Академический Документы
Профессиональный Документы
Культура Документы
MIN
Project: Completion of Public Market-Two Storey Building
Location: Poblacion, Ubay, Bohol
35 km from Tagbilaran City
DERIVATION OF HAULING COST PER KILOMETER
(Aggregates)
MIN
Project: Completion of Public Market-Two Storey Building
Location: Poblacion, Ubay, Bohol
35 km from Tagbilaran City
DERIVATION OF HAULING COST PER KILOMETER
(Portland Cement)
Total Rate of Cargo Truck for One Cycle = P 783.00 per hour x 1.82 hrs = P 1,422.00
BACK-UP COMPUTATION
206.90
SAY : 207.00
Page 13
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City
BACK-UP COMPUTATION
Page 14
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City
BACK-UP COMPUTATION
23.780
SAY: 23.80
Err:509 Err:508
Err:509 Err:508
Err:509 Err:508
Err:509 Err:508
Page 15
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City
BACK-UP COMPUTATION
Err:508
SAY: Err:508
8 Item 1046(2)a - CHB Non Load bearing (including reinforcing steel)100mm 151.00
9 Item 1046(2)b - CHB Non Load bearing (including reinforcing steel)150mm 594.00
Page 16
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City
BACK-UP COMPUTATION
Area ground floor ((87m x 2.8m) 302.40
Area 1st floor ((87mx 2.80m) 302.40
688.70
Less:doors/windows: 95.200 m2 SAY: 594.00
12 Item 1003(1)a1 - Ceiling 4.5mm Metal frame Fiber cement board 337.00
Page 17
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City
BACK-UP COMPUTATION
16 Item 1009(1)a - Jalousie Window Glass 59.40
Page 18
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City
BACK-UP COMPUTATION
Wall(CR) 75.00
Floor(CR) 19.00
Countersink/urinals) 10.00
104.00 m2
columm 115.00
roof beam 90.00
ceiling 302.00
Plaster finish 1,490.00
Fiber cement board 337.00
2,334.00
SAY: 2,334.00 m2
Say: 247.00
Metal railings:
36.7+22.70+2.50 Balcony 16.49
12+ Ramp/handrail 0.87
64+12 Stairs 38.00
42 Fire escape 4.96
60.32 m2
Page 19
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City
BACK-UP COMPUTATION
SAY: 60.30 m2
Roof framing
26-6mmthk x 75mm x 75mm x 6m angle bar -Top Chord kg 1,102.00
19-6mm thk x 75mm x 75mm x 6m angle bar -Bottom Chord kg 805.31
23-6mm thk x 65mm x 65mm x 6m angular bar-webmember kg 844.87
35-6mm thk x 50mm x 50mm x 6m angular bar -web & clip angle kg 988.97
26-1mm thk x 50mm x 6m -filler plate kg 62.22
5 -5mmx40mmx40mm x 6m angle bar kg 94.19
5 - 6mm thk x 100mm x 100mm x 6m angle bar- LRB kg 282.56
154 -2mm thk x20x 65 x 150 x 6m LC purlins kg 4,641.58
24- 25mm thk x 25mm x 25mm angle bar - fascia frame kg 254.31
30 -12 mm Ø x 6.00 m. plain bar for sag rod kg 159.84
34 -16mmØ x 6.0m plain bars for cross brace,grade 40 kg 311.92
6mm thk x 1.2m x 2.4m gusset plate pc 4.00
24-12mm thk x 350mm x 350mm base plate w/4-16mmØ hole pc 24.00
16mmǾ x 350mm machine bolts w/ nuts and washer pc 96.00
12mmǾ x 250mm machine bolts w/ nuts and washer pc 64.00
12mmØ x150mm machine bolts w/ nuts and washer pc 104.00
12mm Ø x 25mm bolts w/ nuts and washer pc 2,700.00
16mmØ turn buckle pc 28.00
12mmØ turn buckle plate pc 12.00
1-uint Fire Escape
23 - 2mm thk x20mmx20mm x 6m -stair nosing kg 86.65
4 - 6mm thk x150mmx150mm base plate w 4-12mm Ø hole pc 4.00
20 - 12mmØ x100mm bolts w/ nut and washer pc 20.00
5mm thk x 1.20m x2.40 base plate kg 113.03
1.25 -6mm thk x1.20mx 2.40m checkerd plate flooring kg 135.63
0.10 - 8mm thk x 1.20 m x 2.40m gusset plate kg 180.84
0.375 - 10mm thk x 1.20 m x 2.40 m gusset plate kg 226.05
2 - 6mm thk x 65mmx65mm angle bar kg 97.96
4 - 6mm thk x50mmx50mm x6m angle bar kg 113.03
8 - 4.5mm thk x38mmx38mm x 6m angle bar kg 32.21
2 -4.5mm x25mmx25mm x 6m angle bar kg 21.19
12mm thk flange w/spider leg (fab.) pc 4.00
Page 20
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City
BACK-UP COMPUTATION
Ramp= 12.00 m
Stairs= 76.00 m
Balcony railing= 61.90 m
Fire Escape = 80.00 m
28 Item 1014(1)b1 - Prepainted Metal sheet above 0.427mm corrugated type,long span 428.00
Page 21
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City
BACK-UP COMPUTATION
Engineer II OIC - Chief, Planning & Design
Page 22
3/4/2016 -As per sir Lucio, a
#REF!
