Академический Документы
Профессиональный Документы
Культура Документы
Bulletin # 010717
July 17, 2001
9) Loosen the top nut on each of the three pieces of all thread. Tighten the bottom nuts
enough to ensure muffler is supported by the base. Tighten the top nuts. Snug up the
two supports between the muffler inlet pipes and its base.
10) Remove the retaining strap that goes over pivot pin. Keep the strap and bolts for
future use.
11) Lower the cradle to the skid via the jackscrews.
12) The muffler is ready for operation.
13) During unit warm up, check the muffler base to insure it is supporting the weight of
the muffler. Repeat steps 8 and 9 if required. Recheck base periodically to assure
that it is supporting the muffler’s weight.
Page 1 of 3
Moving the Muffler from the Operating Position to the Transport Position
1) Allow the muffler and exhaust lines to cool down.
2) Raise the cradle up via the four jackscrews to almost touching the muffler pivot pin.
Align the cradle parallel with the pivot pin, and also have the pivot pin centered in
bottom of cradle.
3) Ideally the muffler pivot pin should stay centered in bottom of cradle during muffler
rotation. Apply oil, grease or WD40 to the pivot pin/cradle interface to minimize the
pivot pin “climbing” the cradle wall.
4) Adjust the cradle height via jackscrews so that “some load” is transferred from the
pivot pin to the cradle.
5) Tighten the cradle’s four tie down bolts securely.
6) Bolt the retaining strap in position over the pivot pin.
7) Rotate the winch handle clockwise (looking from unit cooler side) to put a “little”
tension on the winch’s cable.
8) Loosen the two supports between the muffler’s inlet pipes and base.
9) After loosening the bottom nut on each of the three pieces of all thread, raise the
muffler base by tightening top the nut on each of the three pieces of all thread. If the
tie bar is hanging from the muffler’s counterweight, swing it up, out of the way,
to prevent it from hindering the raising of the base.
10) Connect the tie bar between muffler’s counterweight and muffler’s base.
11) Tighten the bottom nut on each of the three pieces of all thread. Make sure that the
top nuts are tight. Snug up the two supports between the muffler inlet pipes and base.
12) Remove the muffler flange/exhaust line flange bolts. Keep bolts and nuts for future
use.
13) Rotate the winch handle clockwise (looking from unit cooler side) to raise the muffler
slightly. Remove the exhaust line gaskets. Continue raising the muffler to the
transport position.
14) Install the bolt, flat washer and nut that hold the muffler and winch stand together.
The bolt, flat washer and nut should be attached to a chain on the winch stand.
15) Slide the two 2x4 transport supports between the cradle and skid. Lower the cradle
onto the transport supports via the jackscrews. Tighten the four cradle tie down bolts
securely.
16) Use transport-grade load binding equipment to secure the muffler to the main unit
skid or the truck bend prior to transporting.
Page 2 of 3
Muffler/Winch Cable Attachment
If it becomes necessary to replace the connection between winch cable and muffler, the
following is required.
1) A piece of 3/8” x schedule 80 pipe must fit snugly between the muffler prongs.
2) The contact surface for both muffler prongs and pipe ends must be free from
lubricants.
Page 3 of 3
Technical Information
Bulletin # 010911
Revised November 7, 2001
Rebecca® fuel valve cartridges are available for LE, non-LE, AEGIS 2000,
or lay shaft engines.
Installation
1. The cartridge is to be tightened to 110 lbs-ft in the lower housing body. Use of
thread lubricant should not be necessary. However, a small amount of crankcase
oil can be utilized to assure good thread contact and transfer of force to the
cartridge-to-body gasket. Do not use a thread lubricant with nickel, graphite,
molybdenum, or other friction reducing compounds.
2. Verify that the gasket on the set screw's jam nut is in good condition. Then,
tighten the set screw to 10 lbf-ft. Tighten the set screw's jam nut to hold the
screw and cartridge in place. Do not use a thread sealant/adhesive on these
threads.
3. (For AEGIS 2000 engines only) The valve's lift should be 0.150". This is
determined by mechanically depressing the plunger assembly in the assembled
valve, and measuring how far the valve's head extends from the closed position.
This is typically done with the valve assembly held in a vice, and a magnetic
base dial indicator positioned at the valve head. Use shim pack p/n 027-114 to
attain the 0.150" ± 0.003" lift.
4. Use gasket p/n A-2569 between the plunger housing and lower body.
1
Application & Identification
See the attached pages for assembly drawings of the four different complete gas
injection valve assemblies, and the two different Rebecca® cartridges.
2
Technical Information
Bulletin # 020326
March 26, 2002
Check the following MONTHLY (or 800 hours), and correct or repair as necessary
Date: ___ - ___ - ____
perform weekly maintenance
check safety control panel and fuel valve for proper operation and shutdown
panel mounted safety limit switches and set point values
unit mounted safety limit switches
compressor rod packing blow-by
drain oil from compressor distance pieces and record quantity ____ ____ ____
lubricate the throttle linkage
manually actuate scrubber and fuel filter dump valves
MONTHLY (or 800 hours) cont'd.
