Вы находитесь на странице: 1из 53

Dar Al-Handasah Consultants

Cargo Building Electrical

25/may/2019

Checking dimensions of the recess floor boxes.


(customs and police area), Grid 1&2.
Checking the Disabled Toilet.
The height of the two one-way switches is 135mm.
The floor confirmed tiled from the architectural drawing.
(Drawing no.719730- AARco-DRW1-CAR-510).
Checking installation of switches at (HUM 0.18, VAL 0.11 and cold room emergency
hath), Grid 3&4, H&J. Socket heights measured to 130mm.
Checking Toilet Hand drier 135mm.
Floor confirmed tile from architectural drawing.

Checking Outlet-Security at the emergency exit (Grid 5&6, F&G).


The height from floor measure as 248mm.
Dar Al-Handasah Consultants

Cargo Building Electrical

26/may/2019

Casting conduits that rum from bottom slab through columns for Mail 0.15 and VUN 0.17.(Grid 2&3,
D&G)

Installing 20A switch (Height 130mm) and One-way switches (Height 130cm).
(Grid 3&4, G&H)
Installing 16AMP socket for air conditioning (Height 240cm) for the VUN 0.17.(Grid 3&4, G&H)
27/may/2019

Dar Al-Handasah Consultants

Cargo Building Electrical

Casting recess floor boxes in ground slab at the Customs and police area
Installation of socket boxes (Height 130mm) at supervisor 0.23 (Grid 4&5, A&C)
Relocating the 13AMP Toilet Hand Drier socket at Disabled toilet (from 135mm to 105mm Height)
Relocating the one-way switch boxes at the Disabled toilet from 135mm to 105mm Height.
28/may/2019

Dar Al-Handasah Consultants

CARGO BUILDING EMERGENCY LIGHTING BOX INSTALLATON

ITEM TOTAL NUMBER TO BE INSTALLED NUMBER INSTALLED


EMERGENCY LIGHTING BOX 43 11
PERCENTAGE PROGRESS = (11/43) X100 = 25%

ACTIVITIES ON SITE

Casting conduits in which run from ground slab to column at Staff control 0.70 and Supervisor 0.71
(Grid 1&2, A&C)
Daily Site Report
Dar Al-Handasah Consultants
Cargo Building Electrical
29/may/2019
Checking position and alignment of light junction boxes at the Battery charging room. (Grid 5&6
,F&H)

Checking the exact location of the light boxes at the battery charging and work shop (Grid 5&6, F&H)
Checking Cargo building installation of metallic rooftop lighting conduits
Daily Site Report
Dar Al-Handasah Consultants
Cargo Building Electrical
30/may/2019
Checking positions and location of Intelligent Multi Sensor Fire Detectors at the Battery charging area.
(Grid5&6, F&H)
Checking positions and location of Intelligent UV/IR Flame Detectors at the Battery charging area.
(Grid5&6, F&H). They are installed exactly attached to the upstand beam
Checking Elevation/Heights of Outlet-Security (CCTV Cameras) at battery charging area (Grid5&6,
F&H). The height measured from site as 3.0m.
Checks before casting proceeds:
• Connections/wiring systems are put as per the wiring drawing
• Location and positions of Distribution boards before casting
• Location and position of CCVT Cameras and other wall utility boxes
Daily Site Report
Dar Al-Handasah Consultants
Cargo Building Electrical
31/may/2019

Installation of metallic conduits and junction boxes for external lighting at the canopy side along Grid
A
Installation of Available Outlet Over door box at the Mailroom (Grid 5&6, E&G). The height from to of
door way measured as 0.25m as captured in the photo.
Installation of lighting boxes and Multi Intelligent Sensors for fire detection at the Workshop area.
(Grid 5&6, G&J)
01/June/2019

Dar Al-Handasah Consultants

Cargo Building Electrical

Installation of metallic conduits for roof lighting along Grid A


Installation of conduits and box outlets at the MAIL 0.64, VUN 0.65 and DIP 0.63 (Grid 1&3, D&G).

Remarks:

it rained in the afternoon which led to discontinuity of works at the rooftop.


02/ June /2019

Dar Al-Handasah Consultants

Cargo Building Electrical

Installation of metallic conduits for roof lighting along Grid 6


CCTV camera box outlets progress Updates

Number to be Installed 56
Number Installed 21
Percentage Installed (21/56) x100 = 36%
03/ June /2019

Dar Al-Handasah Consultants

Cargo Building Electrical


Installation of lighting and security conduits and outlets at the Toilet and VAL 0.10 Area (Grid 5&6,
G&I)

Socket outlet progress Update


Number to be Installed 145
Number Installed 26
Percentage Installed (26/145) x100 = 18%
05/ June /2019

Dar Al-Handasah Consultants

Cargo Building Electrical


Installation of intelligent photoelectric smoke detectors and Intelligent Multi-sensor fire detectors at
Toilet and VAL 0.10 area respectively (Grid 5&6, I&K)