#REF!
m³
m³
71 5.325
m³
5.325
m³
151.2
m³
Page 23
3/4/2016 -As per sir Lucio, a
liter
m³
Page 24
3/4/2016 -As per sir Lucio, a
Page 25
3/4/2016 -As per sir Lucio, a
m2
m2
Page 26
3/4/2016 -As per sir Lucio, a
m2
l.s
from Facilities of Handicapped Daorong & Kalibo leading to various beach resorts, danao, Pang
m2 2 8.6
1.2 -30.5
set
set
set
Page 27
3/4/2016 -As per sir Lucio, a
m2
set
m2
m2
1 -2.10x .90m hollow core doorflush door(w/ kicking plate) m2
4 - 2.10x.80 m hollow core door flush door m2
5 - 1.20x .60m hollow core door flush door m2
1 - 2.10 x .70m hollow core flush door m2
set
Page 28
3/4/2016 -As per sir Lucio, a
m2
771.498
508.68
226.08
m2
m2 247.8
6.000 6
m2
Page 29
3/4/2016 -As per sir Lucio, a
l.s
86.65296
232.75
113.03
135.63
180.84
226.05
97.96
113.03
32.21
21.19
meter
Page 30
3/4/2016 -As per sir Lucio, a
m2
ls
ls
Err:509
lm
ls
l.s
set
ls
ls
Page 31
3/4/2016 -As per sir Lucio, a
gn
Page 32
r sir Lucio, addt'l 4m width for item 100 (2m both sides)
33AM - disregard stone masonry on left side portion in case magkuwang ang kwarta - as per sir eloy
33AM - As per sir eloy for item 100 magstart sa (see magenta colored dimension)..
Page 33
r sir Lucio, addt'l 4m width for item 100 (2m both sides)
Page 34
Republic of the Philippines
Province of Bohol
Municipality of Bohol
Office of the Municipal Engineer
PART B EARTHWORKS
803(1)c Structure Excavation solid rock 0.14 m³ 5.32 P 502.32 P 2,671.33
804(1)a Embankment from structure excavation 1.11 m³ 2.72 P 7,730.59 P 21,058.13
804(4) Gravel Fill 0.38 m³ 4.01 P 1,809.15 P 7,254.68
1000 (1) Soil Poisoning 0.35 liter 2.00 P 3,353.12 P 6,706.24
PART C REINFORCED CONCRETE
900 (1)c2 Structural Concrete (Footing & Slab on fil )Class A 1.05 m³ 2.26 P 8,843.21 P 19,967.97
28 days
900(1)c3 Structural Concrete(Wall Footing) Class A 28 days 4.13 m³ 0.84 P 93,584.25 P 78,330.02
1046(2)a1 CHB Non load bearing(including reinforcing 2.37 m2 66.74 P 674.01 P 44,983.26
steel)100mm
Page 35 of 235
Republic of the Philippines
Province of Bohol
Municipality of Bohol
Office of the Municipal Engineer
Page 36 of 235
Republic of the Philippines
Province of Bohol
Municipality of Bohol
Office of the Municipal Engineer
Page 37 of 235
Republic of the Philippines
Province of Bohol
Municipality of Bohol
Office of the Municipal Engineer
PART B EARTHWORKS
803(1)c Structure Excavation solid rock #REF! m³ 5.32 P 502.32
804(1)a Embankment from structure excavation #REF! m³ 2.72 P 7,730.59
804(4) Gravel Fill #REF! m³ 4.01 P 1,809.15
1000 (1) Soil Poisoning #REF! liter 2.00 P 3,353.12
PART C REINFORCED CONCRETE
900 (1)c2 Structural Concrete (Footing & Slab on fil )Class A #REF! m³ 2.26 P 8,843.21
28 days
900(1)c3 Structural Concrete(Wall Footing) Class A 28 days #REF! m³ 0.84 P 93,584.25
387
Upon approval 35 km from Tagbilaran City
180
uipment
ption/Nos.
P 19,967.97
P 78,330.02
P 32,690.38
P 29,652.59
P 58,223.46
P 61,655.54
P 44,983.26
P 300,823.81
P 115,222.21
P 10,067.16
P 45,564.06
P 39,791.66
P 21,085.52
P 2,655.15
P 425.44
#REF!
P 879,846.86
P 14,796.71
#REF!
