3.1.2 Connection between microwave and transmission equipment (IP RAN or other
Microwave) .................................................................................................................16
3.3.15 Modulation.........................................................................................................24
1 General Introduction
A total solution including both wireless and transmission for Smartfren new project is
offered by ZTE in terms of Smartfren’s requirement. Wireless provides direct
connection with subscribers and transmission supports normal operation of wireless.
The wireless has 4G LTE service for the requirement of both voice and data.
Java region 12
Sulawesi 139
Kalimantan 253
Total 404
Noted: Scale of Work can be adjusted during deployment according to the actual situation
R8961 is an IP-based all outdoor microwave radio, which widely used for 3G, 4G
LTE and even 5G IP back haul network. ZXMW NR8961 system includes Outdoor
Baseband Unit (OBU) and Outdoor RF Unit (ODU). OBU and ODU work
coordinately in various scenarios. Figure 2-1 shows the appearance of NR8961 system.
Compare to the traditional split system, all outdoor solution can save site rental fee for
operators thus improving return on Investment (ROI). The transmission capacity of
NR8961 can reach up to 5 Gbps based on the industry leading techniques, such as
112MHz bandwidth, 4096QAM modulation scheme. It also supports built-in Wi-Fi
module, IP routing, MPLS and 10GE interface; hardware is prepared for SDN.
OBU ODU/SRU2
RF
RSSI IF
ODU/SRU ODU/HRU
2.1.1 OBU
2.1.2 ODU
ODU is the outdoor unit of the NR8000 split-type system. It delivers power
amplification and radio frequency (RF) conversion functions
NR8961 supports three types of ODU – SRU HRU and SRU2, ZTE and
Smartfren get the agreement , in this project ODU will use the SRU and SRU2.
SRU2: 2nd generation normal transmit power ODU with smaller dimension
and less weight, supports QPSK to 4096 QAM modulation scheme and
[Note3]
7/14/28/40/56/112 MHz channel bandwidth . The frequency bands of
RF in/out
IF in/out RSSI
RF
RF
RSSI IF
Antenna
In this new project, ZTE will deploy NR8961 to support the Microwave network.
BSC
Ring
RNC
EPC
1
NR8960 1
NR8960 1
NR8960
RRU RRU RRU
Power
GE(O/E) Cable
Outdoor Outdoor Outdoor
BBU BBU BBU
-48 VD
-48 VDC -48 VDC power
Supply
In this project ,we get the application link type and Scale from the HLD .
CONFIG Qty
In total 404hops
The ZXMW NR8961 microwave system adopts compact architecture. All functionalities are
integrated in only one all outdoor unit including RF module and Baseband switch.
Female
IF signal input /output interface for channel 1 and
IF1/IF2 TNC
channel 2.
connector
2 pin
PWR -48 V DC supply for non-PoE scenario.
connector
Capacity/
Interface Interface Type
Signal Impedance and Others
Name & Standards
Rate
RJ-45
10/100/1000 TIA/EIA-568-B.1-2001
GE 1000
BaseT Rate: 10/100/1000 Mbps self adaptive.
(electrical) Mbps
IEEE802.3ab Supports MDI/MDI-X.
RFC894
SFP LC
Wave length:
1000 Base-LX
GE 1000 1310/1550nm (single mode fiber)
1000 Base-SX
(optical) Mbps 850nm (multi-mode fiber)
IEEE802.3z
Rate: 1000 Mbps
RFC894
Wave length:
SFP+, LC
850/1310/1550 nm (single mode).
XGE 10GBase-LR/ER
10 Gbps Rate: 10 Gbps.
(optical) SFF-8431,
Frame format: Ethernet V2 (RFC894)
SFF-8432
and IEEE 802.3
ODU is the outdoor unit of the NR8000 series. It delivers power amplification and radio
frequency (RF) conversion functions
There are two types of ODU - SRU,SRU2. In this NEW project, ODU-SRU and
ODU-SRU2 will be used in the network.
