Вы находитесь на странице: 1из 235

Project: Completion of Public Market-Two Storey Building

Location: Poblacion, Ubay, Bohol


35 km from Tagbilaran City
DERIVATION OF HAULING COST PER KILOMETER
(Aggregates)

Computation of Cycle Time, T:


T=D÷R
Where T = Time, Time of Travel (h)
D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

AVERAGE HAULING DISTANCE = 35.00 KM (FLAT, PAVED)


LOADING TIME = 3.00 min
LOADED TRAVEL TIME
First1300 m @ 20 kph = 0.60 min
Succeeding 1300 m @ 35 kph = 59.31 min
Next 200 m @ 20 kph = 0.60 min
UNLOAD AND MANEUVER = 2.00 min
RETURN EMPTY
First 200 m @ 30 kph = 0.40 min
Succeeding 1300 m @ 55 kph = 37.75 min
Next 200 m @ 30 kph = 0.40 min
Cycle Time, T = 104.06 min
Allowance for Delay (10% of cycle time) = 10.41 min
Total Cycle Time, T = 114.47 min

TOTAL NO. OF TRIP/DAY/TRUCK = 8 HRS x 60 MIN ÷ 114


HR
= 4.19 TRIPS SAY
= 5.00 TRIPS
VOLUME PER DAY = 5.00 TRIPS x 10 m³/LOAD
= 50 m³
CAPACITY OF DUMP TRUCK = 10 m³
DUMP TRUCKS RENTAL/DAY = P 11,360.00 /DAY
HAULING COST = P 11,360.00
50 m³
= P 227.20 /m³
Prices based on Validated CMPD for 2nd quarter CY 2016)
COST OF MATERIAL INCLUDING HAULING = P 231.00 /m³ + P 227.20 /m³
(Common Borrow) = P 458.20 /m³
32200

MIN
Project: Completion of Public Market-Two Storey Building
Location: Poblacion, Ubay, Bohol
35 km from Tagbilaran City
DERIVATION OF HAULING COST PER KILOMETER
(Aggregates)

Computation of Cycle Time, T:


T=D÷R
Where T = Time, Time of Travel (h)
D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

AVERAGE HAULING DISTANCE = 35.00 KM (FLAT, PAVED)


LOADING TIME = 3.00 min
LOADED TRAVEL TIME
First1300 m @ 20 kph = 0.60 min
Succeeding 1300 m @ 35 kph = 59.31 min
Next 200 m @ 20 kph = 0.60 min
UNLOAD AND MANEUVER = 2.00 min
RETURN EMPTY
First 200 m @ 30 kph = 0.40 min
Succeeding 1300 m @ 55 kph = 37.75 min
Next 200 m @ 30 kph = 0.40 min
Cycle Time, T = 104.06 min
Allowance for Delay (10% of cycle time) = 10.41 min
Total Cycle Time, T = 114.47 min

TOTAL NO. OF TRIP/DAY/TRUCK = 8 HRS x 60 MIN ÷ 114


HR
= 4.19 TRIPS SAY
= 5.00 TRIPS
VOLUME PER DAY = 5.00 TRIPS x 10 m³/LOAD
= 50 m³
CAPACITY OF DUMP TRUCK = 10 m³
DUMP TRUCKS RENTAL/DAY = P 11,360.00 /DAY
HAULING COST = P 11,360.00
50 m³
= P 227.20 /m³
Prices based on Validated CMPD for 2nd quarter CY 2016)
COST OF MATERIAL INCLUDING HAULING = P 1,246.67 /m³ + P 227.20 /m³
(FINE AGGREGATES) = P 1,473.87 /m³

COST OF MATERIAL INCLUDING HAULING = P 1,210.00 /m³ + P 227.20 /m³


(GRAVEL - G1 & G3/4) = P 1,437.20 /m³

COST OF MATERIAL INCLUDING HAULING = P 1,040.00 /m³ + P 227.20 /m³


(GRAVEL fill) = P 1,267.20 /m³
32200

MIN
Project: Completion of Public Market-Two Storey Building
Location: Poblacion, Ubay, Bohol
35 km from Tagbilaran City
DERIVATION OF HAULING COST PER KILOMETER
(Portland Cement)

Computation of Cycle Time, T:


T=D÷R
Where T = Time, Time of Travel (h)
D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

AVERAGE HAULING DISTANCE = 35.00 KM (FLAT, PAVED)


LOADED TRAVEL TIME
First 200 m @ 20 kph = 0.60 min
Succeeding 1300 m @ 35 kph = 59.31 min
Next 200 m @ 20 kph = 0.60 min
RETURN EMPTY
First 200 m @ 30 kph = 0.40 min
Succeeding 1300 m @ 55 kph = 37.75 min
Next 200 m @ 30 kph = 0.40 min
Cycle Time, T = 99.06 min
Allowance for Delay (10% of cycle time) = 9.91 min
Total Cycle Time, T = 108.97 min
Total Cycle Time, T = 1.82 hours

ACEL RATE of Cargo truck = P 783.00

Total Rate of Cargo Truck for One Cycle = P 783.00 per hour x 1.82 hrs = P 1,422.00

Labor for loading & Unloading = 2 laborers x P47.34/hour x 1.82 hours


= P 171.95

Total Hauling Cost for One Cycle = P 1,593.95

Hauling Cost per bag of cement = P 1,593.95 / 150 bags = P 10.63


Cost of Cement per Bag (Validated CMPD for 2nd quarter CY 2016) = P 258.33

TOTAL COST OF CEMENT PER BAG INCLUDING HAULING COST = P 268.96


32000
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol

BACK-UP COMPUTATION

1 Item #REF! - #REF! #REF!

2 Item #REF! - #REF! #REF!

3 Item B.5 - Project Signboard/billboard 1.00

4 Item B.7 - Occupational Safety & Health Program 5.00

5 Item B.9 - Mobilization/Demobilization 1.00

6 Item 803(1)a - Structure Excavation ,Common soil 207.00

1.) 8 units-Footing(F1) ((1.5*1.4*1.40) *8= 23.520


2.) 8 units-Footing(F2)= ((1.5*2.3*2.3))*8 = 63.480
3.) 8 units -Footing(F3)= (1.5*2.10*2.10))*8 = 52.920
4.) Wall Footing(WF1)= ((.60*.40*6.3) = 21.512
5.) Wall Footing(WF2)= (0.25*0.60*17.75)) 2.663
6.) Footing Tie Beam = ((.50*.30*65) 9.750
7.) Septic Tank = ((2.00*2.3*7.00) 32.200
8.) Fire escape footing = ((.60*.60*.30)2 0.216
9.) 4units (DC2) = ((0.40*.40*4) 0.640

206.90
SAY : 207.00

4 Item 804(1)a - Embankment from structure excavation 165.00

1.)Excavated materials 207.00


2.)Vol. of concrete in place 41.63
Vol.of embankment: 165.00

4 Item 804(1)b - Embankment from borrow 361.00


1.)Typical embankment: ((31.70*9.5*.40) 120.46

2.)Rise in elev. (+800mm) 240.92


SAY: 361.00

5 Item 804(4) - Gravel Fill 30.10


Volume: (31.70x9.5)*(.10) 30.12
SAY: 30.10 m3

Page 13
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol

BACK-UP COMPUTATION

6 Item 1000 (1) - Soil Poisoning 48.00


A=313 m2
Liter=313/6.5 48.15
Say: 48.00 liter
7 Item 900 (1)c2 - Structural Concrete (Footing & Slab on fil )Class A 28 days 76.00

1.) 8-Footing(F1) ((1.40x1.40x0.35)8 5.49


8-Footing(F2) ((2.30x2.30x0.35)8 14.81
8-Footing(F3) ((2.10x2.10x0.35)8 12.35
Wall footing(WF1)inc reataining wall foo((0.40*0.20x7) 7.56
Wall footing(WF2) ((0.40*0.20x17.80) 1.42
Flooring ((247.95 m2 x 0.10) 24.80
Corridor ((79.5 m2 x 0.10 ) 7.950
Ramp ((16.40 m2 x0.10) 1.640
76.017
SAY: 76.00

7 Item 900(1)c3 - Structural Concrete(Wall Footing) Class A 28 days 21.00

2.) FootingTie beams(FTB1) ((0.30x0.50) x(139.40) 20.91


20.91
SAY: 21.00

7 Item 900 (1)c4 - Structural Concrete(Columns)ClassA 28 days 38.30


3.) 24-Column(C1/C2/C3) ((0.40x0.40x(8.375+.80))24 units 35.23
Post Column(PC) ((0.30x0.25x2.5)2 units 0.38
Stiffener columns ((0.15x0.30x5.4)8 units 1.94
Fire Escape Column ((0.20x0.20x0.30)4 units 0.05
2DC1 ((0.20x0.20x6.725)2 units 0.54
2DC2 ((0.20x0.20x1.60)2 units 0.13
38.27
SAY: 38.30

7 Item Err:509 - Err:509 23.80

6.) Reinforced Concrete Slab(2nd Floor)


Slab(S1) ((235.30 m2x0.10) 23.53
Slab(S2) ((2.50 m2 x 0.10) 0.250

Page 14
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol

BACK-UP COMPUTATION
23.780
SAY: 23.80

7 Item 900 (1)c6 - Structural Concrete(Beams/Girder)Class A 28 days 54.80


4.) Beams(CB)
G1 ((0.25x0.40 x 28.5) 2.85
G2 ((0.25x0.40 x 28.5) 2.85
G3 ((0.25x0.40 x 28.5) 2.85
G4 ((0.25x0.40 x 2.5) 0.25
G5 ((0.25x0.50 x 7.00) 0.88
G6 ((0.25x0.40 x 2.5)7 units 1.75
G7 ((0.25x0.50 x7) 7 units 6.13
STB1 & STB2 ((0.20x0.40 x 3)2 0.48
17.55
5.) Roof Girders(RG)
3-Roof Girders(RG1) ((0.20x0.40 x 28.5)3 6.84
8-Roof Girders(RG1) ((0.20x0.40 x 28.5)8 22.80
8-Roof Girders(RG2) ((0.20x0.50 x 7)8 5.60
4-Lintel Roof beam(LRB1) ((0.20x0.25 x 7.56)4 1.51
Lintel beam (.15*.20*1.40)12 0.50
37.26
SAY: 54.80

7 Item 902(1)a1 - Reinforcing Steel Deformed)Grade 40 758.12

Reinforcing Steel for Column Footing,Column & wall footing Err:508

Err:509 Err:508

Err:509 Err:508

Err:509 Err:508

Err:509 Err:508

Reinforcing steel for roof beam Err:508

Reinforcing steel for flooring,corridor &ramp 92.40

Page 15
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol

BACK-UP COMPUTATION
Err:508
SAY: Err:508

7 Item 900 (7) - Reinforced Concrete


18.80
Reinforced Concrete Stair
Riser/thread ((0.40x1.40x3.265) 1.83
((0.40x1.40x3.19) 1.79
Landing ((2.95x1.35x0.10) 0.40

Reinforced Concrete Sunbreaker/counter sink


Sunbreaker ((.15 x.575 x25) 2.16
Countersink ((.60x2x0.10)2 0.24
Septic tank ((7x2.3x0.15) +(7x2.3x.10) 4.03
((2.3x2.10x0.15) 4 2.90
((7.0x2.10x0.15) 2 4.41
Catch basin ((.60x0.60x.15)2*10 1.08
*waterproofing for the septik and catch basin)
Total Volume: 18.82
SAY 18.80

8 Item 1046(2)a - CHB Non Load bearing (including reinforcing steel)100mm 151.00

Area CHB rail,toilets,storage room


((0.90x28.5)+(.90x2.5) 27.45
((0.90x21)+(.90*2.5) 21.15
((0.20x0.20x1.60)2 units 0.13
((14.15 x 2.7) 38.21
((6.85x2.70) 18.50
((8.6 x 3.10)+ (.70*1.60) 27.78
((6.45x2.70) 17.42
150.62
SAY: 151.00

9 Item 1046(2)b - CHB Non Load bearing (including reinforcing steel)150mm 594.00

Page 16
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol

BACK-UP COMPUTATION
Area ground floor ((87m x 2.8m) 302.40
Area 1st floor ((87mx 2.80m) 302.40

Eave wall ((7mx 2.50m) 17.50


Retaining wall: ((.80m x 83m)) 66.40

688.70
Less:doors/windows: 95.200 m2 SAY: 594.00

10 Item 1027(1) - Cement Plaster Finish 1,490.00


Area of CHB 100mm 302.00
Area of CHB 150mm 1,188.00
1,490.00 1,490.00

11 Item 1003(2)e2 - Wall 6mm Wood Frame Ordinary plywood 1.00

6 units blackboard 70.20 m2

12 Item 1003(1)a1 - Ceiling 4.5mm Metal frame Fiber cement board 337.00

Ceiling Area: 336.98 m2


SAY: 337.00 m2

13 Item 1004(2)c - Finishing hardware bolts 10.00

4" door pull set 5.00


4" barrel bolt set 5.00
10.00
14 Item 1004(2)e - Finishing hardware knobs 18.00

Doorknob,kwikset set 18.00

15 Item 1004(2)g - Finishing hardware hinges 39.00

3-1/2"x3 1/2" butt hinges pair 39.00

Page 17
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol

BACK-UP COMPUTATION
16 Item 1009(1)a - Jalousie Window Glass 59.40

Total Quantity: 12-W1; 12-W2; 6-W3


12 - W1 @ 36.120 m2
12 - W2 @ 21.000 m2
6 - W3 @ 2.310 m2
59.430
SAY: 59.400

17 Item 1010 (1) - Frames Jamb,Sill,Head,Transom & Mullions 53.00

For Doors/Windows 53.00 set


12 - W1 (1.50m x2.50m)
12 - W2 (1.50m x 1.40m)
6 -W3 (0.635m x 0.60m)
12 -D1 (.90mx2.10m)
1 -D1 (.90mx2.10m)
4 -D3 (.80mx2.10m)
5 -D4 (.60mx1.20m)
1 -D5 (.70mx1.20m)

18 Item 1010(2)a - Doors Flush 13.70


4 --2.10x
5
1 1.20x
2.10 .90m
2.10x.80 m hollow
x.60m
.70m hollowcore doorflush
coredoor
flush doordoor(w/kicking
doorflush
flush door
doorD3
D5 D4 plate) D2
SAY: 1.89 m2
6.72
3.60
1.47
13.68
14.00
Total Quantity : 11 units
1 -2.10x .90m hollow core doorflush door(w/ kicking plate) 1.89
4 - 2.10x.80 m hollow core door flush door 6.72
5 - 1.20x .60m hollow core door flush door 3.60
1 - 2.10 x .70m hollow core flush door 1.47
13.68 m2
SAY: 13.70 m2

