Addendum No. 2
May 17, 2019
School District No. 20 (Kootenay – Columbia)
RFP2019-SHSS-Service 600V

This Addendum is issued prior to Tender Closing Date, in accordance with the
Tender Documents and shall be considered an integral part of the Contract
Documents, read together with the Drawings, Specifications and Addenda
previously issued and with all subsequent Addenda.
1. Invitation to Tenderers
No change.

2. Instructions to Tenderers
Tender closing date has been changed to Thursday, May 30 at 11:00am.

3. Form of Tender
No change.

4. Form of Agreement
No change.

5. Supplementary General Conditions


No change.

6. Supplementary Specifications
No change

7. Reference Material
No Change

8. Drawings
.1 On 3003-E2(EX) two panels fed from DC-B are both labeled “SA” (Upper
right of drawing). These are panels “HH” and “KK” as shown on 3003-E2.
.2 On 3003-E2, cable sizes for TX1-F1 and TX2-F2 should be swapped. TX1-
F1 is 3x3C#250 and TX2 is 2x3C#350.
.3 On 3003-E2(EX) (Left side of drawing) cable P4 is rerouted into new Panel
SWB-2, not “Panel ##”.

9. General Information
No Change.
School District No. 20 Board Office
2001 – 3rd Avenue
Trail, BC V1R 1R6
t. 250.368.6434 | f. 250.364.3470

10. Questions received:


Q: What kind of flooring was installed last year?
A: Flooring was installed by GW floors. Any replacement flooring would need to
be installed by GW floors. The school currently has some spare flooring that
could be used to replace a small damaged area.

11. Items to note:


.1 Any new cables from SWB-2 are to be sized to the maximum load that
each new feeder breaker could provide.

Please ensure receipt of this Addendum is acknowledged on the Form of Tender.

Ready Engineering (BC) Corp.

Dave McIntosh, AScT


Contract Administrator