SRU: Normal transmit power ODU, operates in the frequency range of 6-42 GHz
(6/7/8/10/11/13/15/18/23/26/28/32/38/42 GHz), support QPSK to 1024 QAM.
RSSI (Received Signal Strength Indication) interface (BNC type) for RF receiver signal
monitoring.
RF in/out
RSSI IF in/out
Traffic connection
Traffic interface:
GE (electrical Interface)
Connection mode:
DCN channel
In-band DCN: DCN data and traffic data shall be assigned different
VLAN ID and integrated into one interface.
Traffic connection
Traffic interface:
Connection mode:
DCN channel
In-band DCN: DCN data and traffic data shall be assigned different
VLAN ID and integrated into one interface.
Traffic connection
All rights reserved. No spreading without permission of ZTE. Page16
Internal Use Only▲
Traffic interface:
Connection mode:
DCN channel
In-band DCN: DCN data and traffic data shall be assigned different
VLAN ID and integrated into one interface.
High performance dual polarization and low profile antenna will be applied to all
configuration. The hardware installation of 1+0 is the same with 2+0 but we just
use one pair of frequency for 1+0, two pairs frequnency use for the 2+0.
Similarly, the hardware installation of 3+0 is the same with 4+0 but we just use
three pairs of frequency for 3+0.
NR8961 supports 2+0 configuration. When using XPIC, NR8961’s two RF channels
work at V and H polarization of same frequency pair. On the contrary, different
frequency pair will be used by NR8961 2+0 configuration without XPIC. Two ODUs
direct mount to the antenna by OMT. But in this project ,we will choose without XPIC
follow SF requirement.
Remark: Please follow regulation which V polarization connection with IF1 port and H
polarization connection with IF2 port.
OBU 1
SRU/SRU2 2
DP Antenna 1
IF Cable 2
OMT 1
NR8961 supports 4+0 configuration with two OBUs and four ODUs, which can be
applied in high capacity link. The two ODUs of each NR8961 with the same
polarization are installed to one coupler, and use the flexible waveguide to connect
the dual polarization antenna. In order to use the same type antenna in the project,
we use DP direct-mounting antenna and flange adapter for 3+0&4+0.
OBU 2
SRU/SRU2 4
DP Antenna
1
(direct-mounting)
Flange Adapter 2
Coupler 2
Flexible Waveguide 2
IF Cable 4
Optical Fiber 2
Remark: Please follow regulation which V polarization connection with IF1 port
and H polarization connection with IF2 port.
CONFIG Qty
In total 404hops
Note: Link frequency can be adjusted during deployment according to the actual link
situation.
Link annual availability in this project refer to 99.995% over a year for each new link,
which is based on Recommendation ITU-R P.530 algorithm. Above KPI is assigned to
the normal situation. If some unexpected situation affects the link KPI, SMARTFREN
and ZTE shall discuss the KPI and come to an agreement of KPI case by case.
For each new link, the Fade Margin should be normally more than 30dB when
BER=10E-6.
Planning tool is using Pathloss 4.0 (Link Budget and Performance calculation)
Rain Region is refer to ITU Rain region: P, Rain Rate (R0.01): 145mm/h
The tree height will be considered as minimum 10 meters in nominal LOS checking.
The actual LOS status should be confirmed by LOS survey.
For new site, the maximum tower height is assumed as 40m in nominal LOS checking.
The actual LOS status should be confirmed by LOS survey.
Antenna type to be used in this project are orthogonal, there are two types antenna in
this project , one antenna is combine with OMT use for the 1+0a&2+0, another
antenna is combine with adapter use for the 3+0&4+0.
Antenna size shall be 0.3m, 0.6m, 0.9m, 1.2m, 1.8m which is based on the design to
meet the link availability.
3.3.15 Modulation
The modulation shall be based on 256QAM in microwave planning. Initial design has
to use 256QAM , open the ACM fuction and fmodulation from QPSK to 256QAM.
The microwave planning should be based on existing transmission and its optimization.
ZTE and SMARTFREN should discuss and agree with on a case by case basis of the
appropriate requirement.
