II CIMIENTOS
2.1 Excavación manual en tierra m3 14.74 18,051.31 266,112.47
2.2 Relleno con material sobrante m3 16.00 7,736.28 123,780.44
III MAMPOSTERIA
3.1 Muro en soga, ladrillo común m2 221.95 45,261.09 10,045,698.00
IV ESTRUCTURAS EN CONCRETO
4.1 Viga de cimentación, 20x25 cm. m.l. 49.28 35,281.78 1,738,686.33
4.2 Columnas, 25x25 cm. m.l. 90.00 75,389.03 6,785,012.86
4.3 Vigas de amarre m.l. 98.56 72,483.73 7,143,996.75
4.4 Escaleras en concreto m2 4.30 150,000.00 645,000.00
4.5 Losa de entrepiso en metaldeck cal 20 m2 78.06 93,416.92 7,292,124.68
VII OTROS
7.1 Formaleta de escaleras segundo piso m2 4.30 30,000.00 129,000.00
7.2 Acero refuerzo de escaleras segundo piso kgr 38.70 2,583.33 99,975.00
7.3 Perfil C Grado 36 por 6 m UND 6.00 143,400.00 860,400.00
7.4 Instalacion metaldeck para losa m2 78.06 45,835.54 3,577,922.13
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
Varenga 2" x 4" m.l. 0.20 650.00 130.00
Estacas und 0.40 500.00 200.00
Puntilla 2" lbr 0.02 2,500.00 50.00
380.00
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
Cuadrilla No. 2 265,612.19 340.00 781.21
781.21
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 39.06
39.06
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
0.00
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 1 51,575.18 40.00 1,289.38
1,289.38
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 64.47
64.47
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
0.00
0.00
0.00
0.00
0.00
0.00
0.00 0.00
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 1 - CARGUE A VOLQUETA 51,575.18 15.00 3,438.35
3,438.35
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 171.92
VOLQUETA 4,000.00
4,171.92
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
0.00
0.00
0.00
0.00
0.00
0.00
0.00 0.00
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 1 51,575.18 3.00 17,191.73
17,191.73
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 859.59
1.00 0.00
1.00 0.00 859.59
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
0.00
0.00
0.00
0.00
0.00
0.00
0.00 0.00
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 1 51,575.18 7.00 7,367.88
7,367.88
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 368.39
368.39
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
CONCRETO 1:2:2.5 M3 1.00 227,914.29 227,914.29
DESPERDICIOS 5% 11,395.71
239,310.00
MANO DE OBRA:
CUADRILLA CANT. Vr.CUADR. REND./DIA Vr.TOTAL SUMA
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 2,030.77
MEZCLADORA 60,000.00 4.00 15,000.00
1.00 0.00 17,030.77
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
LADRILLO TOLETE COMUN UND 100.00 550.00 55,000.00
MORTERO 1:4 M3 0.07 213,871.43 14,971.00
ANDAMIOS GBL 0.00 250.00 0.00
DESPERDICIOS 5% 3,498.55
0.00
0.00
0.00 73,469.55
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 4 110,886.64 8.00 13,860.83
13,860.83
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 693.04
693.04
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
MORTERO 1:3 M3 0.02 257,871.43 5,157.43
CEMENTO GRIS KGR 1.00 500.00 500.00
DESPERDICIOS 5% 282.87
ANDAMIOS GBL 0.00 250.00 0.00
0.00
0.00
0.00 5,940.30
