Академический Документы
Профессиональный Документы
Культура Документы
TABLE OF CONTENTS
1.0 INTRODUCTION........................................................................................................................................................2
2.0 THE PROCUREMENT SYSTEMS .................................................................................................................................2
2.1 TRADITIONAL SYSTEM OR DESIGN-BID-BUILD .........................................................................................................4
2.2 INTEGRATED PROCUREMENT SYSTEMS ..................................................................................................................7
(I)Design and Build ....................................................................................................................................................7
(ii) variants of design and build ...............................................................................................................................10
2.3 MANAGEMENT ORIENTED PROCUREMENT SYSTEMS ...........................................................................................12
(i) Management Contracting ...................................................................................................................................13
(ii) Construction Management ................................................................................................................................16
Concept of Construction Project Management ......................................................................................................19
3.0 TYPES OF CONTRACTS............................................................................................................................................20
3.1 Lump Sum Contracts .........................................................................................................................................20
3.2 Continual Contracts ...........................................................................................................................................20
3.3 Measurement Contracts ...................................................................................................................................21
3.4 Cost Reimbursement Contracts ........................................................................................................................21
4.0 THE BASIS OF CHOICE OF PROCUREMENT STRATEGY ...........................................................................................22
5.0 PUBLIC PRIVATE PARTNERSHIPS ............................................................................................................................24
6.0 PUBLIC PROCUREMENT ACT OF KENYA AND THE EFFECTS OF BUREAUCRACY .....................................................25
6.1 Purpose of the PPDA .........................................................................................................................................26
6.2 Procurement Procedures ..................................................................................................................................26
6.3 An Effective Public Procurement System ..........................................................................................................27
6.2 Public Entity Procurement Inefficiency .............................................................................................................29
7.0 CONCLUSION .........................................................................................................................................................32
8.0 REFERENCES ...........................................................................................................................................................32
1.0 INTRODUCTION
The procurement of construction project is vast in scope because it involves the gathering and
organizing of myriads of separate individuals, firms and companies to design, manage and build
construction products such as houses, office buildings, shopping complex, roads, bridges etc. for
specific clients or “customers”.
Procurement comes the word procure which literally means “to obtain by care or effort”; “to
bring about” and “to acquire”. System is about “organized method, approach, technique,
process or procedure”. In this context, project procurement is very much concerned with the
organized methods or process and procedure of obtaining or acquiring a construction product
such as a house, shopping complex or just a building. It also involves arranging and
coordinating people to achieve prescribed goals or objectives.
Today, there are several types or variations of project procurement systems being widely used
in the construction industry. They range from the traditional system to the many variations of
“fast-tracking” systems. The introduction of many variations of project procurement system
was induced by the quest for more efficient and speedier project delivery system and better
project performance. They are innovations to the traditional delivery method aimed at meeting
the changing demand of clients or customers. The different procurement systems present have
brought changes not only to the process and procedure of project delivery but also the aspects
of management and organization.
Procurement phase is identified as being crucial to eventual project success and a significant
component in project failure.
2) Integrated System
The different category and sub-classification of construction project procurement systems can
be as shown below:
PROCUREMENT
SYSTEMS
Management Construction
Traditional Variant of Design Variant of
contracting management
system Traditional and Build Design and
System Build
Under the sequential method or a single stage tendering approach, the building owner will
appoint a team of consultants to act on his behalf to produce construction drawings,
specifications and tender documents and to administer the tendering processes to select a
contractor. Once selected and awarded the contract, the contractor will carry out based on the
drawings and specifications prepared by the client’s consultants.
Client
Limited delegated power as agent
Consultants Contractor
Figure 3.0 – The Linear or Sequential Process of the Traditional Procurement System
Contract for construction is between client and main contractor. Design is usually completed
prior to procurement and commencement of construction Price from the Contractor is based
upon a bill of quantities, or working drawings and specification, which describes the works in
detail. Final cost is measured, based on the actual quantities of work carried out. Usually much
of the work is sub-contracted to specialist firms but the contractor remains liable. The
consultants administer the contract on behalf of the client and advise on aspects associated
with design, progress and stage payments which must be paid by the client. The separation of
the contractor from the design can mean missed opportunities for contractor or specialist
contractor to input. Specialist elements are tendered separately and the selected contractors
appointed as nominated sub contractors to the main contractor. This strategy is seen as the
least risk approach as there is a level of certainty about design, cost and duration inherent in
the strategy if it is properly implemented. However, the exposure to risk will increase where the
design phase is rushed, where unreasonable time targets are set or where the tender
documents are not fully completed.