19 Item 1010(2)b - Door wood panel 22.70

Total Quantity : 12 -D1


12 -2.10x.90m solid panel door 22.68
SAY: 22.70 m2

20 Item 1017(1)a2 - Roof drain with strainers,75mm Ø 16.00


Reference(plans): 16.00 set

Page 18
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol

BACK-UP COMPUTATION

21 Item 1018(1) - Glazed Tiles & Trims 104.00

Wall(CR) 75.00
Floor(CR) 19.00
Countersink/urinals) 10.00
104.00 m2

22 Item 1032(1)1 - Painting works masonry/concrete 2,334.00

columm 115.00
roof beam 90.00
ceiling 302.00
Plaster finish 1,490.00
Fiber cement board 337.00
2,334.00
SAY: 2,334.00 m2

23 Item 1032(1)a2 - Painting works wood 247.00

Frames (jambs, mullions,


transom ) 174.30
Doors 72.80
247.10

Say: 247.00

24 Item 1032(1)a3 - Painting works steel 60.30

Metal railings:
36.7+22.70+2.50 Balcony 16.49
12+ Ramp/handrail 0.87
64+12 Stairs 38.00
42 Fire escape 4.96
60.32 m2

Page 19
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol

BACK-UP COMPUTATION
SAY: 60.30 m2

25 Item 1047(2)a - Structural Steel 1.00

Roof framing
26-6mmthk x 75mm x 75mm x 6m angle bar -Top Chord kg 1,102.00
19-6mm thk x 75mm x 75mm x 6m angle bar -Bottom Chord kg 805.31
23-6mm thk x 65mm x 65mm x 6m angular bar-webmember kg 844.87
35-6mm thk x 50mm x 50mm x 6m angular bar -web & clip angle kg 988.97
26-1mm thk x 50mm x 6m -filler plate kg 62.22
5 -5mmx40mmx40mm x 6m angle bar kg 94.19
5 - 6mm thk x 100mm x 100mm x 6m angle bar- LRB kg 282.56
154 -2mm thk x20x 65 x 150 x 6m LC purlins kg 4,641.58
24- 25mm thk x 25mm x 25mm angle bar - fascia frame kg 254.31
30 -12 mm Ø x 6.00 m. plain bar for sag rod kg 159.84
34 -16mmØ x 6.0m plain bars for cross brace,grade 40 kg 311.92
6mm thk x 1.2m x 2.4m gusset plate pc 4.00
24-12mm thk x 350mm x 350mm base plate w/4-16mmØ hole pc 24.00
16mmǾ x 350mm machine bolts w/ nuts and washer pc 96.00
12mmǾ x 250mm machine bolts w/ nuts and washer pc 64.00
12mmØ x150mm machine bolts w/ nuts and washer pc 104.00
12mm Ø x 25mm bolts w/ nuts and washer pc 2,700.00
16mmØ turn buckle pc 28.00
12mmØ turn buckle plate pc 12.00
1-uint Fire Escape
23 - 2mm thk x20mmx20mm x 6m -stair nosing kg 86.65
4 - 6mm thk x150mmx150mm base plate w 4-12mm Ø hole pc 4.00
20 - 12mmØ x100mm bolts w/ nut and washer pc 20.00
5mm thk x 1.20m x2.40 base plate kg 113.03
1.25 -6mm thk x1.20mx 2.40m checkerd plate flooring kg 135.63
0.10 - 8mm thk x 1.20 m x 2.40m gusset plate kg 180.84
0.375 - 10mm thk x 1.20 m x 2.40 m gusset plate kg 226.05
2 - 6mm thk x 65mmx65mm angle bar kg 97.96
4 - 6mm thk x50mmx50mm x6m angle bar kg 113.03
8 - 4.5mm thk x38mmx38mm x 6m angle bar kg 32.21
2 -4.5mm x25mmx25mm x 6m angle bar kg 21.19
12mm thk flange w/spider leg (fab.) pc 4.00

26 Item 1051(1) - Metal Railing Steel 230.00

(ramp, balcony,hand rail,stair railings) Length= 230.00 meter

Page 20
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol

BACK-UP COMPUTATION
Ramp= 12.00 m
Stairs= 76.00 m
Balcony railing= 61.90 m
Fire Escape = 80.00 m

28 Item 1014(1)b1 - Prepainted Metal sheet above 0.427mm corrugated type,long span 428.00

Roof Area:(32.70m x 6.55m)*2 428.37 m2


SAY: 428.00 m2

52 Item Err:509 - Err:509 Err:509

52 Item 1001(8) - Sewer Line Works 1.00

52 Item Err:509 - Err:509 Err:509

52 Item Err:509 - Err:509 #REF!

52 Item 1100(30) - Conduits,Boxes & Fittings 1.00

53 Item 1101(42) - Wires and Wiring Devices 1.00

54 Item 1102(27) - Powerload Center,Switchgear and Panelboards 1.00

55 Item 1103(1) - Lighting Fixtures 1.00

55 Item Err:509 - Err:509 Err:509

Quantity: 12.00 set Wall fan

PREPARED BY: SUBMITTED BY:

MARY NOELINE F. RACINES LUCIO L. BAGOL

Page 21
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Bohol 1st District Engineering Office
Tagbilaran City

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol

BACK-UP COMPUTATION
Engineer II OIC - Chief, Planning & Design

Page 22
3/4/2016 -As per sir Lucio, a

#REF!

#REF!

each 03/07/2016; 11:33AM - disreg


03/07/2016; 11:33AM - As pe
Month

71 5.325

5.325

151.2

Page 23
3/4/2016 -As per sir Lucio, a

liter

c1 8 at800m 51.2 9.309091 7


c2 14 89.6 16.29091 13
c3 12 76.8 13.96364 11
Ties
c1 5.333333 at 3.5 168 30.54545
c2 5.333333 at 5 240 43.63636
c3 5.333333 at 5 240 43.63636
117.8182

Page 24
3/4/2016 -As per sir Lucio, a

Page 25
3/4/2016 -As per sir Lucio, a

m2

m2

Page 26
3/4/2016 -As per sir Lucio, a

m2

l.s
from Facilities of Handicapped Daorong & Kalibo leading to various beach resorts, danao, Pang

m2 2 8.6

1.2 -30.5

set

set

set

Page 27
3/4/2016 -As per sir Lucio, a
m2

set

m2

m2
1 -2.10x .90m hollow core doorflush door(w/ kicking plate) m2
4 - 2.10x.80 m hollow core door flush door m2
5 - 1.20x .60m hollow core door flush door m2
1 - 2.10 x .70m hollow core flush door m2

set

Page 28
3/4/2016 -As per sir Lucio, a

m2

771.498

508.68
226.08

m2

m2 247.8

19.200 19.2 38.4 37.8

6.000 6

m2

Page 29
3/4/2016 -As per sir Lucio, a

l.s

Angle bars: 85.74


Purlins: 591.00
844.87
#REF!
#REF!
-
#REF!
0
254.3076
159.84
311.92
6,239.01
826.75

86.65296
232.75

113.03
135.63
180.84
226.05
97.96
113.03
32.21
21.19

meter

Page 30
3/4/2016 -As per sir Lucio, a

m2

ls

ls

Err:509

lm

ls

l.s

set

ls

ls

Php 1,000.00 + P 1,002.10

Page 31
3/4/2016 -As per sir Lucio, a
gn

Page 32
r sir Lucio, addt'l 4m width for item 100 (2m both sides)

33AM - disregard stone masonry on left side portion in case magkuwang ang kwarta - as per sir eloy
33AM - As per sir eloy for item 100 magstart sa (see magenta colored dimension)..

Page 33
r sir Lucio, addt'l 4m width for item 100 (2m both sides)

danao, Panglao, Bohol

Page 34
Republic of the Philippines
Province of Bohol
Municipality of Bohol
Office of the Municipal Engineer

PROGRAM OF WORK BUDGET/COST

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol
Starting time : Upon approval
Appropriation : P 1,898,849.36 Calendar days: 180
Source of Fund : Municipal Fund CY'2019 Date:
Classification : Public Market
Equipment
Description of Work to be done
Description/Nos.

Other General Requirements


Item No. Estimated Cost of Project
Description %Total Unit Quantity
Unit Cost Total Cost
PART A OTHER GENERAL REQUIREMENTS

B.5 Project billboard /Signboard 0.25 each 1.00 P 4,700.27 P 4,700.27


B.7 Occupational safety and Health Program 2.37 month 5.00 P 9,009.57 P 45,047.83

B.9 Mobilization/Demobilization l.s 1.00 P 14,278.01 P 14,278.01

PART B EARTHWORKS
803(1)c Structure Excavation solid rock 0.14 m³ 5.32 P 502.32 P 2,671.33
804(1)a Embankment from structure excavation 1.11 m³ 2.72 P 7,730.59 P 21,058.13
804(4) Gravel Fill 0.38 m³ 4.01 P 1,809.15 P 7,254.68
1000 (1) Soil Poisoning 0.35 liter 2.00 P 3,353.12 P 6,706.24
PART C REINFORCED CONCRETE
900 (1)c2 Structural Concrete (Footing & Slab on fil )Class A 1.05 m³ 2.26 P 8,843.21 P 19,967.97
28 days
900(1)c3 Structural Concrete(Wall Footing) Class A 28 days 4.13 m³ 0.84 P 93,584.25 P 78,330.02

900 (1)c4 Structural Concrete(Columns)ClassA 28 days 1.72 m³ 1.37 P 23,896.47 P 32,690.38


900 (1)c6 Structural Concrete(Beams/Girder)Class A 28 days 1.56 m³ 1.04 P 28,512.10 P 29,652.59

902(1)a1 Reinforcing Steel Deformed)Grade 40 3.07 kg 758.12 P 76.80 P 58,223.46

900 (7) Reinforced Concrete 3.25 m³ 1.00 P 61,903.15 P 61,655.54

PART D MASONRY WORKS

1046(2)a1 CHB Non load bearing(including reinforcing 2.37 m2 66.74 P 674.01 P 44,983.26
steel)100mm

PART E ROOF AND ROOF FRAMING


1047(1) Structural Steel 15.84 l.s 1.00 P 300,823.81 P 300,823.81

Page 35 of 235
Republic of the Philippines
Province of Bohol
Municipality of Bohol
Office of the Municipal Engineer

PROGRAM OF WORK BUDGET/COST

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol
Starting time : Upon approval
Appropriation : P 1,898,849.36 Calendar days: 180
Source of Fund : Municipal Fund CY'2019 Date:
Classification : Public Market
Equipment
Description of Work to be done
Description/Nos.

Other General Requirements


Item No. Estimated Cost of Project
Description %Total Unit Quantity
Unit Cost Total Cost
1014(1)b1 Prepainted Metal sheet G.I Corr. Sheet 6.07 m2 428.00 P 269.21 P 115,222.21

PART F ROOF DRAIN


1017(1)a2 Roof drain with strainers,75mm Ø 0.53 set 5.00 P 2,013.43 P 10,067.16
PART G DOORS,WINDOWS AND HARDWARE
1010(1) Frames (Jamb,sills, head,transoms and mullions) 2.40 set 53.00 P 859.70 P 45,564.06
1009(1)a Jalousie Windows glass 2.10 m2 59.40 P 669.89 P 39,791.66
1010(2)a Doors flush 1.11 m2 3.78 P 5,578.18 P 21,085.52
1004(2)e Finishing hardware, knobs 0.14 set 2.00 P 1,327.57 P 2,655.15
1004(2)g Finishing hardware, hinges 0.02 set 3.00 P 141.81 P 425.44
PART J DRAINAGE AND PLUMBING WORKS
502(4) Structural Concrete Cover-Drainage 46.34 cu.m 48.51 P 18,137.43 P 879,846.86
1001(8) Sewer Line Works 0.78 l.s 1.00 P 14,796.71 P 14,796.71
1002(28) Cold Water Lines 0.51 l.s 1.00 P 9,741.69 P 9,741.69
PART K ELECTRICAL WORKS
1100(30) Conduits,Boxes & Fittings 0.31 l.s 1.00 P 5,979.56 P 5,979.56
1101(42) Wires and Wiring Devices 0.59 l.s 1.00 P 11,278.47 P 11,278.47
1102(27) Powerload Center,Switchgear and Panelboards 0.22 l.s 1.00 P 4,211.13 P 4,211.13
1103(1) Lighting Fixtures 0.53 ls 1.00 P 10,140.23 P 10,140.23
99.25 P 1,898,849.36

1. Labor: Man-day P 578,621.96 A. Direct Cost P 1,513,262.12


2. Materials P 834,452.71 B. Const.Engineering 0.50%
3. Rental of Equipment P 100,187.44 C. OCM, Tax, Profit,Q.C. P 385,587.24
4. OCM, Tax, Profit, Q.C. P 385,587.24 D. Building permit/plans/machine copies
5. Const.Engineering 0.50% E. Soil Testing
6. Building permit/plans/machine copies - F. Total estimated Cost P 1,898,849.36
7. Soil Testing

Page 36 of 235
Republic of the Philippines
Province of Bohol
Municipality of Bohol
Office of the Municipal Engineer

PROGRAM OF WORK BUDGET/COST

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol
Starting time : Upon approval
Appropriation : P 1,898,849.36 Calendar days: 180
Source of Fund : Municipal Fund CY'2019 Date:
Classification : Public Market
Equipment
Description of Work to be done
Description/Nos.

Other General Requirements


Item No. Estimated Cost of Project
Description %Total Unit Quantity
Unit Cost Total Cost
8. Total Cost P 1,898,849.36
-
PREPARED BY: CHECKED BY:

GRACELDA S. QUILATON MARCELO R. BARBANIDA


M.E Staff/Project Inspector Draftsman II

OK AS TO APPROPRIATION: CONCURRED BY:

RUTH C. NANGKIL JUANITA O. BASILAD


Municipal Budget Officer Market Supervisor

Recommending Approval: Approved by:

Page 37 of 235
Republic of the Philippines
Province of Bohol
Municipality of Bohol
Office of the Municipal Engineer

PROGRAM OF WORK BUDGET/COST

Name of Project : Completion of Public Market-Two Storey Building


Location : Poblacion, Ubay, Bohol
Starting time :
Appropriation : #REF! Calendar days:
Source of Fund : Municipal Fund CY'2019 Date:
Classification : Public Market
Equipment
Description of Work to be done
Description/Nos.

