20X10X4 CM m2 452.49 62.54 S/. 28,298.72 0.00 0.00 0.00% 226.25 14,149.36 50.00% 226.25 14,149.36 50.00% 0.00 0.00 0.00% 452.49 28,298.72
03 LOSA DEPORTIVA S/. 492,863.29
03.01 TRABAJOS PRELIMINARES S/. 8,459.46
03.01.01 DEMOLICION DE LOSA DEPORTIVA DE CONCRETO A PULSO, e=10 cm. m2 509.31 14.53 S/. 7,400.27 509.31 7,400.27 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 509.31 7,400.27
03.01.02 DESMONTAJE DE ARCOS DE FULBITO und 2 90.87 S/. 181.74 2.00 181.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 181.74
03.01.03 DESMONTAJE DE JUEGOS RECREATIVOS und 5 175.49 S/. 877.45 5.00 877.45 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 877.45
03.02 MOVIMIENTO DE TIERRAS S/. 220,810.81
03.02.01 CORTE EN TERRENO NATURAL - MANUAL m3 2121.33 48.45 S/. 102,778.44 1,060.67 51,389.22 50.00% 1,060.67 51,389.22 50.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,121.33 102,778.44
“MEJORAMIENTO DEL SERVICIO RECREATIVO EN EL PARQUE SAN MARTIN DE PORRES DE LA
PROYECTO URB. LA RINCONADA 2DA ETAPA, DISTRITO DE TRUJILLO, PROVINCIA DE TRUJILLO - LA
LIBERTAD”
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TRUJILLO