P 9,741.69
P 5,979.56
P 11,278.47
P 4,211.13
P 10,140.23
#REF! -
-
machine copies Err:508
- 11,070,295.00 11,070,295.00
11,070,295.00 ok
-
LO R. BARBANIDA
Draftsman II
A O. BASILAD
ANTINO H. REYES
Unit Price Analysis
1
SUB-TOTAL (B) P 1,062.87
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 3,730.37
.6375m2/hr
.85sheet/hr
6.80sheet/md N
32
576
9
Unit Price Analysis
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 39,724.72
SUB-TOTAL (A)
B. LABOR COST QUANTITY Hourly
No. of Personnel Total Hours Rate
SUB-TOTAL (B)
C. EQUIPMENT COST QUANTITY Hourly
No. of Equipt. Total Hours Rate
SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C)
UNIT COST
0.195
5.1282
TOTAL COST
-
Total
Cost
- - -
Total
Cost
2,720.00
1,825.00
3,910.00
P 5,143.10
15,132.62
P 679.91
P 14,278.01
P 14,278.01 9
Unit Price Analysis
SUB-TOTAL (A)
B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost
Construction Foreman 1 5.00 P 84.66 P 423.30
Laborer 4 5.00 P 47.34 P 946.80
3
SUB-TOTAL (B) P 1,370.10
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
3.708
1.61
5.318
Unit Price Analysis
SUB-TOTAL (A)
B. LABOR COST QUANTITY Hourly
No. of Personnel Total Hours Rate
1
SUB-TOTAL (B)
C. EQUIPMENT COST QUANTITY Hourly
No. of Equipt. Total Hours Rate
SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C)
UNIT COST
4.150
0.66
TOTAL COST
0.42 1.944
0.36
4.2 0.78
1.84
2.724
- 6.04
Total
Cost
P 55.57
P 11,200.64
P 11,256.21
Total
Cost
5,456.59
P 5,456.59
P 16,712.80
P 4,345.33
P 21,058.13
P 7,730.59
Unit Price Analysis
1
SUB-TOTAL (B) P 304.08
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 5,757.68
4.01
BAR CHART FOR ITEM 803 - EXCAVATION O
1 Materials: = -
2 Labor 4 Laborer
3 Equipment: -
ACTIVITIES D
Condition
1 Small Project
2 Common Earth
3 Flat Terrain
4 Urban Location
DURATION
0.33608
0.08402
15.823613425374900
0.3360800
m3/hr
0.125
BAR CHART FOR ITEM 803 - Ba
1 Materials: = -
2 Labor 4 Laborer
3 Equipment: -
ACTIVITIES D
Condition
1 Small Project
2 Common Earth
3 Flat Terrain
4 Urban Location
DURATION
0.33608
0.08402
8.105213044513210
0.3360800
m3/hr
0.125
BAR CHART FOR ITEM 804b - EMBANKMENT ( BORROW)
2 Common Earth
3 Flat Terrain
4 Urban Location
2 Labor 2- Laborer
ACTIVITIES DURATION
2 Labor 2- Laborer
3 Equipment: -
ACTIVITIES DURAT
Condition
1 Small Project
2 Common Earth
3 Flat Terrain
4 Urban Location
DURATION
m3/hr
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1000 (1)
Description : Soil Poisoning
Quantity : 2.00 liter PRODUCTION RATE (liter/hr): 1.350
NUMBER OF HOURS: 25.93
1
SUB-TOTAL (B) P 3,422.42
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 5,322.42
2 Labor 1- Laborer
3 Equipment: -
ACTIVITIES DURA
1.35
EM 1000 - SOIL POISONING
Condition
1 Small Project
2 Common Earth
3 Flat Terrain
4 Urban Location
DURATION
m2/hr
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 900 (1)c2
Description : Structural Concrete (Footing & Slab on fil )Class A 28 days
Quantity : 2.258 m³ PRODUCTION RATE (m3/hr): 0.282
NUMBER OF HOURS: 8.00
Portland cement - approved brand (Portland Type I) bag 23.00 P 260.00 P 5,980.00
Sand - Leyte source cu.m. 2.00 P 1,360.00 P 2,720.00
Gravel - Leyte source cu.m. 3.00 P 1,360.00 P 4,080.00
2
SUB-TOTAL (B) P 1,546.40
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
2.258
2.258
21.451
21.451
1.9193
1.9193
2.258 2.258
0.121002
4.74071
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 900(1)c3
Description : Structural Concrete(Wall Footing) Class A 28 days
Quantity : 0.84 m³ PRODUCTION RATE (m3/hr): 0.0058
NUMBER OF HOURS: 144.00
Portland cement - approved brand (Portland Type I) bag 9.00 P 260.00 P 2,340.00
Sand - Leyte source cu.m. 0.75 P 1,360.00 P 1,020.00
Gravel - Leyte source cu.m. 1.00 P 1,360.00 P 1,360.00
lumber bd.ft 63.00 P 40.00 P 2,520.00
assorted CWN kg 1.00 P 70.00 P 70.00
1/4"x4'x8' ordinary plywood sheet 3.00 P 400.00 P 1,200.00
10.83
0.969
123.30
6.238872
Project : #REF!
