Академический Документы
Профессиональный Документы
Культура Документы
Introduction
Code Criteria
The fire protection and life safety systems within the building are based on meeting the
following codes and standards criteria:
North Carolina Building Code, 2012 – 2009 International Building Code (IBC)
with State Amendments
North Carolina Fire Code, 2012 - 2009 International Fire Code (IFC) with State
Amendments
NFPA 10 – Standard for Portable Fire Extinguishers, 2007
NFPA 13 – Standard for Installation of Sprinkler Systems, 2007
NFPA 14 – Standard for Installation of Standpipe and Hose Systems, 2007
NFPA 20 – Standard for Installation of Stationary Fire Pumps for Fire Protection,
2007
NFPA 70 - National Electrical Code, 2011
NFPA 72 – National Fire Alarm Code, 2007
NFPA 110 - Standard for Emergency and Standby Power Systems, 2005
NFPA 111 - Standard on Stored Electrical Energy Emergency and Standby
Power systems, 2005
NFPA 2001 – Standard for Clean Agent Fire Extinguishing Systems, 2008
Guidelines
The following guidelines are additionally referenced for use during design:
ANSI/BICSI-002 – Data Center Design and Implementation Best Practices
NFPA 75 – Standard for the Fire Protection of Information Technology, 2013
NFPA 291 – Recommended Practice for Fire Flow Testing and Marking of
Hydrants, 2013
NFPA 1221 - Standard for the Installation, Maintenance and Use of Emergency
Services Communications Systems, 2013
NFPA Fire Protection Handbook, Twentieth Edition, 2008
Design Analysis
Life Safety & Building Code Compliance
This project involves the new construction of a 4 story, 87 feet in total building height
housing …. functions for the City of Raleigh. The table below provides a summary of
major parameters applicable to this project.
Required Fire
Building Element Resistance Rating Reference
(Hrs)
Structural Frame (Columns,
girders, trusses supporting 2 IBC Table 601
floor construction above)
Bearing Walls
- Interior 2 IBC Table 601
- Exterior 2
Nonbearing walls and partitions IBC Table 601
- Interior Reference IBC Table 602
- Exterior requirements below Table 508.2.5, NFPA
0 (FSD ≥ 30 ft) 1221
Floor Construction 2 IBC Table 601
Roof Construction 1 IBC Table 601
Vertical Exit Enclosures 2 Section 7.2.2.6
Shaft Enclosures 2 Section 8.6.5
Data/Radio & RF rooms will be 1 hour fire barriers per NFPA 1221 section 4.5.5 and
NFPA 75 section 5.1.3.
ECC floor will be separated from other uses by a 2 hour fire barrier per NFPA 1221
section 4.3.3.
Electrical and UPS/battery storage room must be 1 hour fire barrier, per IBC table
508.2.5.
Mechanical and storage rooms should be smoke partitions in accordance with IBC table
508.2.5 and section 508.2.2.1.
Since building will be fully sprinklered, corridor walls can be unrated.
Interior Wall and Ceiling Finishes
Wall, ceiling, and interior floor finishes will comply with IBC Chapter 8 as summarized
below.
Means of Egress
Occupant Load and Egress Capacity: An occupant load is required to be assigned to all
portions of a building related to that space’s intended use. Occupant loads used for
sizing exits, and exit access arrangements are based on the following factors, per IBC
table 1004.1:
Communications Center, Office Space, Data Center and other spaces not
designated otherwise – 100 gross ft2/occupant
Mechanical, Electrical & Fire Riser Rooms - 300 gross ft2/occupant
Break room, training room, press and conference rooms – 15 net
ft2/occupant
Classrooms - 30 net ft2/occupant
Exercise Room - 50 gross ft2/occupant
Egress width for exits and exit access components will be based on 0.2 inch/occupant
width for level components and 0.3 inch/occupant for stairways, per IBC section 1005.1.
Exits: A minimum of two (2) required exits are to be provided, per IBC 1021.
Arrangement of Means of Egress and Exit Access: Spaces with a maximum calculated
occupant load of 50 or less are allowed to have one exit access doorway for B use, per
IBC table 1015.1. The following table summarizes the limitations from IBC for travel
distance, common path of travel, and dead-end corridor for a fully sprinklered, B/A-3
use. Where a building contains multiple occupancies and means of egress components
are shared by these occupancies, the more stringent requirements are to apply in
accordance with IBC section 1004.9.
Other Exiting Provisions: Egress from new buildings will not pass through adjoining or
intervening rooms or areas, except where such adjoining rooms or areas are accessory
to the area served, are not high-hazard occupancy and provide a discernible path of
egress travel to an exit. Egress will not pass through kitchens, storage rooms, closets,
or spaces used for similar purposes in accordance with IBC section 1014.2.
Accessible Means of Egress: Building is fully sprinklered, so that elevators and stairways
do not have to be designed for mobility impaired movement to traverse during an
emergency, per IBC sections 1007.2.1 and 1007.3. Two-way communication system is
to be provided at each elevator landing on accessible floors, per IBC section 1007.8.