4 EMS Solution
ZTE provides the EMS solution to SMARTFREN to manage the NR8000 in exsiting
network. One set of U31 R58 for NR8000 located at Jakarta BSD Smatfren office, the
other set located at Surabaya core room. EMS will include hardware, software and
All rights reserved. No spreading without permission of ZTE. Page25
Internal Use Only▲
client, For the MW NR8961 new project , We use the exsiting EMS server to monitor
NR 8961 , The exsiting EMS overall design concept as below:
Service compatibility: As shown in the graph above, the traffic stream can be
configured with VLAN ID, such as VLAN 4 and VLAN5. ZTE MW Radio supports
all kinds of service interface, which can meets traffic interconnection requirement on
the data transmission .
Interconnection with 3rd party equipment: Traffic & EMS Interconnection NR8000
NE with Ceragon MW via 1 GE interface, (EMS in-band of traffic, differentiate with
VLAN ID. )
The Geo Redundancy EMS is provided in the exsiting project. One EMS Server
located in Jakarta, the other one Server located in Surabaya.
In remote cluster scheme (1+1 mode), the active and the standby EMS respectively
adopts one server as EMS server. It is generally composed of one active EMS server,
dual-machine disaster recovery software and one standby EMS server mode, the active
and the standby EMS are connected through special VPN.
Monitor-H:19.5" LCD 2
4 in 1 KVM: Interface:USB/Power:AC/LCD:17"/Port
KIT 2
number:8/signal cable:8 /3 year warranty
HDD PCS 24
Oracle DB KIT 2
For the exsiting EMS server memory is only 32G for one side which the capacity can
not support 5000 NE,Need to upgrade 32G to 80G.
For the exsiting software is U31 V12.16.20 version which is too old and can not
monitor NR8961 , so need to upgrade version to U31 R58 V12.18.10 version .
Upgrade Step :
According to the network planning result, all the microwave elements will be divided
into several regions. Each region has a IP_RAN node to aggragate microwave traffic
and send them to FO network. In this new project ,we choose In-band management to
monitor NR8961 NE.
MW EMS Server
FO FO
IPRAN Core
FO
FO FO
IPRAN Site
MW
Step. Description
3 The number of IDUs in each area will be calculated in terms of radio planning
result
6 The remaining host IP addresses in each area are to be allocated in each IDU of
each area.
7 NMS VLAN will be define to each area. This VLAN is not to be shared with
any other service.
Note:
5 Hardware Installation
Plier Crowbar
Tape Sleeve
Grounding resistance
Multimeter
tester
Compass GPS
No Item Description
Note:
1. The new installation will take a considerably high risk of failure if existing topology
and IP/VLAN configuration or cable cross-connection is not fully clear.
2. After getting information above, ZTE will prepare the detailed design for
implementation.
Prerequisite
The OMT polarization modes are the same as that of the SRU2.
1.Install the SRU2 on to the OBU bracket 2 and fasten the screws,see the Figure 5-3
2.Install the OBU onto the OBU bracket 2 and fasten the screws,see Figure 5-4
3.Install the OBU bracket1 on the OBU bracket 2 and fasten the screws,see Figure 5-5
4.Align the adapter screws with SRU2 screw holes, insert and fasten the screws, see
the Figure 5-4
5.Apply a lubricant on the antenna interface of the SRU2, the waveguide interface of
the antenna, and the OMT interface,see Figure 5-5
6.Use M6 captive screws, spring washers, and flat washers to install the OMT on the
feeder source of the antenna, see Figure 5-6
7.Install two SRU2 on the two sides of the OMT,see Figure 5-7
8.Install two IF cables between SRU2 and OBU, see Figure 5-8
All rights reserved. No spreading without permission of ZTE. Page41
Internal Use Only▲
3) Insert the tenons of the bracket into the notches of the mount assembly. Use an M6 Allen
hex wrench to fasten the captive screws on the bracket, see Figure 5-11.
2.Use M6 captive screws, spring washers, and flat washers to install the OMT on the
feeder source of the antenna,and then install two SRUs on the sides of the OMT.