Locaton : #REF!
Item No. : 900 (1)c4
Description : Structural Concrete(Columns)ClassA 28 days
Quantity : 1.368 m³ PRODUCTION RATE (m3/hr): 0.1440
NUMBER OF HOURS: 9.50
Portland cement - approved brand (Portland Type I) bag 14.00 P 260.00 P 3,640.00
Sand - Leyte source cu.m. 1.25 P 1,360.00 P 1,700.00
Gravel - Leyte source cu.m. 1.50 P 1,360.00 P 2,040.00
Lumber bd.ft. 300.00 P 40.00 P 12,000.00
Assorted C. W. Nails kg 3.00 P 70.00 P 210.00
1/4" x 4' x 8' ordinary plywood sheet 4.00 P 350.00 P 1,400.00
8
SUB-TOTAL (B) P 4,033.13
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
1.368
1.1628
36
300
6.34
0.192145
2.87 22.98
Unit Price Analysis
Portland cement - approved brand (Portland Type I) bag 11.00 P 260.00 P 2,860.00
Sand - Leyte source cu.m. 1.00 P 1,360.00 P 1,360.00
Gravel - Leyte source cu.m. 1.25 P 1,360.00 P 1,700.00
Coco Lumber bd.ft. 300.00 P 40.00 P 12,000.00
Assorted C. W. Nails kg 3.00 P 70.00 P 210.00
1/4" x 4' x 8' ordinary plywood sheet 4.00 P 350.00 P 1,400.00
7
SUB-TOTAL (B) P 3,303.16
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
10.4 10.4
0.73
0.99
78.26 187.5
1.57 9.88
2.40 5.7692308
0.884
0.56
0.48
0.56
0.184
1.04
0.744
6.25
429.10
0.169133
2.18 17.47
Unit Price Analysis
5
SUB-TOTAL (B) P 5,937.48
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
4
5.328 159.84 74.592
3.696 96.10 48.048 4.666667 6 46.66667 3.65
10 6.85
2 34.25 18.25
3.696 1023.792
36.96 0.766667 0.333333 50
14.53 0.01917 133.056
10 2.15
26.83333
758.12 10.75
758.12 8.944444 24
14
773.28 2.8
15.16 5 1
773.280
36
23.33333
0.168791
4.666667 36 45
92.4 12 6.55
12 32.75
1.75 5.5
2.25 24
758.12 24 1.75
15.16 4.5 1.5 3
18 1.5
10 1.333333
1.666667
2.666667
2.333333
0.15 3 4
0.3
0.45 6
0.9
24
2.9
14.5 2.8 11.2
1 4
30
6
Unit Price Analysis
Portland cement - approved brand (Portland Type I) bag 11.00 P 260.00 P 2,860.00
Sand - Leyte source cu.m. 8.25 P 1,360.00 P 11,220.00
Gravel - Leyte source cu.m. 10.00 P 1,360.00 P 13,600.00
Lumber bd.ft. 250.00 P 40.00 P 10,000.00
Assorted C. W. Nails kg 4.00 P 70.00 P 280.00
1/4" x 4' x 8' ordinary plywood sheet 3.00 P 350.00 P 1,050.00
Concrete stair
4- 12mmØ x 6.0m def bar kg 21.31 P 45.00 P 958.95
6- 10mmØ x 6.0m def bar kg 22.18 P 45.00 P 998.10
countersink
10- 10mmØ x 6.0m def bar kg 36.96 P 45.00 P 1,663.20
10
SUB-TOTAL (B) P 5,519.02
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
1.15
13
0.996 9.5
27.84 8.075
0.304
9.96 9.5
0.6972 0.70 0.6972 0.304 0.96
0.9462 0.288 1.264
74.95 195.7831 0.304
1.50 0.592 0.161 0.288
3.33 6.024096 0.14 12.008
0.301 1.0744 0.592
4 5499.03
5.328 138.528 21.31 21.312 0.316667 5.624
3.696 181.104 22.18 14.784 7.6 0.5032
80.45 0.893 1.266667 0.592
2.9
5.8
1.4 18
1.61
2.45
4.06
0.406
4
1.266667 4
1.2
4.75
0.6
1.333333
0.8
BAR CHART FOR ITEM 901(c2) - REINFORCED CONCRE
2 Labor 1- Leadman
1- Mason
1- Labor
ACTIVITIES DURAT
Condition
1 Small Project
2 Flat Terrain
3 Urban Location
DURATION
0.125 56.00
0.040321
m3/hr
BAR CHART FOR ITEM 900(1) c3- REINFORCED CONCR
2 Labor 1- Mason
2- Carpenter
2- Labor
1- Lead Man
3 Equipment: - 1 Concrete Mixer, 1 bagger
1 Concrete Vibrator
ACTIVITIES DU
Formworks: ( 201.60 m2 )
Concreting (V = 3.75cu.m.)
