Академический Документы
Профессиональный Документы
Культура Документы
2 VARIATION ON CONTRACT :
2.1 Addition as per V.O. No. RM 102,486.00
2.2 Omission as per V.O. No. RM 0.00
11 LESS: GST for materials purchased on behalf (current month) (RM 112,789.40)
In Words : Ringgit Malaysia Negetive Two Million Fifty Five Thousand One
Hundred Forty Nine And Nineteen Cents Only
PROJECT NAME: PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR APPENDIX I
1MDB REAL ESTATE SDN BHD
Less: Tax invoices ( debited amount per MDL) (3,536,916.43) (5,420,130.91) (1,883,214.48)
GST @ 6% ( per MDL ) (211,979.54) (324,768.94) (112,789.40)
D (3,748,895.97) (5,744,899.85) (1,996,003.88)
Original Contract
Sub-Total B 102,486.00 - - - -
C Variation Order
a) VO No. 1 POURING OF CONCRETE G20 TO EXISTING OVERBURDEN SOIL & 235,962.34 213,935.76 - 213,935.76
FRACTURED ROCK AT IMBI LINK TUNNEL
b) VO No. 2 PPU2 and 1 2,926,225.33 2,912,167.66 - 2,912,167.66 w/o additional rm60/m3
c) V.O No. 3 Extended slab 9,197.29 9,197.30 - 9,197.30 on conc
d) V.O No. 4 staircase 14 830,193.96 617,896.37 - 617,896.37
E Reimbursement Cost
i) Reimbursement Cost for Rebar 775,404.68 - 775,404.68
ii) Reimbursement Cost for Concrete (113,003.50) - (113,003.50)
F Adjustment
i) Adjustment Rate Yet To Capture By Finance -
Sub-Total E - - - - -
REMARKS:
Workdone as off March 2015
Retention sum as off March 2015
PROJECT TITLE : PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE
SDN BHD
3,186,057.53 3,399,403.71
A1 PRELIMINARIES LS
RAFT BASEMENT Panel 1 to 5
IN-SITU CONCRETE
Reinforced vibrated quality control concrete:-
Grade 15:-
B blinding beneath raft slab; 50mm thick m3 250.00 228.50 57,125.00 55.00 228.50 12,567.50 55.00 - 55.00 12,567.50 Section 13 (new) and imbi
link(previous).
PLAIN INSITU CONCRETE
BQ/7of 42
PROJECT TITLE : PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD
Soffits of slabs
N Strutting height not exceeding 3.50m m2 31,376.00 22.00 690,272.00 831.51 22.00 18,293.22 831.51 - 831.51 18,293.22
Faces of walls
O Vertical (imbi) m2 30,179.70 22.00 663,953.40 1,005.88 38.00 38,223.44 1,075.47 - 1,075.47 23,660.34
Vertical (section 13) m2 22.00 - 235.92 38.00 8,964.96 235.92 - 235.92 5,190.24
BQ/8of 42
PROJECT TITLE : PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD
BQ/9of 42
PROJECT TITLE : PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD
In walls
G 600mm wide m 428.70 55.00 23,578.50 80.00 55.00 4,400.00 80.00 - 80.00 4,400.00 Section 13, Ch120-CH80
H 800mm wide m 1,594.80 55.00 87,714.00 336.72 55.00 18,519.60 336.72 - 336.72 18,519.60
J 700mm wide m 175.80 55.00 9,669.00 - - -
K 500mm wide m 54.60 55.00 3,003.00 - - -
L 750mm wide m 114.60 55.00 6,303.00 - - -
M 900mm wide m 294.90 55.00 16,219.50 - - -
Construction joint:-
U Approved PVC waterstop; 330mm wide cast to concrete m 940.80 58.00 54,566.40 180.55 58.00 10,471.90 180.55 - 180.55 10,471.90
V Sika inject hose m 98.70 35.70 3,523.59 - - -
BQ/10of 42
PROJECT TITLE : PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD
VO 1
IN-SITU CONCRETE
Formwork
B Use and waste of sawn formwork:-
SUB-CON
ITEM DESCRIPTION UNIT PROGRESS WORKDONE PPU 1 For extra Rm60/m3 PROGRESS WORKDONE PPU 2 For extra Rm60/m3
SUBMISSION REMARKS
LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM) QTY LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM)
PPU 1
PPU RAFT SLAB
A Preliminaries LS 0.50 - 0.50 100,000.00 50,000.00 - - - - - - 50% as on claim 4
i) Workers accommodation
ii) Small Tools
iii) Mobilisation
iv) Site Staff
v) Safety PPE
BILL 3
1.0 WORK BELOW LOWEST FLOOR FINISH (Grd)
REINFORCED INSITU CONCRETE
A laid on 50mm thick lean concrete. m2 - - - 208.81 208.81 - 208.81 4.00 835.24 GL-17
B exceeding 300mm thick m3 98.18 - 98.18 307.05 30,146.17 21.00 21.00 - 21.00 307.05 6,448.05 grd floor only (ppu2)
D1 450mm thck m3 56.00 56.00 - 56.00 307.05 17,194.80 concrete casting record
Lift pit walls
E 150mm -300mm thick m3
Plinth
F 650mm thick m2
G 300mm thick m2 13.10 - 13.10 307.05 4,022.36 - 307.05 -
Floor beams
H 10mm diameter; links, stirrups, binders and the like kg 5,545.26 - 5,545.26 2.45 13,585.89 553.60 553.60 - 553.60 2.45 1,356.32 grd floor only (ppu2)
J 12mm diameter; links, stirrups, binders and the like kg 467.78 - 467.78 2.45 1,146.06 - 2.45 -
12 of 42
PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD VO 2
PROJECT TITLE :
SUB-CON
ITEM DESCRIPTION UNIT PROGRESS WORKDONE PPU 1 For extra Rm60/m3 PROGRESS WORKDONE PPU 2 For extra Rm60/m3
SUBMISSION REMARKS
LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM) QTY LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM)
Sub Total Brought Forward 176,449.02 44,622.80
A 12mm diameter; straight and bent kg 236.33 - 236.33 2.45 579.01 3.13 3.13 - 3.13 2.45 7.67
B 16mm diameter; straight and bent kg 3,442.22 - 3,442.22 2.45 8,433.44 461.33 461.33 - 461.33 2.45 1,130.26
C 20mm diameter; straight and bent kg 3,051.11 - 3,051.11 2.45 7,475.22 1,035.34 1,035.34 - 1,035.34 2.45 2,536.58
D 25mm diameter; straight and bent kg 10,711.21 - 10,711.21 2.45 26,242.46 23.78 23.78 - 23.78 2.45 58.26
Plinth
K 16mm diameter; straight and bent kg 1,335.02 - 1,335.02 2.45 3,270.80 - 2.45 -
Formwork
BILL 3
2 BASEMENT SLAB & BASEMENT STRUCTURE (BASEMENT 1)
13 of 42
PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD VO 2
PROJECT TITLE :
SUB-CON
ITEM DESCRIPTION UNIT PROGRESS WORKDONE PPU 1 For extra Rm60/m3 PROGRESS WORKDONE PPU 2 For extra Rm60/m3
SUBMISSION REMARKS
LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM) QTY LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM)
Sub Total Brought Forward 409,186.21 100,849.69
In-situ concrete
Reinforced vibrated quality control concrete grade 15
Pile cap m2 0.94 0.94 - 0.94 228.50 214.79 PPU2 only
REINFORCED INSITU CONCRETE
Lift walls
E 150mm -300mm thick m3 13.13 - 13.13 312.05 4,097.22 - 312.05 -
Shear walls
10mm diameter; links, stirrups, binders and the like kg 1,341.96 - 1,341.96 2.45 3,287.80 - 2.45 -
Floor beams
10mm diameter; links, stirrups, binders and the like kg 1,468.77 - 1,468.77 2.45 3,598.49 553.60 553.60 - 553.60 2.45 1,356.32
12mm diameter; links, stirrups, binders and the like kg - - - 2.45 - - 2.45 -
14 of 42
PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD VO 2
PROJECT TITLE :
SUB-CON
ITEM DESCRIPTION UNIT PROGRESS WORKDONE PPU 1 For extra Rm60/m3 PROGRESS WORKDONE PPU 2 For extra Rm60/m3
SUBMISSION REMARKS
LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM) QTY LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM)
Sub Total Brought Forward - 562,192.15 - 135,837.73
Lift walls
10mm diameter; straight and bent kg 473.60 - 473.60 2.45 1,160.32 - 2.45 -
20mm diameter; straight and bent kg 1,015.00 - 1,015.00 2.45 2,486.75 - 2.45 - -Rate Tunnel
Floor beams
12mm diameter; straight and bent kg 7.14 - 7.14 2.45 17.49 3.13 3.13 - 3.13 2.45 7.67
16mm diameter; straight and bent kg 2,406.79 - 2,406.79 2.45 5,896.64 461.33 461.33 - 461.33 2.45 1,130.26
20mm diameter; straight and bent kg 920.51 - 920.51 2.45 2,255.25 1,035.34 1,035.34 - 1,035.34 2.45 2,536.58
25mm diameter; straight and bent kg 1,321.38 - 1,321.38 2.45 3,237.38 23.78 23.78 - 23.78 2.45 58.26
RC plinth at basement 2
16mm diameter, straight and bent kg 724.08 - 724.08 2.45 1,774.00 - 2.45 - as instructed by Edy
Pilecap
16mm diame6ter, straight and bend kg 5,804.47 5,804.47 - 5,804.47 2.45 14,220.95 new
Shear walls
Retaining walls
20mm diameter; straight and bent kg 994.19 994.19 - 994.19 2.45 2,435.77 (PPU2) basement
12mm diameter; straight and bent kg 63.94 63.94 - 63.94 2.45 156.65 (PPU2) basement
15 of 42
PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD VO 2
PROJECT TITLE :
SUB-CON
ITEM DESCRIPTION UNIT PROGRESS WORKDONE PPU 1 For extra Rm60/m3 PROGRESS WORKDONE PPU 2 For extra Rm60/m3
SUBMISSION REMARKS
LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM) QTY LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM)
Sub Total Brought Forward - 764,257.28 - 162,548.80
rectangular; 200mm wide x 150mm depth m2 140.58 - 140.58 28.80 4,048.70 - 28.80 -