UBICACIÓN : DISTRITO: TRUJILLO - PROVINCIA: TRUJILLO - DEPARTAMENTO: LIBERTAD

PLAZO DE EJECUCION : 120 DIAS CALENDARIOS

MES 01 MES 02 MES 03 MES 04 ACUMULADO


Item Descripción Und. MetradoPrecio (S/.) Parcial (S/.)
MET. VAL. % MET. VAL. % MET. VAL. % MET. VAL. % MET. VAL.
03.02.02 RELLENO CON MATERIAL DE PRESTAMO m3 215.74 56.82 S/. 12,258.35 0.00 0.00 0.00% 0.00 0.00 0.00% 215.74 12,258.35 100.00% 0.00 0.00 0.00% 215.74 12,258.35
03.02.03 ELIMINACION MATERIAL EXCEDENTE C/ESPONJAMIENTO, MANUAL., Dist. Min. = 7Km. m3 2864.69 25.69 S/. 73,593.89 1,432.35 36,796.95 50.00% 1,432.35 36,796.95 50.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,864.69 73,593.89
03.02.04 PERFILADO, NIVELACION Y COMPACTACION EN SUB-RASANTE PARA LOSA DEPORTIVA m2 1342.22 3.48 S/. 4,670.93 0.00 0.00 0.00% 1,342.22 4,670.93 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,342.22 4,670.93
03.02.05 SUB BASE PARA LOSA DEPORTIVA e=15 cm m2 959.2 16.05 S/. 15,395.16 0.00 0.00 0.00% 959.20 15,395.16 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 959.20 15,395.16
03.02.06 BASE PARA LOSA DEPORTIVA e=10 cm m2 1246.3 9.72 S/. 12,114.04 0.00 0.00 0.00% 1,246.30 12,114.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,246.30 12,114.04
03.03 MUROS DE CONTENCION S/. 147,518.72
03.03.01 CONCRETO F'C= 210 KG/CM2 PARA MURO DE CONTENCION m3 139.87 487.54 S/. 68,192.22 0.00 0.00 0.00% 27.97 13,638.44 20.00% 111.90 54,553.78 80.00% 0.00 0.00 0.00% 139.87 68,192.22
03.03.02 ENCOFRADO Y DESENCOFRADO PARA MURO DE CONTENCION m2 690.6 65.59 S/. 45,296.45 0.00 0.00 0.00% 690.60 45,296.45 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 690.60 45,296.45
03.03.03 ACERO DE REFUERZO F'Y= 4200 KG/CM2 kg 8444.18 4.03 S/. 34,030.05 0.00 0.00 0.00% 1,688.84 6,806.01 20.00% 6,755.34 27,224.04 80.00% 0.00 0.00 0.00% 8,444.18 34,030.05
03.04 LOSA DEPORTIVA S/. 53,071.86
03.04.01 LOSA DEPORTIVA DE CONCRETO f'c=175 Kg/cm2, e=4" m2 959.2 53.36 S/. 51,182.91 0.00 0.00 0.00% 767.36 40,946.33 80.00% 191.84 10,236.58 20.00% 0.00 0.00 0.00% 959.20 51,182.91
03.04.02 JUNTAS DE DILATACION EN LOSA DEPORTIVA , e=1/2" m 392.8 2.66 S/. 1,044.85 0.00 0.00 0.00% 0.00 0.00 0.00% 392.80 1,044.85 100.00% 0.00 0.00 0.00% 392.80 1,044.85
03.04.03 CURADO DE LOSAS CON CURADOR QUIMICO m2 959.2 0.88 S/. 844.10 0.00 0.00 0.00% 0.00 0.00 0.00% 959.20 844.10 100.00% 0.00 0.00 0.00% 959.20 844.10
03.05 CARPINTERIA METALICA S/. 12,695.94
03.05.01 BARANDA METALICA m 34.4 173.14 S/. 5,956.02 0.00 0.00 0.00% 0.00 0.00 0.00% 34.40 5,956.02 100.00% 0.00 0.00 0.00% 34.40 5,956.02
03.05.02 MALLA GALVANIZADA DE PROTECCION COCADA 2"x2" m 52.8 127.65 S/. 6,739.92 0.00 0.00 0.00% 0.00 0.00 0.00% 52.80 6,739.92 100.00% 0.00 0.00 0.00% 52.80 6,739.92
03.06 GRADERIAS S/. 48,390.59
03.06.01 ENCOFRADO Y DESENCOFRADO PARA GRADERIAS m2 363 45.29 S/. 16,440.27 0.00 0.00 0.00% 272.25 12,330.20 75.00% 90.75 4,110.07 25.00% 0.00 0.00 0.00% 363.00 16,440.27
03.06.02 GRADERIA CON CONCRETO f'c=175 Kg/cm2 m3 75.9 311.4 S/. 23,635.26 0.00 0.00 0.00% 0.00 0.00 0.00% 75.90 23,635.26 100.00% 0.00 0.00 0.00% 75.90 23,635.26
