Вы находитесь на странице: 1из 16

J Intell Manuf (2012) 23:109–124

DOI 10.1007/s10845-009-0289-3

Integrating lean and other strategies for mass customization


manufacturing: a case study
Brandon Stump · Fazleena Badurdeen

Received: 6 December 2008 / Accepted: 30 June 2009 / Published online: 17 July 2009
© Springer Science+Business Media, LLC 2009

Abstract Mass customization (MC) manufacturing zation for the customer. Its limitation is the low efficiency
requires high flexibility to respond to customer needs in a and long lead times. On the other hand mass production and
timely manner. Lean manufacturing principles can be easily the moving assembly line pioneered by Ford (1988) can be a
applied to situations with low levels of MC. However, as the very efficient means of producing in large volume. However,
degree of customization increases and customer involvement the push production philosophy can lead to excessive inven-
occurs earlier in the design and fabrication stages, the direct tory and waste and is inefficient for high variety manufactur-
application of lean principles to maintain flow and low levels ing. The Toyota Production System (Ohno 1988), introduced
of inventory becomes difficult. This paper presents a frame- to the West as lean manufacturing (Womack et al. 1991),
work to show how other strategies such as Quick Response applies pull production concepts linking the shop floor to
manufacturing/POLCA, Theory of Constraints, Flexible/Re- the customer, thereby greatly reducing inventory, throughput
configurable Manufacturing Systems, etc. can be integrated times, lead times, etc. This practice enables manufacturers to
with lean in MC environments. A case study of boat mass add more variety to meet customer requirements while still
customizer is then used to demonstrate how their operations largely being dependent on standardized processes (Womack
are transformed by for more efficient MC. Simulation mod- et al. 1991).
els are used to compare pre- and post-improvement perfor- The fragmentation of the previously stable and homo-
mance. geneous markets in the recent years, where customers are
demanding individually customized goods and/or services
Keywords Mass customization · Make-to-order manufac- has led to the emergence and increasing popularity of mass
turing · Lean manufacturing · Pull · Kanban · CONWIP customization (MC) (Pine 1993). MC can be defined as provi-
sion of individually customized products (or services)
through the use of flexible and highly responsive manufac-
Introduction turing systems (Pine 1993) at a cost near that of mass pro-
duced items (Da Silveira et al. 2001). This combination of
The process of providing goods and services to meet cus- mass production cost and efficiency with individual custom-
tomer need, and the strategy contained therein has been con- ization seems contradictory and unrealistic. However, com-
stantly changing and evolving over the past century, making panies such as Dell, Motorola, Paris Miki, Bally Engineered
great strides in efficiency, but also increasing in complex- Structures, and many others have been pursuing MC success-
ity. This evolution of manufacturing paradigms can be easily fully (Selladurai 2004; Pine 1993). Each of these companies
modeled by the automobile industry. offer products with different degrees of customization and
Automobile manufacturing began with the craft model they therefore possess varying capabilities to offer the MC
of production which provides a great deal of individuali- products.
The need for efficient and flexible manufacturing systems
combining push and pull strategies to deliver mass custom-
B. Stump · F. Badurdeen (B)
University of Kentucky, Lexington, KY, USA ized products has been briefly discussed in the literature (Pine
e-mail: badurdeen@engr.uky.edu 1993; Da Silveira et al. 2001). The potential of applying lean

123
110 J Intell Manuf (2012) 23:109–124

manufacturing (LM) concepts to meet MC manufacturing


requirements has also been raised. While some lean prac- Best Quality – Lowest Cost – Shortest Lead Time – Best Safety –
High Morale
tices are easily applicable others are more difficult to imple-
ment particularly when the degree of MC increases. On the Just-in- Jidoka
other hand, the potential of using many other strategies such Time People & Teamwork (in station
quality)
as Thoery of Constraints (TOC), Flexible/Reconfigurable 1. Takt Time 1. Separate
Manufacturing Systems (FMS/RMS), agile/leagile, Quick 2. Continuous Continuous
man from
machine
Response Manufacturing (QRM) and POLCA to manage Flow Improvement
2. Andon
the complexities of manufacturing have also been discussed. 3. Pull
Systems 3. Problem
However, the potential of applying lean manufacturing prac- 4. SMED Waste Reduction
Solving

tices in different MC environments or the potential of inte-


grating these various other strategies for MC manufacturing Leveled Production (heijunka)
has not yet been addressed in detail.
Stable and Standardized Processes
This paper critically reviews the use of lean manufactur-
ing in the context of its application to MC manufacturing. Visual Management

Various other strategies are qualitatively examined to deter- Toyota Way Philosophy

mine their strengths and weaknesses for application in dif-


ferent MC environments when lean may be inadequate. A Fig. 1 Toyota house (Liker 2003)
theoretical framework is then proposed for the application of
lean and other strategies to combine push and pull mecha-
nisms, as relevant, to provide the flexibility needed in for MC. end customer or the next process operator in line (Bicheno
A customized boat manufacturing company’s operations are 2000; Wantuck 1989; Shingo 1988). However, regardless
then studied, improvements proposed, modeled and evalu- of the resolution of the examination, the lean manufactur-
ated through simulation in an effort to validate and improve ing system operates with a single (or a few) pull signal(s)
the framework. (Liker 2003; Ohno 1988). A monument type process within
a plant may feed multiple production lines, but conceptually
the amount of signals it must fulfill is still finite and relatively
Lean manufacturing overview small.
The use of SMED (single minute exchange of dies) tech-
Lean manufacturing is based on the Toyota Production Sys- niques enable the rapid changeover for mixed model produc-
tem developed by Toyota which focuses on eliminating waste, tion and continuous flow. Jidoka or quality at the source, for
reducing inventory, improving throughput, and encourag- example through the use of poke yoke or mistake proofing,
ing employees to bring attention to problems and suggest ensures that defectives are not passed downstream. Elimi-
improvements to fix them (Womack et al. 1991). Figure 1 nation of all forms of waste and continuous improvement
illustrates “The Toyota House,” showing the basic building through problem solving are main elements of lean manu-
blocks of lean systems operations (Liker 2003). facturing.
In lean manufacturing leveled Production (heijunka) is Kanban and CONWIP (Controlled Work-in-progress) are
used “… to smooth out the perturbations in day-to-day order the two prominent control methods used for material flow
flow…” (Womack and Jones 1996) so that mixed model management. These systems seek to cap inventory and
assembly takes place, as opposed to batch manufacturing. increase the ability for a set of manufacturing processes to
Process standardization is achieved with standardized work flow (Co and Jacobson 1994; Takahashi et al. 2005). Kanban
sheets that outline the steps for each process (Monden 1998). applies the pull system while CONWIP seeks to combine
Visual management of information to provide up-to-date elements of push and pull strategies which allows it to buffer
conditions are achieved through the application of 5s (sort, work content variation between products and processes and
straighten, shine, systematize, and sustain) and Visual Con- better handle the issue of shifting bottlenecks due to variety
trols (e.g.: labeling, color coding, and visual information sys- (Takahashi et al. 2005). A comparison of these production
tems). Just-in-time production is paced at the takt time and control strategies can be found in Gaury et al. (2000).
the pull system helps maintain continuous flow of products at Thus, lean manufacturing implies a shift in the very cul-
all stages. This enables reducing lead time and throughput, as ture of an organization; it is a philosophy and way of doing
products will not wait in large lines of WIP, but move quickly business. It must also be noted that, though the hard side
and directly to the next process in the order of arrival. of lean manufacturing—the tools and techniques—receives
The pull system relies on the downstream customer to sig- more attention in literature, the soft side—respect, team work,
nal that production should commence, whether they be the challenging work environment, as presented in the Toyota

