Вы находитесь на странице: 1из 4

DATA SHEET FOR HDPE PIPES (As per SSR - 2003-04 )

Providing pipe line for water supply with HDPE pipes as per IS 4984/1995 with its
ammedments and revisions thereon with supplyof pipes and trench excavation for earth
work excavation in all types of soils except hard rock which required partial blasting and
depositing on bank with initial lead of 10 mts and lift of 2mts laying of pipes carefully into
trench and laying in alingment and gradient jointing the pipeline with materials including
refilling the trench with excavated soils removal of surplus earth from the soil testing the
pipeline to hydraulic field test pressure including TOT charges but excluding CED, APGST
charges on pipes complete for finished item of work. (Trench size is 0.30x0.50 for 25mm
dia pipe,)

( HDPE - PE 63 grade)
E/W/E Rate - (9b+12b+13b)/3 = (27.00+29.00+30.00) / 3 = 28.67/1 cum

Description of Item 20mm dia


10Kg/ CM2

Cost of Materials
A Cost of pipes including all taxes 11.14

Cost of Civil work 4.30


B Normal rate
5.16
C 120% - 75% extra for narrow foundation

D Lowering laying and jointing of pipes 1.40

E Refilling charges at 6.40/Cum 0.96

F Testing charges 0.60

Total 23.56
DETAILED SUB ESTIMATE FOR CONSTRUCTION OF 2500 Ltrs GLSR
AT PS GOVIDPET (V) ARMOOR (M)
Sl. Description of work No L B D Qty Rate Per Amt.
No.
1 2 3 4 5 6 7 8 9 10
1 Earth work excavation and depositing on bank with intial
lead and lift in all soils including labour charges complete
for Pedastal
For Foundation 1Xll/4 2.00 2.00 0.90 2.83
For plat form 1Xll 2.80 1.20 0.15 1.58
4.41 Cum 46.50 1 Cum 205.00
VPNo.1&13 of MB No.143/2003/B
2 CC (1:5:10) mix using 40mm HBG MC metal including
cost and conveyance of all mateirals and labour charges
etc., complete for Foundation.
For Foundation 1Xll/4 2.00 2.00 0.30 0.94
For plat form 1Xll 2.80 1.20 0.15 1.58
2.52 Cum 1162.70 1 Cum 2935.31
VPNo.4&16 of MB No.143/2003/B
3 RR masonary in CM (1:6) prop using 2nd sort HG stone
inlcuding all material and labour charges etc., complete

For below GL 1Xll/4 1.80 1.80 0.60 1.53 Cum 1086.90 1 Cum 1658.65
VPNo.4 of MB No.143/2003/B

4 CRS masonary in CM (1:6) prop using 2nd sort HG stone


inlcuding all material and labour charges etc., complete
For Above GL 1Xll/4 1.60 1.60 0.60 1.21
VPNo.4 of MB No.143/2003/B 1.21 Cum 1201.10 1 Cum 1448.24

5 CC (1:2:4) mix using 20mm Machine crushed granite


metal including cost and conveyance of all materials and
labour charges etc ., complete
For in side GLSR 1Xll/4 1.60 1.60 0.10 0.20
For Curb wall 1Xll 2.70 0.10 0.10 0.08
VPNo.4&16 of MB No.143/2003/B 0.29 Cum 2606.00 1 Cum 744.64
6 RCC (1:1 1/2:3) mix using 20mm Machine crushed granite
metal including cost and conveyance of all materials and
labour charges etc ., complete

For in bottom slab 1Xll/4 1.60 1.60 0.10 0.20 Cum 2870.00 1 Cum 576.76
VPNo.10of MB No.143/2003/B

7 RCC (1:1 1/2:3) mix using 20mm Machine crushed granite


metal including cost and conveyance of all materials and
labour charges etc ., complete

For side walls 1Xll 1.30 0.10 1.75 0.71


For inside huanches 1Xll/2 1.05 0.15 0.15 0.04
0.75 Cum 9064.00 1 Cum 6811.06
VPNo.10of MB No.143/2003/B
8 Plastering in CM (1:3) 20mm thick with Accoproof powder
including cost and conveyance of all materials labour
charges etc., complete for inside and out side Tank
alround.
For plat form 1Xll 2.60 1.00 0.00 8.16
8.16 Sqm 850.06 10 Sqm 693.99
VPNo.16of MB No.143/2003/B
9 Pointing to CRS masonary in CM (1:6) cost and
conveyance of all materials labour charges etc., complete

For Basement 1xII 1.60 0.00 0.60 3.01


3.01 Sqm 316.01 10 Sqm 95.26
VPNo.16of MB No.143/2003/B
10 Cost of pre casted SGS Roof slab of 1.20m dia 0.05m
thick including all charges etc complete

1.00 No 300.00 1 Each 300.00


VPNo.17of MB No.143/2003/B
11 Add cost of steel and fabrication charges 64.31 Kgs 23.5 1 Kg 1511.29
VPNo.17of MB No.143/2003/B
Total : 16980.19
DATA SHEET AS PER 2003-2004 SSR

Sl. Description of items Rate Per Amount


No. Quantity
1 2 3 4 5 6
1 10.00 sqm Plastering with CM (1:3) 20mm thick including cost and coveyance
of all material and labour charges etc., complete for finished item
of work.
0.21 cum Cost of sand 208.20 1.00 Cum 43.72
2.20 nos Mason 1st Class30% / 70 % and 2nd class 129.70 1.00 Each 285.34
1.75 nos Man mazdoor 94.00 1.00 Each 164.50
1.75 nos Women mazdoor 94.00 1.00 Each 164.50
0.080 MT Cost of cement 2400.00 1.00 MT 192.00
Add sundries
TOTAL 850.06

2 10.00 sqm Pointing to CRS masonary in CM (1:6) including cost and


coveyance of all material and labour charges etc., complete for
finished item of work.
0.06 cum Cost of sand 208.20 1.00 Cum 12.49
0.48 nos Mason 1st Class 143.00 1.00 Each 68.64
0.12 nos Mason 2nd class 124.00 1.00 Each 14.88
0.50 nos Man mazdoor 94.00 1.00 Each 47.00
1.10 nos Women mazdoor 94.00 1.00 Each 103.40
0.029 MT Cost of cement 2400.00 1.00 MT 69.60
Add sundries
TOTAL 316.01
LEAD STATEMENT AS PER 2003-2004 SSR
Add mixing Add machine
Sl.N Place of Availability of Lead in Conveyance Initial cost of Add blasting Deduct stacking Add S/
Name of the Material Unit chargescharg crushing Total
o. Material kM charges Material charges charges charges
es charges
1 2 3 4 5 6 7 8 9 10 11

1 Sand for mortar 1 Cum vaagu 8 95.80 68.00 0.00 3.60 18.00 0.00 30.00 208.20

*NOTE* 1) The above quaries are nearer to site to the best of my knowledge.
2) The above leads are correct to the best of my knowledge.
3) The quaries requires full blasting.

AE/AEE
RWS Mandal ______________________

Вам также может понравиться