Cost constraints in traditional projects make it even more difficult for owners to assure project
quality. A design professional that reduces its fee as a consequence of the owner’s negotiation
pressure is likely to devote a reduced number of hours to the project, often at the expense of
quality control. An owner who uses competitive bidding to obtain the lowest possible
construction price may find that the low bid represents an unrealistically low construction cost
and that the contractor intends to cut corners, adopt an obstructionist or adversarial approach
to the project, and seek excessive change orders or other claims with which to make up the
profit that it left out of its competitive bid.
commences while the final finishing details are still being added to the construction documents.
A less aggressive alternative is to bid or price the project from scope documents (construction
documents which are approximately 70% complete) so that the bidding/pricing phase
considerably overlaps the end of the design phase. In two- Stage tender, the Contractor is
appointed on the basis of a first stage tender which determines the level of overhead and profit
for each Contractor. The Contractor then works with the Project Team during the second stage
to develop the designs and establish detailed costings for separate project work elements. This
process will provide for a fixed price on a detailed design basis. This approach increases the
risks of an increase in overall price and a less certain completion date but contractor
involvement is likely to increase the likelihood that both these criteria are realistically
established.
Competitive fairness, since all tendering contractors are bidding on the same basis
Design-led, with the client able to have direct influence, thus facilitating a high level of
functionality and bespoke quality in the design.
Reasonable price certainty at contract award based upon market forces ( subject always to
design changes or client-led changes which will have cost implication)
Where public expenditure or audit demands are rigid the strategy is satisfactory in terms of
public accountability since it is transparent and based upon competition.
Single Contractual Relationship for Construction Stage
The procedures are well known, enabling confidence to be assured in those involved
throughout the supply chain
Phased tendering of mechanical/electrical/fire protection sub-contracts - can award later
Nominated Sub-Contracts for key specialist elements possible
Disadvantages
The strategy is based on price competition and this can result in adversarial relationships
developing.
Suitable for:
All clients, including inexperienced clients, complex projects and projects where functionality is
prime objective time predictability, cost certainty. However, it is not suitable for fast track
projects.
Particularly attractive to clients with a strictly limited budget or a limit to their borrowing
powers since construction costs can be determined with reasonable certainty before
commencement of construction.
Whilst risk is shifted to the contractor, it is important that design liability insurance is
maintained to cover that risk. Changes made by the client during design can be expensive,
because they affect the whole of the Design-Build contract, rather than just the design team
costs.
Client’s requirements
prepared
Submission of proposals
Contractor A
Contractor B Contractor C
Contractor’s proposal
against client
requirements evaluated
Successful contractor
selected
Successful contractor
finalises design and
produces the building
Client
Client’s
agents
Main
contractor
Quantity
Architect Engineer Contractor’s
surveyor
manager
Organisational relationship
Detail design
Figure 6.0 – The Integrated Process of Project Designing and Construction in the Design and
Build Procurement System
Main characteristics under which the D&B procurement option may be appropriate for a
client’s construction project are when:
Turnkey contract is an American term for “all in” or package contract. Under this
arrangement, a contractor is commissioned to undertake the responsibilities for everything
necessary and required for the construction, completion, commissioning and hand over the
project. The word “turnkey” means that, upon completion, the client is given the key and he
can then enter the project by “turning the key”. The contractor will have to do everything
from preparing project brief, getting approval, designing, financing, construction, furnishing
and decorating to commissioning and handing over completed, cleaned and ready for use
project (Allen, 2001).
Develop and construct is another of the integrated procurement approach which is very
much similar to design and build. In this case, the contractor is still given the responsibility
for both the design and construction of the project. The difference is that, under this
method the client’s design consultants prepare the concept sketches or designs and passed
them to the contractor who will develop them and produce the detailed working drawings.