Other General Requirements


Item No. Estimated Cost of Project
Description %Total Unit Quantity
Unit Cost
PART A OTHER GENERAL REQUIREMENTS
B.5 Project billboard /Signboard #REF! each 1.00 P 4,700.27
B.7 Occupational safety and Health Program #REF! month 5.00 P 9,009.57

PART B EARTHWORKS
803(1)c Structure Excavation solid rock #REF! m³ 5.32 P 502.32
804(1)a Embankment from structure excavation #REF! m³ 2.72 P 7,730.59
804(4) Gravel Fill #REF! m³ 4.01 P 1,809.15
1000 (1) Soil Poisoning #REF! liter 2.00 P 3,353.12
PART C REINFORCED CONCRETE
900 (1)c2 Structural Concrete (Footing & Slab on fil )Class A #REF! m³ 2.26 P 8,843.21
28 days
900(1)c3 Structural Concrete(Wall Footing) Class A 28 days #REF! m³ 0.84 P 93,584.25

900 (1)c4 Structural Concrete(Columns)ClassA 28 days #REF! m³ 1.37 P 23,896.47


900 (1)c6 Structural Concrete(Beams/Girder)Class A 28 days #REF! m³ 1.04 P 28,512.10

902(1)a1 Reinforcing Steel Deformed)Grade 40 #REF! kg 758.12 P 76.80

900 (7) Reinforced Concrete #REF! m³ 1.00 P 61,903.15

PART D MASONRY WORKS

1046(2)a1 CHB Non load bearing(including reinforcing #REF! m2 66.74 P 674.01


steel)100mm

PART E ROOF AND ROOF FRAMING


1047(1) Structural Steel #REF! l.s 1.00 P 300,823.81
1014(1)b1 Prepainted Metal sheet G.I Corr. Sheet #REF! m2 428.00 P 269.21

PART F ROOF DRAIN


1017(1)a2 Roof drain with strainers,75mm Ø #REF! set 5.00 P 2,013.43
PART G DOORS,WINDOWS AND HARDWARE
1010(1) Frames (Jamb,sills, head,transoms and mullions) #REF! set 53.00 P 859.70
1009(1)a Jalousie Windows glass #REF! m2 59.40 P 669.89
1010(2)a Doors flush #REF! m2 3.78 P 5,578.18
1004(2)e Finishing hardware, knobs #REF! set 2.00 P 1,327.57
1004(2)g Finishing hardware, hinges #REF! set 3.00 P 141.81
PART I FINISHING WORKS
#REF! #REF! #REF! #REF! #REF! #REF!
PART J DRAINAGE AND PLUMBING WORKS
502(4) Structural Concrete Cover-Drainage #REF! cu.m 48.51 P 18,137.43
1001(8) Sewer Line Works #REF! l.s 1.00 P 14,796.71
#REF! #REF! #REF! #REF! #REF! #REF!
1002(28) Cold Water Lines #REF! l.s 1.00 P 9,741.69
PART K ELECTRICAL WORKS
1100(30) Conduits,Boxes & Fittings #REF! l.s 1.00 P 5,979.56
1101(42) Wires and Wiring Devices #REF! l.s 1.00 P 11,278.47
1102(27) Powerload Center,Switchgear and Panelboards #REF! l.s 1.00 P 4,211.13
1103(1) Lighting Fixtures #REF! ls 1.00 P 10,140.23
#REF!

1. Labor: Man-day A. Direct Cost


2. Materials B. Const.Engineering 0.50%
3. Rental of Equipment C. OCM, Tax, Profit,Q.C.
4. OCM, Tax, Profit, Q.C. D. Building permit/plans/machine copies
5. Const.Engineering 0.50% E. Soil Testing
6. Building permit/plans/machine copies - F. Total estimated Cost
7. Soil Testing
8. Total Cost -
#REF!
PREPARED BY: CHECKED BY:

GRACELDA S. QUILATON MARCELO R. BARBANIDA


M.E Staff/Project Inspector Draftsman II

OK AS TO APPROPRIATION: CONCURRED BY:

RUTH C. NANGKIL JUANITA O. BASILAD


Municipal Budget Officer Market Supervisor

Recommending Approval: Approved by:

WILFREDA M. PACATANG HON. CONSTANTINO H. REYES


Municipal Engineer Municipal Mayor
371
16

387
Upon approval 35 km from Tagbilaran City
180

uipment
ption/Nos.

stimated Cost of Project


Total Cost
#REF!
P 4,700.27
P 45,047.83
#REF!
P 2,671.33 P 24,538.40 #REF!
P 21,058.13
P 7,254.68
P 6,706.24

P 19,967.97

P 78,330.02

P 32,690.38
P 29,652.59

P 58,223.46

P 61,655.54

P 44,983.26

P 300,823.81
P 115,222.21

P 10,067.16

P 45,564.06
P 39,791.66
P 21,085.52
P 2,655.15
P 425.44

#REF!

P 879,846.86
P 14,796.71
#REF!
P 9,741.69

P 5,979.56
P 11,278.47
P 4,211.13
P 10,140.23
#REF! -

-
machine copies Err:508

- 11,070,295.00 11,070,295.00
11,070,295.00 ok
-

LO R. BARBANIDA
Draftsman II

A O. BASILAD

ANTINO H. REYES
Unit Price Analysis

Project : Completion of Public Market-Two Storey Building


Locaton : Poblacion, Ubay, Bohol
Item No. : B.5
Description : Project billboard /Signboard PRODUCTION RATE: 0.195
Quantity : 1.00 each NUMBER OF HOURS: 5.1282

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

2 pcs - 2"x3"x12' - lumber - Post bd.ft. 12.00 P 40.00 P 480.00


2 pcs - 2"x3"x10' - lumber - Brace bd.ft. 10.00 P 40.00 P 400.00
2 pcs - 1"x2"x10' -lumber - Sway Brace lin.ft. 20.00 P 40.00 P 800.00
Assorted C.W. Nails kg. 1.25 70.00 P 87.50
tarpaulin with standard billboard markings(4 x 8) pc 1.00 900.00 P 900.00

SUB-TOTAL (A) P 2,667.50


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 5.13 P 84.66 P 434.15


Carpenter 2 5.13 P 61.30 P 628.72

1
SUB-TOTAL (B) P 1,062.87
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 3,730.37

E. ADD: INDIRECT COST


1. OCM 12.00% of D 447.64
2. Contractor's Profit 8.00% of D 298.43
3. VAT 5% of (D+OCM+CP) 223.82
TOTAL INDIRECT COST P 969.90

TOTAL COST (D+E) P 4,700.27

UNIT COST P 4,700.27


1003d-1 ceiling frameworks

.6375m2/hr

.85sheet/hr

6.80sheet/md N

32

576

9
Unit Price Analysis

Project : Completion of Public Market-Two Storey Building


Locaton : Poblacion, Ubay, Bohol
Item No. : B.7
Description : Occupational safety and Health Program
Quantity : 5.00 month PRODUCTION RATE: 1.00
NUMBER OF HOURS: 1.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Safety Shoes (Different Sizes) man-days 442.00 P 4.02 P 1,776.84


Safety Helmet (free size) man-days 442.00 P 0.37 P 163.54
Safety Gloves (free size) man-days 442.00 P 8.00 P 3,536.00
Safety Reflectorized vest (free size) man-days 442.00 P 0.37 P 163.54

SUB-TOTAL (A) P 5,639.92


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

First aider 1 720.00 P 47.34 P 34,084.80

SUB-TOTAL (B) P 34,084.80


C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 39,724.72

E. ADD: INDIRECT COST


1. OCM 0% of D -
2. Contractor's Profit 8.000% of D 3,177.98
3. VAT 5.000% of (D+OCM+CP) 2,145.13
TOTAL INDIRECT COST P 5,323.11

TOTAL COST (D+E) P 45,047.83

UNIT COST P 9,009.57


442
Unit Price Analysis

Project : Completion of Public Market-Two Storey Building


Locaton : Poblacion, Ubay, Bohol
Item No. : B.9
Description : Mobilization/Demobilization PRODUCTION RATE:
Quantity : 1.00 l.s NUMBER OF HOURS:

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE

SUB-TOTAL (A)
B. LABOR COST QUANTITY Hourly
No. of Personnel Total Hours Rate

SUB-TOTAL (B)
C. EQUIPMENT COST QUANTITY Hourly
No. of Equipt. Total Hours Rate

Concrete mixer (1 Bagger) 2.00 10.00 136.00


Concrete vibrator 2.00 10.00 91.25
Welding machine 1.00 10.00 391.00
Jack hammer 1.00 10.00 514.31

SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C)

E. ADD: INDIRECT COST


1. OCM 0.00% of D -
2. Contractor's Profit 0.00% of D -
3. VAT 5% of (D+OCM+CP) 679.91
TOTAL INDIRECT COST

TOTAL COST (D+E)

UNIT COST
0.195
5.1282

TOTAL COST

-
Total
Cost

- - -
Total
Cost

2,720.00
1,825.00
3,910.00
P 5,143.10

P 13,598.10 Err:509 Err:509


P 13,598.10

15,132.62

P 679.91

P 14,278.01

P 14,278.01 9
Unit Price Analysis

Project : Completion of Public Market-Two Storey Building


Locaton : Poblacion, Ubay, Bohol
Item No. : 803(1)c
Description : Structure Excavation solid rock
Quantity : 5.32 m³ PRODUCTION RATE (m3/hr): 1.064
NUMBER OF HOURS: 5.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

SUB-TOTAL (A)
B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost
Construction Foreman 1 5.00 P 84.66 P 423.30
Laborer 4 5.00 P 47.34 P 946.80

3
SUB-TOTAL (B) P 1,370.10
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

Jack hammer 1.00 5.00 150.00 P 750.00

SUB-TOTAL (C) P 750.00


D. TOTAL DIRECT COST (A + B + C) P 2,120.10

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 254.41
2. Contractor's Profit 8% of D 169.61
3. VAT 5% of (D+OCM+CP) 127.21
TOTAL INDIRECT COST P 551.23

TOTAL COST (D+E) P 2,671.33

UNIT COST P 502.32


2.592
0.84
0.276

3.708
1.61

5.318
Unit Price Analysis

Project : Construction of 2 STY - 2 Classroom Tabalong National High School


Locaton : Tabalong,Dauis, Bohol
Item No. : 804(1)a
Description : Embankment from structure excavation
Quantity : 2.72 m³ PRODUCTION RATE (m3/hr):
NUMBER OF HOURS:

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE

SUB-TOTAL (A)
B. LABOR COST QUANTITY Hourly
No. of Personnel Total Hours Rate

Construction Foreman 1 0.66 P 84.66


Laborer 4 59.15 P 47.34

1
SUB-TOTAL (B)
C. EQUIPMENT COST QUANTITY Hourly
No. of Equipt. Total Hours Rate

plate compactor 1 59.15 92.25

SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C)

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 2,005.54
2. Contractor's Profit 8.00% of D 1,337.02
3. VAT 5% of (D+OCM+CP) 1,002.77
TOTAL INDIRECT COST

TOTAL COST (D+E)

UNIT COST
4.150
0.66

TOTAL COST

0.42 1.944
0.36

4.2 0.78
1.84

2.724
- 6.04
Total
Cost

P 55.57
P 11,200.64

P 11,256.21
Total
Cost

5,456.59

P 5,456.59
P 16,712.80

P 4,345.33

P 21,058.13

P 7,730.59
Unit Price Analysis

Project : Completion of Public Market-Two Storey Building


Locaton : Poblacion, Ubay, Bohol
Item No. : 804(4)
Description : Gravel Fill
Quantity : 4.01 m³ PRODUCTION RATE (m3/hr): 2.365
NUMBER OF HOURS: 1.70

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Gravel-Leyte source m³ 4.01 P 1,360.00 P 5,453.60

SUB-TOTAL (A) P 5,453.60


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost
Construction Foreman 1 1.70 P 84.66 P 143.55
Laborer 2 1.70 P 47.34 P 160.54

1
SUB-TOTAL (B) P 304.08
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 5,757.68

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 690.92
2. Contractor's Profit 8.00% of D 460.61
3. VAT 5% of (D+OCM+CP) 345.46
TOTAL INDIRECT COST P 1,497.00

TOTAL COST (D+E) P 7,254.68

UNIT COST P 1,809.15


1.61
0.54
1.4
0.46

4.01
BAR CHART FOR ITEM 803 - EXCAVATION O

Quantity (Volume) = 5.32 m³ Factor Materials Qty.

1 Materials: = -

2 Labor 4 Laborer

3 Equipment: -

ACTIVITIES D

1 Excavation 0.275 x 4.00 = 1.10 m3/hr 4.83

Total Time = 4.83 4.83 hrs.

Combine Production Rate = Total Quantity = 5.32 = 1.100


Total Time 4.83
3 - EXCAVATION OF FOOTING AND WALL FOOTING

Condition

1 Small Project
2 Common Earth
3 Flat Terrain
4 Urban Location

DURATION

0.33608
0.08402

15.823613425374900

0.3360800
m3/hr
0.125
BAR CHART FOR ITEM 803 - Ba

Quantity (Volume) = 2.72 m³ Factor Materials Qty.

1 Materials: = -

2 Labor 4 Laborer

3 Equipment: -

ACTIVITIES D

1 Excavation 1.0375 x 4.00 = 4.15 m3/hr 0.66

Total Time = 0.66 0.66 hrs.

Combine Production Rate = Total Quantity = 2.72 = 4.150


Total Time 0.66
OR ITEM 803 - Backfill the excavated

Condition

1 Small Project
2 Common Earth
3 Flat Terrain
4 Urban Location

DURATION

0.33608
0.08402

8.105213044513210

0.3360800
m3/hr
0.125
BAR CHART FOR ITEM 804b - EMBANKMENT ( BORROW)

Quantity (Volume) = 65.00 m³ Factor Materials Qty. Condition

2 Common Earth
3 Flat Terrain
4 Urban Location
2 Labor 2- Laborer

3 Equipment: - 1 unit Plate Compactor

ACTIVITIES DURATION

2.0 Spreading, 1.78 x 2.00 = 3.55 m3/hr 18.30


Tamping &

Total Time = 18.30 18.30 hrs.