03.06.03 ACERO DE REFUERZO fy=4200 Kg/cm2 kg 2063.29 4.03 S/. 8,315.06 0.00 0.00 0.00% 0.00 0.00 0.00% 2,063.29 8,315.06 100.00% 0.00 0.00 0.00% 2,063.29 8,315.06
03.07 PINTURA S/. 1,915.91
03.07.01 PINTURA PARA DEMARCACION DE LOSA DEPORTIVA m 338.5 5.66 S/. 1,915.91 0.00 0.00 0.00% 0.00 0.00 0.00% 338.50 1,915.91 100.00% 0.00 0.00 0.00% 338.50 1,915.91
04 SARDINELES Y JARDINERAS S/. 62,840.78
04.01 TRABAJOS PRELIMINARES S/. 2,349.87
04.01.01 DEMOLICION DE SARDINELES DE CONCRETO A PULSO m 295.35 7.26 S/. 2,144.24 295.35 2,144.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 295.35 2,144.24
04.01.02 TRAZO Y REPLANTEO EN SARDINELES m 302.39 0.68 S/. 205.63 302.39 205.63 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 302.39 205.63
04.02 MOVIMIENTO DE TIERRAS S/. 1,823.61
04.02.01 EXCAVACION DE ZANJAS PARA SARDINELES m 302.39 2.42 S/. 731.78 302.39 731.78 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 302.39 731.78
04.02.02 ELIMINACION MATERIAL EXCEDENTE C/ESPONJAMIENTO, MANUAL., Dist. Min. = 7Km. m3 42.5 25.69 S/. 1,091.83 42.50 1,091.83 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 42.50 1,091.83
04.03 SARDINELES S/. 17,509.46
04.03.01 SARDINEL 0.15X0.40 M DE CONCRETO F'C=175 KG/CM2 m 302.39 35.03 S/. 10,592.72 302.39 10,592.72 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 302.39 10,592.72
04.03.02 ENCOFRADO Y DESENCOFRADO PARA SARDINELES m2 241.91 28.37 S/. 6,862.99 241.91 6,862.99 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 241.91 6,862.99
04.03.03 JUNTAS DE DILATACION EN SARDINELES, e=1/2" m 12.3 4.37 S/. 53.75 12.30 53.75 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.30 53.75
04.04 JARDINERAS S/. 41,157.84
04.04.01 ENCOFRADO Y DESENCOFRADO PARA JARDINERAS m2 319.66 61.05 S/. 19,515.24 319.66 19,515.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 319.66 19,515.24
04.04.02 JARDINERAS DE CONCRETO F'C=210 KG/CM2 m3 15.98 322.51 S/. 5,153.71 15.98 5,153.71 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.98 5,153.71
04.04.03 ACERO DE REFUERZO F'Y= 4200 KG/CM2 kg 758.47 4.03 S/. 3,056.63 758.47 3,056.63 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 758.47 3,056.63
04.04.04 TARRAJEO CON IMPERMEABILIAZANTE PARA JARDINERAS m2 159.83 31.6 S/. 5,050.63 159.83 5,050.63 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 159.83 5,050.63
04.04.05 VESTIDURA DE DERRAMES DE JARDINERAS m 145.3 14.4 S/. 2,092.32 145.30 2,092.32 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 145.30 2,092.32
04.04.06 TARRAJEO TIPO RASPIÑADO EN PAREDES DE JARDINERAS m2 159.83 39.35 S/. 6,289.31 159.83 6,289.31 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 159.83 6,289.31
05 AREA VERDE S/. 97,742.89
05.01 PERFILADO, NIVELACION EN SUB-RASANTE PARA AREAS VERDES. m2 2996.41 3.07 S/. 9,198.98 0.00 0.00 0.00% 0.00 0.00 0.00% 2,097.49 6,439.29 70.00% 898.92 2,759.69 30.00% 2,996.41 9,198.98
“MEJORAMIENTO DEL SERVICIO RECREATIVO EN EL PARQUE SAN MARTIN DE PORRES DE LA
PROYECTO URB. LA RINCONADA 2DA ETAPA, DISTRITO DE TRUJILLO, PROVINCIA DE TRUJILLO - LA
LIBERTAD”
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TRUJILLO