The contractor then takes on ‘finishing off’ the design and construction of the project based
on what it has developed and produced.
Design, Build and Operate This approach would involve the Client Body in selecting a
company or consortium who would carry out the design and construction of the facility, but
would also act as the operations company to manage the facility after construction.
Single Contractual Relationship for all design / construction - This approach has the benefit of
allowing the Client to hand over the complete project (design and construction) to one
company
More price certainty from early stage depending on price variation clauses
You get input from the operations personnel directly at the design stage.
a. The integrated design and construction allows for design and management input fro the
building contractor and this leads to production efficiency in terms of cost and time
b. The method allows for simplified contractual arrangement between client and contractor
with single-point responsibility and improved communication channels between parties to
contract.
c. Project duration is shortened due to contractor’s familiarity with his system and parallel
working on design and construction
d. Client’s total financial commitment os known at an early stage and, provided the client does
not introduce major alterations, this will not change
e. Client obtains competition in design as well as price
f. The closer contractor/client relationship leads to a more efficient design
g. Client obtains a design cost element lower than which an independent designer would
charge under other methods
h. Construction projects using the system have the potential for early completion and lower
overall costs.
11 2.2 Integrated Procurement Systems | Procurement Systems in Building Works
[Construction Contract Administration] January 15, 2010
Disadvantages
a. The building contractor’s in-house design expertise may be insufficient to solve the client's
needs efficiently
b. Tendering costs are high as contractors must design and produce accurate proposals as well
as estimates
c. An inexperienced client will still require construction professionals to advise during
preparation of brief, tender information and evaluation of quality and cost of design
d. The building contractor requires adequate insurance to cover for the design failures as well
as construction
e. Tender comparison becomes complex as it involves evaluation of design, quality and
construction cost.
f. The client finds it difficult and/or costly to introduce variations once production has
commenced on site.
Suitable for:
main responsibility is to manage the design and construction by the design consultants and the
many specialist contractors, respectively.
Client
Detail design
and/or shop
drawings
Project brief Tender doc. & Concept Bidding & Commission &
Feasibility Construction
client req. design contracting hand over
study
Package Contractor’s
responsibility
Figure 8.0 – The Process of Project Designing and Construction in the Management Contracting
& Professional Construction Management Procurement System
1. Early start on site: Where time is of the essence and production cannot wait until design
is fully defined and, hence, the production must proceed in parallel
Early contractor involvement at design phase may lead to better design and detailing which
facilitates productivity and savings on production cost.
The traditional design/construct split is eradicated, enabling the contractor to advise on
quality, buildability, suitability and availability of labour, plant and materials and
construction methods during the design phase.
Design and construction are overlapped as well as overlapping the various work packages.
This saves on project time.
Risk of potential contractual claims is minimized as, from the project’s onset, the MC
identifies contentious project information and recommends its modification prior to
contract.
The ‘them and us’ attitude is eradicated as; from the project’s onset the MC becomes part
of the project team working together to achieve a client’s objectives of time, cost and
quality.
Price is not the only criterion for selection of MC. Rather, in addition, the ability to make
some technical and managerial contribution to the design and production of a prohect is
also considered.
Advance purchasing of essential materials/components and plant can be effected to ensure
their availability for use when required.
Early management contractor’s appointment enables him to give information on the
organization of construction work, site layout, possible works contractors and tendering
arrangements.
Client obtains keener prices owing to the increased competition for his construction project.
Disadvantages
Suitable for:
This approach is generally considered to be appropriate for large, complex fast-track projects
particularly where there is a requirement for maximum flexibility and to overlap design and
construction phases.
Client
Works
contractor
contractual relationship
organizational relationship
Figure 10.0 – The Process of Project Designing and Construction in the Design and Manage
Procurement System
The Construction management (CM) approach to construction procurement emerged due to
clients demand for better quality and faster production at lower costs. Under this strategy, the
client does not allocate risk and responsibility to a single main contractor. Instead, the client
employs the design team and a construction manager is engaged as a fee-earning professional
to manage, programme and co-ordinate the design and construction activities and to facilitate
collaboration in order to improve the buildability of the design. Construction work is carried out
by trade contractors through direct contracts with client for distinct trades or work packages.