108
56 164
DURATION
32.4
4.2
36.6
123.30
0.0058
m3/hr
BAR CHART FOR ITEM 900©bc - REINFORCED CONC
2 Labor 1- Leadman
1- Mason
2 Carpenter
2- Labor
ACTIVITIES D
Formworks: ( 11.52 m2 )
Concreting (V 35.08
Forms
78.4
1.8
0.2
80.4
DURATION
6.34
0.1505
m3/hr
BAR CHART FOR ITEM 900(1)c5 - Suspen
2 Labor 1- Leadman
2 Carpenter
1 Mason
2 laborer
3 Equipment: - 1 Concrete Mixer, 1 bagger
1 Concrete Vibrator
ACTIVITIES DUR
Formworks: ( #REF! m2 )
Concreting (V =26.04cu.m.)
DURATION
32.4
4.2
36.6
#REF!
m3/hr
BAR CHART FOR ITEM 900(1) c6- REINFORCED CONCR
2 Labor 1 - Leadman
2 - Mason
3 - Carpenter
3 - Labor
ACTIVITIES DUR
Formworks: ( 11.52 m2 )
Concreting (V = 12.67cu.m.)
DURATION
0 6.25
0.1522
m3/hr
BAR CHART FOR ITEM 902(1)a1 - R
2 Labor 2 Steelmen
3 Equipment: -
ACTIVITIES
1 Small Project
2 Flat Terrain
3 Urban Location
DURATION
= 42.500
kg/hr
BAR CHART FOR ITEM 900(7) - REINFORCED
2 Labor 1- Leadman
2 Carpenter
1 Mason
2 laborer
3 Equipment: - 1 Concrete Mixer, 1 bagger
1 Concrete Vibrator
ACTIVITIES DUR
Formworks: ( 8.64 m2 )
DURATION
32.4
4.2
36.6
0.0809
m3/hr
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1046(2)a1
Description : CHB Non load bearing(including reinforcing steel)100mm
Quantity : 66.74 m2 PRODUCTION RATE (m2/hr): 1.907
NUMBER OF HOURS: 35.00
14
SUB-TOTAL (B) P 8,911.00
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 35,701.00
A1 393.08
A2 217
A3side 12.5 124.3704
834.25 A3side 12.5
26.07 622.58
1.90 510.49 21
44.49 pcs 3.696 373.30 2.88
9.74 416.875
18.12 226.5
834.25
2.96 376.25 30.1
2.96 147.84 18.0198
9.89
5.4 164.74 37
2.96 22.0242 0.9
37.07778 37.07778
8.99
40.044 1.3348
715.125
147.84 112.375
16.72222
10.06667
0.3326241 37.27778
5.494444
4.994444
35.3325 130.5889
1.6825
57.21
16.3539
18.0198
462.5 1.3348
1.2114
22.0242
6.9
8.74
26.6 66.74
24.5
2 Labor 2- Mason
1- Labor
3 Equipment: -
ACTIVITIES DUR
Condition
DURATION
m2/hr
BAR CHART FOR ITEM 1046(2)a - MASONRY WOR
2 Labor 2- Mason
1- Labor
3 Equipment: -
ACTIVITIES DURAT
DURATION
#REF!
m2/hr
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1018(1)
Description : Unglazed Tiles/Existing Stairs-Landing
Quantity : 108.00 m2 PRODUCTION RATE (m2/hr): 0.900
NUMBER OF HOURS: 120.00
30
SUB-TOTAL (B) P 21,520.80
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 124,120.80
27
108
12
15
0.2097544
10 19 104
BAR CHART FOR ITEM 1027 - CEMENT PLA
2 Labor 2- Mason
2- Labor
3 Equipment: -
ACTIVITIES D
DURATION
#REF!
m2/hr
BAR CHART FOR ITEM 1032(1)a-Masonry painting
Labor: 2 Painter
1 Laborer
Equipment:
ACTIVITIES
DURATION
#REF! 15
6.274
m2/hr
pcs
BAR CHART FOR ITEM 1032(1)b #REF!
Labor: 1 Painter
Equipment:
ACTIVITIES
DURATION
#REF! 15
#REF!
m2/hr
pcs
BAR CHART FOR ITEM ### #REF!
Labor: 1 Painter
Equipment:
ACTIVITIES
DURATION
#REF! 15
#REF!
m2/hr
pcs
BAR CHART
2.Labor
2 mason
3. Equipment:
ACTIVITIES
Total time :
Production rate:
Condition
DURATION(hrs.)
60.48
59.4
Labor: 1 Painter
Equipment:
ACTIVITIES
DURATION
#REF!