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 5 110,886.64 25.00 4,435.47
4,435.47
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 221.77
221.77
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
LADRILLO TOLETE COMUN UND 82.00 550.00 45,100.00
MORTERO 1:4 PEGA M3 0.04 213,871.43 8,554.86
MORTERO 1:3 REPELLO M3 0.04 257,871.43 10,314.86
CONCRETO 1:3:3 TAPA M3 0.04 189,400.00 7,576.00
CEMENTO GRIS PARA IMPER. KGR 1.50 500.00 750.00
HIERRO 3/8" KGR 3.67 2,000.00 7,340.00
ALAMBRE DE AMARRE KGR 0.15 3,500.00 525.00
CONCRETO 1:3:3 SOLADO M3 0.04 189,400.00 7,576.00
DESPERDICIOS 5% 4,386.84 92,123.55
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 4 110,886.64 2.00 55,443.32
55,443.32
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 2,772.17
2,772.17
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
TUBO PVC SANITARIO 4" M.L. 1.05 6,000.00 6,300.00
SOLDADURA PVC 1/4 GAL 0.02 15,000.00 300.00
6,600.00
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 4 110,886.64 40.00 2,772.17
2,772.17
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 138.61
138.61
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
LADRILLO TOLETE COMUN UND 50.00 550.00 27,500.00
MORTERO 1:4 M3 0.04 213,871.43 8,554.86
ANDAMIOS GBL 250.00
36,304.86
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 4 110,886.64 13.00 8,529.74
8,529.74
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 426.49
426.49
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
CONCRETO 1:2:3 M3 0.05 213,800.00 10,690.00
HIERRO DE 3/8" KGR 2.24 2,000.00 4,480.00
HIERRO DE 1/2" KGR 4.00 2,583.33 10,333.33
ALAMBRE DE AMARRE KGR 0.13 3,500.00 455.00
DESPERDICIOS 5% 1,297.92
27,256.25
MANO DE OBRA:
CUADRILLA UND. CANT. Vr.UNIT. Vr.TOTAL SUMA
PRODUCCION DE CONCRETO M3 0.05 33,201.52 1,660.08
ACARREO, VACIADO Y VIBRADO M3 0.05 33,201.52 1,660.08
CORTE Y FLEJADO DE HIERRO KGR 6.24 676.92 4,224.01
7,544.16
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 377.21
MEZCLADORA 25,000.00 240.00 104.17
481.37
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
CONCRETO 1:2:3 M3 0.08 213,800.00 16,035.00
HIERRO DE 3/8" KGR 2.24 2,000.00 4,480.00
HIERRO DE 1/2" KGR 4.00 2,583.33 10,333.33
HIERRO DE 5/8" KGR 3.10 4,666.67 14,466.67
ALAMBRE DE AMARRE KGR 0.11 3,500.00 385.00
FORMALETA M2 0.40 16,564.17 6,625.67
DESPERDICIOS 5% 2,616.28
54,941.95
MANO DE OBRA:
CUADRILLA UND. CANT. Vr.UNIT. Vr.TOTAL SUMA
PRODUCCION DE CONCRETO M3 0.08 33,201.52 2,490.11
ACARREO, VACIADO Y VIBRADO M3 0.08 33,201.52 2,490.11
CORTE Y FLEJADO DE HIERRO KGR 9.34 676.92 6,322.47
FORMALETA M2 0.40 20,307.73 8,123.09 19,425.79
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 971.29
MEZCLADORA 25,000.00 500.00 50.00
1,021.29
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
CONCRETO 1:2:3 M3 0.06 3,400.00 210.80
HIERRO DE 3/8" KGR 2.22 400.00 888.00
HIERRO DE 1/2" KGR 4.00 6,500.00 26,000.00
HIERRO DE 5/8" KGR 3.10 1,800.00 5,580.00
ALAMBRE DE AMARRE KGR 0.11 3,000.00 330.00
FORMALETA M2 0.40 63,536.00 25,414.40
DESPERDICIOS 5% 2,921.16
61,344.36
MANO DE OBRA:
CUADRILLA UND. CANT. Vr.UNIT. Vr.TOTAL SUMA
PRODUCCION DE CONCRETO M3 0.06 33,201.52 2,058.49