The construction manager supervises the construction process and coordinates the design
team.
This is a strategy with little certainty for the client at the outset and one usually adopted where
the primary objective for the client is relative speed for completion. In adopting CM strategy,
the client will be closely involved in each stage of design and construction. The client must have
administrative and project management staff with time and ability to assess the
recommendations of the CM and take necessary action. The client needs to maintain a strong
presence of through a project management team that is technically and commercially astute.
This strategy is therefore not suitable for inexpert or inexperienced clients. The work packages
are tendered individually, for a lumpsum price usually on basis of drawings and/or
specifications. The final costs will only be known once the final work elements have been
awarded.
Disadvantages
Full financial commitment not known at outset of construction- price certainty not known
till last trade package is let. Budgeting depends heavily on design team estimates.
An informed, pro active client is required is required to operate such a strategy
The client must provide a good quality brief to the design team as the design team will not
be complete until the client has committed significant resources to the project
Multiple Construction Contracts with Client
Close time and information control is required.
Risk of conflict at Sub-Contract interfaces – need for co-ordination
Client pays more in professional fees
Client is exposed to a high degree of risk as CM does not take responsibility of late
completion, faulty workmanship etc.
Suitable for:
Note that, construction project management is not a construction procurement system. The
role of the project manager is to select the most appropriate procurement system for the
project. CPM is therefore concerned with management of the whole construction project i.e
the translation of client’s needs into finished functional physical product. The project
management covers:
Coordination of the diverse interests of ultimate users of completed facility and the client
in order to formulate unified client requirement.
Organization of the process of design and construction of project to comply with the client’s
requirements economically and timely.
Design can be tailored to overlap production, thereby reducing the overall project time
Disadvantages
Suitable for: On minor and maintenance works or where there is adequate information to
enable client know his financial commitment.
a. Serial contracts – contractor undertakes to enter into series of separate lumpsum contracts
in accordance with the terms and conditions set out in initial offer. Standing offer may be
determined by competitive pricing of key items in the proposed projects.
b. Continuity contracts – when client wishes to obtain benefits from continuity of work,
building contractor may be asked to enter into negotiations based on original lump sum
contract. One of the negotiations are completed and an agreement reached, the contractor
executes the construction works as separate contract packages within their own
parameters.
Measurement contracts are suitable for projects where clients requirements are not clearly
defined or where prompt commencement on site is required.
Client may wish to influence the execution of works hence, assume entire risk of site
operations
An early start is required but the extent of work cannot accurately be predicted.
Variations to this contractual arrangement may be introduced to motivate and enhance the
contractor’s site performance.
a. Fixed fee – contractor is paid agreed fee based on estimated cost of works. This induces
contractor to work efficiently for profit.
b. Target cost – An estimate is produced for construction project, and once the estimate is
agreed, it becomes the target price which establishes basis for the determination of a fee for
overhead charges and profit. On commencement of site production, contractor is paid the fee
which is adjusted to correspond with increase or decrease of prime cost over target cost. Main
problem of this approach is reaching an agreement of realistic target and the effects of costly
variations which eventually take the construction cost over the agreed target price.
- Increases in level of fluctuations – affect product and trades to be used in the works
- Changes in national or local demand for construction –affect tender price levels
By adopting a simple risk analysis judgement can be done whether contingency sums should
be budgeted for.
b. Client resources – The client’s knowledge, the experience of the client company’s
organization and the environment in which it operates are vital in assessing the appropriate
procurement strategy. The extent to which client is prepared to take a full or active role is a
major consideration.
c. Project characteristics – The size, complexity and location of the project should be carefully
considered and particular attention given to projects with novel elements. e.g if building is
22 4.0 The Basis Of Choice Of Procurement Strategy | Procurement Systems in Building Works
[Construction Contract Administration] January 15, 2010
large and complex, there may be a bigger risk of time and cost overrun. Novel projects
present special risks.
d. Ability to make changes – It is preferable to identify the total needs of the project at early
stages but it is not always possible. Rapidly changing technology often means late changes.