123
J Intell Manuf (2012) 23:109–124 111

Way (2001)—is more important in sustaining the operational Type of Modularity


benefits over the long-term.
Design Fabrication Assembly Use

Design
Point of Customer Involvement
Mass customization overview and classification systems
1 2
MC follows a design-sell-make model where the finished Fabricators Involvers

Assembly Fabrication
product is not manufactured until end-customer order is
received as opposed to the design-make-sell model in tradi-
tional manufacturing (Badurdeen and Liyanage 2009).
Essentially, with MC an order does not exist in the system
until the end customer submits it (Lampel and Mintzberg 3 4
1996). This is in contrast to conventional lean manufacturing Modularizers Assemblers
where (though referred to as a make-to-order system) items

Use
are made to satisfy needs of immediate customers, not the
final consumer. MC therefore involves bypassing the various
intermediate tiers in the supply chain between the manufac- Fig. 2 Types of mass customization (Duray et al. 2000)
turer and end consumer, to directly interact with the latter.
Due to this design-sell-make approach, system operation
for MC manufacturing is very different from the single pull
Involvers engage with customers during the design and fab-
scenario of lean manufacturing; the MC manufacturer
rication stages while using modularity in the assembly and
receives many pull signals from individual consumers. The
delivery stages. Customers are involved early in design, but
effect of these multiple pull signals on operations can be sig-
this design must be created from a selection of standardized
nificant and depends on the extent and type MC adopted by
modules, as no new modules will be designed for them. Fab-
a company.
ricators involve the customer and make use of modularity
Various models have been put forth to classify mass cust-
during the design and fabrication process. Customers cre-
omizers depending on different criteria (Pine 1993; Lampel
ate their custom design, but modularity can be used to some
and Mintzberg 1996; Gilmore and Pine 1997; Duray et al.
degree to create similarities in components. Thus fabricators
2000). Most of these models use a single dimension—the
represent MC with the highest degree of customization in the
point of customer involvement in the value chain to create
product.
the customized product (e.g.: design, fabrication, assembly,
The Duray et al. (2000) model is more detailed and able
and distribution, etc.)—to classify MC manufacturers. The
to identify MC in the early stages of the value chain. Fur-
point of customer involvement is an important dimension
ther, though the importance of modularity for MC was dis-
that reflects the extent to which manufacturing operations
cussed earlier by Pine (1993) it is only fully utilized by Duray
are affected due to MC. However, this alone is not suffient
et al. (2000). As this model provides a more comprehensive
to capture the system complexity that results from different
classification in identifying customer involvement as well as
types of MC. Duray et al. (2000) presented a model that uses
modularity, has an early customer involvement focus than
two dimensions, point of customer involvement and the type
previous models and therefore has a stronger classification
of modularity used in the products to classify MC manufac-
strength, as shown in Fig. 3. Therefore, it will be used in
turers. Modularity is a key concept for efficient MC (Pine
the following sections to assess the capabilities required for
1993) and can be present in the product, process or both
different types of MC.
(Swaminathan 2001); it is a means to provide variety and
speed in delivering the MC products (Duray et al. 2000).
Duray et al. (2000) divide mass customizers into four Post-fabrication and pre-assembly customization
groups: assemblers, modularizers, involvers, and fabricators
(Fig. 2 ). Assemblers involve the customer and use modular- The model in Fig. 2 enables creating two more general cate-
ity in the fabrication and assembly stages, enabling the cus- gories based on the similarities between fabricators/involvers
tomer to select different combinations of standard features. and modularizers/assemblers and the impact on manufactur-
Modularizers are characterized by involving the customer ing operations. These categories will hereafter be referred to
in the assembly and delivery stages, but using modularity in as high-level mass customization and low-level mass custom-
the design and fabrication stages. The producer uses standard ization, respectively as shown in Fig. 4.
modules to design and fabricate a base module, and specific With low-level MC, individualization is achieved by
customer needs are incorporated in assembly and delivery. assembling (and/or packing and distributing) pre-fabricated,

123
112 J Intell Manuf (2012) 23:109–124

Fig. 3 Mass customization


classification model comparison

Fig. 4 High-level and High-Level Mass


low-level mass customization Customization
Design
∑ Highly flexible mfg.
sys.Config.
∑ Process modularity
more important.
∑ Production
planning more
complex.
∑ Increased reliance
Fabrication on teamwork and
learning.

Low-level Mass
Customization

∑ Less need for Assembly


flexible mfg.sys.
Config.
∑ Less need for
process
modularity.
∑ Efficient production
planning more
viable.
∑ Teamwork and Distribution
continuous
improvement

standard components in a customized manner. Thus with Though diverse orders are received from end-consumers
both assemblers and modularizers the design and fabrica- upstream design and fabrication processes can operate with
tion stages of the value chain remain unaffected by customer single pull signals for standard components from downstream
involvement, warranting the combined discussion of these assembly (Fig. 5).
two strategies. With high-level MC, which includes the involver and fab-
Lean manufacturing practices are highly applicable in such ricator strategies, customer involvement occurs in either the
low-level MC where standardized modules can be produced design or fabrication stages; engaging the customer early in
to forecasted demand (in the design and fabrication stages). the value chain (and imposing multiple pull signals on the

