Instructor:
Dr Wong Wai Fan
(PE, Adjudicator)
wwf/Mydocument/CV4201 CV4201-Lecture 3 & 4 1
CV4011/4201
Lecture 3- Planning Act
■ Any new building project development requires two major stages of
approval**:
- Planning approval (governed by Planning Act)
- Building plan approval (governed by Building Control Act)
Route:
Applicationfor Applicationfor Written
OR
Outline Permission Permission
Outlinepermission
Disapproval
granted
URA’s DCD&Consultations,
Directive &Compliances
Provisional Permission
Further Compliances
Resubmission, Dev’t charge ?
Formal Written
Permission
Recommend to Read:
1. Lecture note 1
2. Ref reading :Planning Act
Website Access for Gov. Acts: www.agc.gov.sg
look for Singapore statutes online
Instructor:
Dr Wong Wai Fan
(PE, Adjudicator)
Dep’ts
Obtain BP
Clearances from Dep’ts
Permit will lapse if any of the 3 key parties (Owner, QP and Builder)
cease to be in force
■ An AC must be:
- A person of good character and ability with sufficient years
of practical experience
- Must not have any professional or financial interest in the
particular building project**
- For project more than certain sum, say S$10m, an Accredited
Checking Organization must perform the AC’s role
- AC’s practice is subject to yearly renewal
■ Other buildings:
- 5 years after the issuance of CSC and thereafter at
intervals of not less than 5 years
- The inspection to be carried out by a registered
structural PE
- The PE for inspection must not have any
professional or financial interest in the building**
- Professional interest
- Financial interest