strutting height 3.50 - 5.00m m2 310.63 - 310.63 38.00 11,803.94 230.70 230.70 - 230.70 38.00 8,766.60
new strutting height 5.00 - 6.50m m2 476.16 - 476.16 46.00 21,903.36 - 38.00 -
new Formwork to edge/ side of slab, 200mm m 3.00 - 3.00 38.00 114.00 - 38.00 -
16 of 42
PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD VO 2
PROJECT TITLE :
SUB-CON
ITEM DESCRIPTION UNIT PROGRESS WORKDONE PPU 1 For extra Rm60/m3 PROGRESS WORKDONE PPU 2 For extra Rm60/m3
SUBMISSION REMARKS
LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM) QTY LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM)
Sub Total Brought Forward - 975,683.21 - 178,351.94
3 FRAME
Isolated columns
B 150mm -300mm thick m3 435.05 - 435.05 283.00 123,119.15 19.47 19.47 - 19.47 283.00 5,510.01 Tunnel Rate
Isolated columns kg
D 10mm diameter; links,stirrups, binders and the like kg 20,248.80 - 20,248.80 2.45 49,609.56 1,123.59 1,123.59 - 1,123.59 2.45 2,752.80
Shear walls
E 10mm diameter; links,stirrups, binders and the like Kg 7,243.15 - 7,243.15 2.45 17,745.72
Isolated columns
F 12mm diameter; straight and bent kg 483.11 483.11 - 483.11 2.45 1,183.62
G 16mm diameter; straight and bent kg 7,286.99 - 7,286.99 2.45 17,853.13 361.92 361.92 - 361.92 2.45 886.70
H 20mm diameter; straight and bent Kg 5,193.94 - 5,193.94 2.45 12,725.15 692.76 692.76 - 692.76 2.45 1,697.26
I 25mm diameter; straight and bent Kg 49,361.84 - 49,361.84 2.45 120,936.51 2,392.86 2,392.86 - 2,392.86 2.45 5,862.51
Lift walls
J 10mm diameter; straight and bent kg 2,160.00 - 2,160.00 2.45 5,292.00 - 2.45 -
L 20mm diameter; straight and bent kg 4,406.60 - 4,406.60 2.45 10,796.17 - 2.45 -
Shear walls
M 12mm diameter; straight and bent kg 63.94 63.94 63.94 2.45 156.65
N 20mm diameter; straight and bent kg 32,489.82 - 32,489.82 2.45 79,600.06 9,994.19 994.19 994.19 2.45 2,435.77
O 16mm diameter; straight and bent kg 649.77 - 649.77 2.45 1,591.94 - 2.45 -
17 of 42
PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD VO 2
PROJECT TITLE :
SUB-CON
ITEM DESCRIPTION UNIT PROGRESS WORKDONE PPU 1 For extra Rm60/m3 PROGRESS WORKDONE PPU 2 For extra Rm60/m3
SUBMISSION REMARKS
LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM) QTY LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM)
Sub Total Brought Forward - 1,473,875.59 - 200,026.81
Formwork
4 UPPER FLOORS
REINFORCED INSITU CONCRETE
Concrete grade C35
Floor beams
A exceeding 300mm thick m3 247.22 - 247.22 307.05 75,908.90 16.47 16.47 - 16.47 307.05 5,057.11 Tunnel Rate
Additional rate Rm60/m3 for coming Jan18 onward m3 7.83 7.83 60.00 469.80
Surface treatment
Floor beams
D 10mm diameter; links,stirrups, binders and the like kg 8,071.41 - 8,071.41 2.45 19,774.95 338.17 338.17 - 338.17 2.45 828.52 -Tunnel Rate
E 12mm diameter; links,stirrups, binders and the like kg 310.59 - 310.59 2.45 760.95 - 2.45 - -Tunnel Rate
Floor beams
F 12mm diameter; straight and bent kg 273.47 - 273.47 2.45 670.00 8.61 8.61 - 8.61 2.45 21.09 -Tunnel Rate
G 16mm diameter; straight and bent kg 6,486.39 - 6,486.39 2.45 15,891.66 388.12 388.12 - 388.12 2.45 950.89
H 20mm diameter; straight and bent kg 5,998.22 - 5,998.22 2.45 14,695.64 2,630.58 2,630.58 - 2,630.58 2.45 6,444.92
I 25mm diameter; straight and bent kg 15,409.46 - 15,409.46 2.45 37,753.18 3,651.59 3,651.59 - 3,651.59 2.45 8,946.40
J 12mm diameter ; straight and bent kg 22,331.99 - 22,331.99 2.45 54,713.38 - - 2.45 - -Tunnel Rate
new 10mm diameter ; straight and bent kg 16,868.61 - 16,868.61 2.45 41,328.09 5,501.25 5,501.25 - 5,501.25 2.45 13,478.06
18 of 42
PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD VO 2
PROJECT TITLE :
SUB-CON
ITEM DESCRIPTION UNIT PROGRESS WORKDONE PPU 1 For extra Rm60/m3 PROGRESS WORKDONE PPU 2 For extra Rm60/m3
SUBMISSION REMARKS
LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM) QTY LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM)
Sub Total Brought Forward - 1,984,477.83 - 257,238.71
Formwork
K Sides and soffits of floor beams no exceeding 3.5m m2 - - - 38.00 - 156.79 156.79 - 156.79 38.00 5,958.02 -Tunnel Rate
amend rate RM38/m2
strutting height (3.50m -5.00m) m2 405.18 - 405.18 38.00 15,396.84 - 38.00 -
strutting height (6.50m -8.00m) (FL 48) m2 960.11 - 960.11 38.00 36,484.18 - 38.00 -
strutting height not exceeding (9.5m-11m)(FL50.10) m2 258.74 - 258.74 38.00 9,832.12 - 38.00 -
Formwork
side of parapet wall
C vertical m2 407.97 - 407.97 38.00 15,502.86
Waterstop
D Supercast SW20 swellable system; 250mm wide to concrete m 171.52 - 171.52 32.00 5,488.64
5 ROOF STRUCTURE
Roof beams
a generally m3 79.31 - 79.31 307.05 24,352.14
Additional rate Rm60/m3 for coming Jan18 onward m3 41.12 - 41.12 60.00 2,467.20 -
Roof beams
c 10mm diameter; links,stirrups, binders and the like kg 3,909.94 - 3,909.94 2.45 9,579.35
d 12mm diameter; links,stirrups, binders and the like kg - - - 2.45 -
Roof beams kg
19 of 42
PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD VO 2
PROJECT TITLE :
SUB-CON
ITEM DESCRIPTION UNIT PROGRESS WORKDONE PPU 1 For extra Rm60/m3 PROGRESS WORKDONE PPU 2 For extra Rm60/m3
SUBMISSION REMARKS
LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM) QTY LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM)
Sub Total Brought Forward - 2,358,534.01 - 270,670.19
Formwork
7 STAIR STRUCTURE
Landing beams m3
B 150mm - 300mm thick m3 4.37 - 4.37 283.00 1,236.71 0.19 0.19 - 0.19 283.00 53.77
Additional rate Rm60/m3 for coming Jan18 onward m3 1.25 - 1.25 60.00 75.00 0.19 0.19 60.00 11.40
Staircase, strings and steps
C 150-300mm thick m3 17.07 - 17.07 283.00 4,830.81 1.15 1.15 - 1.15 283.00 325.45
Additional rate Rm60/m3 for coming Jan18 onward m3 4.88 - 4.88 60.00 292.80 1.15 1.15 60.00 69.00
Landing beams
D 10mm diameter; straight and bent kg 74.51 - 74.51 2.45 182.55 - 2.45 -
16mm diameter; straight and bent kg 45.32 - 45.32 2.45 111.03 - 2.45 -
20mm diameter; straight and bent kg 70.77 - 70.77 2.45 173.39 - 2.45 -
G 16mm diameter; straight and bent kg 3,478.36 - 3,478.36 2.45 8,521.98 - 2.45 -
new 12mm diameter; straight and bent kg 55.04 - 55.04 2.45 134.85 198.51 198.51 - 198.51 2.45 486.35
Formwork
20 of 42
PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD VO 2
PROJECT TITLE :
SUB-CON
ITEM DESCRIPTION UNIT PROGRESS WORKDONE PPU 1 For extra Rm60/m3 PROGRESS WORKDONE PPU 2 For extra Rm60/m3
SUBMISSION REMARKS
LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM) QTY LAST QTY THIS QTY TOTAL QTY RATE (RM) AMOUNT (RM) AMOUNT (RM)
Sub Total Brought Forward - 2,467,527.41 - 271,535.76
Formwork
Soffits of staircases
J strutting height 3.00 - 4.50m m2 62.58 - 62.58 38.00 2,378.04 6.56 6.56 - 6.56 42.00 275.52
38.00 -
Edges of suspended landing slabs
K 150mm high m2 1.20 - 1.20 38.00 45.60 3.28 3.28 - 3.28 42.00 137.76
Risers
L 175mm high m2 201.60 - 201.60 11.03 2,223.65 21.20 21.20 - 21.20 11.03 233.84
Edges of staircases
M maximum width 200mm m2 55.94 - 55.94 38.00 2,125.72 10.61 10.61 - 10.61 12.60 133.69
Floor hardener;Internally
Labour on unset concrete
Surface treatment Archi work
C Power float; including non-metallic floor hardener; m2 695.33 - 695.33 18.00 12,515.94 627.00 627.00 - 627.00 18.00 11,286.00 B1=531.725
applied at the rate of 6kg/m2 Grd=163.5
PPU 2
B1=531.725
Grd=163.6
21 of 42
PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB
PROJECT TITLE : REAL ESTATE SDN BHD VO 3
SUB-CONTRACTOR : KIAN BUN ENTERPRISE SDN. BHD. PROGRESS PAYMENT NO. : 14
PERIOD ENDING : April 2018
SUB-CONTRACT WORK: Reinforce concrete works at IMBI Link Tunel DATE : 8/6/2018
ADDITION
REINFORCED INSITU CONCRETE
Concrete grade C35
Floor beams
1 Generally m3 1.25 312.05 390.06 1.25 - 1.25 312.05 390.06
Suspended floor slabs
2 150mm -300mm thick m3 5.69 312.05 1,775.56 5.69 - 5.69 312.05 1,775.56
Formwork
Sides and soffit of floor beams
1 strutting height <3.50m m2 3.80 38.00 144.40 3.80 - 3.80 38.00 144.40
2 strutting height 3.50m-5.00m m2 6.52 38.00 247.76 6.52 - 6.52 38.00 247.76
Addition
Reinforced insitu concete
Insitu concete
Reinforced vibrated quality control concrete grd 15
1.00 To base slab m3 1.70 228.50 388.45 Rate reffer to V.O 2