123
J Intell Manuf (2012) 23:109–124 113

Fig. 5 Low-Level mass


customization

Design Fabrication Assembly Distribution

OR
Legend
Customer
Interaction

Pull Signal End-Consumer

upstream design/fabrication processes) makes it difficult to production and logistics planning (Da Silveira et al. 2001;
apply lean manufacturing practices (see Fig. 6). The diffi- Zipkin 2001; Selladurai 2004), and organizational learning
culty to forecast demand and plan for work content adds to and continuous improvement (Barnett et al. 2004; Pine 1993).
the complexity of manufacturing for this form of MC. Flexible manufacturing system configuration: Flexibility
of the manufacturing system is a key success factor for a mass
customizer (Zipkin 2001; Moser’s 2007); a company cannot
Mass customization competencies expect to benefit from MC without a highly flexible and adap-
tive manufacturing system configuration. There have been
MC is a complete paradigm shift from traditional manufac- some improvements in strategy over dedicated manufactur-
turing. Thus identifying appropriate manufacturing system ing systems (DMS) (Koren et al. 1999; Mehrabi et al. 2000).
configurations and evaluating the use of lean manufacturing Flexible Manufacturing Systems (FMS) often characterized
principles and practices, mandates a review of the competen- by expensive computer controlled machines are capable of
cies necessary to successfully implement the strategy. While producing a variety of products with variable volume mixes
considerable literature exists on MC and related areas, there (Koren et al. 1999). However, they often tend to have lower
have been very few studies that collectively addressed all the throughput than DMS, are costly and are designed to operate
capabilities needed for MC. Zipkin (2001) identified three at full capacity from purchase (Koren et al. 1999; Mehrabi
major capabilities for successful MC as elicitation, process et al. 2000).
flexibility, and logistics. Moser’s (2007) presented a more Reconfigurable Manufacturing Systems (RMS) make use
comprehensive model to classify MC competencies, defin- of modularity both in machine and software to allow for quick
ing eight distinct categories, and exemplified the impact of capacity adjustment, low changeover/setup between prod-
these competencies. Figure 7 provides the competency model ucts, rapid adaptability of software, and quick ramp up to new
put forth by Moser’s (2007). product production (Mehrabi et al. 2000). Another approach
Moser’s (2007) model is more descriptive, identifying the proposed by Badurdeen and Masel (2007) is the design of
competencies needed in manufacturing and support activi- modular minicells to create small cells for the customiz-
ties as well, while Zipkin (2001) mainly focused on primary able options. Products and parts are then routed through the
activities of the value chain. However, both models cover necessary minicells, while bypassing the unnecessary ones
the wide range of activities that must come together for MC (Badurdeen and Masel 2007). Irrespective of the configura-
products to be marketed, configured, manufactured, and tion used, for successful MC, the system must be a flexible
delivered. Because the emphasis in this paper is on imple- and highly responsive manufacturing system configuration
menting lean manufacturing—together with other strategies, for successful MC.
as needed—for MC, manufacturing competencies are more Process modularity: Modularity is another key concept
relevant and discussed further in the following sections. for successful MC that enables creating some commonal-
Based on the literature and empirical evidence, the MC ity between products, allowing for higher efficiencies to be
manufacturing competencies can be broadly classified into achieved while permitting customization. Ulrich and Tung
the following: flexible manufacturing system configuration to (1991) define modularity as “… the use of interchangeable
manage mass and individual production (Koren et al. 1999; units to create product variants.” On the other hand, a mod-
Mehrabi et al. 2000; Berman 2002; Zipkin 2001), process ular process allows sub-processes to be chosen based on the
modularity (Swaminathan 2001; Selladurai 2004), centralized specific product characteristics and be routed accordingly

123
114 J Intell Manuf (2012) 23:109–124

Fig. 6 High-level mass


customization

Design Fabrication Assembly Distribution

OR

Legend
Customer
Interaction

End-Consumer Pull signal

Fig. 7 Mass customization VIII. Process


competencies (Moser’s 2007) documentation and IT
support

VII. Management of
I. Customer Integration flexible organization
and processes

II. Application of Mass VI. Management of


product configuration Customization mass and individual
systems Competencies production

III. Employment of V. Central production


product modularity and logistics planning

IV. Product variant


management

(Swaminathan 2001; Selladurai 2004). Postponement, along The previous sections briefly discussed the various man-
with modularity in both product and process, can be used to ufacturing competencies needed for MC. It must be noted
enable a higher degree of customization (Berman 2002). that as the degree of MC varies (high-level versus low-level
Centralized production and logistics planning: Crucial to MC) so does the extent to which these competencies effect
MC is the elicitation of customer order information production.
(Zipkin 2001) and transmittal of those specifications to the
shop floor for quick turnaround. Given the variability in Applying lean manufacturing for mass customization
customer requirements proper determination of capacity
requirements, accurately predicting over/under utilization of Boynton et al. (1993) claim that becoming lean is an impor-
equipment and taking measures to control capacity will be tant step for a company wishing to transition to MC. While
needed to control inventory levels and maintain predictability the theme of viewing lean as a transitional step to achieving
(Swaminathan 2001). MC occurs with some regularity in the literature, little evi-
Organizational learning and continuous improvement: dence is available on the actual integration of lean principles
MC environments are characterized by shorter product for MC operations. Several works refer to lean manufacturing
life-cycles (Selladurai 2004) and the dynamic work content in a build-to-order or make-to-order environment, but these
requires highly skilled workers capable of working in decen- essentially mean building only to demand as in a pull sys-
tralized and cross-functional teams (Pine 1993; Mehrabi et al. tem (Michel 2002; Clarke 2005). Make-to-order operations
2000). A learning organization with intellectual workers differ from MC in that with the latter no work is done until
(Mehrabi et al. 2000) who continually strive to gain further the customer configures their individual product and delivers
knowledge of product and process is essential for MC. their specifications to the manufacturer.

123
J Intell Manuf (2012) 23:109–124 115

From the previous discussions, it is evident that some manufacturing is responsive manufacturing to survive in
aspects of lean manufacturing are directly transferrable to continuously & unpredictably changing environments
MC while others are not. For example the elimination of all (Buyukozkan et al. 2004) it is entirely different to the lean
forms of waste, team work and learning organization, the paradigm, and even MC (Stratton and Warburton 2003); it
practice of continuous improvement, SMED, visual control focuses on fast response throughout the supply chain to miti-
and 5S are important and applicable to all organizations, irre- gate the effects of variability, while MC is focused on deliver-
spective of whether they engage in MC or not. However, ing customized products to individual consumers. By nature,
when it comes to MC manufacturing, the lean capabilities both paradigms are characterized by high variety and uncer-
and tools that are applicable will vary based on the type of tain demand (Krishnamurthy and Yauch 2007).
MC in use. Many studies show that neither lean nor agile supply is
MC is characterized by very low levels of stability and the answer to most production issues; a combination of both
standardization. Due to the high variability of demand and may often be the best solution. This combination has been
difficulty of accurate forecasting, the concept of takt time termed leagile and involves the positioning of a decoupling
becomes less relevant, particularly with higher levels of MC. point in the supply chain (Mason-Jones et al. 2000) to sep-
Thus production leveling and takt pacing becomes a near arate upstream processes which are operated based wholly
impossibility in many MC environments. Further, due to on lean practices from those downstream that are run based
the multiple pull signals for diverse products from individ- on agile approaches (Yusuf and Adeleye 2002; Mason-Jones
ual customers applying pull manufacturing strategies, too, et al. 2000). Given that the customer involvement takes place
is more challenging as the degree of MC increases. While late in the value chain for low-level MC, these leagile strate-
lean manufacturing is more easily adaptable to low-level MC gies can possibly be implemented with a well placed decou-
operations that delay customer involvement until later stages pling point. The best combination of lean & agile strategies to
of the value chain such as assembly or delivery, the use of increase customer responsiveness will depend on the product
lean practices when the customer is involved in the design or and its market.
fabrication stage is much more abstract, and little research
has been done on the subject. Job shop lean
Jidoka, or source quality, is also increasingly difficult
to adapt to MC environments (particularly high-level MC) Job shop lean is a relatively new method in which certain lean
because as products become increasingly customized and manufacturing practices are applied to job shop environments
variety rises, the concept of good quality becomes obscure (Brink and Ballard 2005). The main focus of job shop lean
and quality control on the shop floor is more difficult. While is value stream mapping to gain a system wide perspective.
self and successor checks could still be implemented, with While it is difficult to quantify information such as process-
much lower degrees of standardization in the product and ing times, lead times, etc. in a job shop environment value
process, these checks become less efficient. However, some stream mapping can still provide enough perspective over
degree of source quality can be used in any MC environment. the system to enable the visualization of many wastes (Brink
For example, the characteristics of a quality weld are con- and Ballard 2005; Huang et al. 2005). Other lean principles
stant regardless of where and on what surface the weld is such as 5s, visual management, WIP control through kanban,
placed, and thus can be efficiently controlled with self and and total productive maintenance have found use in job shop
successor checks and other jidoka practices. environments (Brink and Ballard 2005). There is very little
literature available on the actual application of job shop lean
or accounts of successful implementation and the benefits
Other strategies to manage manufacturing flexibility of applying this strategy to custom manufacturing situations.
Also, it is difficult to see where this strategy differs from that
Various other strategies have emerged in the literature to cope of lean manufacturing other than the environment in which
with changing market requirements. An investigation of these it is applied.
in the context of integrating with lean manufacturing for sit-
uations where it is inadequate to meet the MC manufacturing Flexible manufacturing systems/reconfigurable
needs is presented below. manufacturing systems