Egress Components
The Raleigh Critical Public Safety Facility will be provided throughout with an automatic
fire sprinkler system in accordance with NFPA 13 and NFPA 1221, section 2.5.3. The
emergency communication center (ECC) and the data center will be served by a double-
interlock preaction fire protection system. The remaining spaces of the building will be
protected with an automatic wet-pipe system.
Reductions in remote area size for use of quick response sprinklers will be allowed for
portions of the wet-pipe system in accordance with NFPA 13. Portions of the building
protected with preaction systems will require an increase in remote area size in
accordance with NFPA 13.
To reduce the threat of accidental discharge of water on critical equipment, the data
center will also be protected with a clean agent fire extinguishing system with an
appropriate gaseous agent for the protected equipment, complying with applicable codes
and standards. While halocarbons such as HFC-227 ea (i.e. FM 200) have been widely
used for clean agent systems, the volume of space proposed to be protected may be
well suited for FK-5-1-12 (i.e. Novec 1230). This agent has been proven to protect well
while limiting damage to sensitive equipment, cause fewer adverse health and
environmental effects, and is still considered comparable in costs to other halocarbons.
Maximum protection of sensitive and critical assets within the data center can be
achieved via the use of both a clean agent system and an automatic sprinkler system.
The NFPA Fire Protection Handbook delineates the reason for providing redundant
systems as the primary design objective of a sprinkler system is to provide fire control;
whereas the primary design objective of a clean agent system is to provide fire
extinguishment. Sprinkler systems, including preaction systems, are hence best suited to
the protection of structures; whereas clean agent systems are best suited to the
protection of the contents of the structure. Substantial risk reduction at very high
benefit/cost ratios may be realized by protecting these assets with both a clean agent
system and a sprinkler system which will result in more flexibility with other fire and life
safety issues required by the various applicable codes and standards.
The clean agent suppression system will be configured to reduce the likelihood of water
discharge in the hazard. The sprinkler system may never be activated, as the clean
agent system would most likely suppress the fire before the room reaches a high enough
temperature to actuate a sprinkler. The clean agent system will be actuated using a very
early warning air sampling smoke detection system. Heat detectors, in addition to
sprinkler actuation, will be used to activate the preaction valve, releasing water into the
piping protecting the data center and ECC areas only and flow through the activated
sprinkler(s).
Standpipe System
A Class I Standpipe System is required, per IBC section 905.3.1. In an initial meeting
with Raleigh Fire Department, it was suggested that they will allow the design of a
manual wet standpipe system in lieu of an automatic wet standpipe system designed in
accordance with NFPA 14, 2007. This is permissible under IBC and NFPA 14 when
standpipe system is not serving a high-rise building. System will be designed as a
combined standpipe/automatic sprinkler system as permissible under NFPA 14
provisions.
Water Distribution System
An extensive review of the existing distribution system has not been done. The existing
city water distribution system must be analyzed to verify that it will meet the demand of
the building. A confirming flow test still needs to be completed in accordance with NFPA
13 and NFPA 291. It is assumed at this point with the height of the building and
sprinkler demand, that pressure will need to be boosted by an electric-driven fire pump,
designed and installed in accordance with NFPA 20.
Fire alarm provisions for the Raleigh Critical Public Safety Facility will include fully
automatic and manual functions monitored off-site as a central station fire alarm system
in accordance with IBC, IFC, and NFPA 72. The fire alarm control panel (FACP) will be
fully addressable and will also interface with releasing service fire alarm control unit
(FACU). The FACU will be used to provide sequence of operation for the gaseous clean
agent system in data center and the double interlock preaction system in the data center
and the emergency communication center (ECC). Smoke detectors will be provided
throughout all portions of the building to provide a fully automatic system as required by
applicable standards. The clean agent system will be actuated using a very early
warning air-sampling smoke detection system. Heat detectors, in addition to sprinkler
actuation, will be used to activate the preaction valve, releasing water into the piping
protecting the data center and ECC areas only and flow through the activated
sprinkler(s). Manual alarm pull stations will be provided at all exits and along egress
routes as necessary. Detailed conditions such as fire alarm device type and room
description will be reported at the fire alarm panel and associated annunciators; a
remote annunciator will be provided in the ECC to monitor fire alarm status. Fire alarm
devices will consist of initiating, notifying, supervisory, and control devices. All circuits
will have Class A wiring to provide additional continuity for the system and will meet the
provisions for circuitry in NFPA 70. Notification devices will include strobes, horns, or
combination horn/strobes. Supervisory devices will include sprinkler valve supervisory
switches, duct detection activation, and very early warning system pre-alarm signals.
Pending approval by the local building official, audible appliances will be excluded from
the ECC to maintain critical operational functions of the facility. Control devices will
include relays and control modules. These devices will be used to activate alarm
functions when an alarm or trouble condition appears within the fire alarm system.
Monitor modules will be used to monitor non-addressable or other related fire alarm
devices, such as flow switches, valve supervisory switches, or pre-action system
operations.