Changes in scope of project often means increased costs, especially if during construction.
Some procurement strategies are better than others in handling the introduction of
changes later in the project and reducing the possibvility of having to pay some form of
specific premium.
- Estimates of costs of future buildings at early stage are notoriously inaccurate but
necessary for decision purposes. Where there’s need for price certainty, this influences
both project timing and the procurement strategy to be used. Generally design should be
complete if price certainty is required before construction commences.
- Inflation will inevitably affect total cost where level of variance and increased proce
clauses exist
f. Project timing – Most projects are needed within a time frame or by a specific date. Timing
will influence whether subsequent can occur as planned and in many cases may severely affect
those factors identified as critical or high priority in business case. The programmes of a project
is influenced by many factors and usually a large and complex is likely to require more time for
design, specification, and construction than would for a simple small building. Some
procurement strategies enable overlap between the design and construction stages, so
construction can start earlier than sequential strategies and offer the potential for earlier
completion. Time has both a cost and a value. If the worth of a project is identifiable then the
cost of relatively late completion and the value of relatively early completion can be assessed
and may form an important factor in decision-making process – referred to as time/cost trade
off.
diminishing returns will have influence because of the limited space and the nature of
traditional construction methods (such as concreting, bricklaying).
h. Performance - The required performance of the project measured in terms of both its
response to the needs of the client expressed in the business case and the quality of individual
elements should be clearly identified. If quality and performance are particulary important the
client will probably want to keep direct control over the development of the design. This can be
achieved by employing the design team directly.
i. Assessment of risks - For example – is this to be a contract with the lowest possible risk to the
client overall; what are the priorities in apportioning the risks concerning cost, time, and quality
or performance; where are the speculative risks intended to lie? Your risk management
strategy will strongly influence your choice of procurement method.
This type of contract focuses on final service delivery and relies upon the required performance
standards being properly documented. Building contractors involved in this type of
development are usually part of a consortium. The consortium has responsibility for the design,
construction and delivery of the project.
Government and its agencies, as either direct or indirect purchasers of services from BOOT
projects, bear some level of financial and viability risk. The BOOT process can be modified to
suit particular needs. A few variations already in use are BOT (Build, Own, Transfer) and BOO
(Build, Own, Operate).
This arrangement is more common for infrastructure projects than buildings because the
concession allows for tolls or other payments to be made by end-users to cover the cost of both
procuring the facility and its operation. Extensions of this idea have been cited where buildings
have been renovated and leased back on this basis and other where the facility is required to
be removed and the site returned to an acceptable environmental standard.
An advantage of this is that it extends the ideas of constructability further to embrace lifecycle
cost effectiveness. If the entity proposing the design solution is responsible for maintaining and
operating the facility then they will have the incentive to reduce long term costs and thus
develop a highly cost effective product over the product lifecycle.
The BOT entity undertakes financing, design, and construction as well as operation and so the
client is taking no direct cost risk other than the possibility that the facility does not meet its
needs or that the concession agreement is unsatisfactory. The cost of establishing the
arrangements can be considerable, as there are legal and financing costs to be met. These
should be compared with the client’s legal and finance costs in undertaking the project in other
forms or options. Clearly the option is unlikely to be viable for projects of small scope,
However, governments are increasingly using this option for hospitals, prisons and other
projects previously undertaken through other procurement scenarios.
Experience with BOO/BOT/BOOT schemes reveals some notable failures. Generally, theses have
been based on failures of trust and/or communication.
The Public Procurement and Disposal Act (PPDA), effective as of 1st January 2007, applies to all
procurement of goods, works and services, as well as the disposal of assets by public entities.
Public entities are those that procure goods, services or works utilising public funds. The
definition of public funds includes donor funds in so far as donor stipulations do not supersede
the Act. If they do, the donor terms and conditions take precedence. As such, public entities
include the central and local governments, courts, commissions, state corporations,
cooperatives, and educational institutions such as colleges, schools and universities.