Combine Production Rate = Total Quantity = 65.00 = 3.55


m3/hr
Total Time 18.30
BAR CHART FOR ITEM 804 -GRAVEL

Quantity (Volume) = 11.50 m³ Factor Materials Qty.

1 Materials: = 11.50 m³ Anapog - approved source 1.00 11.50 m³

2 Labor 2- Laborer

3 Equipment: -

ACTIVITIES DURAT

2.0 Spreading, 1.18 x 2.00 = 2.37 m3/hr 4.86


Tamping &

Total Time = 4.86 4.86 hrs.

Combine Production Rate = Total Quantity = 11.50 = 2.365


Total Time 4.86
M 804 -GRAVEL BEDDING

Condition

1 Small Project
2 Common Earth
3 Flat Terrain
4 Urban Location

DURATION

m3/hr
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1000 (1)
Description : Soil Poisoning
Quantity : 2.00 liter PRODUCTION RATE (liter/hr): 1.350
NUMBER OF HOURS: 25.93

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Lentrex soil poisoning solution liter 2.00 P 950.00 P 1,900.00

SUB-TOTAL (A) P 1,900.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost
Construction Foreman 1 25.93 P 84.66 P 2,194.89
Laborer 1 25.93 P 47.34 P 1,227.53

1
SUB-TOTAL (B) P 3,422.42
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 5,322.42

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 638.69
2. Contractor's Profit 8.00% of D 425.79
3. VAT 5% of (D+OCM+CP) 319.34
TOTAL INDIRECT COST P 1,383.83

TOTAL COST (D+E) P 6,706.24

UNIT COST P 3,353.12


0.31 -qty
BAR CHART FOR ITEM 1000 - SOIL P

Quantity (Volume) = 14liters/94.04m2= 0.15 m2 Factor Materials Qty.

1 Materials: = 2.00 liters 1.00 0.15 m³

2 Labor 1- Laborer

3 Equipment: -

ACTIVITIES DURA

soil poisoning = 0.2825 x 1.00 = 0.28 m2/hr 7.08

Total Time = 7.08 7.08 hrs.


1.5
Combine Production Rate = Total Quantity = 229.50 = 32.42
Total Time 7.08

1.35
EM 1000 - SOIL POISONING

Condition

1 Small Project
2 Common Earth
3 Flat Terrain
4 Urban Location

DURATION

m2/hr
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 900 (1)c2
Description : Structural Concrete (Footing & Slab on fil )Class A 28 days
Quantity : 2.258 m³ PRODUCTION RATE (m3/hr): 0.282
NUMBER OF HOURS: 8.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Portland cement - approved brand (Portland Type I) bag 23.00 P 260.00 P 5,980.00
Sand - Leyte source cu.m. 2.00 P 1,360.00 P 2,720.00
Gravel - Leyte source cu.m. 3.00 P 1,360.00 P 4,080.00

SUB-TOTAL (A) P 12,780.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 8.00 P 84.66 P 677.28


Mason 1 8.00 P 61.30 P 490.40
Laborer 1 8.00 P 47.34 P 378.72

2
SUB-TOTAL (B) P 1,546.40
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

concrete mixer 1 4.74 172.00 815.40


concrete vibrator 1 4.74 148.88 705.80

SUB-TOTAL (C) P 1,521.20


D. TOTAL DIRECT COST (A + B + C) P 15,847.60

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 1,901.71
2. Contractor's Profit 8.00% of D 1,267.81
3. VAT 5% of (D+OCM+CP) 950.86
TOTAL INDIRECT COST P 4,120.38

TOTAL COST (D+E) P 19,967.97

UNIT COST P 8,843.21


0.648
22.58 21.451 1.61
1.5806 1.92
2.1451 0.648
2.258
1.61

2.258
2.258

21.451
21.451
1.9193
1.9193
2.258 2.258

0.121002

4.74071
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 900(1)c3
Description : Structural Concrete(Wall Footing) Class A 28 days
Quantity : 0.84 m³ PRODUCTION RATE (m3/hr): 0.0058
NUMBER OF HOURS: 144.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Portland cement - approved brand (Portland Type I) bag 9.00 P 260.00 P 2,340.00
Sand - Leyte source cu.m. 0.75 P 1,360.00 P 1,020.00
Gravel - Leyte source cu.m. 1.00 P 1,360.00 P 1,360.00
lumber bd.ft 63.00 P 40.00 P 2,520.00
assorted CWN kg 1.00 P 70.00 P 70.00
1/4"x4'x8' ordinary plywood sheet 3.00 P 400.00 P 1,200.00

SUB-TOTAL (A) P 8,510.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 144.00 P 84.66 P 12,191.04


Mason 2 144.00 P 47.34 P 13,633.92
Carpenter 2 144.00 P 47.34 P 13,633.92
laborer 2 144.00 47.34 13,633.92
108
SUB-TOTAL (B) P 53,092.80
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

Concrete mixer 1 1.76 172.00 302.25


Concrete vibrator 1 1.76 148.88 261.63

SUB-TOTAL (C) P 563.88


D. TOTAL DIRECT COST (A + B + C) P 62,166.68

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 7,460.00
2. Contractor's Profit 8.00% of D 4,973.33
3. VAT 5% of (D+OCM+CP) 3,730.00
TOTAL INDIRECT COST P 16,163.34

TOTAL COST (D+E) P 78,330.02

UNIT COST P 93,584.25


27.84

8.37 7.9515 0.42


0.5859 0.59 0.5859 0.72
0.79515 0.71145 0.84 0.63
62.98425 0.276 0.207
1.259685 1.116
2.79558 1.14
0.837

10.83

0.969

123.30

6.238872

1.76 172 1,376.00 mixer/vibrator = .4763m3/hr.


148.88 1,191.04
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 900 (1)c4
Description : Structural Concrete(Columns)ClassA 28 days
Quantity : 1.368 m³ PRODUCTION RATE (m3/hr): 0.1440
NUMBER OF HOURS: 9.50

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Portland cement - approved brand (Portland Type I) bag 14.00 P 260.00 P 3,640.00
Sand - Leyte source cu.m. 1.25 P 1,360.00 P 1,700.00
Gravel - Leyte source cu.m. 1.50 P 1,360.00 P 2,040.00
Lumber bd.ft. 300.00 P 40.00 P 12,000.00
Assorted C. W. Nails kg 3.00 P 70.00 P 210.00
1/4" x 4' x 8' ordinary plywood sheet 4.00 P 350.00 P 1,400.00

SUB-TOTAL (A) P 20,990.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 9.50 P 84.66 P 804.27


Mason 2 9.50 P 61.30 P 1,164.70
Carpenter 2 9.50 P 61.30 P 1,164.70
Laborer 2 9.50 P 47.34 P 899.46

8
SUB-TOTAL (B) P 4,033.13
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

Concrete mixer 1 2.87 172.00 494.01


Concrete vibrator 1 2.87 148.88 427.60

SUB-TOTAL (C) P 921.61


D. TOTAL DIRECT COST (A + B + C) P 25,944.74

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 3,113.37
2. Contractor's Profit 8.00% of D 2,075.58
3. VAT 5% of (D+OCM+CP) 1,556.68
TOTAL INDIRECT COST P 6,745.63

TOTAL COST (D+E) P 32,690.38

UNIT COST P 23,896.47


original volume 35.8
additional 2.31m3

1.368

13.68 12.996 0.912


0.96 1.16
1.30
102.94
2.06
4.57 5.116959 12.996

1.1628

36

300

6.34

0.192145

2.87 22.98
Unit Price Analysis

Project : Completion of Public Market-Two Storey Building


Locaton : Poblacion, Ubay, Bohol
Item No. : 900 (1)c6
Description : Structural Concrete(Beams/Girder)Class A 28 days
Quantity : 1.04 m³ PRODUCTION RATE (m3/hr): 0.1486
NUMBER OF HOURS: 7.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Portland cement - approved brand (Portland Type I) bag 11.00 P 260.00 P 2,860.00
Sand - Leyte source cu.m. 1.00 P 1,360.00 P 1,360.00
Gravel - Leyte source cu.m. 1.25 P 1,360.00 P 1,700.00
Coco Lumber bd.ft. 300.00 P 40.00 P 12,000.00
Assorted C. W. Nails kg 3.00 P 70.00 P 210.00
1/4" x 4' x 8' ordinary plywood sheet 4.00 P 350.00 P 1,400.00

SUB-TOTAL (A) P 19,530.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 7.00 P 84.66 P 592.62


Mason 2 7.00 P 61.30 P 858.20
Carpenter 2 7.00 P 61.30 P 858.20
Laborer 3 7.00 P 47.34 P 994.14

7
SUB-TOTAL (B) P 3,303.16
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

Concrete Mixer 1 2.18 172.00 375.56


Concrete vibrator 1 2.18 148.88 325.08

SUB-TOTAL (C) P 700.64


D. TOTAL DIRECT COST (A + B + C) P 23,533.80

E. ADD: INDIRECT COST


1. OCM 12.000000% of D 2,824.06
2. Contractor's Profit 8.00% of D 1,882.70
3. VAT 5% of (D+OCM+CP) 1,412.03
TOTAL INDIRECT COST P 6,118.79

TOTAL COST (D+E) P 29,652.59

UNIT COST P 28,512.10


9.015 12.715 ok
#NAME?

10.4 10.4
0.73
0.99
78.26 187.5
1.57 9.88
2.40 5.7692308
0.884

0.56
0.48
0.56
0.184
1.04

0.744

6.25
429.10

0.169133

2.18 17.47
Unit Price Analysis

Project : Completion of Public Market-Two Storey Building


Locaton : Poblacion, Ubay, Bohol
Item No. : 902(1)a1
Description : Reinforcing Steel Deformed)Grade 40
Quantity : 758.12 kg PRODUCTION RATE (kg/hr): 42.118
NUMBER OF HOURS: 18.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

1.0 Reinforcing Steel for Column Footing,Column & wall footing


45 - 12mmØ x 6.0m def bar kg 239.76 P 45.00 P 10,789.20
46 -10mmØ x6.0m def. bar kg 170.02 P 45.00 P 7,650.90

6.0 Reinforcing steel for roof beam


30 -12mmØ x 6.00 m def bar kg 159.84 P 45.00 P 7,192.80
26 -10mmØ x 6.00m def bar kg 96.10 P 45.00 P 4,324.50

7.0 Reinforcing steel for flooring,corridor &ramp


25 - 10mmØ x 6.0m def bar kg 92.40 P 45.00 P 4,158.00

#16 GI Tie Wire kg 15.16 P 70.00 P 1,061.20

SUB-TOTAL (A) P 35,176.60


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 18.00 P 84.66 P 1,523.88


Steelman 4 18.00 P 61.30 P 4,413.60

5
SUB-TOTAL (B) P 5,937.48
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

Bar Cutter 1.00 8.92 219.75 1,959.96


Bar bender 1.00 8.92 351.5 3,135.05

SUB-TOTAL (C) P 5,095.01


D. TOTAL DIRECT COST (A + B + C) P 46,209.09

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 5,545.09
2. Contractor's Profit 8.00% of D 3,696.73
3. VAT 5% of (D+OCM+CP) 2,772.55
TOTAL INDIRECT COST P 12,014.36

TOTAL COST (D+E) P 58,223.46

UNIT COST P 76.80


5.328 218.45 239.76 4.8 103.488 3
3.696 170.02 24
35 6 23.33333 35

4
5.328 159.84 74.592
3.696 96.10 48.048 4.666667 6 46.66667 3.65
10 6.85
2 34.25 18.25
3.696 1023.792
36.96 0.766667 0.333333 50
14.53 0.01917 133.056

10 2.15
26.83333
758.12 10.75
758.12 8.944444 24
14
773.28 2.8

15.16 5 1
773.280
36
23.33333
0.168791
4.666667 36 45

92.4 12 6.55
12 32.75
1.75 5.5
2.25 24
758.12 24 1.75
15.16 4.5 1.5 3
18 1.5
10 1.333333
1.666667

2.666667
2.333333
0.15 3 4
0.3
0.45 6

0.9

24
2.9
14.5 2.8 11.2

1 4

30

6
Unit Price Analysis

Project : Completion of Public Market-Two Storey Building


Locaton : Poblacion, Ubay, Bohol
Item No. : 900 (7)
Description : Reinforced Concrete
Quantity : 1.00 m³ PRODUCTION RATE (m3/hr): 0.077
NUMBER OF HOURS: 13.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Portland cement - approved brand (Portland Type I) bag 11.00 P 260.00 P 2,860.00
Sand - Leyte source cu.m. 8.25 P 1,360.00 P 11,220.00
Gravel - Leyte source cu.m. 10.00 P 1,360.00 P 13,600.00
Lumber bd.ft. 250.00 P 40.00 P 10,000.00
Assorted C. W. Nails kg 4.00 P 70.00 P 280.00
1/4" x 4' x 8' ordinary plywood sheet 3.00 P 350.00 P 1,050.00

Concrete stair
4- 12mmØ x 6.0m def bar kg 21.31 P 45.00 P 958.95
6- 10mmØ x 6.0m def bar kg 22.18 P 45.00 P 998.10

countersink
10- 10mmØ x 6.0m def bar kg 36.96 P 45.00 P 1,663.20

#16 GI Tie Wire kg 1.61 P 70.00 P 112.70

SUB-TOTAL (A) P 42,742.95


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 13.00 P 84.66 P 1,100.58


Mason/Carpenter 4 13.00 P 61.30 P 3,187.60
Laborer 2 13.00 P 47.34 P 1,230.84

10
SUB-TOTAL (B) P 5,519.02
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

Concrete mixer (one bagger) 1 2.09 P 172.00 P 359.67


Conrete vibrator 1 2.09 P 148.88 P 311.33

SUB-TOTAL (C) P 671.00


D. TOTAL DIRECT COST (A + B + C) P 48,932.97

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 5,871.96
2. Contractor's Profit 8.00% of D 3,914.64
3. VAT 5% of (D+OCM+CP) 2,935.98
TOTAL INDIRECT COST P 12,722.57

TOTAL COST (D+E) P 61,655.54

UNIT COST P 61,903.15


250

1.15
13
0.996 9.5

27.84 8.075
0.304
9.96 9.5
0.6972 0.70 0.6972 0.304 0.96
0.9462 0.288 1.264
74.95 195.7831 0.304
1.50 0.592 0.161 0.288
3.33 6.024096 0.14 12.008
0.301 1.0744 0.592
4 5499.03
5.328 138.528 21.31 21.312 0.316667 5.624
3.696 181.104 22.18 14.784 7.6 0.5032
80.45 0.893 1.266667 0.592

3.696 258.72 36.96 0.791667


4.75 4
1.61
2.6 1.2
1.916667 1.333333
36.96 0.6 150
5.75 8 2.666667
2.533333 8 2.666667
2.4 0.096
0.288
5 0.833333 1.75
80.45 0.533333
5 1.666667 0.304 15.2
0.129121 18.48 0.9
3
80.45 0.592 0.9
55.44 9.5 3
2.09
1.61 0.031667 5.624
3.333333
0.5032
0.0592
.
.
1.75

2.9
5.8

1.4 18

1.61
2.45

4.06
0.406
4

1.266667 4

1.2
4.75

0.6
1.333333
0.8
BAR CHART FOR ITEM 901(c2) - REINFORCED CONCRE

Quantity (Volume) = 2.26 m³ Factor Materials Qty.