UBICACIÓN : DISTRITO: TRUJILLO - PROVINCIA: TRUJILLO - DEPARTAMENTO: LIBERTAD

PLAZO DE EJECUCION : 120 DIAS CALENDARIOS

MES 01 MES 02 MES 03 MES 04 ACUMULADO


Item Descripción Und. MetradoPrecio (S/.) Parcial (S/.)
MET. VAL. % MET. VAL. % MET. VAL. % MET. VAL. % MET. VAL.
05.02 RELLENO CON TIERRA DE CHACRA EN AREAS VERDES e=0.10 mts (material de prestamo) m2 2996.41 7.54 S/. 22,592.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,996.41 22,592.93 100.00% 2,996.41 22,592.93
05.03 PREPARACION DE TIERRA DE CHACRA INCLUYE FERTILIZANTES m2 2996.41 6.7 S/. 20,075.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,996.41 20,075.95 100.00% 2,996.41 20,075.95
05.04 SEMBRADO DE GRASS NATURAL POR BLOQUES (25x25 CM) m2 2996.41 15.03 S/. 45,036.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,996.41 45,036.04 100.00% 2,996.41 45,036.04
05.05 RIEGO DE GRASS CON MANGUERA m2 2996.41 0.28 S/. 838.99 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,996.41 838.99 100.00% 2,996.41 838.99
06 MODULOS Y MOBILIARIOS PARA PARQUES S/. 86,942.27
06.01 MOVIMIENTO DE TIERRAS S/. 172.98
06.01.01 EXCAVACION DE ZANJAS PARA DADOS DE CONCRETO m3 4.76 36.34 S/. 172.98 0.00 0.00 0.00% 0.00 0.00 0.00% 4.76 172.98 100.00% 0.00 0.00 0.00% 4.76 172.98
06.02 CONCRETO SIMPLE S/. 3,545.58
06.02.01 DADOS DE CONCRETO EN JUEGOS RECREATIVOS f'c=175 KG/CM2 m3 4.76 405.6 S/. 1,930.66 0.00 0.00 0.00% 0.00 0.00 0.00% 4.76 1,930.66 100.00% 0.00 0.00 0.00% 4.76 1,930.66
06.02.02 BASES PARA BANCAS Y TACHOS DE BASURA CONCRETO f'c=175 Kg/cm2, e=4" m2 26.64 60.62 S/. 1,614.92 0.00 0.00 0.00% 0.00 0.00 0.00% 26.64 1,614.92 100.00% 0.00 0.00 0.00% 26.64 1,614.92
06.03 MODULOS PARA PARQUES S/. 12,722.41
06.03.01 PERGOLA CENTRAL SEGUN DISEÑO und 1 12722.4 S/. 12,722.41 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 12,722.41 100.00% 0.00 0.00 0.00% 1.00 12,722.41
06.04 MOBILIARIO PARA PARQUES S/. 37,288.84
06.04.01 BANCA DE MADERA Y FIERRO FUNDIDO SEGUN DISEÑO und 6 1222.14 S/. 7,332.84 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 7,332.84 100.00% 0.00 0.00 0.00% 6.00 7,332.84
06.04.02 BANCA DE MADERA Y CONCRETO und 26 801.88 S/. 20,848.88 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 20,848.88 100.00% 0.00 0.00 0.00% 26.00 20,848.88
06.04.03 BANQUETA DE CONCRETO F'C=175 KG/CM2 und 8 447.39 S/. 3,579.12 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 3,579.12 100.00% 0.00 0.00 0.00% 8.00 3,579.12
06.04.04 TACHO DE BASURA SEGUN DISEÑO und 16 345.5 S/. 5,528.00 0.00 0.00 0.00% 0.00 0.00 0.00% 16.00 5,528.00 100.00% 0.00 0.00 0.00% 16.00 5,528.00
06.05 MAQUINA PARA EJERCICIOS S/. 17,674.35
06.05.01 SUMINISTRO E INSTALACION DE MAQUINA DE EJERCICIOS – BANCA ABDOMINALES und 1 3293.61 S/. 3,293.61 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,293.61 100.00% 0.00 0.00 0.00% 1.00 3,293.61
06.05.02 SUMINISTRO E INSTALACION DE MAQUINA DE EJERCICIOS – ELIPTICA und 1 8498.89 S/. 8,498.89 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 8,498.89 100.00% 0.00 0.00 0.00% 1.00 8,498.89
06.05.03 SUMINISTRO E INSTALACION DE MAQUINA DE EJERCICIOS – CAMINADORES und 1 5881.85 S/. 5,881.85 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,881.85 100.00% 0.00 0.00 0.00% 1.00 5,881.85
06.06 JUEGOS INFANTILES S/. 15,538.11