Addition rm60/m3 to all concrete m3
2.00 To ground beam m3 1.58 228.50 361.03 casting record 3.5m3
3.00 Rc wall
600mm thick m3 143.30 312.05 44,716.77
Addition rm60/m3 to all concrete m3
Reinforcement
(A) Base slab
Mild steel bar reinforcement
1.00 10mm dia.: link stirrups, binder and the like kg - 2.45 -
Rc Ground beam
(B) Mild steel bar reinforcement
1.00 10mm dia, link stirups binder and the like kg 717.06 2.45 1,756.80
Rc wall
c) Mild steel bar reinforcement
1.00 10mm dia, link stirups binder and the like kg - 2.45 -
Formwork
1.00 Side of ground slab m2 -
a side of ground slab m2 12.35 38 469.30
3.00
a structting height <3.5m m2 - 38 -
b structting height 3.5m-5.0m m2 477.65 42 20,061.30
Waterstop
(A) Design water stop joint; PVC Joint sure-stop CJ-958 or approved
approved equivalent; embedded in concrete; including specail
purpose made or specail angles, intersection and connectors;
measure net-no allowance made for laps
In walls
a) 600mm wide m 39.86 55 2,192.30
Base Slab
A To existing well m 9.65 95.00 916.75
New Wall
B To Existing Wall m 10.00 95.00 950.00
2.00 Rc wall
600mm thick m3 193.09 312.05 60,253.73 193.09 - 193.09 312.05 60,253.73
Rc Ground wall
(B) Mild steel bar reinforcement
1.00 10mm dia, link stirups binder and the like kg - -
Formwork
1.00 Side of ground slab (raft slab) m2 29.36 38.00 1,115.68 29.36 - 29.36 38.00 1,115.68
3.00 RC wall
a structting height <3.5m m2 213.14 213.14 45,428.66 213.14 - 213.14 38.00 8,099.32
b structting height 3.5m-5.0m m2 430.48 430.48 185,313.03 430.48 - 430.48 42.00 18,080.16
Suspended slab
a structting height <3.5m m2 56.38 56.38 3,178.70 56.38 - 56.38 38.00 2,142.44
b structting height 3.5m-5.0m m2 47.02 47.02 2,210.88 47.02 - 47.02 42.00 1,974.84
Risers
e 175mm high m2 26.84 42.00 1,127.28 - 26.84 26.84 83.00 2,227.72
Edge of staircase
f Maximum width 200m m2 13.29 42.00 558.18 - 13.29 13.29 38.00 505.02
Waterstop
(A) Design water stop joint; PVC Joint sure-stop CJ-958 or approved
approved equivalent; embedded in concrete; including specail
purpose made or specail angles, intersection and connectors;
measure net-no allowance made for laps
In walls
a) 600mm wide m 86.80 55.00 4,774.00 86.80 - 86.80 55.00 4,774.00
b) waterstop on top of beam- cockjoint m 33.00 55.00 1,815.00 33.00 - 33.00 55.00 1,815.00
Base Slab
A To existing well m 10.00 95.00 950.00 10.00 - 10.00 95.00 950.00
New Wall
B To Existing Wall m 7.80 95.00 741.00 29.40 - 29.40 95.00 2,793.00
new* supercast SW20 swellable system; 250mm wide cast to concrete m 20.00 32.00 640.00 - - - 32.00 - doesnot shown in dwg
MATERIAL ON SITE
as of peg.p TOTAL
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT Remarks
(RM) (RM)
Note:
1 Bundle of Rebar
40mm dia = 1.065
32mm dia = 1.061
25mm dia = 1.017
20mm dia = 1.006
16mm dia = 1.023
12mm dia = 1.023
10mm dia = 1.02
ITEM DESCRIPTION UNIT QTY RATE AMOUNT QTY RATE AMOUNT Remarks
(RM) (RM) (RM) (RM)
Add. 1
1/3/2017
1 Md Jasin Uddin day 1,959.38 26.13 75.00 1,959.38
2 Abdul Halim day 450.00 6.00 75.00 450.00
3 Abdul Razak day 1,443.75 19.25 75.00 1,443.75
4 Banda ilham sapurata day 1,443.75 19.25 75.00 1,443.75
5 Dulal day 1,293.75 17.25 75.00 1,293.75
6 day 1,293.75 Same person work as
signalman
Nour Nobi Hassan
7 day 1,293.75 17.25 75.00 1,293.75
Muhammad Kharis
8 day 712.50 9.50 75.00 712.50
Maksimus bouibae
9 Salau day 525.00 7.00 75.00 525.00
10 Mohamed Ismail day 618.75 8.25 75.00 618.75
11 Ferdi Nandas day 525.00 7.00 75.00 525.00
12 Sererinus Mbomba day 712.50 9.50 75.00 712.50
13 Budianto day 618.75 8.25 75.00 618.75
14 Alamgir Holader day 1,931.25 25.75 75.00 1,931.25
15 Md Sajahan day 1,912.50 25.50 75.00 1,912.50
16 Bablu day 1,293.75 17.25 75.00 1,293.75
18,028.13 16,734.38
1/4/2017
1 Tajul Rubel day 712.50 9.50 75.00 712.50
2 Easen day 768.75 10.25 75.00 768.75
3 Alom day 768.75 10.25 75.00 768.75
4 Badawi day 890.63 11.88 75.00 890.63
5 Rubal day 768.75 10.25 75.00 768.75
6 Sancan day 768.75 10.25 75.00 768.75
7 Johongir day 768.75 10.25 75.00 768.75
ITEM DESCRIPTION UNIT QTY RATE AMOUNT QTY RATE AMOUNT Remarks
(RM) (RM) (RM) (RM)
Signalman
1/3/2017
1 Badal day 3,300.00 44.00 75.00 3,300.00
2 Arif Hossain day 3,300.00 44.00 75.00 3,300.00
1/4/2017
1 Badal day 3,121.88 41.63 75.00 3,122.25
2 Arif Hossain day 2,568.75 34.25 75.00 2,568.75
1/5/2017
1 Badal day 3,121.88 32.13 75.00 2,409.38
2 Salau day 2,568.75 34.13 75.00 2,559.38
1/6/2017
1 Badal day 3,121.88 34.25 75.00 2,568.75
2 Salau day 2,568.75 29.75 75.00 2,231.25
ITEM DESCRIPTION UNIT QTY RATE AMOUNT QTY RATE AMOUNT Remarks
(RM) (RM) (RM) (RM)
to stricon
6 Yunus day 342.00 9.38 3,207.96 42.75 75.00 3,206.25
7 Nazrul day 342.00 9.38 3,207.96 42.75 75.00 3,206.25
8 Chao Gozi day 342.00 9.38 3,207.96 42.75 75.00 3,206.25
9 Miah day 342.00 9.38 3,207.96 42.75 75.00 3,206.25
10 Amir day 342.00 9.38 3,207.96 42.75 75.00 3,206.25
11 Alom day 270.00 9.38 2,532.60 33.75 75.00 2,531.25
12 Baidowi day 270.00 9.38 2,532.60 33.75 75.00 2,531.25
13 Hazroz Ali day 270.00 9.38 2,532.60 33.75 75.00 2,531.25
14 Md Purban day 270.00 9.38 2,532.60 33.75 75.00 2,531.25
26,625.00 26,625.00
hours per hour per day
basement 3
(bckcharget
starter bar.
o stricon ).
staircase
1 Amin day 4.00 9.38 37.52 0.50 75.00 37.50
Cut
At
2 Bidal Piah day 4.00 9.38 37.52 0.50 75.00 37.50
75.00 75.00
basement 3
(bckcharge
Dismantle
water tank
to stricon)
3 Asgar Ali day 24.00 9.38 225.12 3.00 75.00 225.00
F/W
4 Nazrul Liton day 24.00 9.38 225.12 3.00 75.00 225.00
5 Mohamad Amir day 24.00 9.38 225.12 3.00 75.00 225.00
6 Ansori Baedowi day 24.00 9.38 225.12 3.00 75.00 225.00
1,350.00 1,350.00
1 DAYWORK
5 WATER SUPPLY
6 MATERIAL
7 Foreign worker permit renew 10nos. For batch Jun17 and July 17 22,535.20 - 22,535.20 DA/KB/DDT/004/17
Page 33 of 42
PROJECT TITLE : TUN RAZAK EXCHANGE (REFERRED TO AS "TRX") PROPOSED EARTHWORKS, RETAINING WALLS AND FOUNDATION
WORKS FOR PHASE 1 OF CADANGAN PEMBANGUNAN BERCAMPUR "KUALA LUMPUR INTERNATIONAL FINANCIAL
DISTRICT" (NOW KNOWN AS "TUN RAZAK EXCHANGE") DI ATAS SEBAHAGIAN LOT 11
ITEM DESCRIPTION UNIT QTY RATE (RM) AMOUNT Remarks AMOUNT Remarks
(RM)
SAFETY DEDUCTION
1 Access card to 86 personal nos. 86 10.00 860.00 Issue on 5/7/2017 (860.00) Jan-18
3 Access card to 50 personal pcs 50 10.00 500.00 Issue on 31/10/2017 (500.00) Nov-17
\\W381-FENDI\Users\User\Documents\W391 - Contract 2\Sub-contractor's claim\Kianbun\Cert no. 14 may 18\W391 Kianbun May18-Cert 014 Page 34 of 42
PROJECT TITLE : TUN RAZAK EXCHANGE (REFERRED TO AS "TRX") PROPOSED EARTHWORKS, RETAINING WALLS AND FOUNDATION
WORKS FOR PHASE 1 OF CADANGAN PEMBANGUNAN BERCAMPUR "KUALA LUMPUR INTERNATIONAL FINANCIAL
DISTRICT" (NOW KNOWN AS "TUN RAZAK EXCHANGE") DI ATAS SEBAHAGIAN LOT 11
PROVISIONAL DEDUCTION
ITEM DESCRIPTION UNIT QTY RATE (RM) AMOUNT Remarks AMOUNT Remarks
(RM)
DIESEL DEDUCTION
1.00 July (DDT/005/17) Lt 210.00 2.03 426.30 D.A issue on 27/ july (426.30) included in tax invoice
2.00 July (DDT/006/17) Lt 415.00 2.03 842.45 D.A issue on 27/ july -
4.00 Aug(DDT/008/17) LT 262.00 1.83 479.46 D.A issue on 4/ Nov (479.46) included in tax invoice
5.00 Sept(DDT/010/17) LT 234.00 1.91 446.94 D.A issue on 4/ Nov (446.94) included in tax invoice
6.00 Jun(DDT/011/17) LT 107.00 1.73 185.11 D.A issue on 4/ Nov (185.11) included in tax invoice
\\W381-FENDI\Users\User\Documents\W391 - Contract 2\Sub-contractor's claim\Kianbun\Cert no. 14 may 18\W391 Kianbun May18-Cert 014 Page 35 of 42
PROJECT TITLE : PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD
CONCRETE
1 14/3/2017 INV259920 112.00 179.00 20,048.00 183.00 188.00 219.00 236.00 230.00 21,056.00 Apr-17
CTI-0000007759
2 15/3/2017 INV259921 144.00 179.00 25,776.00 183.00 188.00 219.00 236.00 230.00 27,072.00 Apr-17
3 18/3/2017 1013469 INV259922 4.00 174.00 179.00 696.00 183.00 188.00 219.00 236.00 230.00 732.00 Apr-17
4 21/3/2017 1013597 INV259923 9.00 179.00 1,611.00 183.00 188.00 219.00 236.00 230.00 1,692.00 Apr-17
5 21/3/2017 1013599 INV259923 9.00 179.00 1,611.00 183.00 188.00 219.00 236.00 230.00 1,692.00 Apr-17