Agile/leagile manufacturing Flexible/Reconfigurable manufacturing systems (FMS/RMS)


offer flexibility in manufacturing environments often using
Agility is defined as “… using market knowledge and a numerically controlled machines and automated equipment
virtual corporation to exploit profitable opportunities in a (Byrkett et al. 1988; Mehrabi et al. 2000). They are designed
volatile market place,” (Naylor et al. 1999). While agile to combine the flexibility of job shops and the efficiency

123
116 J Intell Manuf (2012) 23:109–124

of high-volume manufacturing lines (Chan and Chan 2004). across all operations in order to gain responsiveness to the
Quick changeover and the ability to handle a broad range of customer and employs the paired cell-overlapping-loops of-
products in an efficient manner can be used to the benefit cards-with authorization (POLCA) for controlling flow and
of any type of MC. While limited to application in equip- inventory in manufacturing environments that face a high
ment intensive environments they can have a profound impact number of complex product routings (Suri 1998; Fernandes
on throughput. As lean manufacturing also advocates setup and Carmo-Silva 2006). POLCA cards are used for a rout-
reduction, the combination of lean on the shop floor with ing between two cells, and are attached to the product upon
FMS/RMS capable equipment will be beneficial to any type entering the first cell in the routing and detached upon leaving
of MC. However, benefits are likely to increase as customer the second cell (Suri 1998) thus controlling inventory levels
integration moves up the value chain towards high-level MC. between each pair of cells and across all product routings as
illustrated in Fig. 9.
Theory of constraints QRM and POLCA appear to be robust systems that can aid
in situations where customization & variety is high and lean
The Theory of Constraints (TOC) focuses on a constraint or manufacturing is unable to meet the MC needs. High-level
bottleneck in the system which determines the throughput MC faces high variety with customer interaction occurring
and can be used as a pacemaker (Goldratt 2004). Control as early as the design stage. Lean principles such as Just-
is established through the drum-buffer-rope (DBR) mecha- in-Time, pull manufacturing, and leveled production fail at
nism, where the constraint is the drum or pacemaker, a buffer this point and inventory control through kanban is likely to
is placed between the drum and the downstream processes to be impossible. Thus, in such situations, the application of
eliminate stoppage of the constraint, and the rope is employed POLCA for inventory control and minimizing lead time is a
to pull product to the bottleneck from the upstream processes key benefit for MC manufacturers. Manufacturers can also
(Klusewitz and Rerick 1996; Goldratt 2004) as illustrated in use POLCA in tandem with kanban, employing POLCA to
Fig. 8. manage routings and inventory between many cells, while
Thus, TOC provides a means of inventory control and sys- kanban controls material flow within the cells themselves
tem pacing on the shop floor. However, literature on quan- (Suri 1994, 1998; Fernandes and Carmo-Silva 2006).
tifying its effectiveness or the integration of TOC with lean While the competencies required for successful MC and
manufacturing is lacking (Steele et al. 2005). While the strat- the principles associated with lean manufacturing are well
egy could be very effective for shop floor management in documented and defined, it is apparent from the literature
some environments it could be difficult to apply in many MC reviewed that there is a need for further investigation into
situations. applying lean manufacturing practices to different MC envi-
MC manufacturers are often faced with high work con- ronments. Overall there is little literature to support or dis-
tent variations due to the make-to-order of individualized count the application of lean manufacturing for MC or the
products (particularly with high-level MC). Thus the system successful integration of other common manufacturing strat-
constraint is likely to shift with high frequency. The DBR egies. Based on the foregoing discussion on types of mass
mechanism can be used with varying bottlenecks by identi- customizers, MC manufacturing competencies needed, and
fying and adjusting the system accordingly (Goldratt 2004). the potential of applying lean manufacturing practices for
However, for MC manufacturers it is likely that the constraint those situations, Fig. 10 presents an integrated framework for
will shift frequently, with a greater impact on low volume applying lean manufacturing and other strategies to different
manufacturers with larger cycle time ranges. Thus while TOC MC environments.
could prove efficient in some MC environments; in others In the figure, the four categories of mass customizers—
the nature of MC will make its application too cumbersome assemblers, modularizers, involvers, fabricators—are shown
(fabricators and involvers, i.e. high level MC). With low- in the middle. The lean manufacturing principles and prac-
level MC the customer interaction takes place later (assem- tices and MC competencies needed are presented at the top
bly stage), variety the work content variation will be lower of the figure. The shading is used to highlight the ease of
than with fabricators and involvers. Thus the bottleneck is applying these lean principles and the extent of the MC com-
likely to more stable, making the application of TOC more petencies required for the MC categories. As indicated, pull
feasible for low-level MC. production techniques with one-piece flow and stable/stan-
dard processes can be easily applied with low-level MC
Quick response manufacturing (assemblers and modularizers). However, as one moves to
the right of the figure, i.e. high-level MC, lean techniques
Quick response manufacturing (QRM) is a manufacturing turn out to be more difficult to implement. The people and
control strategy that has found use in many situations where team work aspect of lean, the soft side, are vital and can be
product variety can be high. QRM seeks to reduce lead times applied by any type of MC; they are shown at the top of the

123
J Intell Manuf (2012) 23:109–124 117

Drum Buffer Downstream


Upstream (Pacemaker Process) (Prevents stoppage of drum) Process
Process

Rope
(Links drum pacing with order release)

Fig. 8 Drum-buffer-rope (DBR) mechanism in TOC

Three Assembly
Cells

Two Fabrication
One Printing Cells
Cells
F1
A1 One Shipping
Cell
P1F1
P1
Loop F1A2
Loop
A2S1
Loop
A2 S1

F2

A3

Fig. 9 Control using POLCA (Suri 1998)