1 Materials: 22.00 bags - Portland Cement 10.00 22.58 bags


1.13 m³ Sand 0.50 1.13 m³
2.15 m³ Gravel 0.95 2.15 m³

2 Labor 1- Leadman
1- Mason
1- Labor

3 Equipment: - 1 Concrete Mixer, 1 bagger


1 Concrete Vibrator

ACTIVITIES DURAT

1 1-bagger Mixing - 0.476 x 1.00 = 0.4763 m3/hr 4.74

2 Placing Concrete - 0.415 x 2.00 = 0.830 m3/hr 2.72

Total Time = 7.46 7.46 hrs.

Combine Production Rate = Total Quantity = 2.26 = 0.303


Total Time 7.46
NFORCED CONCRETE FOOTING,SLAB ON FILL

Condition

1 Small Project
2 Flat Terrain
3 Urban Location

DURATION

0.125 56.00

0.040321
m3/hr
BAR CHART FOR ITEM 900(1) c3- REINFORCED CONCR

Quantity (Volume) = 0.84 m³ Factor Materials Qty.

2 Labor 1- Mason
2- Carpenter
2- Labor
1- Lead Man
3 Equipment: - 1 Concrete Mixer, 1 bagger
1 Concrete Vibrator

ACTIVITIES DU
Formworks: ( 201.60 m2 )

1 Installation 0.2725 x 6.00 = 1.635 m3/hr 123.30

2 Stripping 0.825 x 6.00 = 4.95 m3/hr 40.73 20.3636

Concreting (V = 3.75cu.m.)

1 1-bagger Mixing - 0.4763 x 1.00 = 0.4763 m3/hr 1.76

2 Placing Concrete - 0.1275 x 6.00 = 0.765 m3/hr 1.09

Total Time = 143.67 143.67 hrs.

Combine Production Rate = Total Quantity = 0.84 =


Total Time 143.67
REINFORCED CONCRETE for tie beam & lintel beam

Materials Qty. Condition

108
56 164

DURATION
32.4
4.2
36.6

123.30

0.0058
m3/hr
BAR CHART FOR ITEM 900©bc - REINFORCED CONC

Quantity (Volume) = 1.37 m³ Factor Materials Qty.

2 Labor 1- Leadman
1- Mason
2 Carpenter
2- Labor

3 Equipment: - 1 Concrete Mixer, 1 bagger


1 Concrete Vibrator

ACTIVITIES D
Formworks: ( 11.52 m2 )

1 Installation 0.3575 x 6.00 = 2.145 m3/hr 5.37

2 Stripping 0.995 x 6.00 = 5.97 m3/hr 1.93 0.96482

Concreting (V 35.08

1 1-bagger Mixing - 0.4763 x 1.00 = 0.4763 m3/hr 2.87

2 Placing Concrete - 0.1275 x 6.00 = 0.765 m3/hr 1.79

Total Time = 9.09 9.09 hrs.

Combine Production Rate = Total Quantity = 1.37 =


Total Time 9.09
REINFORCED CONCRETE COLUMN,PC & STIFFENER

Materials Qty. Condition

Forms
78.4
1.8
0.2
80.4
DURATION

6.34

0.1505
m3/hr
BAR CHART FOR ITEM 900(1)c5 - Suspen

Quantity (Volume) = #REF! m³ Factor Materials Qty.

2 Labor 1- Leadman
2 Carpenter
1 Mason
2 laborer
3 Equipment: - 1 Concrete Mixer, 1 bagger
1 Concrete Vibrator

ACTIVITIES DUR
Formworks: ( #REF! m2 )

1 Installation 0.3225 x 6.00 = 1.935 m3/hr #REF!

2 Stripping 0.2388 x 6.00 = 1.4328 m3/hr #REF!


erecting/forming per 100 m2 contract surface

Concreting (V =26.04cu.m.)

1 1-bagger Mixing - 0.4763 x 1.00 = 0.4763 m3/hr #REF!

2 Placing Concrete - 0.11 x 5.00 = 0.550 m3/hr #REF!

Total Time = #REF! #REF! hrs.

Combine Production Rate = Total Quantity = #REF! =


Total Time #REF!
TEM 900(1)c5 - Suspended slab

Materials Qty. Condition

DURATION
32.4
4.2
36.6

ing per 100 m2 contract surface #REF!


#REF!

#REF!
m3/hr
BAR CHART FOR ITEM 900(1) c6- REINFORCED CONCR

Quantity (Volume) = 1.04 m³ Factor Materials Qty.

2 Labor 1 - Leadman
2 - Mason
3 - Carpenter
3 - Labor

3 Equipment: - 1 Concrete Mixer, 1 bagger


1 Concrete Vibrator

ACTIVITIES DUR
Formworks: ( 11.52 m2 )

1 Installation 0.2725 x 9.00 = 2.453 m3/hr 4.70

2 Stripping 0.825 x 9.00 = 7.425 m3/hr 1.55 0.77576

Concreting (V = 12.67cu.m.)

1 1-bagger Mixing - 0.4763 x 6.00 = 2.8578 m3/hr 0.36

2 Placing Concrete - 0.1275 x 6.00 = 0.765 m3/hr 1.36

Total Time = 6.83 6.83 hrs.

Combine Production Rate = Total Quantity = 1.04 =


Total Time 6.83
6- REINFORCED CONCRETE BEAMS/GIRDERS

Materials Qty. Condition

2 1.05 28.35 56.7


7 7 0.49 3.43
60.13

DURATION

0 6.25

0.1522
m3/hr
BAR CHART FOR ITEM 902(1)a1 - R

Quantity (Kgs.) = 758.12 kg Factor Materials Qty.

1 Materials: = 276pcs - 10mmØ x 6.0m def bar


#16 GI Tie Wire
hacksaw blade

2 Labor 2 Steelmen

3 Equipment: -

ACTIVITIES

1 Fabrication - 8.5 x 5.00 = 42.500 kg/hr 17.84

2 Placing 10.625 x 8.00 = 85 m3/hr

Total Time = 17.84 17.84 hrs.

Combine Production Rate = Total Quantity = 758.12


Total Time 17.84
TEM 902(1)a1 - REINFORCING STEELDEFORMED GRADE 40

Materials Qty. Condition

1 Small Project
2 Flat Terrain
3 Urban Location

DURATION

Equipment(hrs. 14.796 51.24 8.92

= 42.500
kg/hr
BAR CHART FOR ITEM 900(7) - REINFORCED

Quantity (Volume) = 1.00 m³ Factor Materials Qty.

2 Labor 1- Leadman
2 Carpenter
1 Mason
2 laborer
3 Equipment: - 1 Concrete Mixer, 1 bagger
1 Concrete Vibrator

ACTIVITIES DUR
Formworks: ( 8.64 m2 )

1 Installation 0.3225 x 6.00 = 1.935 m3/hr 4.47

2 Stripping 0.2388 x 6.00 = 1.4328 m3/hr 6.03


erecting/forming per 100 m2 contract surface

1 1-bagger Mixing - 0.4763 x 1.00 = 0.4763 m3/hr 2.09

2 Placing Concrete - 0.11 x 5.00 = 0.550 m3/hr 1.81

Total Time = 12.31 12.31 hrs.

Combine Production Rate = Total Quantity = 1.00 =


Total Time 12.31
M 900(7) - REINFORCED CONCRETE

Materials Qty. Condition

DURATION
32.4
4.2
36.6

ing per 100 m2 contract surface 3.01508


7.48

0.0809
m3/hr
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1046(2)a1
Description : CHB Non load bearing(including reinforcing steel)100mm
Quantity : 66.74 m2 PRODUCTION RATE (m2/hr): 1.907
NUMBER OF HOURS: 35.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

4" concrete hollow block pc 840.00 P 14.50 P 12,180.00


Portland cement - approved brand (Portland Type I) bag 19.00 P 260.00 P 4,940.00
Sand - Leyte source cu.m. 2.00 P 1,360.00 P 2,720.00
40 - 10mmØ x 6.00m def bar kg 147.84 P 45.00 P 6,652.80
#16 GI Tie Wire kg 2.96 P 70.00 P 207.20
hacksaw blade pc 2.00 P 45.00 P 90.00

SUB-TOTAL (A) P 26,790.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 35.00 P 84.66 P 2,963.10


Mason 2 35.00 P 61.30 P 4,291.00
Laborer 1 35.00 P 47.34 P 1,656.90

14
SUB-TOTAL (B) P 8,911.00
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 35,701.00

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 4,284.12
2. Contractor's Profit 8.00% of D 2,856.08
3. VAT 5% of (D+OCM+CP) 2,142.06
TOTAL INDIRECT COST P 9,282.26

TOTAL COST (D+E) P 44,983.26

UNIT COST P 674.01


150mm 502 m2
100mm 140.289 m2

A1 393.08
A2 217
A3side 12.5 124.3704
834.25 A3side 12.5
26.07 622.58
1.90 510.49 21
44.49 pcs 3.696 373.30 2.88
9.74 416.875
18.12 226.5
834.25
2.96 376.25 30.1
2.96 147.84 18.0198
9.89
5.4 164.74 37
2.96 22.0242 0.9
37.07778 37.07778
8.99
40.044 1.3348
715.125
147.84 112.375
16.72222

10.06667

0.3326241 37.27778
5.494444
4.994444
35.3325 130.5889

1.6825

376.25 16.72222 33.65


226.5 10.06667
112.375 4.994444
42 1.866667
757.125 60.57

57.21

16.3539
18.0198
462.5 1.3348
1.2114

22.0242

6.9
8.74
26.6 66.74
24.5

0.8 3.68 59.84


2.88 56.16
BAR CHART FOR ITEM 1046(2)a-CHB Non load

Quantity (Area) = 66.74 m2 Factor Materials Qty.

2 Labor 2- Mason
1- Labor

3 Equipment: -

ACTIVITIES DUR

1 CHB Laying 0.6375 x 3.00 = 1.9125 m2/hr 34.90

Total Time = 34.90 34.90 hrs.

Combine Production Rate = Total Quantity = 66.74 = 1.913


Total Time 34.90
a-CHB Non load bearing 100mm

Condition

DURATION

m2/hr
BAR CHART FOR ITEM 1046(2)a - MASONRY WOR

Quantity (Area) = #REF! m2 Factor Materials Qty.

2 Labor 2- Mason
1- Labor

3 Equipment: -

ACTIVITIES DURAT

1 CHB Laying 0.5313 x 3.00 = 1.5939 m2/hr #REF!

Total Time = #REF! #REF! hrs.

Combine Production Rate = Total Quantity = #REF! =


Total Time #REF!
(2)a - MASONRY WORKS, 6" CHB

Materials Qty. Condition

DURATION

#REF!
m2/hr
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1018(1)
Description : Unglazed Tiles/Existing Stairs-Landing
Quantity : 108.00 m2 PRODUCTION RATE (m2/hr): 0.900
NUMBER OF HOURS: 120.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Unglazed Tiles sq.m 108.00 950.00 102,600.00


Including Tile Trim & Tile Adhesive

SUB-TOTAL (A) P 102,600.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 120.00 P 84.66 P 10,159.20


mason 2 120.00 P 47.34 P 11,361.60

30
SUB-TOTAL (B) P 21,520.80
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 124,120.80

E. ADD: INDIRECT COST


1. OCM 12.00000% of D 14,894.50
2. Contractor's Profit 8.00% of D 9,929.66
3. VAT 5.00% of (D+OCM+CP) 7,447.25
TOTAL INDIRECT COST P 32,271.41

TOTAL COST (D+E) P 156,392.21

UNIT COST P 1,448.08

Ground floor second floor


7.52
12.8 1.6
8.64 8
8.1 5.76
1.6 5.44
0.8 7.52
39.46 35 74.46
40 35 75
2,835.00 5m2/kl Flooring:
49.25 ###
10.80 21.6
10.80 2.7 Toilet: floor /wall
no.of bag/10
Sink & Counter
18
9

27

108

12

15

0.2097544
10 19 104
BAR CHART FOR ITEM 1027 - CEMENT PLA

Quantity (Area) = #REF! m2 Factor Materials Qty.

2 Labor 2- Mason
2- Labor

3 Equipment: -

ACTIVITIES D

1 Cement Plaster Finish 1.1875 x 4.00 = 4.75 m2/hr #REF!

Total Time = #REF! #REF! hrs.

Combine Production Rate = Total Quantity = #REF! =


Total Time #REF!
1027 - CEMENT PLASTER FINISH

Materials Qty. Condition

DURATION

#REF!
m2/hr
BAR CHART FOR ITEM 1032(1)a-Masonry painting

Quantity (Kgs.) = 425.58 m2 Factor

Labor: 2 Painter
1 Laborer
Equipment:
ACTIVITIES

1 Masonry Paint 2.0913 x 3.00 = 6.274 m2/hr 67.83

Total Time = 67.83 67.83 hrs.

Combine Production Rate = Total Quantity = 425.58 =


Total Time 67.83
a-Masonry painting(includes beams & columns)

Materials Qty. Condition

DURATION

#REF! 15

6.274
m2/hr
pcs
BAR CHART FOR ITEM 1032(1)b #REF!

Quantity (Kgs.) = #REF! m2 Factor

Labor: 1 Painter

Equipment:
ACTIVITIES

1 Wooden Paint 2.8813 x 1.00 = 2.881 m2/hr #REF!

Total Time = #REF! #REF! hrs.