3.Connect the SRUs and OBU through two IF cables, see Figure 5-13
1.Install the two SRU2 installation brackets on the pole. See Figure 5-15
2.Install the two combiners on the two ODU installation brackets respectively, see
Figure 5-16 Installing the two combiners
3.Install the SRU2 on to the OBU bracket 2 and fasten the screws,see the Figure 5-17
4.Install the OBU onto the OBU bracket 2 and fasten the screws,see Figure 5-18
5.Install the OBU bracket1 on the OBU bracket2 and fasten screws,see Figure 5-19
6.Align the adapter screws with SRU2 screw holes, insert and fasten the screws, see
the Figure 5-20
7.Install the four SRU2 on the two combiners respectively, see Figure 5-21
8.Connect the UDR ends of the two flexible waveguides to the antenna and the PDR
ends of the two flexible waveguide to the two SRU2 installation brackets
respectively.And then install four IF cable between SRU2 and OBUs , see Figure 5-22
9.Fix the flexible waveguide with a clamp(if the waveguide legth longer than 0.6m),
apply a lubricant on the flexible waveguide surface, and label the two ends of the
fxexible waveguide.
10.Install the Eth cable and PLA cable, see Figure 5-23
3) Insert the tenons of the bracket into the notches of the mount assembly. Use an M6 Allen
hex wrench to fasten the captive screws on the bracket, see Figure 5-26.
3.Connect the UDR ends of the two flexible waveguide to the antenna and the PDR
ends of the two flexible waveguide to the two SRUs installation brackets respectively.
4.Install the IF cables between the SRUs and OBUs, see Figure 5-27
5.Fix the flexible waveguide with a clamp(if the waveguide legth longer than 0.6m),
apply a lubricant on the flexible waveguide surface, and label the two ends of the
fxexible waveguide.
6.Install the Eth cable and PLA cable, see Figure 5-28
device, and a single-hole terminal ground. For how to fibricate a grounding cable,see
Figure 5-30
1.Connect the device end of the grounding cable to the grounding point of the
NR8961, see Figure 5-31
a. Peel off the shield layer at the end of the power cable. For the peeled cable size,
see Figure 5-32
b. Insert the cable to a tube terminal,see Figure 5-33.After the cable is inserted,
0.5mm-1mm of the core should be exposed.
1) Pass the power cable with a crimped cube terminal through the outer cable
jacket,rubber plug, and inner cable jacket in turn,see Figure 5-34
2) Insert the special tools into the pressing holes at the top of the DC power cable
connector,press the tool until the clamp springs are opened, connect the power
cable ,and loosen the tool,see Figure 5-35
3) Insert the power connector to the power interface, see Figure 5-36
1. Cut the Ethernet cable in proper length in accordance with the engineering survey
requirements.
2. Fabricate the Ethernet cable and add lables on both ends of the Ethernet cable.
3. Reserve an end long enough for operation, Lay the Ethernet cable from the
installation position on the NR8961 to the equipment room.
4. Install the waterproof protective tube to the Ethernet cable, see Figure 5-38
5.Push the waterproof protective tube upwards, fasten the screws and fixing nuts, see Figure
5-39
6.Connect the other end of the Ethernet cable to the local maintenance terminal or the port.
1. Pass the optical fiber through the outer cable jacket, rubber plug, inner cable jacket,
and tensile piece in turn, see Figure 5-40
2. Insert the optical fiber connector into the corresponding interface until you hear a
click, see Figure 5-41
2. Make connnectors of the IF jumper and the IF cable, After the connectors are made,
take appropriate protection measures to protect the connectors from being damaged
during the hoisting or cabling process.
4. Connect the other end of the IF cable to the IF interface of the OBU, and fasten
it,see Figure 5-44
BC Boundary Clock
CS Channel Spacing
DEM Demodulator
DEMUX Demultiplexer
FD Frequency Diversity
FE Fast Ethernet
IF Intermediate Frequency
MUX Multiplexing
NE Network Element
OC Ordinary Clock
RF Radio Frequency
Rx Receiver
SD Space Diversity
Sync Synchronization
TC Transparent Clock