Fig. 10 Theoretical framework for applying lean manufacturing for MC

123
118 J Intell Manuf (2012) 23:109–124

figure. Similarly, while the MC competencies are essential combination of make-to-stock (30%) and make-to-order
for any type of MC, the shading is used to indicate those that (70%) production, the former being sent to dealerships based
become more critical (darker shades) as companies transition on forecasted demand while the latter is configured through
from low-level to high-level MC. customer-dealer interaction.
The framework also shows avenues of integrating QRM, Manufacturing system configuration: The manufacturing
TOC, Agile/Leagile and FMS/RMS in combination with lean system at SCT Boats is set up as a traditional moving assem-
manufacturing for different types of MC. Arrows show bly line with various feeder lines. All feeder lines are func-
which mass customizer(s) a particular strategy is most likely tionally arranged by department. The main components of
to be useful whereas the thickness shows the degree to each boat; the deck and hull, move through lamination, rig-
which it could be useful in relation to other types of mass ging, final assembly and inspection, while components such
customizers. as upholstery and plastics sync up with the product along the
It should be noted that while this framework attempts to way.
give a clear picture of how lean and other manufacturing Process modularity: Process modularity is in use in nearly
strategies can be combined for MC environments, it is by no every process at SCT Boats. While each product is signifi-
means a complete representation of all cases. For instance, cantly different from the other, the subset of steps for com-
the indication that QRM is beneficial for high-level MC is pletion of a particular process is similar, if not the same, for
meant to show that these are the areas where QRM will most each product. For example, in lamination, each boat must
likely be needed. Obviously, the specific applications of these have its mold prepared then be gel coated. The gel coat pro-
strategies will differ on a case-by-case basis. Overall it is an cess involves spraying several different layers of a gel paint
attempt to combine the existing findings into a comprehen- substance into the mold, with each layer being of different
sive framework to aid in further research. color, thickness, and shape. This is the point of variety explo-
sion in the manufacturing process. To re-quote Swaminathan
(2001) and Selladurai (2004), a modular process is “… one
Mass customization case study: SCT Boats where each product undergoes a discrete set of operations
making it possible to store inventory in semi-finished form
In an attempt to validate the framework and assess the poten- and where products differ from each other in terms of the
tial of applying LM and other strategies for MC, a company subset of operations that are performed on them.” The gel
that manufacturers customized high-end boats is chosen for coat and essentially all of the other processes at SCT Boats
study (to maintain anonymity the company will be referred follow this trend.
to as SCT Boats throughout the remainder of the paper). Production planning: The company does not apply any
The competition wakeboarding boat market is a fragmented form of centralized production planning or control. There is
niche market with high-end products sold to customers with no WIP control or a clear picture of cycle times in any of its
varying degrees of customization. SCT Boats is a company processes that could be used to predict capacity requirements.
located in the mid-west region of the US and offers two base This makes dynamic and efficient production planning nearly
model lines of boats; the Mini and the higher end Jumbo. impossible.
Within these lines, there are several different models (6 for Organizational learning and continuous improvement:
Mini and 10 for Jumbo) from which the customer can choose This is an area the company is actively seeking to better them-
from. Within the 16 base models there are many different selves. They have educated team members on the basics of
options for customization, the highest being the boat gel coat lean concepts and assigned lean improvement projects (such
pattern, or paint scheme (not paint color); 37 patterns for as 5S). They have also used these teams to seek more active
Jumbo and 20 for Mini. In addition, there are many other cus- involvement of employees in improvement projects.
tomizable options for each boat, including paint color, engine To fully understand operations at SCT Boats a simplified
options, canvas options, audio/video options, performance (details such as cycle times, setup times, WIP levels and num-
options, trailer options and other miscellaneous options such ber of operators, etc. is not shown) current state value stream
as an automatic fire suppression system all leading to an map (VSM) is presented in Fig. 11. The process begins in
explosion in the variety of products manufactured by SCT the fabrication department where the deck and hull compo-
Boats. nents are moulded. Mould prep is the first operation, where
According to the Duray et al. (2000) model SCT Boats matching deck and hull moulds are selected and taped off
can be classified as an assembler as customers are allowed according to the customizable paint scheme ordered by the
to configure products by choosing from a range of options. customer. After 3 different coats of gel are applied the empty
Standard modules (the product models) are used as a base- cavities are filled with foam to harden for strength, moulds
line and specific customer needs are taken into account in are pulled and sent to grinding to remove excess material and
the assembly and use stages. The company incorporates a holes cut for other components to be added.

123
J Intell Manuf (2012) 23:109–124 119

Skier’s Choice
Monthly Make-to-stock
MRP Production Control
Dealer Orders
Monthly/Quarterly Orders
Weekly Order Buckets
To Stations

Suppliers Weekly Orders Customized Individual Orders Customers

FABRICATION (3 Parallel lines; one deck line, one hull line, one deck/hull line)

Gel/Barrier Core Spray/ Grind/Hole


M o ld P r e p Skinning Bulk
Finish Pull cut
Inspect
Coat

Daily
Daily/Weekly/
Monthly

135 135 45 90 22.5 112.5 90 225


20/35 40/60 40/50 40/50 35/55 30 50/65 40

COMPONENTS FEEDER
Finished
Mold Prep Gel Coat Skinning Pull Goods
Staging
Jumbo Hull
ASSEMBLY & INSPECTION

Receiving
Warehouse Cap & Rail Final Assy

45 180 0 450
20/25 30/40 30/40 20

Jumbo
Deck

UPHOLSTERY

V in y l C u t S e wi n g 135 Pool Test Lake Test Decals Shrink Wrap

Upholstery
Assembly

Mini Deck 180 225 270


35 40 30/40 30/35
Plastic Cut Foam

180
Cap & Rail Final Assy

Mini Hull

LEGEND

Inventory Pull Production Pulse Production


Jumbo Lead Time (best/worst): 2285 min. / 2530 min.
Push Production Manual Information Supermarket
Mini Lead Time (best/worst): 2260 min. / 2550 min.
Material Flow Electronic Information Deliver by Truck

Fig. 11 SCT Boats current state (simplified) VSM

The components department operates in a manner sim- Subsequent to fabrication, the deck and hull components
ilar to fabrication, but creates simpler, smaller parts to be are briefly inspected to repair blemishes and the deck & hull
installed in various stages of production (in fabrication and are also mated to ensure proper fit. From there, boats are sent
final assembly). The department is functionally arranged and to two separate lines (Jumbo and Mini) in the assembly area
consists of several machines commonly found in a wood where decks and hulls run parallel to each other (within each
shop, such as table saws, routers, and mitre saws. This area line) initially to add other interior components such as bilge
creates a large variety of simply shaped plastic pieces which pumps, the engine, and wiring, as well as underwater gear
provide structural support for components added in assembly such as propellers.
and as frames for components made in upholstery. The parts Finally, the deck and hull are mated permanently together
are made to stock and held in store fronts leading to a lot of and the boat undergoes a series of final finish processes
inventory. based on the options specified by the consumer. In the final
In the upholstery department parts are acquired from the inspection stage boats are first taken for pool testing and
plastics store front and assembled into frames based on the then for lake testing. Subsequently, each unit is cleaned, and
specifications of the boat. Foam, which comes roughly pre- final components such as decals and compartment covers are
cut from the supplier, is then glued to the frames and excess added.
foam is removed. Meanwhile, a CNC cutting machine, the As it is there is little control over the system at SCT Boats
only computerized equipment in the plant, cuts out pieces and even less visibility. The amount of WIP on the shop floor
of vinyl based on the size, shape, and color required by the is large in comparison to the daily volume the plant produces,
boat specifications. They are then sorted and sent to a sewing and this WIP amounts to a significant cost given the relatively
department where team members sew the pieces together to high product cost. Also of note is the fact that for the vast
create a skin. Lastly, the skins and frames are matched, and majority of the production process the main body of the boat
the skins are pulled over the frames and stapled before being is in two pieces which must be matched late in the assembly
sent to various stages of final assembly. stage. Obviously if one of these components are not ready the