ACARREO, VACIADO Y VIBRADO M3 0.06 33,201.52 2,058.49
CORTE Y FLEJADO DE HIERRO KGR 6.22 676.92 4,210.47
FORMALETA M2 0.11 20,307.73 2,233.85 10,561.31
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 528.07
MEZCLADORA 25,000.00 500.00 50.00
578.07
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
CONCRETO 1:2:3 M3 0.08 213,800.00 17,104.00
MALLA ELECTROSOLDADA DE 25x25 e=5MM UND 0.02 75,000.00 1,500.00
METAL DECK DE 2" CAL 20 M2 1.00 45,822.00 45,822.00
FORMALETA M2 0.24 30,000.00 7,200.00
DESPERDICIOS 5% 3,581.30
75,207.30
MANO DE OBRA:
CUADRILLA UND. CANT. Vr.UNIT. Vr.TOTAL SUMA
PRODUCCION DE CONCRETO M3 0.08 33,201.52 2,656.12
ACARREO, VACIADO Y VIBRADO M3 0.08 33,201.52 2,656.12
CORTE E INSTALACION DE MALLA KGR 0.02 676.92 13.54
FORMALETA M2 0.24 20,307.73 4,873.85 10,199.64
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 509.98
MEZCLADORA 60,000.00 8.00 7,500.00
8,009.98
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
CONCRETO 1:3:3 M3 1.30 213,800.00 277,940.00
VARENGA PARA DILATAC. M.L. 1.33 650.00 864.50
DESPERDICIOS 5% 13,940.23
292,744.73
MANO DE OBRA:
CUADRILLA UND. CANT. Vr.UNIT. Vr.TOTAL SUMA
PRODUCCION DE CONCRETO M3 1.30 33,201.52 43,161.98
ACARREO, VACIADO Y VIBRADO M3 1.30 33,201.52 43,161.98
86,323.96
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 4,316.20
MEZCLADORA 25,000.00 170.00 147.06
4,463.26
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
CODO PVC SANITARIO C*C 2" UND 0.00 2,100.00 0.00
CODO PVC SANITARIO C*C 3" UND 2.00 3,400.00 6,800.00
CODO PVC SANITARIO C*E 2" UND 0.00 2,000.00 0.00
REJILLA 2" UND 0.00 1,000.00 0.00
SIFON PVC SANITARIO DE 2" UND 0.00 2,700.00 0.00
UNION PVC SANITARIO DE 2" UND 0.00 1,000.00 0.00
TUBERIA PVC SANITARIA 2" M.L. 0.00 3,000.00 0.00
TUBERIA PVC SANITARIA 3" M.L. 9.00 4,500.00 40,500.00
TUBERIA PVC SANITARIA 4" M.L. 0.00 6,000.00 0.00
YEE PVC SANITARIA 2" UND 0.00 1,000.00 0.00
DESPERDICIOS 5% 2,365.00 49,665.00
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.PUNTO SUMA
CUADRILLA No. 5 :PUNTO SANITARIO 110,886.64 6.00 18,481.11
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 1,848.11
1,848.11
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
TUBO PVC PRESION 1/2" M.L. 16.50 1,400.00 23,100.00
TEE PVC PRESION 1/2" UND 5.00 1,500.00 7,500.00
CODO 90° PRESION 1/2" UND 12.00 1,000.00 12,000.00
UNION PVC PRESION 1/2" UND 2.00 1,000.00 2,000.00
TAPON PVC PRESION 1/2" UND 6.00 1,000.00 6,000.00
ADAPTADOR MACHO PVC 1/2" UND 9.00 1,000.00 9,000.00
CODO GALVANIZADO 1/2" UND 2.00 450.00 900.00
LLAVE PASO DE BOLA 1/2" UND 1.00 3,000.00 3,000.00
CINTA TEFLON UND 1.00 300.00 300.00
LIMPIADOR PVC 1/4 GAL 0.25 9,000.00 2,250.00
SOLDADURA PVC 1/4 GAL 0.20 15,000.00 3,000.00
DESPERDICIOS 5% 3,452.50 72,502.50
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
PUNTO HIDRAULICO CUADR. No.5 110,886.64 6.00 18,481.11
(SON 6 PUNTOS HIDRAULICOS) 110,886.64
110,886.64
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 5,544.33
5,544.33
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
ALAMBRE DE COBRE No. 10 M.L. 0.00 500.00 0.00
ALAMBRE DE COBRE No. 12 M.L. 0.00 350.00 0.00