6 21/3/2017 1013602 INV259923 10.00 179.00 1,790.00 183.00 188.00 219.00 236.00 230.00 1,880.00 Apr-17
7 21/3/2017 1096103 INV260419 10.00 179.00 1,790.00 183.00 188.00 219.00 236.00 230.00 1,880.00 Apr-17
8 21/3/2017 1096117 INV260419 8.00 179.00 1,432.00 183.00 188.00 219.00 236.00 230.00 1,504.00 Apr-17
9 21/3/2017 1096138 INV260419 10.00 179.00 1,790.00 183.00 188.00 219.00 236.00 230.00 1,880.00 Apr-17
CTI-0000007811
10 27/3/2017 1014013 INV260134 9.00 179.00 1,611.00 183.00 188.00 219.00 236.00 230.00 1,692.00 Apr-17
11 27/3/2017 1014019 INV260134 10.00 179.00 1,790.00 183.00 188.00 219.00 236.00 230.00 1,880.00 Apr-17
12 27/3/2017 1014027 INV260134 10.00 179.00 1,790.00 183.00 188.00 219.00 236.00 230.00 1,880.00 Apr-17
13 22/3/2017 1013663 INV260133 6.00 174.00 179.00 1,044.00 183.00 188.00 219.00 236.00 230.00 1,098.00 Apr-17
14 22/3/2017 App.1 INV260133 35.00 179.00 6,265.00 183.00 188.00 219.00 236.00 230.00 6,580.00 Apr-17
15 30/3/2017 App.2 INV261000 38.00 179.00 222.00 8,436.00 183.00 188.00 219.00 236.00 230.00 8,968.00 Apr-17
16 31/3/2017 App.3 INV261001 122.00 179.00 222.00 27,084.00 183.00 188.00 219.00 236.00 230.00 28,792.00 Apr-17
17 6/4/2017 1014728 INV261286 5.00 174.00 179.00 870.00 183.00 188.00 219.00 236.00 230.00 915.00 Apr-17
18 6/4/2017 1014748 INV261286 8.00 174.00 179.00 1,392.00 183.00 188.00 219.00 236.00 230.00 1,464.00 Apr-17
19 11/4/2017 1015067 INV262294 8.00 174.00 179.00 222.00 1,776.00 183.00 188.00 219.00 236.00 230.00 1,888.00 Apr-17
20 11/4/2017 1015068 INV262294 7.00 174.00 179.00 222.00 1,554.00 183.00 188.00 219.00 236.00 230.00 1,652.00 Apr-17
21 CTI-0000007937 1/4/2017 App.1 INV261282 138.00 179.00 24,702.00 183.00 188.00 219.00 236.00 230.00 25,944.00 Apr-17
22 3/4/2017 App.2 INV261283 104.00 179.00 18,616.00 183.00 188.00 219.00 236.00 230.00 19,552.00 Apr-17
23 5/4/2017 App.3 INV261285 32.00 179.00 5,728.00 183.00 188.00 219.00 236.00 230.00 6,016.00 Apr-17
24 10/4/2017 App.4 INV262293 85.00 174.00 179.00 222.00 18,870.00 183.00 188.00 219.00 236.00 230.00 20,060.00 Apr-17
25 4/4/2017 App.5 INV261284 152.00 179.00 27,208.00 183.00 188.00 219.00 236.00 230.00 28,576.00 Apr-17
6.00
DEBIT NOTE FOR APRIL 2017 23.00 802.00 - 266.00 -
1 CTI-0000008014 1015289 7.00 174.00 179.00 222.00 1,554.00 183.00 188.00 219.00 236.00 230.00 1,652.00 May-17
2 CTI-0000008014 1015291 4.00 174.00 179.00 222.00 888.00 183.00 188.00 219.00 236.00 230.00 944.00 May-17
3 CTI-0000008131 1016264 10.00 174.00 179.00 222.00 2,220.00 183.00 188.00 219.00 236.00 230.00 2,360.00 May-17
4 CTI-0000008131 1016273 8.00 174.00 179.00 222.00 1,776.00 183.00 188.00 219.00 236.00 230.00 1,888.00 May-17
5 CTI-0000008131 21/4/2017 Appendix 1 72.00 174.00 179.00 222.00 15,984.00 183.00 188.00 219.00 236.00 230.00 16,992.00 May-17
6 CTI-0000008131 22/4/2017 Appendix 2 66.00 174.00 179.00 222.00 14,652.00 183.00 188.00 219.00 236.00 230.00 15,576.00 May-17
7 CTI-0000008166 14/4/2017 Appendix 1 168.00 174.00 179.00 222.00 37,296.00 183.00 188.00 219.00 236.00 230.00 39,648.00 May-17
8 CTI-0000008291 1016826 10.00 174.00 179.00 222.00 2,220.00 183.00 188.00 219.00 236.00 230.00 2,360.00 May-17
9 CTI-0000008291 1016827 8.00 174.00 179.00 222.00 1,776.00 183.00 188.00 219.00 236.00 230.00 1,888.00 May-17
10 CTI-0000008291 1016828 1.00 174.00 179.00 222.00 222.00 183.00 188.00 219.00 236.00 230.00 236.00 May-17
11 CTI-0000008291 1101628 10.00 174.00 179.00 222.00 2,220.00 183.00 188.00 219.00 236.00 230.00 2,360.00 May-17
12 CTI-0000008291 1016920 10.00 174.00 179.00 222.00 2,220.00 183.00 188.00 219.00 236.00 230.00 2,360.00 May-17
13 CTI-0000008291 1016961 10.00 174.00 179.00 222.00 2,220.00 183.00 188.00 219.00 236.00 230.00 2,360.00 May-17
14 CTI-0000008291 1/5/2017 Appendix 1 45.00 174.00 179.00 222.00 9,990.00 183.00 188.00 219.00 236.00 230.00 10,620.00 May-17
15 CTI-0000008291 5/5/2017 Appendix 2 45.00 174.00 179.00 222.00 9,990.00 183.00 188.00 219.00 236.00 230.00 10,620.00 May-17
16 CTI-0000008291 9/5/2017 Appendix 3 38.00 174.00 179.00 222.00 8,436.00 183.00 188.00 219.00 236.00 230.00 8,968.00 May-17
17 CTI-0000008291 10/5/2017 Appendix 4 58.00 174.00 179.00 222.00 12,876.00 183.00 188.00 219.00 236.00 230.00 13,688.00 May-17
DEBIT NOTE FOR MAY 2017 - - - 570.00 -
1 CTI-0000008356 1016978 INV264784 6.00 174.00 179.00 222.00 1,332.00 183.00 188.00 219.00 236.00 230.00 1,416.00 Jun-17
2 CTI-0000008356 1017273 INV265552 10.00 174.00 179.00 222.00 2,220.00 183.00 188.00 219.00 236.00 230.00 2,360.00 Jun-17
3 CTI-0000008356 15/5/2017 Appendix 1 INV265551 45.00 174.00 179.00 222.00 9,990.00 183.00 188.00 219.00 236.00 230.00 10,620.00 Jun-17
4 CTI-0000008356 18/5/2017 Appendix 2 INV265595 52.00 174.00 179.00 222.00 11,544.00 183.00 188.00 219.00 236.00 230.00 12,272.00 Jun-17
5 CTI-0000008356 19/5/2017 Appendix 3 INV265596 28.00 174.00 179.00 222.00 6,216.00 183.00 188.00 219.00 236.00 230.00 6,608.00 Jun-17
6 CTI-0000008356 20/5/2017 Appendix 4 INV265597 29.00 174.00 179.00 222.00 6,438.00 183.00 188.00 219.00 236.00 230.00 6,844.00 Jun-17
7 CTI-0000008356 20/5/2017 Appendix 4 INV265597 27.00 174.00 179.00 222.00 5,994.00 183.00 188.00 219.00 236.00 230.00 6,372.00 Jun-17
8 CTI-0000008399 1017801 INV266138 8.00 174.00 179.00 222.00 1,776.00 183.00 188.00 219.00 236.00 230.00 1,888.00 Jun-17
9 CTI-0000008399 1017811 INV266138 4.00 174.00 179.00 222.00 888.00 183.00 188.00 219.00 236.00 230.00 944.00 Jun-17
10 CTI-0000008399 1017993 INV266260 5.00 174.00 179.00 222.00 1,110.00 183.00 188.00 219.00 236.00 230.00 1,180.00 Jun-17
11 CTI-0000008399 1018073 INV266261 9.00 174.00 179.00 222.00 1,998.00 183.00 188.00 219.00 236.00 230.00 2,124.00 Jun-17
12 CTI-0000008399 1018081 INV266261 9.00 174.00 179.00 222.00 1,998.00 183.00 188.00 219.00 236.00 230.00 2,124.00 Jun-17
13 CTI-0000008399 21/5/2017 Appendix 1 INV266137 40.00 174.00 179.00 222.00 8,880.00 183.00 188.00 219.00 236.00 230.00 9,440.00 Jun-17
14 CTI-0000008399 27/5/2017 Appendix 2 INV266262 209.00 174.00 179.00 222.00 46,398.00 183.00 188.00 219.00 236.00 230.00 49,324.00 Jun-17
15 CTI-0000008547 1018483 INV266909 5.00 174.00 179.00 222.00 1,110.00 183.00 188.00 219.00 236.00 230.00 1,180.00 Jun-17
16 CTI-0000008547 1018594 INV267105 6.00 174.00 179.00 222.00 1,332.00 183.00 188.00 219.00 236.00 230.00 1,416.00 Jun-17
17 CTI-0000008547 1018723 INV267106 5.00 174.00 179.00 222.00 1,110.00 183.00 188.00 219.00 236.00 230.00 1,180.00 Jun-17
18 CTI-0000008547 1018902 INV267523 9.00 174.00 179.00 222.00 1,998.00 183.00 188.00 219.00 236.00 230.00 2,124.00 Jun-17
19 CTI-0000008547 1018912 INV267523 10.00 174.00 179.00 222.00 2,220.00 183.00 188.00 219.00 236.00 230.00 2,360.00 Jun-17
20 CTI-0000008547 1018938 INV267524 8.00 174.00 179.00 222.00 1,776.00 183.00 188.00 219.00 236.00 230.00 1,888.00 Jun-17
21 CTI-0000008547 118951 INV267524 6.00 174.00 179.00 222.00 1,332.00 183.00 188.00 219.00 236.00 230.00 1,416.00 Jun-17
CONCRETE
1 1019105 INV268402 7.00 222.00 1,554.00 183.00 188.00 219.00 236.00 230.00 1,652.00 Jul-17
2 CTI-0000008634 1019120 7.00 222.00 1,554.00 183.00 188.00 219.00 236.00 230.00 1,652.00 Jul-17
3 1019232 INV268021 4.00 222.00 888.00 183.00 188.00 219.00 236.00 230.00 944.00 Jul-17
4 1019335 10.00 222.00 2,220.00 183.00 188.00 219.00 236.00 230.00 2,360.00 Jul-17
5 1019344 INV268165 10.00 222.00 2,220.00 183.00 188.00 219.00 236.00 230.00 2,360.00 Jul-17
6 1019355 8.00 222.00 1,776.00 183.00 188.00 219.00 236.00 230.00 1,888.00 Jul-17
1/7/2017
7 1019634 INV268708 6.00 222.00 1,332.00 183.00 188.00 219.00 236.00 230.00 1,416.00 Jul-17
8 CTI-0000008659 APPENDIX 1 INV268706 100.00 222.00 22,200.00 183.00 188.00 219.00 236.00 230.00 23,600.00 Jul-17
9 APPENDIX 2 INV268707 121.00 222.00 26,862.00 183.00 188.00 219.00 236.00 230.00 28,556.00 Jul-17
10 APPENDIX 3 INV268709 73.00 222.00 16,206.00 183.00 188.00 219.00 236.00 230.00 17,228.00 Jul-17
11 APPENDIX 4 INV268710 46.00 222.00 10,212.00 183.00 188.00 219.00 236.00 230.00 10,856.00 Jul-17
12 APPENDIX 5 INV269099 174.00 222.00 38,628.00 183.00 188.00 219.00 236.00 230.00 41,064.00 Jul-17
DEBIT NOTE FOR JULY 2017 AS ABOVE - - - 566.00 -