123
120 J Intell Manuf (2012) 23:109–124

assembly is halted (leading to build up of inventory); how- Theory of constraints: As a mass customizer with high
ever, there is no clear method of sequencing products and variability in work content, SCT Boats faces the problem of
correctly matching the components to the correct boat. inconsistent cycle times in many of its processes. This means
that the constraint is likely to shift on a boat by boat basis.
Applicability of lean & other strategies The ability of TOC to control flow and WIP in the system will
be greatly diminished in this situation of a frequently shifting
In this section a discussion on the applicability of lean and constraint, as it will be very difficult to control the system
other strategies (presented in the framework) to improve the based on a single process when this constraint to throughput
overall flow and reduce lead time at SCT Boats is discussed. is constantly moving. While TOC as a whole is an effective
Based on the product portfolio offered and how the boats method for systems control in manufacturing, the high var-
are produced to meet individual customer needs, SCT Boats iability faced by SCT Boats makes it an unlikely means of
can be classified as an assembler. With an assembler, stan- improving performance.
dard modules are used in the product and customization is Quick response manufacturing: When examining the oper-
achieved by allowing each customer to select different com- ations at SCT Boats it is apparent that all boats undergo the
binations of standard features, based on their specific needs. same product routing from beginning to end, while the work
According to the framework (Fig. 11) this means that lean content at each process along that routing differs from one
manufacturing techniques can be easily applied with pull order to the next. Because routing variation is low, the appli-
production and one-piece flow. Thus, the final production cation of POLCA seems unnecessary in this situation; the
schedule (sequenced) for custom assembled items would be benefits gained are not likely to outweigh the difficulties of
released to assembly where each boat can be put together managing the POLCA system.
based on individual needs. All upstream areas should then The foregoing discussion reveals that SCT Boats is an
deliver standard components to final assembly based on pull assembler but with variety explosion occurring at the early
production. However, the challenge to implement lean man- stages of the manufacturing process. Therefore, the other
ufacturing in this manner at SCT Boats arises due to the strategies are too complex, not suitable or even unneces-
fact that though the components are standard in size, most sary due to SCT Boats’ system configuration, resource needs
other features such as the gel coat scheme and color are all (highly labor-intensive) and production volume/variety.
individually chosen and affect the first two operations in the Therefore, lean manufacturing techniques, with some adap-
manufacturing process—the completed deck and hull are tation to address the specific issues faced by the mass custom-
therefore highly custom parts. Thus, though SCT Boats izer will be most suitable for system improvement. Though
appears to be an assembler, they share some features of fabri- the pull strategy may not work to control flow in all opera-
cators because some components are fabricated after receiv- tions the use of route specific kanbans and CONWIP cards to
ing customer orders. Therefore, the applicability of other apply a combination of pull and push strategies will be most
strategies presented in Fig. 11 are investigated below. appropriate. The framework provided a means to review the
Agile/leagile manufacturing: At SCT Boats the use of production capabilities needed for the MC of SCT Boats and
postponement to decouple production and downstream oper- the applicability of the other strategies for potential integra-
ations is not an option as the variety explosion occurs early tion with lean techniques.
in the process. For this reason, the use of a decoupling point
in the context of the manufacturing operations at SCT Boats,
is not feasible. While agility is certainly a desirable feature Restructuring the operations
for MC to respond to markets, due to the inability to employ
a decoupling point the application of leagile is unviable SCT With SCT Boats the main concern is the improvement of
Boats. product flow and reduction of lead time across the system.
Job shop lean: Due to the production volume and prod- The use of lean principles such as kanban, CONWIP, and
uct variety at SCT Boats restructuring the shop floor as a job just-in-time to facilitate the transition to a lean system is
shop will be highly inefficient. Therefore job shop lean is not described below.
suitable for this particular mass customizer. In the fabrication department the major issues involve
Flexible/reconfigurable manufacturing systems: Flexible/ lack of flow, inventory control, and poor visibility. These
Reconfigurable Manufacturing Systems (FMS/RMS), as dis- problems can be addressed by restructuring and dedicating
cussed earlier, are equipment strategies intended to enable separate lines for Jumbo and Mini and using CONWIP to
manufacturing equipment to handle broad ranges of prod- control WIP. Each boat type can have two lines, one for hulls
uct types with fast changeover and setups. Due to the high and another for decks, thus synchronizing the flow through-
amount of labor content in producing wakeboarding boats, out the department and avoiding build-up of WIP at the end
the use of FMS/RMS will be of little use to SCT Boats. due to mismatching hulls/decks.

123
J Intell Manuf (2012) 23:109–124 121

Table 1 Number of CONWIP


cards Scenario Inter-arrival time Fabrication CONWIP Assembly CONWIP Inspection CONWIP

