25/may/2019
26/may/2019
Casting conduits that rum from bottom slab through columns for Mail 0.15 and VUN 0.17.(Grid 2&3,
D&G)
Installing 20A switch (Height 130mm) and One-way switches (Height 130cm).
(Grid 3&4, G&H)
Installing 16AMP socket for air conditioning (Height 240cm) for the VUN 0.17.(Grid 3&4, G&H)
27/may/2019
Casting recess floor boxes in ground slab at the Customs and police area
Installation of socket boxes (Height 130mm) at supervisor 0.23 (Grid 4&5, A&C)
Relocating the 13AMP Toilet Hand Drier socket at Disabled toilet (from 135mm to 105mm Height)
Relocating the one-way switch boxes at the Disabled toilet from 135mm to 105mm Height.
28/may/2019
ACTIVITIES ON SITE
Casting conduits in which run from ground slab to column at Staff control 0.70 and Supervisor 0.71
(Grid 1&2, A&C)
Daily Site Report
Dar Al-Handasah Consultants
Cargo Building Electrical
29/may/2019
Checking position and alignment of light junction boxes at the Battery charging room. (Grid 5&6
,F&H)
Checking the exact location of the light boxes at the battery charging and work shop (Grid 5&6, F&H)
Checking Cargo building installation of metallic rooftop lighting conduits
Daily Site Report
Dar Al-Handasah Consultants
Cargo Building Electrical
30/may/2019
Checking positions and location of Intelligent Multi Sensor Fire Detectors at the Battery charging area.
(Grid5&6, F&H)
Checking positions and location of Intelligent UV/IR Flame Detectors at the Battery charging area.
(Grid5&6, F&H). They are installed exactly attached to the upstand beam
Checking Elevation/Heights of Outlet-Security (CCTV Cameras) at battery charging area (Grid5&6,
F&H). The height measured from site as 3.0m.
Checks before casting proceeds:
• Connections/wiring systems are put as per the wiring drawing
• Location and positions of Distribution boards before casting
• Location and position of CCVT Cameras and other wall utility boxes
Daily Site Report
Dar Al-Handasah Consultants
Cargo Building Electrical
31/may/2019
Installation of metallic conduits and junction boxes for external lighting at the canopy side along Grid
A
Installation of Available Outlet Over door box at the Mailroom (Grid 5&6, E&G). The height from to of
door way measured as 0.25m as captured in the photo.
Installation of lighting boxes and Multi Intelligent Sensors for fire detection at the Workshop area.
(Grid 5&6, G&J)
01/June/2019
Remarks:
Number to be Installed 56
Number Installed 21
Percentage Installed (21/56) x100 = 36%
03/ June /2019
Installation of metallic conduits at the roof walkway for roof lighting system
Installation of metallic conduits for external lighting at the Canopy along Grid K
Casting PVC conduits in beams and columns at the MAIL 0.64, VUN 0.654 and DIP 0.63(Grid 1&3,
D&H)
Installation of distribution two (2) box outlets, one at the Battery charging area and the other at the
workshop. The dimensions are 24x38cm and 28x43cm. (Grid 5&6, G&H)
06/ June /2019
Casting slab and beams with PVC conduits, Distribution boxes and box outlets at the Battery charging,
workshop, toilets and VAL 0.10 Areas. (Grid 5&6, E&J).
07/ June /2019
Installation of Lighting and Fire detection alarm system conduits and boxes at the Supervisor 0.23,
Staff control 0.22, Cargo office 0.19, Waiting room 0.21 and Counter room Areas. (Grid 3&5, B&C)
Note: Today the contractor has worked half day and work is to proceed tomorrow.
10/ June /2019
Installation of metallic conduits at the roof walk-way for roof illuminations installation
Installation of PVC conduits in columns at the Customs 0.00 and Police 0.91
Installation of Switch outlets at the Mail 0.15 room. (Grid 3&4, D&F)
11/ June /2019
NOTE:
There has not been any installation works at the cargo building today but the contractor has prepared
a platform/scaffolds and utilities to be installed the following day.
Installation of PVC conduits for Switch Boxes at the HUM 0.66. (Grid 1&2, G&H)
Installation of Distribution board boxes at the Stuff control 0.22 and Supervisor 0.23 areas. (Grid 4&5,
B&C). The boxes are of dimensions 400x200mm and at a distance of 400mm from the beam
Casting PVC conduits in columns the Forwarder/integrator 0.82. (Grid 1&2, D&G)
13/ June /2019
Casting slab and beam with conduits, distribution boxes, intelligent photoelectric smock detector
outlets and Fire Alarm systems at the Counter room 0.20, Waiting room 0.21, Cargo office 0.19,
Disabled toilet 0.37, Staff control 0.22 and supervisor room 0.23. (Grid 2&5, A&C)
WORK PROGRESS UPDATES
NOTE:
Values in Red implies slow progress below 50%.
• Distribution boxes area seen in the ground floor slabs drawings (17973-ELE0-DRW7-
CAR-200) but have checked on site and not seen them. (Grid 1&3, D&D)
• Roof Light Protecting layout (71973-ELE0-DWR7-CAR-600) shows that copper trips will
be connected to all columns to be grounded but on site they are not connected to all
columns.