Combine Production Rate = Total Quantity = #REF! =


Total Time #REF!
Materials Qty. Condition

DURATION

#REF! 15

#REF!
m2/hr
pcs
BAR CHART FOR ITEM ### #REF!

Quantity (Kgs.) = #REF! m2 Factor

Labor: 1 Painter

Equipment:
ACTIVITIES

1 Wooden Paint 2.8813 x 1.00 = 2.881 m2/hr #REF!

Total Time = #REF! #REF! hrs.

Combine Production Rate = Total Quantity = #REF! =


Total Time #REF!
Materials Qty. Condition

DURATION

#REF! 15

#REF!
m2/hr
pcs
BAR CHART

ITEM: 1018 b Ceramic Tiles 20 floor


22 72 wall
QUANTITY: 108.00 m2 Factor

2.Labor
2 mason
3. Equipment:

ACTIVITIES

1. Installation of ceramic tiles unglazed .28x 2 0.56 m2/hr


.275x2 0.55

Total time :
Production rate:
Condition

DURATION(hrs.)

60.48
59.4

Total time : 119.88


Production rate: 0.9009 m2/hr
BAR CHART FOR ITEM = #REF!

Quantity (Kgs.) = #REF! m Factor

Labor: 1 Painter

Equipment:
ACTIVITIES

1 Laying of 150mm PVC pipe 0.6250 x 2.00 = 1.250 m/hr #REF!


and includes sand bedding

Total Time = #REF! #REF! hrs.

Combine Production Rate = Total Quantity = #REF!


Total Time #REF!
#REF!

Materials Qty. Condition

DURATION

#REF!

= #REF!
lm/hr
15 pcs
BAR CHART FOR #REF! #REF!

Quantity (Kgs.) = 1.00 lin.m. Factor


4100 m

Labor: 2 eectrician

Equipment:
ACTIVITIES

1 PVC pipe (150mm mdia) 0.1950 x 2.00 = 0.3900 lm/hr 92.31

Total Time = 92.31 92.31 hrs.

Combine Production Rate = Total Quantity = 109.00


Total Time 92.31
Materials Qty. Condition

DURATION

#REF!

= 1.181
unit/hr
15 pcs
BAR CHART FOR ITEM 1100 - POWERLOAD CENTER

Quantity (Kgs.) = m2 Factor


4100 m
44.352

Labor: 2 skilled worker


4 unskilled
Equipment:
ACTIVITIES

1 chb laying 0.6372 x 3.00 = 1.9116 lm/hr 8.79

2 Fabrication 8.5000 x 3.00 25.5000 1.74


2 Stripping 0.8250 x 3.00 2.4750 6.79

3 Placing of concrete 11.9600 * 3.00 35.8800 0.03

Total Time = 17.34 17.34 hrs.

Combine Production Rate = Total Quantity = 10.00


Total Time 17.34
Materials Qty. Condition

DURATION

#REF!

= 0.577
unit/hr
15 pcs
Unit Price Analysis

Project : Improvements Public Market


Locaton : Poblacion, Ubay, Bohol
Item No. : 502(4)
Description : Structural Concrete Cover-Drainage
Quantity : 48.51 cu.m PRODUCTION RATE (each/hr):
NUMBER OF HOURS:

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE

a. Portland Cement bag 462.000 260.00


b. Sand m³ 41.500 1,360.00
c. Gravel m³ 49.000 1,360.00
d. Reinforcing Steel bar kg. 1164.240 45.00
e # 16 G.I Tie Wire (2% of RSB) kg. 24.000 70.00
f 1/2" Ordinary Plywood- set 96.000 650.00
g 2"x2"x10' good lumber bd.ft 1800.000 40.00
h. C.W Nails kg. 15.000 70.00

SUB-TOTAL (A)
B. LABOR COST QUANTITY Hourly
No. of Personnel Total Hours Rate

Construction Foreman 1 70.000 677.28


painter 2 70.000 490.40
laborer 4 70.000 378.72

304
SUB-TOTAL (B)
C. EQUIPMENT COST QUANTITY Hourly
No. of Equipt. Total Hours Rate

a. One bagger Mixer 1 44.000 172.00


b. Bar Cutter, Single Phase 1 44.000 219.75
c Concrete Vibrator 1 44.000 91.26
Minor Tools (10% of Labor Cost)

SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C)

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 83,794.94
2. Contractor's Profit 8.0000% of D 55,863.29
3. VAT 5% of (D+OCM+CP) 41,897.47
TOTAL INDIRECT COST

TOTAL COST (D+E)

UNIT COST
167.076 236.47
37.2
54.4 52.8
75.476 26.775
156.895
0.30
70.00 37.5172727273

TOTAL COST 1368 482.79


P 1,140.00 41.23
120,120.00 1.430 1,630.20
56,440.00 0.075 85.50 460.85
66,640.00 0.150 171.000 41.23
52,390.80 46.460 52,964.40 41.23
1,680.00 0.930 1,060.20 69.3333333333
62,400.00 0.330 376.20 19.6
72,000.00 - 76.8333333333
1,050.00
1.62 234
432,720.80 P 69,970,953.36 59.7727272727 54.6
Total 23.2848
Cost 47,436.00
677.28 154
47,409.60 490.4 23.2848
68,656.00 37872
106,041.60 820.512
129,816.24 27 16.41024
1164.24
222,107.20 P 35,914,734.24
Total 83.00 23.28
Cost 192.5
0.5
7,568.00 1.7142857 96.25
9,669.00 2.21 192.5
4,015.44 2.21
22,210.72 9.2 96.25
8.8
43,463.16 P 7,027,992.97
698,291.16 18

1.8 1.76 1.76


4.14
3.96

181,555.70 8.1 16.2 3.726 6.875


1.84
879,846.86 1.76 23.4
6.1875
18,137.43 P 879,846.86 3.6 7.2 1.656
11.5695
81.246 65.8585 167.076 236.47 46.5318 65.8585
1.2 4.2 9.6 2.1 2.1 576 36.96
1.44 2.4 157.476 14.4 44.4318 13.86
78.606 59.2585 10.08 4.5
7.2 3.36 59.2585

50.82

8.8704 4080
816
460.845 85.68
1800 41.2335 396.00
500 231.00
48.51 0

408 462.00
120
186.2 163.33333 9 13.6 475.60
217.1
20.944 870.22224 72.4608
337.1
660 66
360 72.4608
2275
77 10.5 77.7
2925
292 55 3.4285714286
99.75
33

606.1 77 556
416
466.1 234 128.33333

311 385 9.2


#REF!
2400

0.5808 1235.54

0
7.5 5.85
729.6 325.468
5.85 631.8 245.7

157.95 67.8
631.8 50.85 30
729.6
30 296.55
326.55
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1001(8)
Description : Sewer Line Works
Quantity : 1.00 l.s PRODUCTION RATE (l.s/hr): 0.059
NUMBER OF HOURS: 17.00

A. MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

50mmØ x 3m PVC pipe series 1000 pc 2.00 295.00 590.00


100mmØ x 3m PVC pipe series1000 pc 5.00 779.00 3,895.00
100mm Ø PVC 45 deg elbow pc 6.00 79.00 474.00
4"Ø PVC 45 deg. elbow pc 6.00 79.00 474.00
4"Ø PVC 90 deg. elbow pc 6.00 92.00 552.00
100mmØ PVC tee pc 6.00 190.00 1,140.00
100mmØ PVC WYE pc 4.00 170.00 680.00
100mmØ x 50mmØ PVC reducer tee pc 3.00 65.00 195.00
Solvent can 2.00 110.00 P 220.00

SUB-TOTAL (A) P 8,220.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 17.00 P 84.66 P 1,439.22


Plumber 2 17.00 P 61.30 P 2,084.20

5
SUB-TOTAL (B) P 3,523.42
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 11,743.42

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 1,409.21
2. Contractor's Profit 8.00% of D 939.47
3. VAT 5% of (D+OCM+CP) 704.61
TOTAL INDIRECT COST P 3,053.29

TOTAL COST (D+E) P 14,796.71

UNIT COST P 14,796.71


0.0346021 17

Quantity = 150 l.m

1 Conduits 0.255 x 2.00 = 0.51 lm/hr

Output: 294.11765

0.4286399
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1002(28)
Description : Cold Water Lines
Quantity : 1.00 l.s PRODUCTION RATE:(l.s/hr) 0.026
NUMBER OF HOURS: 38.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

12mmØ x 3m uPVC pipe, blue pc 5.00 49.90 249.50


12mmØ uPVC 90O elbow, plain pc 20.00 8.00 160.00
12mmØ uPVC 90O elbow, threaded one end pc 8.00 49.00 392.00
12mmØ uPVC tee plain pc 5.00 15.00 75.00
12mmØ PVC coupling pc 1.00 45.00 45.00
12mm"Ø angle valve pc 5.00 199.00 995.00
Flexible Hose pcs. 5.00 20.00 100.00
PVC solvent cement (1 Lit) can 2.00 200.00 400.00
teflon tape roll 10.00 10.00 100.00
GAte Valve pcs. 1.00 199.00 199.00

SUB-TOTAL (A) P 2,715.50


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 38.00 P 84.66 P 3,217.08


Plumbers 1 38.00 P 47.34 P 1,798.92

5
SUB-TOTAL (B) P 5,016.00
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C) P 7,731.50

E. ADD: INDIRECT COST


1. OCM 12.00% of D 927.78
2. Contractor's Profit 8.000% of D 618.52
3. VAT 5.000% of (D+OCM+CP) 463.89
TOTAL INDIRECT COST P 2,010.19

TOTAL COST (D+E) P 9,741.69

UNIT COST P 9,741.69


Carpenter Installer
Mason Electrician

Laborer
cian
BAR CHART FOR ITEM = 1001(8)

Quantity (Kgs.) = 21.00 lm Factor

sand paper #120 1

Labor: 1 Painter

Equipment:
ACTIVITIES

1 Laying of pipes 0.6375 x 2.00 = 1.275 lm/hr 16.47


coupling and its fitting 0.1250 x 2.00 0.2500

Total Time = 16.47 16.47 hrs.

Combine Production Rate = Total Quantity = 1.00 =


Total Time 16.47
Sewer Line Works

Materials Qty. Condition

6
15 21
DURATION

#REF! 15

0.06071
lm/hr
pcs
BAR CHART FOR ITEM = #REF!

Quantity (Kgs.) = #REF! ls Factor

20 fixtures

Labor: 2 Painter

Equipment:
ACTIVITIES

1 Installation of fixtures 0.2220 x 2.00 = 0.444 m2/hr 45.05

Total Time = 45.05 45.05 hrs.

Combine Production Rate = Total Quantity = #REF! =


Total Time 45.05
#REF!

Materials Qty. Condition

DURATION

#REF! 15

#REF!
set/hr
pcs
BAR CHART FOR ITEM = #REF!

Quantity (Kgs.) = #REF! m2 Factor

Labor: 1 installer

Equipment:
ACTIVITIES

1 Installation of mirror 0.3375 x 1.00 = 0.338 m2/hr #REF!

Total Time = #REF! #REF! hrs.

Combine Production Rate = Total Quantity = #REF! =


Total Time #REF!
#REF!

Materials Qty. Condition

DURATION

#REF! 15

#REF!
m2/hr
pcs
BAR CHART FOR ITEM = 1002(28)

Quantity (Kgs.) = 1.00 ls Factor

Labor: 2 plumber

Equipment:
ACTIVITIES

1 Pipes and its fittings 1.4260 x 2.00 = 2.852 m2/hr 37.87

Total Time = 37.87 37.87 hrs.

Combine Production Rate = Total Quantity = 1.00 =


Total Time 37.87
Cold Water Lines

Materials Qty. Condition

DURATION

#REF! 15

0.0264
m2/hr
pcs
Unit Price Analysis
Project : #REF!
Locaton : #REF!
Item No. : 1047(1)
Description : Structural Steel
Quantity : 1.00 l.s PRODUCTION RATE (l.s/hr) 0.00410
NUMBER OF HOURS: 244.00
A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST
Roof framing
18-3/16"x2"x2" x 6m angle bar -Top Chord kg 399.60 P 57.00 P 22,777.20
7-3/16"x 1 1/2"x 1 1/2" x 6m angle bar -Web Member/clip angle kg 49.20 P 57.00 P 2,804.40
/fascia frame
9-2"x3"x1.2mm Cee Purlins pcs. 9.00 P 423.00 P 3,807.00
4 -12 mm Ø x 6.00 m. def. bar for sag rod kg 63.94 P 42.00 P 2,685.48
4 -16mmØ x 6.0m. Std Def. bars for cross brace,grade 40 kg 37.90 P 45.00 P 1,705.50
Red oxide gal 2.00 P 495.00 P 990.00
paint thinner gal 1.00 P 250.00 P 250.00

Hand/Ramp railings-Stairs
8 - 50mmØ Stainless Pipe(handrail & support) pc 14.00 P 4,400.00 P 61,600.00
12 - 20mm x 20mm square bar (railing) kg 177.55 P 57.00 P 10,120.46
welding rod kg 5.00 P 150.00 P 750.00
Hacksaw blade pc 5.00 P 45.00 P 225.00

SUB-TOTAL (A) P 107,715.04


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 244.00 P 84.66 P 20,657.04


welder/steelman 4 244.00 P 61.30 P 59,828.80
laborer 2 244.00 P 47.34 P 23,101.92

183
SUB-TOTAL (B) P 103,587.76
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

welding machine 1.00 129.46 212.00 27,446.25

SUB-TOTAL (C) P 27,446.25


D. TOTAL DIRECT COST (A + B + C) P 238,749.06
E. ADD: INDIRECT COST
1. OCM 12.000% of D 28,649.89
2. Contractor's Profit 8.000% of D 19,099.92
3. VAT 5.000% of (D+OCM+CP) 14,324.94
TOTAL INDIRECT COST P 62,074.75

TOTAL COST (D+E) P 300,823.81

UNIT COST P 300,823.81


399.6

10MM 0.62 28.54


1101.9996 12MM 0.888 113.1 295.2 399.6
805.3074 16MM 1.529 201.1
988.974 28MM 4.83 6.15.75 49.2

159.84 7
322.116 2.54 #REF! 3.75 1.16666667
3
2.5 1.5*2
21.312 1.5
37.90
0.23 1.40 9
0.08 1488.1704 #REF!
177.55 5.5

63.94
177.552 2.40
1.67 4.80
14.40
1.65
733.19 2.4 2 5
14.4

0.73333333
2.4
2.5 2.4 1.66666667 0.73333333 9.9
35.25 1.46666667
0.9616833095
3.33333333
0.90909091 0.81818182
4.8