Jumbo Mini Jumbo Mini Jumbo Mini

A 96 80 10 11 11 12 8
B 80 68 14 15 11 12 8

To control inventory, CONWIP loops, that are better for above, on performance by conducting what-if analyses (Chan
linear flow and variable cycle time environments, as here, will and Chan 2004). Therefore, a simulation model to test the
be effective. To enable matching of decks and hulls, a pair implementation of the proposed changes at SCT Boats was
of color coded (separately for each model Jumbo and Mini) built using the Simul8 simulation software.
CONWIP cards can be employed. Thus, to begin work on an
order in fabrication two CONWIP cards of same color must
be available and attached to the deck and hull. Finally, when Testing and results
the boat exits lamination, the cards are detached and returned
to the beginning of the lamination process. The employment Number of CONWIP cards is a measure of the inventory
of the CONWIP system allows overall WIP to be capped in the system and can be managed to control WIP. How-
while still using push within the system to help reduce the ever, stressing the system too fast, by having too few CON-
effect of variable work content. WIP cards can starve some operations and delay meeting
Unlike in lamination, the cycle times as well as the vari- customer orders. Therefore, there is a need to identify the
ations are much less in the components department because best number of CONWIP cards to maintain smooth perfor-
the processing of the parts for various boats only differs in mance initially. As the system performance stabilizes with
size and occasionally color. Route specific kanbans are better these quantities of CONWIP cards, the system can be further
for high variety situations and can be used here. Since each stressed and improved. The preliminary number of CON-
boat requires multiple parts from this line, it is also desirable WIP cards to be used with SCT Boats was evaluated through
to employ kitting at the end of the line. Lastly, this department the simulation by testing different scenarios. To evaluate the
can be restructured to contain two parallel lines (for Jumbo variability of demand on the system, two demand scenarios
and Mini) to allow for more stability and standardization. are considered (inter-arrival times are, low = 96, 80 min and
For restructuring the upholstery department, dedicated high = 80, 68 min for Jumbo and Mini, respectively). Differ-
work cells is likely the best choice for SCT Boats. The com- ent numbers of CONWIP cards for Jumbo and Mini lines
pany has already taken the initial steps in this direction by (fabrication, assembly and inspection) were chosen for each
defining a number of cells and the parts that will be manu- of the demand scenarios. An experimental design with 36
factured in each of them. These cells are identified as stage (=3 loops × 2 levels of CONWIP cards for each loop × 2
1, 2, and 3 cells based on the point at which the components demand scenarios) combinations was formulated and tested
that are made in the cell are actually installed during the final using the simulation. A separate simulation model was devel-
assembly process. While this is an important initial step for oped for the current state without the CONWIP loops or
the department, it can certainly be taken further. any other changes described previously. The CONWIP card
Similar to the fabrication line, the assembly area has linear requirements for the scenarios that gave the best lead time
flow and faces high work content variation making a CON- and inventory levels, compared to the current state is pre-
WIP loop very suitable. Also as in fabrication, the deck and sented in Table 1. The corresponding average lead time (all
hulls travel separately until the cap and rail process, so there times are in minutes) and system WIP is shown in Table 2
is again a need for a matching mechanism. In inspection the (complete results for all situations tested not presented here
cycle times for pool and lake testing are only slightly variable due to space limitations). The reason for the difference in the
and processing time is same across all models. Therefore a lead time quoted in Fig. 11 and those in Table 2 below is that
simple CONWIP loop can serve to cap the inventory and help the former only included the manufacturing lead time; the
to control flow in the system. latter also includes the time orders are waiting to be released
to production.
Results from the simulation showed a significant reduc-
Simulation model design and testing tion in lead time from the current state to, 45% for the low
demand scenario and 41% for the high demand scenario. It
Simulation is a very effective tool to evaluate the poten- is apparent from these results that the CONWIP loops are
tial impact of system design changes, such as that discussed accomplishing their task of limiting WIP and helping the

123
122 J Intell Manuf (2012) 23:109–124

Table 2 Average lead time and


Scenario Inter-arrival time Average lead time Average total WIP
WIP comparison
Jumbo Mini Future Current % Reduction Future Current % Reduction

A 96 80 4,421 8,045 45 49.3 64 23


B 80 68 5,356 9,147 41 49.3 64 23

system to flow smoothly. Comparison of average WIP in hand, FMS/RMS are likely to be the more appropriate choice
these situations revealed a reduction of up to 23% for both for high-level MC (fabricators and involvers) with large vol-
demand scenarios. When considering the high cost of the ume production. MC companies with cellular configurations
boats these inventory reductions can turn out to be signifi- (or those suitable to be reconfigured as such due to medium-
cant savings for the company. These changes to the system volume, medium-variety manufacturing) with high routing
configuration at SCT Boats will help the company to be more variations in the process will be candidates for applying QRM
responsive as a mass customizer and reduce overall cost of and POLCA together with appropriate lean techniques. Many
operations as well. MC companies will often have a clearly identifiable and fixed
bottleneck (e.g.: B2B mass customizer of industrial trans-
formers with a limited capacity oven for baking the cores;
Discussion and conclusions Shuaib and Badurdeen 2009) which affects its operations.
Such companies can effectively integrate TOC to improve
The applicability of lean principles varies depending on the the flexibility of their MC operations. Thus, the framework
type of MC and the point of customer involvement in the presented in this paper can be used by companies engaged
value chain. Certain lean principles such as continuous in MC to identify how best lean manufacturing, and other
improvement, waste reduction, visual management, 5s, etc. principles, can be integrated to improve its performance.
can be readily implemented in most manufacturing environ- As demonstrated by the case study, the specific applica-
ments. However, the ease of applying other lean practices tion of these various strategies will vary on a case-by-case
such as JIT manufacturing and load leveling for MC is less basis. Though the case company was engaged in low-level
straightforward. This paper investigated various MC strate- MC, some customized features were incorporated upstream,
gies and the application of the lean principles for those sce- starting from the first operation in the fabrication process.
narios. The integration of various other strategies such as Due to this variety explosion way early, complete pull man-
agile/leagile manufacturing, job shop lean, FMS/RMS and ufacturing was not possible throughout the process; a com-
QRM/POLCA, too, were examined. Based on this investi- bination of push and pull manufacturing was found to be the
gation, a theoretical framework for applying lean manufac- most suitable. Therefore, the framework must be seen as a
turing, and the integration of other strategies when lean is generic representation of the applicability of lean and other
inadequate, for different MC manufacturing environments strategies for different types of MC. Each company engaged
was presented. in MC will need to select the most appropriate strategy, or
According to the framework, most lean principles are a combination of them, based on the specific circumstances
applicable to low-level MC where customer involvement is they are faced with.
low and products are often assembled-to-order. However, as The framework presented here can be further validated
degree of customization and customer involvement increases and refined, if necessary, by studying the operations of other
(high-level MC), some aspects of lean, such as JIT and pro- types of mass customizers (modularizers, fabricators and in-
duction leveling become more difficult to apply. In such volvers) and the applicability of lean and other strategies to
situations companies can integrate other strategies with lean their specific situations. One aspect that was not explicitly
concepts to increase the efficiency of MC operations. For evaluated in the case study and needs further consideration
example, if a company engaged in low-level MC (assem- is the importance of the soft side (people and team work) of
blers and modularizers) can identify a clear decoupling point lean manufacturing for MC. As the extent of customization
for its operations (where processes are more standardized increases companies will require highly skilled and flexible
upstream) agile/leagile strategies will be more suitable. Also, work teams to cope with the dynamic work content needed
if the production volume is not significantly high, a mass for different customer orders. This aspect of lean manufac-
customizer with a functional configuration can choose to turing and its importance and implications for different types
improve performance by applying job shop lean. On the other of mass customizers need to be further investigated.