1 14/7/2017 1020907 INV270695 7.00 179.00 222.00 1,554.00 183.00 188.00 219.00 236.00 230.00 1,652.00 Aug-17
2 18/7/2017 1021353/54 INV270590 17.00 179.00 222.00 3,774.00 183.00 188.00 219.00 236.00 230.00 4,012.00 Aug-17
CTI-0000008910
3 13/7/2017 APPENDIX 1 INV270694 110.00 179.00 222.00 24,420.00 183.00 188.00 219.00 236.00 230.00 25,960.00 Aug-17
4 19/7/2017 APPENDIX 2 INV270591 176.00 179.00 222.00 39,072.00 183.00 188.00 219.00 236.00 230.00 41,536.00 Aug-17
5 22/7/2017 1021769 INV270654 9.00 174.00 179.00 198.00 222.00 216.00 1,998.00 183.00 188.00 219.00 236.00 230.00 2,124.00 Aug-17
6 22/7/2017 1021772 INV270654 8.00 174.00 179.00 198.00 222.00 216.00 1,776.00 183.00 188.00 219.00 236.00 230.00 1,888.00 Aug-17
7 22/7/2017 1021775 INV270654 5.00 174.00 179.00 198.00 222.00 216.00 1,110.00 183.00 188.00 219.00 236.00 230.00 1,180.00 Aug-17
8 22/7/2017 1022074 INV271060 9.00 174.00 179.00 198.00 222.00 216.00 1,998.00 183.00 188.00 219.00 236.00 230.00 2,124.00 Aug-17
9 CTI-0000008958 22/7/2017 1022092 INV271060 3.00 174.00 179.00 198.00 222.00 216.00 522.00 183.00 188.00 219.00 236.00 230.00 549.00 Aug-17
10 22/7/2017 1022245 INV271323 8.00 174.00 179.00 198.00 222.00 216.00 1,776.00 183.00 188.00 219.00 236.00 230.00 1,888.00 Aug-17
11 22/7/2017 1022267 INV271323 5.00 174.00 179.00 198.00 222.00 216.00 1,110.00 183.00 188.00 219.00 236.00 230.00 1,180.00 Aug-17
12 22/7/2017 1022287 INV271323 3.00 174.00 179.00 198.00 222.00 216.00 666.00 183.00 188.00 219.00 236.00 230.00 708.00 Aug-17
13 22/7/2017 Appendix 1 INV270653 84.00 174.00 179.00 198.00 222.00 216.00 18,648.00 183.00 188.00 219.00 236.00 230.00 19,824.00 Aug-17
26 CTI-0000009008 1022156 INV271322 3.00 174.00 179.00 198.00 222.00 216.00 666.00 183.00 188.00 219.00 236.00 230.00 708.00 Aug-17
27 1/8/2017 1022513 INV272330 22.00 174.00 179.00 198.00 222.00 216.00 4,356.00 183.00 188.00 219.00 236.00 230.00 4,818.00 Aug-17
28 2/8/2017 1022532 INV272331 4.00 174.00 179.00 198.00 222.00 216.00 888.00 183.00 188.00 219.00 236.00 230.00 944.00 Aug-17
29 3/8/2017 1022627 4.00 174.00 179.00 198.00 222.00 216.00 864.00 183.00 188.00 219.00 236.00 230.00 920.00 Aug-17
30 3/8/2017 1022635 4.00 174.00 179.00 198.00 222.00 216.00 864.00 183.00 188.00 219.00 236.00 230.00 920.00 Aug-17
31 3/8/2017 1022646 4.00 174.00 179.00 198.00 222.00 216.00 864.00 183.00 188.00 219.00 236.00 230.00 920.00 Aug-17
32 7/8/2017 1022967 6.00 174.00 179.00 198.00 222.00 216.00 1,296.00 183.00 188.00 219.00 236.00 230.00 1,380.00 Aug-17
CTI-0000009177
33 7/8/2017 1022978 4.00 174.00 179.00 198.00 222.00 216.00 864.00 183.00 188.00 219.00 236.00 230.00 920.00 Aug-17
34 8/8/2017 1023049 3.00 174.00 179.00 198.00 222.00 216.00 648.00 183.00 188.00 219.00 236.00 230.00 690.00 Aug-17
35 9/8/2017 1023218 2.00 174.00 179.00 198.00 222.00 216.00 348.00 183.00 188.00 219.00 236.00 230.00 366.00 Aug-17
36 10/8/2017 1023347 8.00 174.00 179.00 198.00 222.00 216.00 1,728.00 183.00 188.00 219.00 236.00 230.00 1,840.00 Aug-17
37 10/8/2017 1023367 9.00 174.00 179.00 198.00 222.00 216.00 1,944.00 183.00 188.00 219.00 236.00 230.00 2,070.00 Aug-17
38 10/8/2017 1023389 5.00 174.00 179.00 198.00 222.00 216.00 1,080.00 183.00 188.00 219.00 236.00 230.00 1,150.00 Aug-17
DEBIT NOTE FOR August 2017 AS ABOVE 5.00 - 22.00 448.00 47.00
1 CTI-0000009252 12/8/2017 1023590 INV273318 2.00 174.00 179.00 198.00 222.00 216.00 432.00 183.00 188.00 219.00 236.00 230.00 460.00 Sep-17
2 CTI-0000009252 12/8/2017 1023527 INV273317 41.00 174.00 179.00 198.00 222.00 216.00 8,856.00 183.00 188.00 219.00 236.00 230.00 9,430.00 Sep-17
3 CTI-0000009346 15/8/2017 1023740 INV273471 8.00 174.00 179.00 198.00 222.00 216.00 1,728.00 183.00 188.00 219.00 236.00 230.00 1,840.00 Sep-17
4 CTI-0000009346 15/8/2017 1024056 INV273996 7.00 174.00 179.00 198.00 222.00 216.00 1,512.00 183.00 188.00 219.00 236.00 230.00 1,610.00 Sep-17
4 CTI-0000009346 1024075 INV273996 8.00 174.00 179.00 198.00 222.00 216.00 1,728.00 183.00 188.00 219.00 236.00 230.00 1,840.00 Sep-17
5 CTI-0000009346 1024182 INV273997 5.00 174.00 179.00 198.00 222.00 216.00 990.00 183.00 188.00 219.00 236.00 230.00 1,095.00 Sep-17
6 CTI-0000009346 1024198 INV273997 3.00 174.00 179.00 198.00 222.00 216.00 594.00 183.00 188.00 219.00 236.00 230.00 657.00 Sep-17
6 CTI-0000009346 23/8/2017 1024343 INV274104 5.00 174.00 179.00 198.00 222.00 216.00 1,110.00 183.00 188.00 219.00 236.00 230.00 1,180.00 Sep-17
7 CTI-0000009346 23/8/2017 1024359 INV274104 5.00 174.00 179.00 198.00 222.00 216.00 990.00 183.00 188.00 219.00 236.00 230.00 1,095.00 Sep-17
8 CTI-0000009346 29/8/2017 1024873 INV274940 9.00 174.00 179.00 198.00 222.00 216.00 1,998.00 183.00 188.00 219.00 236.00 230.00 2,124.00 Sep-17
8 CTI-0000009346 29/8/2017 1024877 INV274940 10.00 174.00 179.00 198.00 222.00 216.00 2,220.00 183.00 188.00 219.00 236.00 230.00 2,360.00 Sep-17
9 CTI-0000009346 29/8/2017 1024886 INV274940 3.00 174.00 179.00 198.00 222.00 216.00 666.00 183.00 188.00 219.00 236.00 230.00 708.00 Sep-17
10 CTI-0000009445 1023810 INV273472 3.00 174.00 179.00 198.00 222.00 216.00 648.00 183.00 188.00 219.00 236.00 230.00 690.00 Sep-17
10 CTI-0000009445 1023886 INV273994 5.00 174.00 179.00 198.00 222.00 216.00 1,080.00 183.00 188.00 219.00 236.00 230.00 1,150.00 Sep-17
11 CTI-0000009445 1023896 INV273994 4.00 174.00 179.00 198.00 222.00 216.00 864.00 183.00 188.00 219.00 236.00 230.00 920.00 Sep-17
12 CTI-0000009445 1023964 INV273995 8.00 174.00 179.00 198.00 222.00 216.00 1,392.00 183.00 188.00 219.00 236.00 230.00 1,464.00 Sep-17
12 CTI-0000009445 1023973 INV273995 8.00 174.00 179.00 198.00 222.00 216.00 1,392.00 183.00 188.00 219.00 236.00 230.00 1,464.00 Sep-17
13 CTI-0000009445 1024491 INV274335 9.00 174.00 179.00 198.00 222.00 216.00 1,566.00 183.00 188.00 219.00 236.00 230.00 1,647.00 Sep-17
14 CTI-0000009445 1024499 INV274335 6.00 174.00 179.00 198.00 222.00 216.00 1,044.00 183.00 188.00 219.00 236.00 230.00 1,098.00 Sep-17
14 CTI-0000009445 28/9/2017 1024689 INV274938 5.50 174.00 179.00 198.00 222.00 216.00 1,089.00 183.00 188.00 219.00 236.00 230.00 1,204.50 Sep-17
15 CTI-0000009445 28/9/2017 1024718 INV274938 6.00 174.00 179.00 198.00 222.00 216.00 1,188.00 183.00 188.00 219.00 236.00 230.00 1,314.00 Sep-17
16 CTI-0000009445 29/8/2017 appendix1 INV274939 143.00 174.00 179.00 198.00 222.00 216.00 31,746.00 183.00 188.00 219.00 236.00 230.00 33,748.00 Sep-17
16 CTI-0000009445 29/8/2017 1024809 INV274939 6.50 174.00 179.00 198.00 222.00 216.00 1,287.00 183.00 188.00 219.00 236.00 230.00 1,423.50 Sep-17
17 CTI-0000009445 29/8/2017 1024822 INV274939 3.00 174.00 179.00 198.00 222.00 216.00 594.00 183.00 188.00 219.00 236.00 230.00 657.00 Sep-17
18 CTI-0000009519 1025131 INV276768 6.00 174.00 179.00 198.00 222.00 216.00 1,188.00 183.00 188.00 219.00 236.00 230.00 1,314.00 Sep-17
18 CTI-0000009519 1025133 INV276768 6.00 174.00 179.00 198.00 222.00 216.00 1,188.00 183.00 188.00 219.00 236.00 230.00 1,314.00 Sep-17
19 CTI-0000009519 1025222 INV276769 7.50 174.00 179.00 198.00 222.00 216.00 1,485.00 183.00 188.00 219.00 236.00 230.00 1,642.50 Sep-17
20 CTI-0000009519 1025476 INV275778 8.00 174.00 179.00 198.00 222.00 216.00 1,776.00 183.00 188.00 219.00 236.00 230.00 1,888.00 Sep-17
20 CTI-0000009519 1025493 INV275778 8.00 174.00 179.00 198.00 222.00 216.00 1,776.00 183.00 188.00 219.00 236.00 230.00 1,888.00 Sep-17
21 Appendix 1 INV276770 126.00 174.00 179.00 198.00 222.00 216.00 27,972.00 183.00 188.00 219.00 236.00 230.00 29,736.00 Sep-17
DEBIT NOTE FOR SEPT 2017 AS ABOVE 31.00 - 53.50 312.00 78.00
1 CTI-0000009674 sept 1026365 INV276948 5.50 174.00 179.00 198.00 222.00 216.00 1,089.00 183.00 188.00 219.00 236.00 230.00 1,204.50 Oct-17
2 CTI-0000009674 sept 1026499 INV276949 3.00 174.00 179.00 198.00 222.00 216.00 594.00 183.00 188.00 219.00 236.00 230.00 657.00 Oct-17
3 CTI-0000009674 27/9/2017 1026759 INV277190 7.50 174.00 179.00 198.00 222.00 216.00 1,485.00 183.00 188.00 219.00 236.00 230.00 1,642.50 Oct-17