25 6.0 Public Procurement Act Of Kenya And The Effects Of Bureaucracy | Procurement Systems in
Building Works
[Construction Contract Administration] January 15, 2010
The Act also establishes the Public Procurement Administrative Review Board, which handles
complaints, reviews and appeals stemming from procurement.
This covers the legal and regulatory instruments from the highest level (national law, act,
regulation, decree, etc.) down to detailed regulation, procedures and bidding documents
formally in use.
Pillar II looks at how the procurement system as defined by the legal and regulatory framework
in a country is operating in practice through the institutions and management systems that are
part of the overall public sector governance in the country.
This Pillar looks at the operational effectiveness and efficiency of the procurement system at
the level of the implementing entity responsible for issuing individual procurement actions. It
looks at the market as one means of judging the quality and effectiveness of the system when
putting procurement procedures into practice. This Pillar is distinguished from Pillars I and II in
that it is not looking at the legal/regulatory or institutional systems in a country but more at
how they operate. It looks at the efficiency of the operations and operational practices as
implemented by the procuring agencies. Efficiency is considered to mean that the operational
practices result in timely award of contracts at competitive market prices as determined by
effective and fair implementation of procurement procedures. There are four sub-indicators (a-
d) to be rated under this indicator.
Pillar IV covers indicators that are considered necessary to provide for a system that operates
with integrity, has appropriate controls that support the implementation of the system in
accordance with the legal and regulatory framework and has appropriate measures in place to
address the potential for corruption in the system. It also covers important aspects of the
procurement system that include stakeholders as part of the control system. This Pillar takes
27 6.0 Public Procurement Act Of Kenya And The Effects Of Bureaucracy | Procurement Systems in
Building Works
[Construction Contract Administration] January 15, 2010
aspects of the procurement system and governance environment and seeks to ensure that they
are defined and structured to contribute to integrity and transparency.
While respecting and acknowledging the goals and principles of the system of public
procurement, the prevention of corruption in the system of public procurement is based on the
following measures:
1. Strengthening the legal framework
The aim of strengthening the legal framework is to ensure that all procedures in which the state
is a partner or a contractual party are subject to strict rules, thus reducing the risk of
corruption. It is therefore necessary to regulate the overall system of public procurement,
which, along with the conclusion of public contracts for products, works and services, includes
concession contracts and public-private partnerships. By amending the legislative framework of
public procurement, stricter rules and conditions for the participation of economic operators at
competition tender procedures will apply if they are in any way (in terms of interests,
ownership or family relations) connected with the contracting authority. In addition, the
provisions on the nullity of public contracts will be amended if the conclusion of such contracts
is a consequence of corruption by the tenderer or the responsible person in the tenderer.
Transparent procedures contribute to reducing corruption risks.
2. Strengthening the control mechanisms
Further strengthening of the control mechanisms will proceed in the domain of supervision and
control. An anti-corruption body, which provides assistance to the system of public
procurement through its visible work.
3. Co-operation with other control bodies
This is with the aim of better co-ordination and joint activity of internal and external institutions
of control and audit, and to avoid any overlapping of competencies.
4. Training concerning anti-corruption and ethics
Methods and conditions of training in the public procurement system, along with other
educational programmes for the system of preventing corruption in public procurement should
be encouraged. This should include both basic and advanced knowledge of the professional
integrity of all those involved in public procurement activities. The programme to include
education of officials who work on public procurement in state, local and regional self-
government units , and other persons involved in the procedures. The course should serve to
acquire basic and advanced knowledge about the harmfulness of corruption, its appearance,
recognition, risks, prevention and criminal prosecution of the perpetrators.
5. Raising awareness of the importance of preventing corruption in the system of public
procurement
28 6.0 Public Procurement Act Of Kenya And The Effects Of Bureaucracy | Procurement Systems in
Building Works
[Construction Contract Administration] January 15, 2010
Activities aimed at raising public awareness of the importance of public procurement and the
risks of corruption to be organised both independently and in co-operation with civil society
organisations through campaigns, round tables and conferences, brochures, clips and posters,
etc.