The compressor unit needs to be shut down and blocked in for the following:
clean or replace air filters
lubricate the water pump with one shot of grease/point
lubricate the cooler bearings with one shot of grease/point
lubricate the idler bearing with one shot of grease/point
inspect the belts for proper tension, replace if worn
clean debris from the cooler
drain the power cylinder scavenger ports and record quantity
clean or replace spark plugs and spark plug wires (gap the plugs at OEM specs)
clean the LE check valves and orifice nipples
inspect the LE fuel filter
tightness of external fasteners
frame to skid
compressor crosshead guide (to the frame and the skid)
compressor cylinder supports, adjust if necessary
compressor cylinder to crosshead guide
Check the following ANNUALLY (or 8000 hours), and correct or repair as necessary
Date: ___ - ___ - ____
perform weekly and monthly maintenance
change crankcase oil, clean the crankcase, inspect for metal, water, etc
Bump check rod bearings replace if necessary
clean the crankcase breathers, or renew replaceable elements
drain and clean the lubricator box
remove and inspect the fuel injection valves
crosshead-to-guide, and pin-to-bushing clearances, and record
internal fasteners for proper torque
piston rods for wear and scuffing
change rod packing if leakage is noted
remove and inspect compressor valves, inspect compressor cylinder condition through
the valve ports
remove, clean, and inspect mixer valves; assure a smooth, scratch-free seating area and
replace all the valve plates (reed strips) and springs
inspect power cylinders through fuel injection port and LE ignitor port
Check the following every 16,000 Operating Hours, and correct or repair as necessary
Date: ___ - ___ - ____
perform weekly, monthly, and annual maintenance
re-ring power and compressor cylinders
replace wiper and pressure packing
inspect pistons, rods and cylinders
inspect crosshead pins and bushings
inspect connecting rod and main bearings
Technical Information
Bulletin # 020718
July 18, 2002
The following component dimensional specifications and wear limits should be used as a
guide for preventative maintenance programs for Ajax equipment. Problems can be
detected early before failures occur.
These specifications are based on data gathered from a broad range of Ajax installations
covering many decades of operating experience.
Specific unit performance and maintenance requirements may vary based on application
conditions and preventative maintenance practices.
The following component dimensional specifications and wear limits should be used as a
guide for preventative maintenance programs for Ajax equipment. Problems can be
detected early before failures occur.
These specifications are based on data gathered from a broad range of Ajax installations
covering many decades of operating experience.
Specific unit performance and maintenance requirements may vary based on application
conditions and preventative maintenance practices.
The following component dimensional specifications and wear limits should be used as a
guide for preventative maintenance programs for Ajax equipment. Problems can be
detected early before failures occur.
These specifications are based on data gathered from a broad range of Ajax installations
covering many decades of operating experience.
Specific unit performance and maintenance requirements may vary based on application
conditions and preventative maintenance practices.
Ajax began using divider block lubrication system as standard equipment for all production units
during the 3rd quarter of 2002.
Part of this system is a digital electronic monitor that provides two main operational features:
1) safety shutdown sensing for low flow rate to either engine or compressor sections of the system,
2) displays the lube rate for both the engine and compressor sections.
Temporary Power:
For ignition voltage powered DLM-926PM monitors, a 9V battery can provide sufficient power to
check the configuration values in its memory. A RadioShack® 9V battery connector with leads,
their 270-324 (or equivalent), allows easy connection of the battery to the monitor. Be certain to
disconnect the ignition power wiring during this operation.
ALARM ENGINE
Ajax compressors with a concrete filled skid or separate concrete filled base can be set directly
onto the ground.
The rectangular pit’s length and width is illustrated in Figure 1. Its depth depends upon the
height of the skid’s I-beam. Conventional depth is ¼ of the beam’s height plus 6” for the sand
pad. For example, if the main skid beam is 12”H, then ¼ x 12” = 3”, plus 6” of sand = 9” deep
pit. Also, it must be level and well drained.
After the sand is put into the pit, arrange a trough beneath the crankshaft area of the skid. Its
dimensions should be 3” deep, 2’ either side of the crankshaft center line, and the width of the
pit. This will allow any discontinuities on the skid’s bottom to be supported by sand as it
migrates to fill voids during engine operation.
Crankshaft Centerline
Skid Footprint
Trough Beneath
Crankshaft Area
Sand Pad
Figure 1
After the compressor package is set on the sand pad and leveled, put additional sand along the
full length of the skid’s outside runners. The top of the ramped up sand should be halfway up the
height of the skid runner as illustrated in Figure 2
After the compressor starts running, the “energy” of the skid will pull the sand under the skid –
filling voids and building up a dense and reliable foundation. Care must be taken to maintain a
supply of sand to the areas from which it migrated under the skid.
This process should allow the compressor package to “settle in” and produce a smooth running
unit.