4 CTI-0000009674 27/9/2017 1026780 INV277190 6.00 174.00 179.00 198.00 222.00 216.00 1,188.00 183.00 188.00 219.00 236.00 230.00 1,314.00 Oct-17
5 CTI-0000009674 27/9/2017 1026795 INV277191 8.00 174.00 179.00 198.00 222.00 216.00 1,584.00 183.00 188.00 219.00 236.00 230.00 1,752.00 Oct-17
6 CTI-0000009674 27/9/2017 1026799 INV277191 3.00 174.00 179.00 198.00 222.00 216.00 594.00 183.00 188.00 219.00 236.00 230.00 657.00 Oct-17
7 CTI-0000009674 1/10/2017 1026980 INV277191 9.00 174.00 179.00 198.00 222.00 216.00 1,782.00 183.00 188.00 219.00 236.00 230.00 1,971.00 Oct-17
8 CTI-0000009674 1/10/2017 Appendix 1 INV276947 23.00 174.00 179.00 198.00 222.00 216.00 4,554.00 183.00 188.00 219.00 236.00 230.00 5,037.00 Oct-17
9 CTI-0000009674 1/10/2017 Appendix 1 INV276947 90.00 174.00 179.00 198.00 222.00 216.00 17,820.00 183.00 188.00 219.00 236.00 230.00 19,710.00 Oct-17
10 CTI-0000009902 5/10/2017 1027855 INV279298 7.00 174.00 179.00 198.00 222.00 216.00 1,386.00 183.00 188.00 219.00 236.00 230.00 1,533.00 Oct-17
11 CTI-0000009638 5/10/2017 1025529 INV275779 4.00 174.00 179.00 198.00 222.00 216.00 792.00 183.00 188.00 219.00 236.00 230.00 876.00 Oct-17
12 CTI-0000009958 5/10/2017 1027043 INV277800 10.00 174.00 179.00 198.00 222.00 216.00 1,980.00 183.00 188.00 219.00 236.00 230.00 2,190.00 Oct-17
13 CTI-0000009958 5/10/2017 1027050 INV277800 9.00 174.00 179.00 198.00 222.00 216.00 1,782.00 183.00 188.00 219.00 236.00 230.00 1,971.00 Oct-17
14 CTI-0000009958 5/10/2017 1027334 INV278389 10.00 174.00 179.00 198.00 222.00 216.00 1,980.00 183.00 188.00 219.00 236.00 230.00 2,190.00 Oct-17
15 CTI-0000009958 5/10/2017 1027343 INV278389 9.00 174.00 179.00 198.00 222.00 216.00 1,782.00 183.00 188.00 219.00 236.00 230.00 1,971.00 Oct-17
16 CTI-0000009958 5/10/2017 1027349 INV278389 9.00 174.00 179.00 198.00 222.00 216.00 1,782.00 183.00 188.00 219.00 236.00 230.00 1,971.00 Oct-17
17 CTI-0000009958 5/10/2017 1027588 INV278391 6.00 174.00 179.00 198.00 222.00 216.00 1,188.00 183.00 188.00 219.00 236.00 230.00 1,314.00 Oct-17
18 CTI-0000009958 5/10/2017 1027626 INV278391 5.50 174.00 179.00 198.00 222.00 216.00 1,089.00 183.00 188.00 219.00 236.00 230.00 1,204.50 Oct-17
19 CTI-0000009958 5/10/2017 Appendix 1 INV278391 46.00 174.00 179.00 198.00 222.00 216.00 9,108.00 183.00 188.00 219.00 236.00 230.00 10,074.00 Oct-17
CONCRETE
1 CTI-0000010083 1028254 INV 279630 10.00 174.00 179.00 198.00 222.00 216.00 209.00 1,980.00 183.00 188.00 219.00 236.00 230.00 236.00 2,190.00 Nov-17
2 CTI-0000010083 1028259 INV 279630 10.00 174.00 179.00 198.00 222.00 216.00 209.00 1,980.00 183.00 188.00 219.00 236.00 230.00 236.00 2,190.00 Nov-17
3 CTI-0000010083 1028260 INV 279630 8.00 174.00 179.00 198.00 222.00 216.00 209.00 1,584.00 183.00 188.00 219.00 236.00 230.00 236.00 1,752.00 Nov-17
4 CTI-0000010083 1028462 INV 279631 7.00 174.00 179.00 198.00 222.00 216.00 209.00 1,218.00 183.00 188.00 219.00 236.00 230.00 236.00 1,281.00 Nov-17
5 CTI-0000010083 1028421 INV 279631 7.00 174.00 179.00 198.00 222.00 216.00 209.00 1,386.00 183.00 188.00 219.00 236.00 230.00 236.00 1,533.00 Nov-17
6 CTI-0000010083 1028443 INV 279631 9.00 174.00 179.00 198.00 222.00 216.00 209.00 1,782.00 183.00 188.00 219.00 236.00 230.00 236.00 1,971.00 Nov-17
7 CTI-0000010083 1028569 INV 279633 2.00 174.00 179.00 198.00 222.00 216.00 209.00 396.00 183.00 188.00 219.00 236.00 230.00 236.00 438.00 Nov-17
8 CTI-0000010083 1028640 INV 279633 8.00 174.00 179.00 198.00 222.00 216.00 209.00 1,584.00 183.00 188.00 219.00 236.00 230.00 236.00 1,752.00 Nov-17
9 CTI-0000010083 1029065 INV 280188 4.00 174.00 179.00 198.00 222.00 216.00 209.00 792.00 183.00 188.00 219.00 236.00 230.00 236.00 876.00 Nov-17
10 CTI-0000010083 1029153 INV 280189 10.00 174.00 179.00 198.00 222.00 216.00 209.00 1,980.00 183.00 188.00 219.00 236.00 230.00 236.00 2,190.00 Nov-17
11 CTI-0000010083 16/10/2017 app 1 INV 279299 37.00 174.00 179.00 198.00 222.00 216.00 209.00 7,326.00 183.00 188.00 219.00 236.00 230.00 236.00 8,103.00 Nov-17
12 CTI-0000010083 1028517 INV 279632 3.00 174.00 179.00 198.00 222.00 216.00 209.00 666.00 183.00 188.00 219.00 236.00 230.00 236.00 708.00 Nov-17
13 CTI-0000010083 20/10/2017 app2 INV 279632 8.00 174.00 179.00 198.00 222.00 216.00 209.00 1,392.00 183.00 188.00 219.00 236.00 230.00 236.00 1,464.00 Nov-17
14 CTI-0000010083 1028542 INV 279632 8.00 174.00 179.00 198.00 222.00 216.00 209.00 1,584.00 183.00 188.00 219.00 236.00 230.00 236.00 1,752.00 Nov-17
15 CTI-0000010083 31/10/2017 app3 INV 280797 110.00 174.00 179.00 198.00 222.00 216.00 209.00 24,420.00 183.00 188.00 219.00 236.00 230.00 236.00 25,960.00 Nov-17
16 CTI-0000010326 1/11/2017 1029749 INV281188 10.00 174.00 179.00 198.00 222.00 216.00 209.00 1,980.00 183.00 188.00 219.00 236.00 230.00 236.00 2,190.00 Nov-17
17 CTI-0000010326 1/11/2017 1029751 INV281188 9.00 174.00 179.00 198.00 222.00 216.00 209.00 1,782.00 183.00 188.00 219.00 236.00 230.00 236.00 1,971.00 Nov-17
18 CTI-0000010326 1/11/2017 1029753 INV281188 10.00 174.00 179.00 198.00 222.00 216.00 209.00 1,980.00 183.00 188.00 219.00 236.00 230.00 236.00 2,190.00 Nov-17
19 CTI-0000010326 1/11/2017 1119566 INV281694 6.00 174.00 179.00 198.00 222.00 216.00 209.00 1,296.00 183.00 188.00 219.00 236.00 230.00 236.00 1,380.00 Nov-17
20 CTI-0000010326 1/11/2017 1029959 INV281287 7.00 174.00 179.00 198.00 222.00 216.00 209.00 1,386.00 183.00 188.00 219.00 236.00 230.00 236.00 1,533.00 Nov-17
21 CTI-0000010326 1/11/2017 1030094 INV281289 5.00 174.00 179.00 198.00 222.00 216.00 209.00 1,080.00 183.00 188.00 219.00 236.00 230.00 236.00 1,150.00 Nov-17
22 CTI-0000010326 1/11/2017 1030111 INV281289 5.00 174.00 179.00 198.00 222.00 216.00 209.00 990.00 183.00 188.00 219.00 236.00 230.00 236.00 1,095.00 Nov-17
23 CTI-0000010326 9/11/2017 1030137 INV282228 7.00 174.00 179.00 198.00 222.00 216.00 209.00 1,386.00 183.00 188.00 219.00 236.00 230.00 236.00 1,533.00 Nov-17
24 CTI-0000010326 10/11/2017 1030190 INV282228 8.00 174.00 179.00 198.00 222.00 216.00 209.00 1,672.00 183.00 188.00 219.00 236.00 230.00 236.00 1,888.00 Nov-17
25 CTI-0000010326 10/11/2017 1030194 INV282229 10.00 174.00 179.00 198.00 222.00 216.00 209.00 2,090.00 183.00 188.00 219.00 236.00 230.00 236.00 2,360.00 Nov-17
26 CTI-0000010326 10/11/2017 1030198 INV281186 8.00 174.00 179.00 198.00 222.00 216.00 209.00 1,672.00 183.00 188.00 219.00 236.00 230.00 236.00 1,888.00 Nov-17
27 CTI-0000010326 11/11/2017 1030293 INV281187 6.00 174.00 179.00 198.00 222.00 216.00 209.00 1,188.00 183.00 188.00 219.00 236.00 230.00 236.00 1,314.00 Nov-17
28 CTI-0000010326 1/11/2017 App1 INV281186 55.00 174.00 179.00 198.00 222.00 216.00 209.00 12,210.00 183.00 188.00 219.00 236.00 230.00 236.00 12,980.00 Nov-17
29 CTI-0000010326 3/11/2017 App2 INV281187 46.00 174.00 179.00 198.00 222.00 216.00 209.00 9,108.00 183.00 188.00 219.00 236.00 230.00 236.00 10,074.00 Nov-17
30 CTI-0000010326 8/11/2017 App3 INV281188 33.00 174.00 179.00 198.00 222.00 216.00 209.00 7,128.00 183.00 188.00 219.00 236.00 230.00 236.00 7,590.00 Nov-17
31 CTI-0000010326 1029967 INV281188 5.00 174.00 179.00 198.00 222.00 216.00 209.00 990.00 183.00 188.00 219.00 236.00 230.00 236.00 1,095.00 Nov-17
32 CTI-0000010515 14/11/2017 1030340 Inv282231 84193 15.00 174.00 179.00 198.00 222.00 216.00 209.00 2,970.00 183.00 188.00 219.00 236.00 230.00 236.00 3,285.00 Nov-17
33 CTI-0000010515 15/11/2017 1030553 Inv282232 9.00 174.00 179.00 198.00 222.00 216.00 209.00 1,998.00 183.00 188.00 219.00 236.00 230.00 236.00 2,124.00 Nov-17
34 CTI-0000010515 15/11/2017 1030546 Inv282232 84193 28.00 174.00 179.00 198.00 222.00 216.00 209.00 5,544.00 183.00 188.00 219.00 236.00 230.00 236.00 6,132.00 Nov-17
35 CTI-0000010515 16/11/2017 1030627 Inv282233 84193 11.00 174.00 179.00 198.00 222.00 216.00 209.00 2,442.00 183.00 188.00 219.00 236.00 230.00 236.00 2,596.00 Nov-17
36 CTI-0000010515 16/11/2017 1030615 Inv282233 29.00 174.00 179.00 198.00 222.00 216.00 209.00 5,742.00 183.00 188.00 219.00 236.00 230.00 236.00 6,351.00 Nov-17
37 CTI-0000010515 17/11/2017 1030730 Inv282234 84193 10.00 174.00 179.00 198.00 222.00 216.00 209.00 1,980.00 183.00 188.00 219.00 236.00 230.00 236.00 2,190.00 Nov-17