ALMBRE DE COBRE No. 14 M.L. 0.00 250.00 0.00
CAJA DE CONEXIÓN RECTAN. UND 0.00 1,000.00 0.00
CAJA DE CONEXIÓN EXAG. UND 0.00 1,000.00 0.00
TOMACORRIENTE DOBLE UND 0.00 3,500.00 0.00
TOMA INTERRUPTOR UND 0.00 4,650.00 0.00
INTERRUPTOR SENCILLO UND 0.00 2,500.00 0.00
INTERRUPTOR DOBLE UND 0.00 2,500.00 0.00
TOMA TRIFASICA ESTUFA UND 0.00 4,500.00 0.00
PLAFON DE PORCELANA UND 0.00 2,500.00 0.00
MANGUERA POLIETILENO 1/2" M.L. 4.00 400.00 1,600.00
DESPERDICIOS 5% 80.00 1,680.00
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
PUNTO ELECTRICO - CUADRILLA No. 5 110,886.64 12.00 9,240.55
9,240.55
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 462.03
462.03
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
TABLERO DE DISTRIBUCION UND 1.00 18,000.00 18,000.00
ALAMBRE DE COBRE No.8 M.L. 12.00 800.00 9,600.00
TACOS PROTECCION 30 AMP. UND 1.00 6,600.00 6,600.00
TACOS PROTECCION 15 AMP. UND 2.00 6,600.00 13,200.00
TUBERIA CONDUFLEX 3/4" M.L. 6.00 500.00 3,000.00
DESPERDICIOS 5% 2,520.00
52,920.00
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
PUNTO ELECTRICO - CUADRILLA No. 5 110,886.64 12.00 9,240.55
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 924.06
924.06
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
APARATO SANITARIO UND 1.00 150,000.00 150,000.00
ACOPLE SANITARIO UND 1.00 2,500.00 2,500.00
MORTERO 1:3 REVOQUE M3 0.01 257,871.43 2,578.71
DESPERDICIOS 5% 7,753.94
162,832.65
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 5 - PUNTO SANITARIO 110,886.64 6.00 18,481.11
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 1,848.11
1,848.11
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
LAVAMANOS MANCESA UND 1.00 60,000.00 60,000.00
ACOPLE LAVAMANOS UND 1.00 2,500.00 2,500.00
MORTERO 1:3 REVOQUE M3 0.01 257,871.43 2,578.71
DESPERDICIOS 5% 3,253.94
68,332.65
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 5 - PUNTO SANITARIO 110,886.64 6.00 18,481.11
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 1,848.11
1,848.11
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
JUEGO DUCHA CORRIENTE UND 1.00 20,000.00 20,000.00
CODO GALVANIZADO 1/2" UND 1.00 450.00 450.00
ADAPTADOR MACHO 1/2" UND 2.00 1,000.00 2,000.00
CINTA TEFLON UND 0.50 300.00 150.00
LIMPIADOR 1/4 GAL 0.06 9,000.00 540.00
SOLDADURA 1/4 GAL 0.06 15,000.00 900.00
DESPERDICIOS 5% 1,202.00 25,242.00
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 5 - PUNTO SANITARIO 110,886.64 6.00 18,481.11
18,481.11
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 924.06
924.06
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
PUERTA METALICA 2x1 m. UND 1.00 95,000.00 95,000.00
MORTERO 1:3 REVOQUE M3 0.01 257,871.43 2,578.71
DESPERDICIOS 5% 4,878.94
102,457.65
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 5 110,886.64 6.00 18,481.11
18,481.11
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 924.06
924.06
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
VENTANA METALICA LAMINA M2 1.00 19,000.00 19,000.00
MORTERO 1:3 REVOQUE M3 0.01 257,871.43 2,578.71
DESPERDICIOS 5% 1,078.94
22,657.65
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 5 110,886.64 15.00 7,392.44
