MRT JAKARTA PHASE II

Features & Challenges

Jakarta, 6 November 2018

#UbahJakarta
OUTLINE

MRT Jakarta at Glance

Contract Package of MRT Jakarta Phase 2

Construction Challenge of MRT Jakarta Phase 2

Addressing the Challenge

2
DEPO
MRT JAKARTA NETWORK

I SOUTH – NORTH LINE


II (Lebak Bulus – Bundaran HI – Kampung Bandan)

Corridor : Lebak Bulus - Bundaran HI


Length : ± 15.7 Km
Construction Type : Elevated & Underground
Stations : 13 Stations & 1 Depot

Corridor : Bundaran HI – Kampung Bandan


Length : ± 7.8 Km
Construction Type : Underground & At-grade
Stations : 8 Stations & 1 Depot

III EAST – WEST LINE

Corridor : Cikarang – Balaraja


Length : ± 87 Km
Stations : 41 Stations

Phase I : Ujung Menteng – Kembangan


Length : ± 27 Km
Construction Type : Undergound & Elevated DEPO
Stations : 22 Stations & 2 Depots
Underground Station Elevated Station

3
MRT JAKARTA PHASE 2 FEATURE
PROJECT FEATURES NORTH – SOUTH LINE
(Lebak Bulus – Kampung Bandan)
Length ± 23 km (total) ; ± 7.8 km (phase 2)
Station Distance 0,6 – 1,0 km
Headway 3-5 minutes
Gauge width 1.067 mm
Train Operation Automatic Train Operation (ATO)
Signalling Communication-Based Train Control (CBTC)
Commencement date (fase 2) January 2025

Challenges
 Construction near & crossing canal
 Crowded & narrow construction space
 Utility Diversion
 Construction in heritage area
 Construction in national landmark with high security requirements
 Soft Soil & Land Subsidence

4
PHASE 2 CONTRACT PACKAGE

ALIGNMENT
PHASE II

Bid start
Contract Package Form Period Contents
(Const. start)

CP201 UG Civil 1 D&B 61 mo • 2 Underground stations Dec 2018


(2.678 km) (FIDIC • Bored tunnel (1.96 km) (Dec 2019)
Yellow) • C&C tunnel (0.22km)

CP202 UG Civil 2 D&B 57 mo • 3 Underground stations Mar 2019


(1.827 km) • Bored tunnel (1.19 km) (Apr 2020)

CP203 UG Civil 3 D&B 57 mo • 2 Underground stations Mar 2019


(1.296 km) • Bored tunnel ( 0.69 km) (Apr 2020)
• C&C tunnel (0.18km)

CP204 UG, AG, Sta and Depot D&B 53 mo • Transition UG to AG Jul 2019
• At-Grade station (Aug 2020)
• Depot

CP205 E&M Systems, Track D&B 54 mo • Supply & Install E&M systems & tracks Jun 2019
(Jul 2020)

CP206 Rolling Stock D&B 54 mo • 14 train set (84 cars) Jun 2019
(Jul 2020)
5
PHASE 2 PROJECT SCHEDULE
2018 2019 2020 2021 2022 2023 2024
CP201 Bidding Design Civil & Structural
UG Civil 1 Architectural & BS
(61 months) T&C

CP202 Bidding Design Civil & Structural


UG Civil 2 Architectural & BS
(57 months) T&C

CP203 Bidding Design Civil & Structural


UG Civil 3 Architectural & BS
(57 months) T&C

CP204 Bidding Design Civil & Structural


UG Civil 2 Architectural & BS
(53 months) T&C

CP205 Bidding Design Manufacturing


E&M System + TW TW, Power, Sig & Com
(54 months ) T&C

CP206 Bidding Design Manufacturing


Rolling Stock Delivery
(54 months) T&C
T&C: Test & Commission, Integ. Test, Test Run, BS: Building Service, RS: Rolling Stock, Sig & Com: Signal & Comm Sys, TW: Trackwork,
PHASE 2 ISSUE

1 Contractual Condition under Review by JICA


• Japanese Products Percentage under STEP condition
• Foreign Contractor’s Tax issues
• Price Adjustment

2 New Items on Employer’s Requirement


• Utility common ducts shall be constructed under interfacing with Bina Marga
• Application of Building Information Modeling (BIM) is required in design and as-built drawings
• Green initiative: CT VT design to consider surrounding environment and application of green fence along
construction area