6. Encouraging the use of e-procurement
The use of new ICTs in all segments of public administration and the openness of access to
information, in accordance with the legislation in the field of the protection of the secrecy of
data and other regulations relating to the accessibility of data, may have a major role in
preventing corruption through better transparency of the procedures of the authorities and
economic operators involved in the processes of building and procuring new values.
7. Establishment of central public procurement bodies
By providing advisory and consulting services and implementing pilot projects, efforts are made
to encourage the establishment of central public procurement bodies with a view to achieving
financial savings by reducing costs and the number of staff conducting public procurement
procedures, and the risks of corruption.
i. Corruption
Corrupt practices are clearly evident in the procurement process. These practices permeate the
systems and occur at every level. Confidential interviews with small enterprises indicate that in
some instances it is the only way they are able to participate in the process. Officials all give the
impression that their procurement processes are above board, yet meetings with suppliers
waiting in corridors outside the offices give a totally different perspective. These enterprises
often indicate that this is the cost of doing business with public entities, and the amounts they
pay are all factored into their quotations.
the next quarter to receive government funds to pay the supplier), corruption, staff absences,
and poor work ethics all contribute to delays in payment. Contractors/Suppliers tend to factor
in these delays in their quotations and raise their prices as a result. Given the bureaucracy
attached to payments, authorisation takes long. Most suppliers are not aware of the penalty
provision. Even those suppliers who know of the provision do not try to enforce it. They feel
that it would prejudice future business with the entity.
v. Poor planning
Despite being required by the PPDA, very little procurement planning seems to take place in
public entities. This is particularly evident at provincial, district and local authority levels. It
should be noted, however, that in many instances this is not the fault of the PO. POs rely on the
various departments or ministries for their procurement plans and often do not receive them.
In instances where they do receive them, procurement often does not take place as laid out in
the plan, but rather occurs on an ad hoc basis. The resulting multiple small volume
procurement not only significantly adds to the cost of goods, works and services, but also puts
tremendous strain on the procurement and financial bureaucracy. Overall this results in high
acquisition costs in both price and effort.
30 6.0 Public Procurement Act Of Kenya And The Effects Of Bureaucracy | Procurement Systems in
Building Works
[Construction Contract Administration] January 15, 2010
Corruption can occur at different points of the government hierarchy and have varying effects.
b. Corruption
c. Inefficiencies
e. Improves accountability
f. Fairness is exercised
31 6.0 Public Procurement Act Of Kenya And The Effects Of Bureaucracy | Procurement Systems in
Building Works
[Construction Contract Administration] January 15, 2010
7.0 CONCLUSION
The use of the various project procurement systems shows that the construction industry is
now trying to meet the clients’ needs. This is because the different procurement method will
have different effect on the cost, time and quality of the project. Each project procurement
system has its own peculiarity in term of the pre-tender and post tender activities and
processes, division of risks between client and contractors, and the effectiveness of project
monitoring and control.
It is very important at the very outset of the project to carefully consider all factors when
selecting the most appropriate procurement approach for a construction project. This is
because each system has its own feature and peculiarity that will have effect on the cost, time
and quality of the project i.e. the project performance.
8.0 REFERENCES
1. Akintoye, A and Fitzgerald E (1995) – Design and Build: A Survey of Architects’ Views, Engineering, Construction
and Architectural management
2. Ashworth A (2001) Contractual Procedures in the Construction Industry, UNITEC, New Zealand
3. Chitkara K K (2005): Project Management - Planning, Scheduling and Controlling – Tata McGraw Hill, New Delhi
5. Lam, E W M, Albert P C and Chan D W M (2003) Is Design and Build the Preferred Option to Procure all Projects?
Research Fellow, Department of Building and Real estate, The Hong Kong Polytechnic University
8. Rowlinson, S (1987) Design and Build – Its development and Present Status, Ascot – CIOB
9. Songer A D and Molenaar K R (1996) : Selecting Design and Build – Public and Private Sector Owner Attitudess,
Journal of Management in Engineering, ASCE.
rd
10. The Aqua Group (2001) Tenders and Contract for Building- 3 . Edition Blackwell Science, London