= #REF!
lm/hr
15 pcs
BAR CHART FOR #REF! #REF!
Labor: 2 eectrician
Equipment:
ACTIVITIES
DURATION
#REF!
= 1.181
unit/hr
15 pcs
BAR CHART FOR ITEM 1100 - POWERLOAD CENTER
DURATION
#REF!
= 0.577
unit/hr
15 pcs
Unit Price Analysis
SUB-TOTAL (A)
B. LABOR COST QUANTITY Hourly
No. of Personnel Total Hours Rate
304
SUB-TOTAL (B)
C. EQUIPMENT COST QUANTITY Hourly
No. of Equipt. Total Hours Rate
SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C)
UNIT COST
167.076 236.47
37.2
54.4 52.8
75.476 26.775
156.895
0.30
70.00 37.5172727273
50.82
8.8704 4080
816
460.845 85.68
1800 41.2335 396.00
500 231.00
48.51 0
408 462.00
120
186.2 163.33333 9 13.6 475.60
217.1
20.944 870.22224 72.4608
337.1
660 66
360 72.4608
2275
77 10.5 77.7
2925
292 55 3.4285714286
99.75
33
606.1 77 556
416
466.1 234 128.33333
0.5808 1235.54
0
7.5 5.85
729.6 325.468
5.85 631.8 245.7
157.95 67.8
631.8 50.85 30
729.6
30 296.55
326.55
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1001(8)
Description : Sewer Line Works
Quantity : 1.00 l.s PRODUCTION RATE (l.s/hr): 0.059
NUMBER OF HOURS: 17.00
5
SUB-TOTAL (B) P 3,523.42
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 11,743.42
Output: 294.11765
0.4286399
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1002(28)
Description : Cold Water Lines
Quantity : 1.00 l.s PRODUCTION RATE:(l.s/hr) 0.026
NUMBER OF HOURS: 38.00
5
SUB-TOTAL (B) P 5,016.00
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C) P 7,731.50
Laborer
cian
BAR CHART FOR ITEM = 1001(8)
Labor: 1 Painter
Equipment:
ACTIVITIES
6
15 21
DURATION
#REF! 15
0.06071
lm/hr
pcs
BAR CHART FOR ITEM = #REF!
20 fixtures
Labor: 2 Painter
Equipment:
ACTIVITIES
DURATION
#REF! 15
#REF!
set/hr
pcs
BAR CHART FOR ITEM = #REF!
Labor: 1 installer
Equipment:
ACTIVITIES
DURATION
#REF! 15
#REF!
m2/hr
pcs
BAR CHART FOR ITEM = 1002(28)
Labor: 2 plumber
Equipment:
ACTIVITIES
DURATION
#REF! 15
0.0264
m2/hr
pcs
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1047(1)
Description : Structural Steel
Quantity : 1.00 l.s PRODUCTION RATE (l.s/hr) 0.00410
NUMBER OF HOURS: 244.00
A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST
Roof framing
18-3/16"x2"x2" x 6m angle bar -Top Chord kg 399.60 P 57.00 P 22,777.20
7-3/16"x 1 1/2"x 1 1/2" x 6m angle bar -Web Member/clip angle kg 49.20 P 57.00 P 2,804.40
/fascia frame
9-2"x3"x1.2mm Cee Purlins pcs. 9.00 P 423.00 P 3,807.00
4 -12 mm Ø x 6.00 m. def. bar for sag rod kg 63.94 P 42.00 P 2,685.48
4 -16mmØ x 6.0m. Std Def. bars for cross brace,grade 40 kg 37.90 P 45.00 P 1,705.50
Red oxide gal 2.00 P 495.00 P 990.00
paint thinner gal 1.00 P 250.00 P 250.00
Hand/Ramp railings-Stairs
8 - 50mmØ Stainless Pipe(handrail & support) pc 14.00 P 4,400.00 P 61,600.00
12 - 20mm x 20mm square bar (railing) kg 177.55 P 57.00 P 10,120.46
welding rod kg 5.00 P 150.00 P 750.00
Hacksaw blade pc 5.00 P 45.00 P 225.00
183
SUB-TOTAL (B) P 103,587.76
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
159.84 7
322.116 2.54 #REF! 3.75 1.16666667
3
2.5 1.5*2
21.312 1.5
37.90
0.23 1.40 9
0.08 1488.1704 #REF!