6.45
7.2
3
3

0.75

4.88888889
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1014(1)b1
Description : Prepainted Metal sheet G.I Corr. Sheet
Quantity : 428.00 m2 PRODUCTION RATE (m2/hr): 2.816
NUMBER OF HOURS: 152.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST


Kitchen building
#-24 G.I Corr. Sheet x10' sheet 12.00 P 335.00 P 4,020.00
#-24 G.I Corr. Sheet x12' sheet 7.00 P 410.00 P 2,870.00
Texscrew pc 160.00 P 3.00 P 480.00
0.40mm thk x 24 " x 8' pre fabd gutter pc 29.00 P 357.00 P 10,353.00
0.40mm thk x 12" x 8' pre fabd fascia cover pc 29.00 P 238.00 P 6,902.00
blind rivet pc 500.00 P 1.00 P 500.00
silicon selant qtrs 1.00 180.00 180.00

Public Market-Roof
#-24 G.I Corr. Sheet x12' sheet 7.00 P 410.00 P 2,870.00
Texscrew pc 1224.00 P 3.00 P 3,672.00
#-24 G.I Sheet Plain x10' pc 95.00 P 220.00 P 20,900.00

SUB-TOTAL (A) P 52,747.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost
Construction Foreman 1 152.00 P 84.66 P 12,868.32
tinsmith 2 152.00 P 61.30 P 18,635.20
laborer 1 152.00 P 47.34 P 7,195.68

57
SUB-TOTAL (B) P 38,699.20
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 91,446.20

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 10,973.54
2. Contractor's Profit 8.000% of D 7,315.70
3. VAT 5% of (D+OCM+CP) 5,486.77
TOTAL INDIRECT COST P 23,776.01

TOTAL COST (D+E) P 115,222.21

UNIT COST P 269.21


22.5

6.328 144
32.9 208.1912
416.3824
11.42857
70
144 210
3.333333
2.5

0.35mm thk prepainted long span rib type lm 86.00 P 420.00 P 36,120.00
0.35mm thk x 24" x 8' pre fabd gutter pc 19.00 P 237.00 P 4,503.00
0.35mm thk x 12 " x 8'pre fab fascia cover pc 19.00 P 238.00 P 4,522.00

self drilling screw, 2 -1/2 pc 530.00 P 2.00 P 1,060.00


blind rivet 1/8Ø x 3/8" pc 263.00 P 0.75 P 197.25

84

1140
1224

0.73367585
- 6 pcs in every square meter
- 3 pcs in every square meter
BAR CHART FOR ITEM = 1047(1) Structural Steel

Quantity (Kgs.) = 1.00 ls


728.19

ACTIVITIES DURATION

1 Fab. of angle bar 17.00 x 6.00 = 102.00 kg./hr 7.14 1.00


2 Inst. of angle bar 8.500 x 6.00 = 51.00 kg./hr 14.28 950
Installation of trusses 0.0125 x 6.00 0.08 80.00
3 Installation of purlins 4.500 x 6.00 = 27.00 lin./hr 35.19 actual length of purlins=924 m
4 Painting of angle bar 4.250 x 6.00 = 25.50 lin/hr 35.33 901 lin m angle bar
Installation of railings 8.500 x 6.00 51.00 11.65
5 Painting of Purlins and railings,pipe 4.250 x 6.00 = 25.50 lin/hr 59.53 1518
6. Installation of trusses

Total Time = 243.11 243.11 hrs.

Combine Production Rate = Total Quantity = 1.00 = 0.00411


kg/hr
Total Time 243.11

Equipment hours: 129.46


BAR CHART FOR ITEM 1014 (1)- PREP

Quantity (Kgs.) = 428.00 m2 Factor

Equipment:
ACTIVITIES

1 Installation of Roofing 1.0375 x 3.00 = 3.1125 m2/hr 137.51


4 Installation of Flashings 5.3125 x 3.00 = 15.9375 L.M./hr 14.31
L= 228.00 m.

Total Time = 151.82 151.82 hrs.

Combine Production Rate = Total Quantity = 428.00


Total Time 151.82
M 1014 (1)- PREPAINTED METAL SHEET

Materials Qty. Condition

Labor: 2 carpenter
1 laborer

DURATION

= 2.819
m2/hr

228
BAR CHART FOR ITEM 403 - METAL STRUCTURE (ROOF FR

Quantity (Kgs.) = #REF! meter

ACTIVITIES

1 Fab. of angle bar 8.50 x 4.00 = 34.00 kg./hr #REF!


2 Inst. of angle bar 8.500 x 4.00 = 34.00 kg./hr #REF!
3 Installation of purlins 4.500 x 6.00 = 27.00 lin./hr
4 Painting of angle bar 4.250 x 6.00 = 25.50 lin/hr
5 Installation of railings 8.500 x 6.00 51.00 #REF!
6 Fire escape 0.250 x 6.00 = 1.50 lin/hr 0.67

Total Time = #REF!

Combine Production Rate = Total Quantity


Total Time

ACTIVITIES

1 Fab. of column/trusses 17.00 x 6.00 = 102.000 kg/hr #REF!


2 Erection of col./trusses 0.063 x 2.00 = 0.125 set/hr 48.00
using chainblock
3 Inst. of column/trusses 0.0125 x 6.00 = 0.075 set/hr 0.00
4 Fabrication of beams 17.00 x 6.00 = 102.000 kg/hr 0.00
5 Installation of beams 0.0125 x 6.00 = 0.075 set/hr
6 Installation of Purlins 4.50 x 6.00 = 27.000 L.M./hr 34.22
7 Framing of Sidings 8.50 x 6.00 = 51.000 kg./hr 0.00
8 Installation of Railings 0.125 x 6.00 = 0.750 L.M./hr 0.00
9 Installation of Grab Bar 0.063 x 6.00 = 0.375 L.M./hr 0.00
10 Painting of Item 403 1.7425 x 6.00 = 10.455 m2/hr 0.00
(application of red oxide)

Total Time = #REF!

Combine Production Rate = Total Quantity


Total Time
RUCTURE (ROOF FRAMING)

DURATION

#REF! 9,546.80
#REF! 950

Area: 37.8
#REF!
0.67 1518

#REF! hrs.

Total Quantity = #REF! = #REF!


kg/hr
Total Time #REF!

DURATION

#REF!
48.00 6 set of trusses

0.00
0.00

34.22
0.00
0.00
0.00 assumed 0.06250
0.00

#REF! hrs.

Total Quantity = #REF! =


#REF! kg/hr
Total Time #REF!
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1010(1)
Description : Frames (Jamb,sills, head,transoms and mullions)
Quantity : 53.00 set PRODUCTION RATE (set/hr): 0.4000
NUMBER OF HOURS: 132.50

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

6pcs - 2" x 6" x 12' Mahogany or gemelina(jamb)-window bd.ft 72.00 P 40.00 P 2,880.00
16 pcs - 2" x 6" x 8' Mahogany or gemelina(jamb) bd.ft 128.00 P 40.00 P 5,120.00
CW nails(asstd.) kg 10.00 P 70.00 P 700.00

SUB-TOTAL (A) P 8,700.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel
Total Hours Rate Cost

Construction Foreman 1 132.50 P 84.66 P 11,217.45


Carpenter 2 132.50 P 61.30 P 16,244.50

34
SUB-TOTAL (B) P 27,461.95
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt.Total Hours Rate Cost

SUB-TOTAL (C) -
TOTAL DIRECT COST (A + B + C) P 36,161.95

D. ADD: INDIRECT COST


1. OCM 12.0000% of D 4,339.43
2. Contractor's Profit 8.0000% of D 2,892.96
3. VAT 5.0000% of (D+OCM+C 2,169.72
E. TOTAL INDIRECT COST P 9,402.11

TOTAL COST (D+E) P 45,564.06

UNIT COST P 859.70


3.6

3.15654598
3
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1009(1)a
Description : Jalousie Windows glass
Quantity : 59.40 m2 PRODUCTION RATE (m2/hr): 0.6750
NUMBER OF HOURS: 88.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Aluminum Jalousie frame for 14 blades (A1), double control sq.m 2.88 P 2,250.00 P 6,480.00
Aluminum Jalousie frame for 7 blades (A1), double control sq.m 0.80 P 2,250.00 P 1,800.00
4.5mm thk x 100mm x537.50mm clear glass jalousie blade pc. 77.00 P 25.00 P 1,925.00
1"Cove moulding-8' pc. 12.00 P 240.00 P 2,880.00
Assorted C.W. Nails kg 6.00 P 42.80 P 256.80

P 13,341.80
B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 88.00 P 84.66 P 7,450.08


Carpenter 2 88.00 P 61.30 P 10,788.80

22
SUB-TOTAL (B) P 18,238.88
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 31,580.68

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 3,789.68
2. Contractor's Profit 8.000% of D 2,526.45
3. VAT 5% of (D+OCM+CP) 1,894.84
TOTAL INDIRECT COST P 8,210.98

TOTAL COST (D+E) P 39,791.66

UNIT COST P 669.89


2.666667
0.8
2.88
56
2250

6,480.00 28
56

2.666667
21 77

1.36704792

0.24
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1010(2)a
Description : Doors flush
Quantity : 3.78 m2 PRODUCTION RATE (m2/hr):
NUMBER OF HOURS:

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE

2 -2.10x.90m flush type door m2 3.78 P 2,800.00


CW nails(asstd.) kg 2.00 P 70.00

SUB-TOTAL (A)
B. LABOR COST QUANTITY Hourly
No. of Personnel Total Hours Rate

Construction Foreman 1 29.00 P 84.66


Carpenter 2 29.00 P 61.30

8
SUB-TOTAL (B)
C. EQUIPMENT COST QUANTITY Hourly
No. of Equipt. Total Hours Rate

SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C)

E. ADD: INDIRECT COST


1. OCM 12.00000% of D 2,008.14
2. Contractor's Profit 8.00% of D 1,338.76
3. VAT 5% of (D+OCM+CP) 1,004.07
TOTAL INDIRECT COST

TOTAL COST (D+E)

UNIT COST
0.1303
29.00

TOTAL COST

P 10,584.00 3.78
P 140.00 5,292.00

P 10,724.00
Total
Cost

P 2,455.14
P 3,555.40

P 6,010.54 0.56047557
Total
Cost

-
P 16,734.54

P 4,350.98

P 21,085.52

P 5,578.18
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1004(2)e
Description : Finishing hardware, knobs
Quantity : 2.00 set PRODUCTION RATE (set/hr): 2.0000
NUMBER OF HOURS: 1.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

Doorknob,kwikset pcs. 2.00 P 950.00 P 1,900.00

SUB-TOTAL (A) P 1,900.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 1.00 P 84.66 P 84.66


carpenter 2 1.00 P 61.30 P 122.60

1
SUB-TOTAL (B) P 207.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 2,107.26

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 252.87
2. Contractor's Profit 8.000% of D 168.58
3. VAT 5% of (D+OCM+CP) 126.44
TOTAL INDIRECT COST P 547.89

TOTAL COST (D+E) P 2,655.15

UNIT COST P 1,327.57


2.00 set

0.5312 2 1.0624 1.8825301

Output 1.0624

10.9084211
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1004(2)g
Description : Finishing hardware, hinges
Quantity : 3.00 set PRODUCTION RATE (set/hr): 81.2500
NUMBER OF HOURS: 0.04

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

3-1/2"x3 1/2" butt hinges pair 3.00 P 110.00 P 330.00

SUB-TOTAL (A) P 330.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 0.04 P 84.66 P 3.13


carpenter 2 0.04 P 61.30 P 4.53

21
SUB-TOTAL (B) P 7.65
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 337.65

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 40.52
2. Contractor's Profit 8.000% of D 27.01
3. VAT 5% of (D+OCM+CP) 20.26
TOTAL INDIRECT COST P 87.79

TOTAL COST (D+E) P 425.44

UNIT COST P 141.81


3.00

1.875 2 3.75 0.80

output 3.75

2.31899301
BAR CHART FOR ITEM 10
1010(1) Frames (Jamb,sills, head,transoms and mul

Quantity (Kgs.) = 53 set Factor

Equipment:
ACTIVITIES

1 Fabrication & installation 0.2000 x 2.00 = 0.4000 unit/hr 132.50


of jambs

Total Time = 132.50 132.50 hrs.

Combine Production Rate = Total Quantity = 53.00


Total Time 132.50
transoms and mullions)

Materials Qty. Condition

DURATION

= 0.400
m2/hr
BAR CHART FOR ITEM 1009(1) - GLASS

Quantity (Kgs.) = 59.40 m2 Factor

Labor: 2 Carpenter

Equipment:
ACTIVITIES

1 Fabrication & installation 0.2000 x 2.00 = 0.4000 unit/hr


of jambs
3 Installation of jalousie 0.3375 x 2.00 = 0.6750 m2/hr 88.00
and its frames

Total Time = 88.00 88.00 hrs.

Combine Production Rate = Total Quantity = 59.40 =


Total Time 88.00
1009(1) - GLASS JALOUSIE WINDOWS

Materials Qty. Condition

DURATION

#REF! 12

0.6750
set/hr
units
Item 1010(2)a Doors flush

Quantity = 2.00 SET m2 Factor

Labor: 2 carpenter

Equipment:
ACTIVITIES

1 Inst. of flush door 0.2363 x 2.00 = 0.4726 m2/hr 4.23

Total Time = 4.23 4.23 hrs.

Combine Production Rate = Total Quantity = 2.00 =


Total Time 4.23
Materials Qty. Condition

DURATION

12.69573

0.4726
m2/hr

0.4726
#REF! ###

Quantity = #REF! m2 Factor

Labor: 2 carpenter

Equipment:
ACTIVITIES

1 Inst. of solid panel door 0.2363 x 2.00 = 0.4726 m2/hr #REF!

Total Time = #REF! #REF! hrs.

Combine Production Rate = Total Quantity = #REF! =


Total Time #REF!
Materials Qty. Condition

DURATION

12.69573

#REF!
m2/hr
BAR CHART FOR ITEM #REF!

Quantity (Kgs.) = #REF! #REF! Factor

1
Labor 2 carpenter

Equipment:
ACTIVITIES

1 Installation of locksets 1.8750 x 2.00 = 3.7500 set/hr #REF!

Total Time = #REF! #REF! hrs.