123
J Intell Manuf (2012) 23:109–124 123

References Semiconductor Manufacturing Conference and Workshop, (pp. 7–


12). 12–14 November 1996, Cambridge, MA.
Badurdeen, F., & Liyanage, J. P. (2009). Promoting sustainability Koren, Y., Heisel, U., Jovane, F., Moriwaki, T., Pritschow, G., Ulsoy,
through mass customization: A framework and directions for G., & Van Brussel, H. (1999). Reconfigurable manufacturing
future research. International Journal of Sustainable Manufactur- systems. Annals of the CIRP, 48(2), 527–540.
ing. Accepted. Krishnamurthy, R., & Yauch, C. A. (2007). Leagile manufactur-
Badurdeen, F., & Masel, D. (2007). A modular minicell configuration ing: A proposed corporate infrastructure. International Journal
for mass customization manufacturing. International Journal of of Operations & Production Management, 27(6), 588–604.
Mass Customisation, 2(1/2), 39–56. Lampel, J., & Mintzberg, H. (1996). Customizing customization. Sloan
Barnett, L., Rahimifard, S., & Newman, S. (2004). Distributed sched- Management Review, 38(1), 21–30.
uling to support mass customization in the shoe industry. Inter- Liker, J. K. (2003). The toyota way. Wisconsin: McGraw-Hill.
national Journal of Computer Integrated Manufacturing, 17(7), Mason-Jones, R., Naylor, B., & Towill, D. R. (2000). Lean, agile, or
623–632. leagile? matching your supply chain to the marketplace. Inter-
Berman, B. (2002). Should your firm adopt a mass customization national Journal of Production Research, 38(17), 4061–4070.
strategy?. Business Horizons, 45(4), 52–60. Mehrabi, M. G., Ulsoy, A. G., & Koren, Y. (2000). Reconfigurable
Bicheno, J. (2000). The lean toolbox (2nd ed.). England: PICSIE manufacturing systems: Key to future manufacturing. Journal of
Books. Intelligent Manufacturing, 11, 403–419.
Boynton, A. C., Victor, B., & Pine, B. J., II (1993). New com- Michel, R. (2002). Multiple paths to lean. MSI, 20(11), 54–57.
petitive strategies: Challenges to organizations and information Monden, Y. (1998). Toyota production system (3rd ed.). Georgia: Engi-
technology. IBM Systems Journal, 32(1), 40–64. neering and Management Press.
Brink, T., & Ballard, G. (2005). Slam—A case study in applying Moser, K. (2007). Mass customization strategies-development of a
lean to job shops. ASCE Construction Research Congress. 5–7 competence-based framework for indentifying different mass cus-
April 2005, San Diego, CA. tomization strategies. Morrisville, NC: Lulu Enterprises, Inc.
Buyukozkan, G., Dereli, T., & Baykasoglu, A. (2004). A survey Naylor, J. B., Naim, M. M., & Berry, D. (1999). Leagility: Integrating
on the methods and tools of concurrent new product develop- the lean and agile manufacturing paradigms in the total supply
ment and agile manufacturing. Journal of Intelligent Manufactur- chain. International Journal of Production Economics, 62, 107–
ing, 15, 731–751. 118.
Byrkett, D. l., Ozden, M. H., & Patton, J. M. (1988). Integrating Ohno, T. (1988). Toyota production system: Beyond large-scale pro-
flexible manufacturing systems with traditional manufacturing, duction. New York: Productivity Press.
planning and control. Journal of Production and Inventory Man- Pine, J. B. (1993). Mass customization: The new frontier in business
agement, 29, 15–21. competition. MA: Harvard Business School Press.
Chan, F. T. S., & Chan, H. K. (2004). A comprehensive survey and Selladurai, R. S. (2004). Mass customization in operations manage-
future trends of simulation study on FMS scheduling. Journal ment: Oxymoron or reality?. Omega, 32(4), 295–300.
of Intelligent Manufacturing, 15(1), 87–102. Shingo, S. (1988). Non-stock production: The shingo system for con-
Clarke, C. (2005). Do you want to be lean or agile?. Manufacturing tinuous improvement. Oregon: Productivity Press.
Computer Solutions, 11(3), 14–15. Shuaib, M., & Badurdeen, F. (2009). Job scheduling in associative par-
Co, H. C., & Jacobson, S. H. (1994). Kanban assignment problem in allel machines to minimize average flow time. In Proceedings of
serial just-in-time production systems. IIE Transactions (Institute the Indian Sub-continent Decision Sciences Institute Conference
of Industrial Engineers), 26(2), 76–85. (pp. 102–112) 2–5 January 2009, Mumbai, India.
Da Silveira, G., Borenstein, D., & Fogliatto, F. S. (2001). Mass custom- Steele, D. C., Philipoom, P. R., Malhotra, M. K., & Fry, T. D.
ization: Literature review and research directions. International (2005). Comparisons between drum-buffer-rope and material
Journal of Production Economics, 72(1), 1–13. requirements planning: A case study. International Journal of
Duray, R., Ward, P. T., Milligan, G. W., & Berry, W. L. Production Research, 43(15), 3181–3208.
(2000). Approaches to mass customization: Configura- Stratton, R., & Warburton, R. D. H. (2003). The strategic integration
tions and empirical validation. Journal of Operations Manage- of agile and lean supply. International Journal of Production
ment, 18(6), 605–625. Economics, 85, 183–198.
Fernandes, N. O., & Carmo-Silva, S. (2006). Generic POLCA- Suri, R. (1994). Common misconceptions and blunders in implement-
A production and materials flow control mechanism for quick ing quick response manufacturing. Technical Paper—Society of
response manufacturing. International Journal of Production Eco- Manufacturing Engineers 1994, (pp. 1–23).
nomics, 62(1–2), 119–132. Suri, R. (1998). Quick response manufacturing: A company wide
Ford, H. (1988). Today and tomorrow. Oregon: Productivity Press. approach to reducing lead times. Oregon: Productivity Press.
Gaury, E. G. A., Pierreval, H., & Kleijnen, J. P. C. (2000). An evolu- Swaminathan, J. M. (2001). Enabling customization using standard
tionary approach to select a pull system among Kanban, Conwip operations. California Management Review, 43(3), 125–135.
and Hybrid. Journal of Intelligent Manufacturing, 11, 157–167. Takahashi, K., Hirotani, M., & Hirotani, D. (2005). Comparing
Gilmore, J. H., & Pine, J. B. (1997). The four faces of customization CONWIP, synchronized CONWIP, and Kanban in complex sup-
(pp. 91–101). Harvard Business Review. ply chains. International Journal of Production Economics, 93–
Goldratt, E. M. (2004). The goal: A process of ongoing improve- 94, 25–40.
ment. Minnesota: Highbridge Company. Ulrich, K., & Tung, K. (1991). Fundamentals of product modular-
Huang, C., Tseng, T., & Chang, H. (2005). A novel approach to lean ity. Issues in Design Manufacture/Integration, 39, 73–79.
control. In Proceedings of IIE Annual conference and Exposition, Wantuck, K. A. (1989). Just in time for America. Michigan: Edwards
14–18 May 2005, Atlanta, GA. Brothers Inc.
Klusewitz, G., & Rerick, R. (1996). Constraint management through the Womack, J. P., & Jones, D. T. (1996). Lean thinking. New York: Simon
drum-buffer-rope system. In Proceedings of IEEE/SEMI Advanced & Schuster.

123
124 J Intell Manuf (2012) 23:109–124

Womack, J. P., Jones, D. T., & Roos, D. (1991). The machine that in the UK. Modeling, Planning and Scheduling of Manufacturing
changed the world. New York: HarperCollins Publishers. Systems, 40(17), 4545–4562.
Yusuf, Y. Y., & Adeleye, E. O. (2002). A comparative study of lean Zipkin, P. (2001). The limits of mass customization. Sloan Management
and agile manufacturing with a related survey of current practices Review, 42(3), 81–87.

123

Вам также может понравиться