177.55 5.5
63.94
177.552 2.40
1.67 4.80
14.40
1.65
733.19 2.4 2 5
14.4
0.73333333
2.4
2.5 2.4 1.66666667 0.73333333 9.9
35.25 1.46666667
0.9616833095
3.33333333
0.90909091 0.81818182
4.8
6.45
7.2
3
3
0.75
4.88888889
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1014(1)b1
Description : Prepainted Metal sheet G.I Corr. Sheet
Quantity : 428.00 m2 PRODUCTION RATE (m2/hr): 2.816
NUMBER OF HOURS: 152.00
Public Market-Roof
#-24 G.I Corr. Sheet x12' sheet 7.00 P 410.00 P 2,870.00
Texscrew pc 1224.00 P 3.00 P 3,672.00
#-24 G.I Sheet Plain x10' pc 95.00 P 220.00 P 20,900.00
57
SUB-TOTAL (B) P 38,699.20
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 91,446.20
6.328 144
32.9 208.1912
416.3824
11.42857
70
144 210
3.333333
2.5
0.35mm thk prepainted long span rib type lm 86.00 P 420.00 P 36,120.00
0.35mm thk x 24" x 8' pre fabd gutter pc 19.00 P 237.00 P 4,503.00
0.35mm thk x 12 " x 8'pre fab fascia cover pc 19.00 P 238.00 P 4,522.00
84
1140
1224
0.73367585
- 6 pcs in every square meter
- 3 pcs in every square meter
BAR CHART FOR ITEM = 1047(1) Structural Steel
ACTIVITIES DURATION
Equipment:
ACTIVITIES
Labor: 2 carpenter
1 laborer
DURATION
= 2.819
m2/hr
228
BAR CHART FOR ITEM 403 - METAL STRUCTURE (ROOF FR
ACTIVITIES
ACTIVITIES
DURATION
#REF! 9,546.80
#REF! 950
Area: 37.8
#REF!
0.67 1518
#REF! hrs.
DURATION
#REF!
48.00 6 set of trusses
0.00
0.00
34.22
0.00
0.00
0.00 assumed 0.06250
0.00
#REF! hrs.
Project : #REF!
Locaton : #REF!
Item No. : 1010(1)
Description : Frames (Jamb,sills, head,transoms and mullions)
Quantity : 53.00 set PRODUCTION RATE (set/hr): 0.4000
NUMBER OF HOURS: 132.50
6pcs - 2" x 6" x 12' Mahogany or gemelina(jamb)-window bd.ft 72.00 P 40.00 P 2,880.00
16 pcs - 2" x 6" x 8' Mahogany or gemelina(jamb) bd.ft 128.00 P 40.00 P 5,120.00
CW nails(asstd.) kg 10.00 P 70.00 P 700.00
34
SUB-TOTAL (B) P 27,461.95
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt.Total Hours Rate Cost
SUB-TOTAL (C) -
TOTAL DIRECT COST (A + B + C) P 36,161.95
3.15654598
3
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1009(1)a
Description : Jalousie Windows glass
Quantity : 59.40 m2 PRODUCTION RATE (m2/hr): 0.6750
NUMBER OF HOURS: 88.00
Aluminum Jalousie frame for 14 blades (A1), double control sq.m 2.88 P 2,250.00 P 6,480.00
Aluminum Jalousie frame for 7 blades (A1), double control sq.m 0.80 P 2,250.00 P 1,800.00
4.5mm thk x 100mm x537.50mm clear glass jalousie blade pc. 77.00 P 25.00 P 1,925.00
1"Cove moulding-8' pc. 12.00 P 240.00 P 2,880.00
Assorted C.W. Nails kg 6.00 P 42.80 P 256.80
P 13,341.80
B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost
22
SUB-TOTAL (B) P 18,238.88
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 31,580.68
6,480.00 28
56
2.666667
21 77
1.36704792
0.24
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1010(2)a
Description : Doors flush
Quantity : 3.78 m2 PRODUCTION RATE (m2/hr):
NUMBER OF HOURS:
SUB-TOTAL (A)
B. LABOR COST QUANTITY Hourly
No. of Personnel Total Hours Rate
8
SUB-TOTAL (B)
C. EQUIPMENT COST QUANTITY Hourly
No. of Equipt. Total Hours Rate
SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C)
UNIT COST
0.1303
29.00
TOTAL COST
P 10,584.00 3.78
P 140.00 5,292.00
P 10,724.00
Total
Cost
P 2,455.14
P 3,555.40
P 6,010.54 0.56047557
Total
Cost
-
P 16,734.54
P 4,350.98
P 21,085.52
P 5,578.18
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1004(2)e
Description : Finishing hardware, knobs
Quantity : 2.00 set PRODUCTION RATE (set/hr): 2.0000
NUMBER OF HOURS: 1.00
1
SUB-TOTAL (B) P 207.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 2,107.26
Output 1.0624
10.9084211
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1004(2)g
Description : Finishing hardware, hinges
Quantity : 3.00 set PRODUCTION RATE (set/hr): 81.2500
NUMBER OF HOURS: 0.04
21
SUB-TOTAL (B) P 7.65
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 337.65
output 3.75
2.31899301
BAR CHART FOR ITEM 10
1010(1) Frames (Jamb,sills, head,transoms and mul
Equipment:
ACTIVITIES
DURATION
= 0.400
m2/hr
BAR CHART FOR ITEM 1009(1) - GLASS
Labor: 2 Carpenter
Equipment:
ACTIVITIES
DURATION
#REF! 12
0.6750
set/hr
units
Item 1010(2)a Doors flush
Labor: 2 carpenter
Equipment:
ACTIVITIES
DURATION
12.69573
0.4726
m2/hr
0.4726
#REF! ###
Labor: 2 carpenter
Equipment:
ACTIVITIES
DURATION
12.69573
#REF!
m2/hr
BAR CHART FOR ITEM #REF!