06.06.01 SUMINISTRO E INSTALACION DE JUEGOS RECREATIVOS – CARRUSEL und 1 4890 S/. 4,890.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,890.00 100.00% 0.00 0.00 0.00% 1.00 4,890.00
06.06.02 SUMINISTRO E INSTALACION DE JUEGOS RECREATIVOS – COLUMPIO und 1 2832.65 S/. 2,832.65 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,832.65 100.00% 0.00 0.00 0.00% 1.00 2,832.65
06.06.03 SUMINISTRO E INSTALACION DE JUEGOS RECREATIVOS – BALANCIN und 1 2612.5 S/. 2,612.50 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,612.50 100.00% 0.00 0.00 0.00% 1.00 2,612.50
06.06.04 SUMINISTRO E INSTALACION DE JUEGOS RECREATIVOS – TOBOGAN und 1 5202.96 S/. 5,202.96 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,202.96 100.00% 0.00 0.00 0.00% 1.00 5,202.96
07 VARIOS S/. 31,062.62
07.01 NIVELACION Y REPOSICION DE CAJA DE AGUA h.prom=0.15m. und 1 61.74 S/. 61.74 0.00 0.00 0.00% 1.00 61.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 61.74
07.02 SUMINISTRO E INSTALACION DE GRASS ARTIFICIAL m2 436.34 63.8 S/. 27,838.49 0.00 0.00 0.00% 0.00 0.00 0.00% 436.34 27,838.49 100.00% 0.00 0.00 0.00% 436.34 27,838.49
07.03 PEDESTAL PARA PLACA SEGUN DISEÑO und 1 1007.89 S/. 1,007.89 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,007.89 100.00% 0.00 0.00 0.00% 1.00 1,007.89
07.04 LIMPIEZA PERMANENTE DE OBRA m2 6950 0.31 S/. 2,154.50 1,737.50 538.63 25.00% 1,737.50 538.63 25.00% 1,737.50 538.63 25.00% 1,737.50 538.63 25.00% 6,950.00 2,154.50
08 INSTALACIONES SANITARIAS S/. 4,789.65
08.01 EXCAVACION Y RELLENO DE ZANJAS PARA TUBERIA DE INST. SANITARIAS. m 179.12 7.26 S/. 1,300.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 179.12 1,300.41 100.00% 179.12 1,300.41
08.02 CONEXION DE TUBERIA DE 3/4" - PVC CLASE 10 EN CAJA DE AGUA EXISTENTE. und 1 318.49 S/. 318.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 318.49 100.00% 1.00 318.49
08.03 SUMINISTRO E INSTALACION DE TUBERIA DE 3/4" - PVC CLASE 10 m 179.12 14.01 S/. 2,509.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 179.12 2,509.47 100.00% 179.12 2,509.47
08.04 VALVULA DE COMPUERTA DE BRONCE DE 3/4" und 1 73.38 S/. 73.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 73.38 100.00% 1.00 73.38
08.05 CAJAS DE PUNTO DE RIEGO und 5 117.58 S/. 587.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 587.90 100.00% 5.00 587.90
09 INSTALACIONES ELECTRICAS S/. 61,439.44
09.01 EXCAVACION PARA DADOS DE CONCRETO DE LUMINARIAS (0.50*0.50*0.60m.) m3 7.78 32.3 S/. 251.29 0.00 0.00 0.00% 0.00 0.00 0.00% 7.78 251.29 100.00% 0.00 0.00 0.00% 7.78 251.29
09.02 DADOS DE CONCRETO f'c=175 KG/CM2 PARA POSTES DE LUMINARIAS m3 6.08 299.92 S/. 1,823.51 0.00 0.00 0.00% 0.00 0.00 0.00% 6.08 1,823.51 100.00% 0.00 0.00 0.00% 6.08 1,823.51
09.03 TABLERO TD MONOF. (30 POLOS) und 1 545.39 S/. 545.39 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 545.39 100.00% 0.00 0.00 0.00% 1.00 545.39
09.04 MURETE PARA TABLERO DE DISTRIBUCION Y REJILLA DE PROTECCION und 1 1025.57 S/. 1,025.57 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,025.57 100.00% 0.00 0.00 0.00% 1.00 1,025.57
“MEJORAMIENTO DEL SERVICIO RECREATIVO EN EL PARQUE SAN MARTIN DE PORRES DE LA
PROYECTO URB. LA RINCONADA 2DA ETAPA, DISTRITO DE TRUJILLO, PROVINCIA DE TRUJILLO - LA
LIBERTAD”
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TRUJILLO