Example of Green Construction Fence Example of Green CT VT Design

7
MRT JAKARTA PHASE 2 – CHALLENGES
CONSTRUCTION NEAR & CROSSING CANAL WITH LIMITED CONSTRUCTION SPACE

• Station Harmoni – Mangga Besar positioned


under Jalan Gajah Mada near Kali Batang Hari
• Entrance corridor will cross under Kali Batang Hari
• 4 Stories Stacked Station at Sawah Besar and
Mangga Besar chosen due to the limited
construction space

8
MRT JAKARTA PHASE 2 – CHALLENGES
UTILITY DIVERSION

• There are a lot of utilities along construction area


• Major utility work (i.e. protection, diversion) to be expected during construction stage
• Limited construction space will be extra challenge for utility diversion work
9
MRT JAKARTA PHASE 2 – CHALLENGES
CONSTRUCTION IN HERITAGE AREA
1 Stasiun Jakarta Kota
• MRT Jakarta Phase 2 will be constructed along
heritage & cultural area.
1
• Ground Level Design along Harmoni – Kota need to
be designed to preserve cultural identity of the
surrounding area
2 Gedung Arsip Nasional
• Several building along MRT Jakarta Phase 2
2 classified as class A heritage building

• Construction method needs to consider impact to


surrounding building
3

3 Restoran Istana Harmoni


MRT JAKARTA PHASE 2 – CHALLENGES
CONSTRUCTION NEAR NATIONAL LANDMARK

BANK INDONESIA PRESIDENTIAL PALACE

• There are 2 national landmarks with high security requirement near MRT Jakarta Phase 2 construction area
1. Bank Indonesia near Sarinah Station
2. Presidential Palace near Monas – Harmoni Station
• Risk and high security requirement need to be implemented during design (station & tunnel design),
construction & operation phase through security provisions due to the sensitivity of these two national
landmarks
MRT JAKARTA PHASE 2 – CHALLENGES
SOFT SOIL & LAND SUBSIDENCE
SARINAH STATION Ground Consol. 10 30 50 90 Final
Water Degree (%)
Lowering
Subsidence 0.2 2.1 5.9 25.5
(m)
Time (year)
-2 Subsidence 0.02 0.07 0.12 0.22 0.24
amount (m)
-4 0.05 0.14 0.24 0.47 0.47
-6 0.07 0.21 0.35 0.63 0.7
-8 0.09 0.28 0.46 0.83 0.92

• MRT Jakarta Phase 2 corridor will face worse soil condition than
Phase 1.
• Soft soil condition & Land Subsidence most likely to occur at MRT
Jakarta Phase 2
• Soil improvement measure is required
• Construction method, temporary works design, station & tunnel
design need to consider this condition 12
ADDRESSING THE CHALLENGE

Good Coordination with Related Stakeholder STAKEHOLDERS:

• National Government
(Bappenas, MoF, MoT,
MPWH, etc.)
Technologies • Regional Government
(Gubernur, TGUPP,
• Safe Dishub, DBM, Citata,
Construction • Economic etc.)
Challenges – SUCCESSFUL
• On-time • Private parties (land
Phase 2 PROJECT owner, utility owner,
• Eco-friendly etc.)
Know-how /
experience

Experienced Contractor
Informasi yang terdapat dalam presentasi ini dimaksudkan semata-mata untuk penggunaan pribadi atau entitas kepada siapa PT MRT JAKARTA
ditujukan dan lain-lainnya yang berwenang untuk menerimanya. Presentasi ini mungkin berisi informasi rahasia atau informasi Wisma Nusantara 21st Floor
pribadi. Jika Anda bukan penerima yang dituju, dengan ini ditegaskan bahwa setiap pengungkapan, penyalinan, pendistribusian Jl. MH. Thamrin 59
atau pengambilan tindakan apapun berdasarkan isi presentasi ini sangat dilarang dan memiliki kemungkinan pelanggaran Jakarta 10350-Indonesia
hukum. Jika Anda menerima presentasi ini karena kekeliruan, harap segera hubungi kami dengan membalas email ini atau Phone: +6221-3906454
hubungi kami di alamat yang disebutkan di atas. Fax: +6221-3155846 / 3142273
Website: www.jakartamrt.co.id
The information contained in this presentation is intended solely for the use of the individual or entity to whom it is addressed and Facebook: www.facebook.com/jakartamrt
others authorized to receive it. It may contain confidential or legally privileged information. If you are not the intended recipient, Twitter: @mrtjakarta
you are hereby notified that any disclosure, copying, distribution or taking any action in reliance on the contents of Instagram: @mrtjkt
this presentation is strictly prohibited and may be unlawful. If you have received this presentation in error, please notify us
immediately by responding to this email or contact us at the address mentioned above
For further information:
Corporate Secretary PT MRT Jakarta