7,392.44
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 369.62
369.62
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
LADRILLO TOLETE COMUN UND 75.00 550.00 41,250.00
MORTERO PEGA 1:4 M3 0.04 213,871.43 8,554.86
MORTERO REPELLO 1:3 M3 0.08 257,871.43 20,629.71
CONCRETO LOSA 1:3:4 M3 0.02 169,942.86 3,398.86
CEMENTO IMPERMEABILIZAC. KGR 4.95 500.00 2,475.00
CODO GALVANIZADO 1/2" UND 1.00 450.00 450.00
NIPLE GALVANIZADO 8 cm. UND 1.00 700.00 700.00
UNION GALVANIZADA 1/2" UND 1.00 400.00 400.00
GRIFO COMUN UND 1.00 6,500.00 6,500.00
VALVULA POZUELO 2" UND 2.00 1,800.00 3,600.00
HIERRO 3/8" KGR 4.00 2,000.00 8,000.00
ALAMBRE DE AMARRE KGR 0.12 3,500.00 420.00
DESPERDICIOS 5% 4,818.92 101,197.35
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
GLOBAL
20,000.00
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 1,000.00
1,000.00
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
VALOR LAVAPLATOS UND 1.00 25,000.00 25,000.00
MORTERO 1:3 REVOQUE M3 0.01 257,871.43 2,578.71
27,578.71
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 5 - INSTALACION 110,886.64 6.00 18,481.11
18,481.11
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 924.06
924.06
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
VALOR CERRADURA UND 1.00 22,000.00 22,000.00
22,000.00
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
INCLUIDA EN PUERTA METALICA
0.00
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 0.00
0.00
MATERIALES:
MATERIAL UND CANT. Vr.UNIT. Vr.TOTAL SUMA
VIDRIO INCOLORO 3 mm. M2 1.00 13,500.00 13,500.00
MASILLA LBR 0.50 350.00 175.00
DESPERDICIOS 5% 683.75
14,358.75
MANO DE OBRA:
CUADRILLA Vr.CUADR. REND./DIA Vr.TOTAL SUMA
CUADRILLA No. 5 110,886.64 30.00 3,696.22
3,696.22
EQUIPO Y HERRAMIENTA:
EQUIPO TARIFA REND./DIA Vr.TOTAL SUMA
Herramienta menor 184.81
184.81
PROYECTO: URBANIZACION
OBRA: 86 SOLUCIONES DE VIVIENDA SUBSIDIADA
PRESUPUESTO PARA CONSTRUCCION DE UNA (1) CASA
ZAPATAS:
VIGAS DE CIMENTACION:
COLUMNAS:
LOSAS:
SALARIO
Salario Mínimo A 828,116.00 D 27,603.87 G 10,075,411.33 100.00%
Subsidio de transporte B 97,032.00 E 3,234.40 H 1,180,556.00 11.72% 111.72%
Total C 925,148.00 F 30,838.27 I 11,255,967.33
PRESTACIONES
Cesantía Anual F x 36 1,110,177.60 11.02%
Intereses Cesantía 12%*C.A. 133,221.31 1.32%
Vacaciones Dx15 414,058.00 4.11%
Prima Dx30 828,116.00 8.22% 24.67%
SEGURIDAD SOCIAL
I.V.M.(75% de 11.5% Cuota Patronal) 8,625% x I 970,827.18 9.64%
A.T.E.P. (100% patronal) 5,6% x I 630,334.17 6.26%
E.G.M.(67% de 8% cuota patronal) 5,36% x I 603,319.85 5.99% 21.88%
APORTES AL SENA
Aporte Ordinario 2% x I 225,119.35 2.23%
Fondo Industria de la Construcción 1,67% x I 187,974.65 1.87% 4.10%
OTROS APORTES
Aportes al I.C.B.F. 3% x I 337,679.02 3.35%
Subsidio Familiar 4% x I 450,238.69 4.47% 7.82%
OTROS COSTOS
Ropa de trabajo 2% x I 225,119.35 2.23%
Seguro colectivo 0,5% x I 56,279.84 0.56% 2.79%
HORAS HABILES
Número de semanas al año 52
Número de horas a la semana 48
TOTAL HORAS HABILES LABORALES AÑO(THHLA) 2,496
HORAS NO TRABAJADAS
Festivos: 17 días x 8 h/d 136
Incapacidades no atendidas por el ISS: 3 días x 8 h/d 24
TOTAL DE HORAS PAGADAS NO TRABAJADAS 160