38 CTI-0000010516 22/11/2017 1031025 19 174.00 179.00 198.00 222.00 216.00 209.00 3,971.00 183.00 188.00 219.00 236.00 230.00 236.00 4,484.00 Nov-17
39 CTI-0000010516 22/11/2017 TRX 1031011 12.00 174.00 179.00 198.00 222.00 216.00 209.00 2,376.00 183.00 188.00 219.00 236.00 230.00 236.00 2,628.00 Nov-17
40 CTI-0000010516 24/11/2017 TRX 1031197 26.00 174.00 179.00 198.00 222.00 216.00 209.00 5,148.00 183.00 188.00 219.00 236.00 230.00 236.00 5,694.00 Nov-17
41 CTI-0000010516 25/11/2017 TRX 1031279 60.5 174.00 179.00 198.00 222.00 216.00 209.00 12,644.50 183.00 188.00 219.00 236.00 230.00 236.00 14,278.00 Nov-17
42 CTI-0000010688 29/11/2017 TRX 1031562 3.50 174.00 179.00 198.00 222.00 216.00 209.00 609.00 183.00 188.00 219.00 236.00 230.00 236.00 640.50 Nov-17
43 CTI-0000010688 29/11/2017 TRX 1031553 14.00 174.00 179.00 198.00 222.00 216.00 209.00 2,772.00 183.00 188.00 219.00 236.00 230.00 236.00 3,066.00 Nov-17
44 CTI-0000010688 30/11/2017 TRX 1031617 5.00 174.00 179.00 198.00 222.00 216.00 209.00 990.00 183.00 188.00 219.00 236.00 230.00 236.00 1,095.00 Nov-17
45 CTI-0000010516 13/11/2017 TRX 1030340 Inv282230 84193 84.00 174.00 179.00 198.00 222.00 216.00 209.00 16,632.00 183.00 188.00 219.00 236.00 230.00 236.00 18,396.00 Nov-17
46 CTI-0000010516 20/11/2017 1030858 Inv282235 38.00 174.00 179.00 198.00 222.00 216.00 209.00 7,524.00 183.00 188.00 219.00 236.00 230.00 236.00 8,322.00 Nov-17
DEBIT NOTE FOR NOV 2017 AS ABOVE 18.50 - 479.00 188.00 44.00 105.50
1 CTI-000010833 12-Dec Inv285114 4.50 174.00 179.00 198.00 222.00 216.00 209.00 891.00 183.00 188.00 219.00 236.00 230.00 236.00 985.50 Dec-17
2 CTI-000010833 14-Dec Inv285116 13.00 174.00 179.00 198.00 222.00 216.00 209.00 2,574.00 183.00 188.00 219.00 236.00 230.00 236.00 2,847.00 Dec-17
3 CTI-000010833 13-Dec Inv285115 37.00 174.00 179.00 198.00 222.00 216.00 209.00 7,326.00 183.00 188.00 219.00 236.00 230.00 236.00 8,103.00 Dec-17
INV1032589-
4 CTI-00001085 1-Jan 110.00 115.00 174.00 179.00 198.00 222.00 216.00 209.00 46,620.00 183.00 188.00 219.00 236.00 230.00 236.00 50,540.00 Dec-17
285853
5 CTI-000010986 1-Jan inv258373 3.50 6.00 174.00 179.00 198.00 222.00 216.00 209.00 1,797.00 183.00 188.00 219.00 236.00 230.00 236.00 1,954.50 Dec-17
INV286368-
CTI-0000111106
6 11-Jan 286802 170.00 174.00 179.00 198.00 222.00 216.00 209.00 33,660.00 183.00 188.00 219.00 236.00 230.00 236.00 37,230.00 Dec-17
1 CTI-0000011202 18-Jan Inv286803 5.00 174.00 179.00 198.00 222.00 216.00 209.00 990.00 183.00 188.00 219.00 236.00 230.00 236.00 1,095.00 Jan-18
2 CTI-0000011202 18-Jan Inv287749 10.00 174.00 179.00 198.00 222.00 216.00 209.00 1,980.00 183.00 188.00 219.00 236.00 230.00 236.00 2,190.00 Jan-18
3 CTI-0000011202 18-Jan Inv287748 38.00 174.00 179.00 198.00 222.00 216.00 209.00 7,524.00 183.00 188.00 219.00 236.00 230.00 236.00 8,322.00 Jan-18
4 CTI-0000111247 29-Jan Inv288343 40.00 174.00 179.00 198.00 222.00 216.00 209.00 8,360.00 183.00 188.00 219.00 236.00 230.00 236.00 9,440.00 Jan-18
5 CTI-0000111247 29-Jan Inv288729 5.00 174.00 179.00 198.00 222.00 216.00 209.00 990.00 183.00 188.00 219.00 236.00 230.00 236.00 1,095.00 Jan-18
6 CTI-0000111247 29-Jan Inv288728 12.00 174.00 179.00 198.00 222.00 215.00 209.00 2,508.00 183.00 188.00 219.00 236.00 230.00 236.00 2,832.00 Jan-18
7 CTI-0000011296 29-Jan Inv288727 227.00 174.00 179.00 198.00 222.00 216.00 215.00 48,805.00 183.00 188.00 219.00 236.00 230.00 236.00 53,572.00 Jan-18
8 CTI-0000011296 29-Jan Inv288727 5.00 174.00 179.00 198.00 222.00 216.00 209.00 990.00 183.00 188.00 219.00 236.00 230.00 236.00 1,095.00 Jan-18
9 CTI-0000011403 29-Jan Inv287873 2.00 174.00 179.00 198.00 222.00 216.00 209.00 396.00 183.00 188.00 219.00 236.00 230.00 236.00 438.00 Jan-18
10 CTI-0000011403 29-Jan Inv287750 50.00 174.00 179.00 198.00 222.00 216.00 209.00 10,800.00 183.00 188.00 219.00 236.00 230.00 236.00 11,500.00 Jan-18
11 CTI-0000011418 7-Feb Inv289597 154.00 174.00 179.00 198.00 222.00 216.00 215.00 33,110.00 183.00 188.00 219.00 236.00 230.00 236.00 36,344.00 Jan-18
12 CTI-0000011418 7-Feb Inv289598 10.50 174.00 179.00 198.00 222.00 216.00 209.00 2,079.00 183.00 188.00 219.00 236.00 230.00 236.00 2,299.50 Jan-18
13 CTI-0000011418 7-Feb Inv289600 20.00 174.00 179.00 198.00 222.00 216.00 209.00 4,320.00 183.00 188.00 219.00 236.00 230.00 236.00 4,600.00 Jan-18
CONCRETE
1 CTI-0000011202 1-Feb Inv286803 45.00 174.00 179.00 198.00 216.00 216.00 215.00 8,910.00 183.00 188.00 219.00 236.00 230.00 236.00 9,855.00 Feb-18
2 CTI-0000011247 1-Feb 288729-288 5.00 40.00 12.00 174.00 179.00 198.00 216.00 216.00 215.00 12,210.00 183.00 188.00 219.00 236.00 230.00 236.00 13,367.00 Feb-18
3 CTI-0000011296 1-Feb Inv288727 5.00 227.00 174.00 179.00 198.00 216.00 216.00 215.00 49,795.00 183.00 188.00 219.00 236.00 230.00 236.00 54,667.00 Feb-18
4 CTI-0000011403 1-Feb 287873-287751 2.00 50.00 174.00 179.00 198.00 216.00 216.00 215.00 11,196.00 183.00 188.00 219.00 236.00 230.00 236.00 12,238.00 Feb-18
5 CTI-0000011418 11-Feb 289598-289597 10.50 20.00 154.00 174.00 179.00 198.00 216.00 216.00 215.00 39,509.00 183.00 188.00 219.00 236.00 230.00 236.00 43,363.50 Feb-18
1 CTI-0000011558 1-Mar 290588-291052 2.00 26.00 40.00 174.00 179.00 198.00 216.00 216.00 215.00 14,136.00 183.00 188.00 219.00 236.00 230.00 236.00 15,500.00 Mar-18
2 CTI-0000011595 1-Mar 289601-290584 43.00 161.00 174.00 179.00 198.00 216.00 216.00 215.00 43,903.00 183.00 188.00 219.00 236.00 230.00 236.00 48,144.00 Mar-18
3 CTI-0000011621 1-Mar 290587-290586 17.00 23.00 174.00 179.00 198.00 216.00 216.00 215.00 8,334.00 183.00 188.00 219.00 236.00 230.00 236.00 9,151.00 Mar-18
4 CTI-0000011743 11-Mar 291348-291393 3.00 14.00 30.00 174.00 179.00 198.00 216.00 216.00 215.00 9,744.00 183.00 188.00 219.00 236.00 230.00 236.00 10,695.00 Mar-18
5 CTI-0000011769 11-Mar Inv292035 10.00 4.00 174.00 179.00 198.00 216.00 216.00 215.00 2,844.00 183.00 188.00 219.00 236.00 230.00 236.00 3,134.00 Mar-18
DEBIT NOTE FOR Mar 2018 AS ABOVE 5.00 - 67.00 110.00 - 191.00
1 CTI-0000011897 1-Apr Inv293196 39.00 174.00 179.00 198.00 216.00 216.00 215.00 8,424.00 183.00 188.00 219.00 236.00 230.00 236.00 9,204.00 Apr-18
2 CTI-0000012010 1-Apr Inv292796 15.00 174.00 179.00 198.00 216.00 216.00 215.00 3,240.00 183.00 188.00 219.00 236.00 230.00 236.00 3,540.00 Apr-18
3 CTI-0000012264 11-Apr Inv295663 2.50 10.00 174.00 179.00 198.00 216.00 216.00 215.00 2,595.00 183.00 188.00 219.00 236.00 230.00 236.00 2,817.50 Apr-18
QTY FROM QAQC LIST NOT CAPTURE IN DEBIT NOTE since Sept 2017
1 1/4/2017 110.00 174.00 179.00 198.00 222.00 216.00 209.00 183.00 188.00 225.00 236.00 249.00 236.00
2 7/11/2017 1029967 12.00 174.00 179.00 198.00 222.00 216.00 209.00 183.00 188.00 225.00 236.00 249.00 236.00
3 8/11/2017 1030039 33.00 174.00 179.00 198.00 222.00 216.00 209.00 183.00 188.00 225.00 236.00 249.00 236.00
4 21/9/2017 1026237 6.00 174.00 179.00 198.00 222.00 216.00 209.00 183.00 188.00 225.00 236.00 249.00 236.00
5 21/9/2017 1026250 107.00 174.00 179.00 198.00 222.00 216.00 209.00 183.00 188.00 225.00 236.00 249.00 236.00
3) Variance = 1,181.56 m3
4) Prov.Deduction= 34.00 m3
PROJECT TITLE :
PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND ROADWAY WORKS AT THE TUN RAZAK EXCHANGE (TRX) FOR 1MDB REAL ESTATE SDN BHD
Reimbursement Cost
Steel Bar
Quantity (ton) Debit Note Charging Price (RM/ton) Pegging Price (RM/ton)
Debit Note Month
Remarks
Item Debit No. Date DO No. Description T10 T12 T16 T20 T25 T32 T40 T10 T12 T16 T20 T25 T32 T40 Total Amount T10 T12 T16 T20 T25 T32 T40 Total Amount
1 CTI-0000007658 11/3/2017 L4DOP49806 Y20mm x 12m HTDB 20.160 2,220.00 44,755.20 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 34,272.00 Mar-17
DEBIT NOTE UP TO APRIL 2017 - - - 20.160 - - -
2 1/4/2017 L4DOP49808 Y25mm x 12m HTDB 30.480 2,220.00 2,220.00 67,665.60 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 51,816.00 Apr-17
3 1/4/2017 L4DOP49809 Y25mm x 12m HTDB 30.480 2,220.00 2,220.00 67,665.60 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 51,816.00 Apr-17