UBICACIÓN : DISTRITO: TRUJILLO - PROVINCIA: TRUJILLO - DEPARTAMENTO: LIBERTAD

PLAZO DE EJECUCION : 120 DIAS CALENDARIOS

MES 01 MES 02 MES 03 MES 04 ACUMULADO


Item Descripción Und. MetradoPrecio (S/.) Parcial (S/.)
MET. VAL. % MET. VAL. % MET. VAL. % MET. VAL. % MET. VAL.
09.05 SUMINISTRO E INSTALACION DE CABLE N2XOH 2X6 mm2 (INCL. EXCAVACION Y RELLENO DE ZANJA
m 613.53 35.83 S/. 21,982.78 0.00 0.00 0.00% 0.00 0.00 0.00% 613.53 21,982.78 100.00% 0.00 0.00 0.00% 613.53 21,982.78
09.06 LUMINARIA PARA SENDEROS PEATONALES - FAROLA CONICA SPC HG 125W und 27 917.93 S/. 24,784.11 0.00 0.00 0.00% 0.00 0.00 0.00% 10.80 9,913.64 40.00% 16.20 14,870.47 60.00% 27.00 24,784.11
09.07 LUMINARIA PARA LOSA DEPORTIVA - REFLECTOR ALOGENURO 400 W und 8 1259.4 S/. 10,075.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 10,075.20 100.00% 8.00 10,075.20
09.08 POZO PUESTA A TIERRA und 1 951.59 S/. 951.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 951.59 100.00% 1.00 951.59
10 IMPACTO AMBIENTAL S/. 1,529.00
10.01 RIEGO EN ZONA DE TRABAJO PARA MITIGAR LA CONTAMINACION AMBIENTAL - POLVO m2 6950 0.22 S/. 1,529.00 1,737.50 382.25 25.00% 1,737.50 382.25 25.00% 1,737.50 382.25 25.00% 1,737.50 382.25 25.00% 6,950.00 1,529.00
11 SEGURIDAD Y SALUD EN EL TRABAJO S/. 19,773.80
11.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL GLB 1 4938.75 S/. 4,938.75 1.00 4,938.75 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,938.75
11.02 EQUIPO DE PROTECCION INDIVIDUAL GLB 1 6862.55 S/. 6,862.55 1.00 6,862.55 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 6,862.55
11.03 EQUIPO DE PROTECCION COLECTIVA GLB 1 4980 S/. 4,980.00 1.00 4,980.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,980.00
11.04 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1 1257.5 S/. 1,257.50 1.00 1,257.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,257.50
11.05 CAPACITACION EN SEGURIDAD Y SALUD GLB 1 675 S/. 675.00 1.00 675.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 675.00
11.06 RECURSO PARA RESPUESTA ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABA GLB 1 1060 S/. 1,060.00 1.00 1,060.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,060.00
COSTO DIRECTO 1,223,791.67 251,348.04 450,766.05 398,766.20 122,911.39 1,223,791.67
GASTOS GENERALES (10.00%) 122,379.17 25134.8 45076.61 39876.63 12291.14 122,379.17
UTILIDADES (5.00%) 61,189.58 12567.40 22538.30 19938.31 6145.57 61,189.58
SUB TOTAL 1,407,360.42 289,050.24 518,380.96 458,581.14 141,348.10 1,407,360.42
IGV ( 18.00%) 253,324.88 52029.04 93308.58 82544.61 25442.66 253,324.88
TOTAL 1,660,685.30 341,079.28 611,689.54 541,125.75 166,790.76 1,660,685.30
PORCENTAJE DE AVANCE 20.54% 36.83% 32.58% 10.04% 100.00%
CRONOGRAMA DE DESEMBOLSOS
PROYECTO: “MEJORAMIENTO DEL SERVICIO RECREATIVO EN EL PARQUE SAN MARTIN DE PORRES DE LA URB. LA RINCONADA
2DA ETAPA, DISTRITO DE TRUJILLO, PROVINCIA DE TRUJILLO - LA LIBERTAD”

PRESUPUESTO AL 28/03/2018

2DO 3ER
DESCRIPCIÓN PARCIAL (S/.) 1ER MES 4TO MES TOTAL
MES MES
COSTO DIRECTO 1,223,791.67 251,348.04 450,766.05 398,766.20 122,911.39 1,223,791.67
GASTOS GENERALES (10%) 122,379.17 25,134.80 45,076.61 39,876.62 12,291.14 122,379.17
UTILIDAD (5%) 61,189.58 12,567.40 22,538.30 19,938.31 6,145.57 61,189.58
SUB TOTAL 1,407,360.42 289,050.25 518,380.96 458,581.13 141,348.10 1,407,360.42
IMPUESTO GNERAL A LAS VENTAS (18%) 253,324.88 52,029.04 93,308.57 82,544.60 25,442.66 253,324.88
TOTAL PRESUPUESTO 1,660,685.30 341,079.29 611,689.53 541,125.73 166,790.76 1,660,685.30
PORCENTAJE DE AVANCE PROGRAMADO MENSUAL (%) 20.54 36.83 32.58 10.04 100.00
PORCENTAJE DE AVANCE PROGRAMADO ACUMULADO (%) 0.00 57.37 89.96 100.00