Installation of metallic conduits at the roof walkway for roof lighting system
Installation of metallic conduits for external lighting at the Canopy along Grid K

Casting PVC conduits in beams and columns at the MAIL 0.64, VUN 0.654 and DIP 0.63(Grid 1&3,
D&H)
Installation of distribution two (2) box outlets, one at the Battery charging area and the other at the
workshop. The dimensions are 24x38cm and 28x43cm. (Grid 5&6, G&H)
06/ June /2019

Dar Al-Handasah Consultants

Cargo Building Electrical

Casting slab and beams with PVC conduits, Distribution boxes and box outlets at the Battery charging,
workshop, toilets and VAL 0.10 Areas. (Grid 5&6, E&J).
07/ June /2019

Dar Al-Handasah Consultants

Cargo Building Electrical

Installation of Lighting and Fire detection alarm system conduits and boxes at the Supervisor 0.23,
Staff control 0.22, Cargo office 0.19, Waiting room 0.21 and Counter room Areas. (Grid 3&5, B&C)
Note: Today the contractor has worked half day and work is to proceed tomorrow.
10/ June /2019

Dar Al-Handasah Consultants

Cargo Building Electrical

Installation of metallic conduits at the roof walk-way for roof illuminations installation

Installation of PVC conduits in columns at the Customs 0.00 and Police 0.91
Installation of Switch outlets at the Mail 0.15 room. (Grid 3&4, D&F)
11/ June /2019

Dar Al-Handasah Consultants

Cargo Building Electrical

NOTE:
There has not been any installation works at the cargo building today but the contractor has prepared
a platform/scaffolds and utilities to be installed the following day.

Scaffolding for works at higher grounds


Sockets introduced to be installed after scaffolds erection in the next work sessions.
12/ June /2019

Dar Al-Handasah Consultants

Cargo Building Electrical

Installation of PVC conduits for Switch Boxes at the HUM 0.66. (Grid 1&2, G&H)

Installation of Distribution board boxes at the Stuff control 0.22 and Supervisor 0.23 areas. (Grid 4&5,
B&C). The boxes are of dimensions 400x200mm and at a distance of 400mm from the beam
Casting PVC conduits in columns the Forwarder/integrator 0.82. (Grid 1&2, D&G)
13/ June /2019

Dar Al-Handasah Consultants

Cargo Building Electrical

Installation of IT and power conduits conduit at the roof walk way


14/ June /2019

Dar Al-Handasah Consultants

Cargo Building Electrical

Casting slab and beam with conduits, distribution boxes, intelligent photoelectric smock detector
outlets and Fire Alarm systems at the Counter room 0.20, Waiting room 0.21, Cargo office 0.19,
Disabled toilet 0.37, Staff control 0.22 and supervisor room 0.23. (Grid 2&5, A&C)
WORK PROGRESS UPDATES

ITEM LOCATION Number Number to % progress


installed be installed
ONE-WAY SWITCH GROUND FLOOR 103 153 67

TWO-WAY SWITCH GROUND FLOOR 14 20 70

INTERMEDIATE SWITCH GROUND FLOOR 3 3 100

EMERGENCY LIGHTING BOX GROUND FLOOR 12 43 28


OUTLETS
CCTV CARMERA BOX UTLETS GROUND FLOOR 22 56 40

SOCKET OUTLET BOXES GROUND FLOOR 32 145 22

DISTRIBUTION BOX OUTLETS. GROUND FLOOR - - -

LIGHTINING PROTECTION ROOF 19 101 20

LIGHTINING PROTECTION GROUND FLOOR 20 20 100

ROOF AND EXTERNAL FAÇADE ROOF 30 30 100


SECURITY LIGHTING PROVISIONS
INTELLIGENT UV/IR FLAME GROUND FLOOR 2 4 50
DETECTOR OUTLET
INTELLIGENT MULTI SENSOR FIRE GROUND FLOOR 12 76 15
DETECTOR OUTLET
INTELLIGENT PHOTOELECTRIC GROUND FLOOR 16 52 30
SMOCK DETCTOR OUTLET

NOTE:
Values in Red implies slow progress below 50%.

• Distribution boxes area seen in the ground floor slabs drawings (17973-ELE0-DRW7-
CAR-200) but have checked on site and not seen them. (Grid 1&3, D&D)

• Roof Light Protecting layout (71973-ELE0-DWR7-CAR-600) shows that copper trips will
be connected to all columns to be grounded but on site they are not connected to all
columns.
Dar Al-Handasah Consultants

CARGO BUILDING LIGHT SWITCH BOXES INSTALLATON

27/may/2019

SWITCH TYPE TOTAL NUMBER TO BE INSTALLED NUMBER INSTALLED


ONE-WAY SWITCH 153 102
TWO-WAY SWITCH 20 12
INTERMEDIATE SWITCH 3 3
TOTAL=176 TOTAL=62

PERCENTAGE PROGRESS = (62/176)X100 = 35%