Skid Runner
Sand
Ramp
6”+ 1/4 H
H
Ground
1/2 H 6” Sand Pad
Figure 2
Setting the compressor upon a sand pad that is not below grade (Figure 3) is not recommended.
The sand can easily wash or migrate away from beneath the compressor.
Figure 3
Technical Information
Bulletin # 031104
November 4, 2003
Subject: Hydraulic Fuel Injection System
a) Potential Fire Hazard
b) Purging Procedure
c) Recommended System Modifications
A potential fire hazard exists on Ajax engines with hydraulic fuel injection:
2) A damaged purge valve assembly can allow hydraulic fluid to leak and contact a hot
exhaust pipe and ignite .
As seen in Figure 1, the bleed valve is assembled to the cap of the injection valve by use of a
pipe nipple and pipe tee. These assembled parts can be bumped and damaged when servicing
adjacent components such as cylinder heads. The pipe nipple can also be damaged if the gas
injection valve assembly is mishandled during servicing.
Figure 1
As seen in Figure 2, relocation of the bleed valve to the topmost part of the gas injection valve
minimizes damage potential, and permits more efficient purging of the hydraulic system.
Convert to the current design by replacing the injection valve’s cap with the current design.
A parts kit for the conversion is available, or individual pieces can be specified. See the
appropriate table below for a kit P/N or the individual P/Ns.
Subject: Main Bearing & Crankshaft Installation on DPC-2803 & DPC-2804 model series
Bearing halve
numbers
corresponding to
numbers on tie bars,
caps, and journals
Prior to bearing installation, ensure that all main journal bores (saddles and caps) are clean, dry (no oil) and free of burrs. Be
certain that nothing is placed between the bearing back and the journal bore surfaces.
Place the bottom half of each bearing set in its assigned frame saddle, except the main/thrust bearing. (The main/thrust
bearing is installed after the crankshaft is located in place, and discussed later.) On the cap, be certain that the holes in the
bearing half are aligned with the cap’s dowel pins. (These are locating pins to assure correct placement of both halves
during the “torque down” of the cap. The pins do not prevent bearing rotation, that is done by proper fit and fastener
tightening.)
Each bearing half should fit snugly in its saddle or cap. If it must be forced into place, a problem exists. Remove it, and
check the mating surfaces for burrs and dimensional inconsistencies. Each bearing half must be square with its companion
saddle or cap. Use a feeler gauge to check the gap between the bearing’s flange and saddle or cap surface; a uniform gap
(± 0.002”of the gap) is expected
Page 1 of 4
Crankshaft Installation
Before the crankshaft is installed, wipe the installed bearing surfaces clean. Then apply a generous amount of oil on the
exposed surface of each bearing.
NOTE: It is very important that nothing (including oil) is between the bearing back and the surface
of the engine frame’s bearing bore (the saddle). It will cause insufficient clearance, and lead to
imminent failure
Lifting
sling #1 power throw
locations
#3 power throw
Page 2 of 4
Main/Thrust Bearing Installation
Install the main/thrust bearing after the crankshaft is setting on the other main bearings. Otherwise the bearing’s thrust
surfaces would be damaged if the crankshaft were slightly not square to the frame while lowering it into place.
The main/thrust bearing is to be “rolled” into place. Remember, do not allow oil on the back of the bearing or the saddle
surface. It may be helpful to have the crankshaft rotated very slowly during this process. Bearing installation/removal tool
p/n A-4676-3 (for DPC-2803s), or A-4676-4 (for DPC-2804s), can also be used.
Bearing Clearances
Crankshaft to bearing clearance of 0.004”-0.007” is most readily determined by use of blue Plastigage®. (See their
instructions for application details.) Place each prepared bearing cap on its appropriate frame location – do not tighten the
stud nuts, yet. Then, install the tie bars in their assigned locations, and tighten their cap screws to 260 lbs-ft torque. The
bearing cap stud nuts should next be tightened in a “zigzag” manner and in 90 lbs-ft torque increments to a total of 360 lbs-
ft torque.
Remove the tie bars, then remove the bearing caps, and measure the blue Plastigage®. If the required 0.004”-0.007”
clearance is not attained, disassemble and measure the component parts to determine a dimensional irregularity for
correction.
Plastigage® Measurement
Once the bearing to crankshaft clearances are acceptable, and the tie bars and bearing caps re-installed and retightened,
check the thrust for 0.010” to 0.020” clearance. If the required clearance is not attained, disassemble and measure the
component parts to determine a dimensional irregularity for correction.
Page 3 of 4
Crankshaft Web Deflection
After all of the bearing clearances are confirmed as acceptable, measure the crankshaft’s power throw web deflections.
Place the dial indicator (Starrett # 900-728, Ajax P/N 111-355) as shown below. The limit for total indicator runout (TIR)
for a full crank revolution is 0.0010” maximum without the flywheel installed. If the flywheel is installed, power throw #1
is permitted 0.0013” TIR maximum.
Page 3 of 4
4-Throw Crankshaft
Refer to Ajax engineering standard ES 4025 for details for measurement techniques and details, and a sample report form.
Page 4 of 4