Академический Документы
Профессиональный Документы
Культура Документы
In Fig. 2 the principle design of GIL is shown. The outer enclosure (1) is
made of aluminum and holds the insulation gas with an overpressure of up to
0,8 MPa inside the GIL.
17
This guide will focus on the on-site assembled, because the prefabricated and
tested sections are typical of GIS installations.
• The onsite assembled GIL is built of minimal components (enclosure and
conductor pipe), which are delivered directly from the sub-supplier to site,
where they are prepared for final assembly.
• This reduces the risk of transport damages, but also requires more
temporary/lay down space close to the installation site.
59
General
IEEE Std C37.122 and IEC 62271-204 define three types of tests for GIL: type
(design) tests, routine tests, and commissioning tests.
Short Circuit test (63 kA)
High voltage test (420 kV Um)
73
Pressure
switch
Pressurized
zone
Connects to
gas
compartment
87
A B
GPS or equivalent synchronisation
FMK signal
FMK
Internal Internal
clock clock
PCU PCU
I/O I/O
module module
Process bus
Typical installations
Schluchsee, Germany
Design ratings:
Features:
The installation connects a peak loading hydropower plant to the 420 kV
transmission system. The GIL is installed in a tunnel that was laid through a
mountain, and operated at rated currents during pumping and peak load
generation operations. The GIL has been in continuous, reliable operation
since 1976.
109
Typical installations
Schluchsee, Germany
Typical installations
Nagoya (Shinmeika-Tokai line)
Design ratings:
Features:
The 275 kV GIL is constructed in weded design with pure SF6 as a insulation gas. The
very high current rating of 6300 A shows the main feature of GIL for high power
transmission.
The GIL is laid on steel structure in middle of the tunnel and a rail system provides fast
transportation for personnel and material in the 3,3 km long tunnel.
The GIL transmission line is seperated in gas compartments by gas tight cast resin
insulators, equipped with gas density sensors for monitoring the GIL in operation.
112
Typical installations
Nagoya (Shinmeika-Tokai line)
Typical installations
Geneva, Switzerland (Palexpo)
Design ratings:
Features:
In this application, two circuits, totaling 3680 m were installed using an SF6/N2
gas mixture. The GIL has a bending radius of 700 m, accomplished using no
elbows, and connects to an overhead line at the Geneva Airport. The GIL was
installed in 2001, and remains in service today. This GIL was installed using a
prefabrication tent at site.
The connection of the GIL section is made by welding the enclosure and
conductor pipes using an automated orbital welding machine to provide gas
tight welds.
115
Typical installations
Geneva, Switzerland (Palexpo)
View into the tunnel with two GIL three phase systems fixed to the
tunnel wall (left) and delivery of GIL sections to the assembly tent (right)
117
Typical installations
China (Laxiwa Hydroelectric Power Plant)
Design ratings:
Features:
This application was installed inside a mountain for a hydroelectric power
plant to reach the 800 kV transmission system. It consisted of a 200 m vertical
shaft, as well as a 300 m horizontal tunnel.
Two three phase GIL system are installed to the tunnel walls by using steel
structures. To follow the tunnel directional change angle elements are used
for the GIL. The vertical shafts are equipped with the GIL standing on the
ground floor and connected to the wall.
118
Typical installations
China (Laxiwa Hydroelectric Power Plant)
Typical installations
Vicksburg, Mississippi, USA (Baxter Wilson Power Plant)
Design ratings:
Features:
This application consists of a single circuit GIL with SF6 to air bushing at each
end of the line. Total length is 1250 m. This was installed in 2001, and was
decommissioned in 2009. The bus was sent back to the factory and
reconditioned for use at a different site by the owner.
122
Typical installations
Vicksburg, Mississippi, USA (Baxter Wilson Power Plant)
Views of the GIL route to connect overhead lines to the power plant
124
Typical installations
Riyadh Saudi Arabia (Power Plant #9)
Design ratings:
Features:
GIL was selected in this application for high reliability in a demanding environment,
high power transfer capability, low losses, and simplified installation requirements.
The GIL is about 17 km and connects eight separate lines between the step-up power
transformers and the plant’s 420 kV GIS. The GIL is installed at heights between 7 m
and 9 m on steel supports.
The GIL design features include: extruded aluminum alloy tubes with welded flanges
for bolted connections, conical insulators with long creepage distances for conductors
support and compartment partitioning, and rollers fixed on steel supports to allow the
free movements of the enclosures when exposed to thermal variations. An outdoor
moveable tent allowed the enclosures to be assembled in a manner that avoided
airborne contamination in dusty and windy conditions.
125
Typical installations
Typical installations
North Warwickshire, England (Hams Hall)
Design ratings:
Features:
This GIL connection is through an existing AIS 420-275 kV substation, and is
partly above ground (within the substation) in a vertical formation and partly
in covered concrete trenches (outside the substation).
Features of this design include: low wear contacts, use of particle traps
around contacts and in the enclosures, conical insulators with long creepage
distance, connection between enclosures by welding on site, gas monitoring
by electronic system using digital serial connections measurement, and UHF
sensors for partial discharge measurement.
128
Typical installations
Typical installations
Direct buried
Design requirements:
132
Typical installations
Jersey City, Hudson Switching Station
View into the trench with one three phase GIL system (left)
and angle elements (right)
164