1
Labor 2 carpenter
Equipment:
ACTIVITIES
DURATION
= #REF!
m2/hr
BAR CHART FOR ITEM 1004(2)e
1 Labor 1 carpenter
Equipment:
ACTIVITIES
DURATION
= 3.125
set/hr
BAR CHART FOR ITEM 1004(2)g
Labor 2 carpenter
Equipment:
ACTIVITIES
DURATION
= 81.250
m2/hr
BAR CHART FOR ITEM 1100 - POW
Labor: 2 eectrician
Equipment:
ACTIVITIES
1 Small Project
2 Flat Terrain
3 Urban Location
DURATION
#REF!
= 1.453
unit/hr
15 pcs
BAR CHART FOR ITEM 10
Equipment:
ACTIVITIES
DURATION
=
m2/hr
BAR CHART FOR ITEM 10
#REF! #REF!
1 Labor 3 carpenter
Equipment:
ACTIVITIES
DURATION
= 0.052
m2/hr
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1017(1)a2
Description : Roof drain with strainers,75mm Ø
Quantity : 5.00 set PRODUCTION RATE (m2/hr): 0.59
NUMBER OF HOURS: 8.50
2
SUB-TOTAL (B) P 2,803.81
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C) P 7,989.81
.6375m2/hr
.85sheet/hr
6.80sheet/md N
11.7
146.25
7.5 292.5
0.54064983
BAR CHART FOR ITEM 1017- Roof D
Labor: Skilled
1 workwer
Equipment:
ACTIVITIES
DURATION
#REF! 15
0.596
m2/hr
pcs
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1100(30)
Description : Conduits,Boxes & Fittings
Quantity : 1.00 l.s PRODUCTION RATE (lm/hr): 0.056
NUMBER OF HOURS: 18.00
5
SUB-TOTAL (B) P 3,730.68
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 4,745.68
Labor: 2 electrician
Equipment:
ACTIVITIES
Materials Qty.
DURATION
#REF!
0.056
unit/hr
0.056
15 pcs
Unit Price Analysis
Project : #REF!
Location : #REF!
Item No. : 1101(42)
Description : Wires and Wiring Devices
Quantity : 1.00 l.s PRODUCTION RATE (l.s/hr): 0.034
NUMBER OF HOURS: 29.50
8
SUB-TOTAL (B) P 6,114.17
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 8,951.17
215.52%
0.00%
BAR CHART FOR ITEM 1101(42)
Labor: 2 eectrician
Equipment:
ACTIVITIES
DURATION
#REF!
0.034
unit/hr
15 pcs
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1102(27)
Description : Powerload Center,Switchgear and Panelboards
Quantity : 1.00 l.s PRODUCTION RATE (set/hr): 0.14
NUMBER OF HOURS: 7.00
1
SUB-TOTAL (B) P 1,052.17
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 3,342.17
Labor: 2 eectrician
Equipment:
ACTIVITIES
1 Small Project
2 Flat Terrain
3 Urban Location
DURATION
#REF!
0.143
unit/hr
15 pcs
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1103(1)
Description : Lighting Fixtures
Quantity : 1.00 ls PRODUCTION RATE (set/hr): 0.033
NUMBER OF HOURS: 30.00
2-36 watts flourescent lighting fixtures box type set 2.00 P 915.00 P 1,830.00
w/ aluminum reflector(7" x 48")
8
SUB-TOTAL (B) P 6,217.80
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 8,047.80
3.3977049
#REF!
BAR CHART FOR ITEM 1103(1)
60.00 fixtures
Labor: 2 eectrician
Equipment:
ACTIVITIES
DURATION
#REF!
unit/hr
0.033
15 pcs
BAR CHART FOR ITEM #REF!
Labor: 2 installer
Equipment:
ACTIVITIES
DURATION
#REF!
unit/hr
#REF!
15 pcs
BAR CHART FOR ITEM 900(1)c5 - Suspe
2 Labor 1- Leadman
2 Carpenter
1 Mason
2 laborer
3 Equipment: - 1 Concrete Mixer, 1 bagger
1 Concrete Vibrator
ACTIVITIES D
Formworks: ( 155.52 m2 )
Concreting (V =26.04cu.m.)
DURATION
32.4
4.2
36.6
0.2873
m3/hr