Combine Production Rate = Total Quantity = 10.00


Total Time #REF!
#REF!

Materials Qty. Condition

DURATION

= #REF!
m2/hr
BAR CHART FOR ITEM 1004(2)e

Quantity (Kgs.) = 2.00 m2 Factor

1 Labor 1 carpenter

Equipment:
ACTIVITIES

1 knobs 3.1250 x 1.00 = 3.1250 m2/hr 0.64

Total Time = 0.64 0.64 hrs.

Combine Production Rate = Total Quantity = 2.00


Total Time 0.64
Finishing hardware, knobs

Materials Qty. Condition

DURATION

= 3.125
set/hr
BAR CHART FOR ITEM 1004(2)g

Quantity (Kgs.) = 3.00 set

Labor 2 carpenter

Equipment:
ACTIVITIES

1 door lockset 3.1250 x 2.00 = 6.2500 m2/hr 0.48

Total Time = 0.48 0.48 hrs.

Combine Production Rate = Total Quantity = 39.00


Total Time 0.48
Finishing hardware, hinges

DURATION

= 81.250
m2/hr
BAR CHART FOR ITEM 1100 - POW

Quantity (Kgs.) = 1.00 lin.m. Factor


150 m
1 Materials: Utility Box- 2" x 4" 7
Junction box 5
3/4" Ø x 3m PVC electical conduit pipe 1
1/2" Ø x 3m PVC electical conduit pipe 33
1/2" Ø PVC elbow 4
Solvent cement 1
3/4" Ø entrance cap 1
Screw insulator 2

Labor: 2 eectrician

Equipment:
ACTIVITIES

1 PVC pipe (150mm mdia) 1.0000 x 2.00 = 2.0000 lm/hr 75.00

Total Time = 75.00 75.00 hrs.

Combine Production Rate = Total Quantity = 109.00


Total Time 75.00
OR ITEM 1100 - POWERLOAD CENTER

Materials Qty. Condition

1 Small Project
2 Flat Terrain
3 Urban Location

DURATION

#REF!

= 1.453
unit/hr
15 pcs
BAR CHART FOR ITEM 10

Quantity (Kgs.) = 21.00 m2 Factor

Equipment:
ACTIVITIES

1 Frameworks 0.6375 x 3.00 = 1.9125 m2/hr 10.98


2 Plyuwood installations 0.8500 x 3.00 = 2.5500 m2/hr 8.24

Total Time = 19.22 19.22 hrs.

Combine Production Rate = Total Quantity = 1.00


Total Time 19.22
RT FOR ITEM 1014 - Dry wall

Materials Qty. Condition

DURATION

=
m2/hr
BAR CHART FOR ITEM 10
#REF! #REF!

Quantity (Kgs.) = 21.00 m2 Factor

1 Labor 3 carpenter

Equipment:
ACTIVITIES

1 Frameworks 0.6375 x 3.00 = 1.9125 m2/hr 10.98


2 Plyuwood installations 0.8500 x 3.00 = 2.5500 m2/hr 8.24

Total Time = 19.22 19.22 hrs.

Combine Production Rate = Total Quantity = 1.00


Total Time 19.22
Materials Qty. Condition

DURATION

= 0.052
m2/hr
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1017(1)a2
Description : Roof drain with strainers,75mm Ø
Quantity : 5.00 set PRODUCTION RATE (m2/hr): 0.59
NUMBER OF HOURS: 8.50

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

75mmØ PVC coupling (90⁰)elbow pc 5.00 P 52.00 P 260.00


75 mmØ PVC coupling pc 8.00 P 57.00 P 456.00
75mmØ PVC x 3m PVC pipe pc 8.00 P 440.00 P 3,520.00
PVC solvent ( 1 liter) can 1.00 P 200.00 P 200.00
roof strainers pc 5.00 P 150.00 P 750.00

SUB-TOTAL (A) P 5,186.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 8.50 P 84.66 P 719.61


plumber 4 8.50 P 61.30 P 2,084.20

2
SUB-TOTAL (B) P 2,803.81
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C)
D. TOTAL DIRECT COST (A + B + C) P 7,989.81

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 958.78
2. Contractor's Profit 8.00% of D 639.18
3. VAT 5% of (D+OCM+CP) 479.39
TOTAL INDIRECT COST P 2,077.35

TOTAL COST (D+E) P 10,067.16

UNIT COST P 2,013.43


1003d-1 ceiling frameworks

.6375m2/hr

.85sheet/hr

6.80sheet/md N

11.7

146.25

7.5 292.5

0.54064983
BAR CHART FOR ITEM 1017- Roof D

Quantity (Kgs.) = 5.00 m2 Factor

Labor: Skilled
1 workwer

Equipment:
ACTIVITIES

1 Installation of roof strainers 1.0000 x 2.00 = 2.000 pc/hr 8.00

2 Installation of downspout 6.3750 x 2.00 = 12.7500 lm/hr 0.39

Total Time = 8.39 8.39 hrs.

Combine Production Rate = Total Quantity = 5.00 =


Total Time 8.39
TEM 1017- Roof Drains &strainers

Materials Qty. Condition

DURATION

#REF! 15

0.596
m2/hr
pcs
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1100(30)
Description : Conduits,Boxes & Fittings
Quantity : 1.00 l.s PRODUCTION RATE (lm/hr): 0.056
NUMBER OF HOURS: 18.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

utility box-2"x4" pc 3.00 30.00 P 90.00


junction box pc 3.00 31.00 P 93.00
1/2"Ø x3m PVC electrical conduit pc 3.00 69.00 P 207.00
Cable Tie 10" pack 1.00 30.00 P 30.00
square box pcs. 1.00 60.00 P 60.00
grounding rod lengt 1.00 85.00 P 85.00
Flexible Conduit 1/2@ dia. m 20.00 10.00 P 200.00
Meter box pc. 1.00 200.00 P 200.00
Entrance Cap 1/2 pc. 1.00 50.00 P 50.00

SUB-TOTAL (A) P 1,015.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 18.00 P 84.66 P 1,523.88


electrician 2 18.00 P 61.30 P 2,206.80

5
SUB-TOTAL (B) P 3,730.68
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 4,745.68

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 569.48
2. Contractor's Profit 8.000% of D 379.65
3. VAT 5% of (D+OCM+CP) 284.74
TOTAL INDIRECT COST P 1,233.88

TOTAL COST (D+E) P 5,979.56

UNIT COST P 5,979.56


0.04
0.60
BAR CHART FOR ITEM 1100(30)

Quantity (Kgs.) = 1.00 ls Factor

Labor: 2 electrician

Equipment:
ACTIVITIES

1 installation of conduits 4.5000 x 1.00 = 4.5000 lin.m./hr 0.22

3 Installation ofboxes and 3.5000 x 1.00 = 3.5000 pcs/hr 17.71


fittings

Total Time = 17.71 17.71 hrs.

Combine Production Rate = Total Quantity = 1.00 =


Total Time 17.71
Conduits,Boxes & Fittings

Materials Qty.

DURATION

#REF!

0.056
unit/hr
0.056
15 pcs
Unit Price Analysis

Project : #REF!
Location : #REF!
Item No. : 1101(42)
Description : Wires and Wiring Devices
Quantity : 1.00 l.s PRODUCTION RATE (l.s/hr): 0.034
NUMBER OF HOURS: 29.50

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

TW Stranded Wire #14 m 30.00 P 15.00 P 450.00


Tw Stranded Wire #10 m 15.00 32.00 480.00
TW Stranded Wire #12 m. 25.00 23.00 575.00
conveneince outlet flush type 2 gang pc 2.00 85.00 170.00
wall fan outlet pc 1.00 125.00 125.00
2 gang switch, flush type with plate pc 1.00 127.00 127.00
electrical tape pc 1.00 30.00 30.00
Service Drop Wire no.6 m 40.00 22.00 880.00

SUB-TOTAL (A) P 2,837.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 29.50 P 84.66 P 2,497.47


electrician 2 29.50 P 61.30 P 3,616.70

8
SUB-TOTAL (B) P 6,114.17
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 8,951.17

E. ADD: INDIRECT COST


1. OCM 12.00% of D 1,074.14
2. Contractor's Profit 8.00% of D 716.09
3. VAT 5.00% of (D+OCM+CP) 537.07
TOTAL INDIRECT COST P 2,327.30

TOTAL COST (D+E) P 11,278.47

UNIT COST P 11,278.47


8

1.00 l.s output

18.75 x 1 18.75 0.0533333


0.9756098

215.52%

0.00%
BAR CHART FOR ITEM 1101(42)

Quantity (Kgs.) = 1.00 l.s Factor


1560

Labor: 2 eectrician

Equipment:
ACTIVITIES

1 wiring 18.7500 x 2.00 = 37.5000 lin.m./hr 41.60

2 devices 1.0000 x 2.00 = 2.0000 pcs/hr 29.50

Total Time = 29.50 29.50 hrs.

Combine Production Rate = Total Quantity = 1.00 =


Total Time 29.50
Wires and Wiring Devices

Materials Qty. Condition

DURATION

#REF!

0.034
unit/hr
15 pcs
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1102(27)
Description : Powerload Center,Switchgear and Panelboards
Quantity : 1.00 l.s PRODUCTION RATE (set/hr): 0.14
NUMBER OF HOURS: 7.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

panel board 4 branches set 1.00 P 1,270.00 P 1,270.00


circuit breaker-30 amperes set 1.00 P 340.00 P 340.00
circuit breaker-20 amperes set 1.00 P 340.00 P 340.00
circuit breaker-15 ampers set 1.00 P 340.00 P 340.00

SUB-TOTAL (A) P 2,290.00


B. LABOR COST QUANTITY Hourly Total
No. of PersonnelTotal Hours Rate Cost

Construction Foreman 1 7.00 P 84.66 P 592.62


electrician 1 7.00 P 65.65 P 459.55

1
SUB-TOTAL (B) P 1,052.17
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 3,342.17

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 401.06
2. Contractor's Profit 8.000% of D 267.37
3. VAT 5% of (D+OCM+CP) 200.53
TOTAL INDIRECT COST P 868.96

TOTAL COST (D+E) P 4,211.13

UNIT COST P 4,211.13


0.04
0.20
BAR CHART FOR ITEM 1102(27)

Quantity (Kgs.) = 1.00 ls Factor

1 Materials: Utility Box- 2" x 4" 7


Junction box 5
3/4" Ø x 3m PVC electical conduit pipe 1
1/2" Ø x 3m PVC electical conduit pipe 33
1/2" Ø PVC elbow 4
Solvent cement 1
3/4" Ø entrance cap 1
Screw insulator 2

Labor: 2 eectrician

Equipment:
ACTIVITIES

1 panel boards 1.0000 x 1.00 = 1.0000 lin.m./hr 7.00

Total Time = 7.00 7.00 hrs.

Combine Production Rate = Total Quantity = 1.00 =


Total Time 7.00
Powerload Center,Switchgear and Panelboards

Materials Qty. Condition

1 Small Project
2 Flat Terrain
3 Urban Location

DURATION

#REF!

0.143
unit/hr
15 pcs
Unit Price Analysis

Project : #REF!
Locaton : #REF!
Item No. : 1103(1)
Description : Lighting Fixtures
Quantity : 1.00 ls PRODUCTION RATE (set/hr): 0.033
NUMBER OF HOURS: 30.00

A) MATERIALS : COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST

2-36 watts flourescent lighting fixtures box type set 2.00 P 915.00 P 1,830.00
w/ aluminum reflector(7" x 48")

SUB-TOTAL (A) P 1,830.00


B. LABOR COST QUANTITY Hourly Total
No. of Personnel Total Hours Rate Cost

Construction Foreman 1 30.00 P 84.66 P 2,539.80


electrician 2 30.00 P 61.30 P 3,678.00

8
SUB-TOTAL (B) P 6,217.80
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost

SUB-TOTAL (C) -
D. TOTAL DIRECT COST (A + B + C) P 8,047.80

E. ADD: INDIRECT COST


1. OCM 12.0000% of D 965.74
2. Contractor's Profit 8.000% of D 643.82
3. VAT 5% of (D+OCM+CP) 482.87
TOTAL INDIRECT COST P 2,092.43

TOTAL COST (D+E) P 10,140.23

UNIT COST P 10,140.23


x 1.00 = #REF! lm/hr

3.3977049
#REF!
BAR CHART FOR ITEM 1103(1)

Quantity (Kgs.) = 1.00 ls Factor

60.00 fixtures

Labor: 2 eectrician

Equipment:
ACTIVITIES

1 lightings 1.0000 x 2.00 = 2.0000 lin.m./hr 30.00

Total Time = 30.00 30.00 hrs.

Combine Production Rate = Total Quantity = 1.00 =


Total Time 30.00
Lighting Fixtures

Materials Qty. Condition

DURATION

#REF!

unit/hr
0.033
15 pcs
BAR CHART FOR ITEM #REF!

Quantity (Kgs.) = #REF! #REF! Factor

Labor: 2 installer

Equipment:
ACTIVITIES

1 installation of fan 0.4315 x 2.00 = 0.8630 lin.m./hr 13.90

Total Time = 13.90 13.90 hrs.

Combine Production Rate = Total Quantity = #REF! =


Total Time 13.90
#REF!

Materials Qty. Condition

DURATION

#REF!

unit/hr
#REF!
15 pcs
BAR CHART FOR ITEM 900(1)c5 - Suspe

Quantity (Volume) = 81.30 m³ Factor Materials Qty.

2 Labor 1- Leadman
2 Carpenter
1 Mason
2 laborer
3 Equipment: - 1 Concrete Mixer, 1 bagger
1 Concrete Vibrator

ACTIVITIES D
Formworks: ( 155.52 m2 )

1 Installation 0.3225 x 6.00 = 1.935 m3/hr 80.37

2 Stripping 0.2388 x 6.00 = 1.4328 m3/hr 108.54


erecting/forming per 100 m2 contract surfac

Concreting (V =26.04cu.m.)

1 1-bagger Mixing - 0.4763 x 1.00 = 0.4763 m3/hr 170.69

2 Placing Concrete - 0.11 x 5.00 = 0.550 m3/hr 147.82

Total Time = 282.46 283.00 hrs.

Combine Production Rate = Total Quantity = 81.30 =


Total Time 283.00
TEM 900(1)c5 - Suspended slab

Materials Qty. Condition

DURATION
32.4
4.2
36.6

ing per 100 m2 contract surface 54.2714


134.64

0.2873
m3/hr

Вам также может понравиться