4 1/4/2017 L4DOP49813 Y32mm x 12m HTDB 31.800 2,220.00 2,220.00 2,220.00 70,596.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 54,060.00 Apr-17
5 CTI-0000007760 1/4/2017 L4DOP49814 Y32mm x 12m HTDB 26.500 2,220.00 2,220.00 2,220.00 58,830.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 45,050.00 Apr-17
6 1/4/2017 L4DOP49807 Y20mm x 12m HTDB 20.160 2,220.00 2,220.00 2,220.00 44,755.20 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 34,272.00 Apr-17
7 1/4/2017 L4DOP49812 Y32mm x 12m HTDB 21.200 2,220.00 2,220.00 2,220.00 47,064.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 36,040.00 Apr-17
8 1/4/2017 L4DOP49811 Y32mm x 12m HTDB 21.200 2,220.00 2,220.00 2,220.00 47,064.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 36,040.00 Apr-17
9 1/4/2017 L4DOP51143 Y25mm x 12m HTDB 39.624 2,220.00 2,150.00 85,191.60 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 67,360.80 Apr-17
10 1/4/2017 L4DOP51134 Y16mm x 12m HTDB 20.480 2,150.00 2,220.00 2,150.00 44,032.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 34,816.00 Apr-17
11 1/4/2017 L4DOP51135 Y16mm x 12m HTDB 29.696 2,150.00 2,220.00 2,150.00 63,846.40 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 50,483.20 Apr-17
12 1/4/2017 L4DOP51144 Y32mm x 12m HTDB 31.800 2,150.00 2,220.00 2,150.00 2,150.00 68,370.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 54,060.00 Apr-17
13 1/4/2017 L4DOP51150 Y32mm x 12m HTDB 20.140 2,150.00 2,220.00 2,150.00 2,150.00 43,301.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 34,238.00 Apr-17
14 CTI-0000007813 1/4/2017 L4DOP51136 Y20mm x 12m HTDB 30.240 2,150.00 2,220.00 2,220.00 65,016.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 51,408.00 Apr-17
15 1/4/2017 L4DOP51137 Y20mm x 12m HTDB 30.240 2,150.00 2,220.00 2,220.00 65,016.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 51,408.00 Apr-17
16 1/4/2017 L4DOP51147 Y32mm x 12m HTDB 31.800 2,150.00 2,220.00 2,150.00 68,370.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 54,060.00 Apr-17
17 1/4/2017 L4DOP51148 Y32mm x 12m HTDB 31.800 2,150.00 2,220.00 2,150.00 68,370.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 54,060.00 Apr-17
18 1/4/2017 L4DOP51138 Y20mm x 12m HTDB 30.240 2,150.00 2,220.00 2,220.00 65,016.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 51,408.00 Apr-17
19 1/4/2017 L4DOP51138 Y20mm x 12m HTDB 30.240 2,150.00 2,220.00 2,220.00 65,016.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 51,408.00 Apr-17
20 CTI-0000007813 1/4/2017 L4DOP51132 Y12mm x 12m HTDB 20.460 2,300.000 2,150.00 2,220.00 2,220.00 47,058.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 34,782.00 Apr-17
21 CTI-0000007813 1/4/2017 L4DOP51133 Y12mm x 12m HTDB 29.667 2,300.000 2,150.00 2,220.00 2,220.00 68,234.10 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 50,433.90 Apr-17
22 1/4/2017 L4DOP51140 Y20mm x 12m HTDB 29.232 2,150.00 2,220.00 2,220.00 62,848.80 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 49,694.40 Apr-17
23 1/4/2017 L4DOP51145 Y32mm x 12m HTDB 31.800 2,150.00 2,220.00 2,150.00 68,370.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 54,060.00 Apr-17
24 1/4/2017 L4DOP51146 Y32mm x 12m HTDB 31.800 2,150.00 2,220.00 2,150.00 68,370.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 54,060.00 Apr-17
25 1/4/2017 L4DOP51149 Y32mm x 12m HTDB 21.200 2,150.00 2,220.00 2,150.00 45,580.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 36,040.00 Apr-17
26 1/4/2017 L4DOP51141 Y25mm x 12m HTDB 30.480 2,220.00 2,150.00 65,532.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 51,816.00 Apr-17
27 1/4/2017 L4DOP51142 Y25mm x 12m HTDB 30.480 2,220.00 2,150.00 65,532.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 51,816.00 Apr-17
1 CTI-0000009732 26-Sep 17091811390 Y12mm x 12m HTDB-Grade B500B 60.357 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 124,938.99 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 102,606.90 Oct-17
Y32mm x 8.50m HTDB-grade B500B
2 CTI0000009732
25-Sep L4Dop62172 cut to size 22.527 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 46,630.27 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 38,295.39 Oct-17
1 CTI-000010952 10mm x 12m HTDB-Grade B500B 5.110 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 10,577.70 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 8,687.00 Jan-18
2 CTI-000010952 Y12mm x 12m HTDB-Grade B500B 10.230 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 21,176.10 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 17,391.00 Jan-18
3 CTI-000010952 16mm x 12m HTDB-Grade B500B 15.360 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 31,795.20 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 26,112.00 Jan-18
4 CTI-000010952 32mm x 12m HTDB-Grade B500B 30.740 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 2,070.00 63,631.80 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 52,258.00 Jan-18
1 CTI-000011419 11-Feb L4DOP71741 16mmx12mm HTDB-Grade B500B 15.360 2,730.00 2,730.00 2,580.00 2,580.00 2,580.00 2,580.00 39,628.80 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 26,112.00 Feb-18
2 CTI-000011419 11-Feb L4DOP71741 20mm x12m HTDB-Grade B500B 15.120 2,730.00 2,730.00 2,580.00 2,580.00 2,580.00 2,580.00 39,009.60 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 25,704.00 Feb-18
3 CTI-000011419 11-Feb L4DOP71740 10mmx 12m HTDB-Grade B500B 15.330 2,730.00 2,730.00 2,580.00 2,580.00 2,580.00 2,580.00 41,850.90 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 26,061.00 Feb-18
4 CTI-000011419 11-Feb L4DOP71740 12mmx 12m HTDB-Grade B500B 15.345 2,730.00 2,730.00 2,580.00 2,580.00 2,580.00 2,580.00 41,891.85 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 26,086.50 Feb-18
5 CTI-000011419 11-Feb L4DOP71743 32mmx 12m HTDB-Grade B500B 30.740 2,730.00 2,730.00 2,580.00 2,580.00 2,580.00 2,580.00 79,309.20 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 52,258.00 Feb-18
6 CTI-000011419 11-Feb L4DOP71742 20mmx 12m HTDB-Grade B500B 5.040 2,730.00 2,730.00 2,580.00 2,580.00 2,580.00 2,580.00 13,003.20 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 8,568.00 Feb-18
7 CTI-000011419 11-Feb L4DOP71742 25mmx 12m HTDB-Grade B500B 25.400 2,730.00 2,730.00 2,580.00 2,580.00 2,580.00 2,580.00 65,532.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 43,180.00 Feb-18
DEBIT NOTE UP TO Feb 2018 15.330 15.345 15.360 20.160 25.400 30.740 -
1 CTI-000012031 1-Apr 10mm x 12m HTDB-Grade B500B 15.330 2,730.00 2,730.00 2,580.00 2,580.00 2,580.00 2,580.00 41,850.90 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 26,061.00 Apr-18
2 CTI-000012031 1-Apr 12mm x 12mm HTDB-Grade B500B 25.575 2,730.00 2,730.00 2,580.00 2,580.00 2,580.00 2,580.00 69,819.75 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 43,477.50 Apr-18
QTY FROM QAQC LIST NOT CAPTURE IN DEBIT NOTE JULY 2017
1 35.450 40.700 2,220.000 2,220.000 2,220.000 2,220.000 2,220.000 2,220.000 2,220.000 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00
DEBIT NOTE FOR Nov 2017 28.560 23.699 16.709 38.557 62.436 12.730 -
OVERALL QTY 114.408 235.460 197.957 380.769 349.964 513.234 -
Deduct th ecost of cut & bend from supplier Allsize - - - - - - 146.197 150.00 21929.55
Deduct th ecost of cut & bend length from supplier - - - - - - - 80.00
TOTAL AMOUNT IN D.B 70.52 186.19 181.25 322.05 287.53 500.50 - 3,532,805.37 2,757,400.69
REIMBURSEMENT COST 775,404.68
Total qty 114.408 235.460 197.957 380.769 349.964 513.234 -
Workdone (ton) 87.683 196.823 120.394 228.592 146.728 509.452 -
Wastage 5% 4.384 9.841 6.020 11.430 7.336 25.473 -
Balance qty 22.341 28.796 71.543 140.748 195.900 (21.691) - - - - - - - - -
Adjustment rate 437.64
Checking
1) Total Workdone = 1,289.67 ton
5% Wastage = 64.48 ton
MOS= 436.99 ton
1,791.14 ton
Total Delivery
2) Captured in DN= 1,384.42 ton
Total DO w/o invoice
(Prov.deduction not 76.150 ton Certified < Delivery (DN)
captured by DN)=
Material Transfer to
others = - ton
Material Transfer
from others = 106.541 ton
1,567.11 ton
SUMMARY OF RECOUPMENT