Академический Документы
Профессиональный Документы
Культура Документы
Introduction... ... ... . .. ... ... ... ... . . ... ... . . ... ... . . 3
Part I: Risk Assessment Report... 4
Summary of Aggregate Risk at Bank Level. """""""".".""". 4
Findings on Risks and Control Gaps Assessed... ................... ..... 5
Governance & Oversight........................................................ 5
Credit Risk... 8
Market Risk... 14
Liquidity Risk....................................................................... 16
Operational (Non-IT) Risk..................... .. ............................. 19
Operational (IT) Risk 23
Other Pillar II Risks................................ .... ............. .... ...... 24
Part II: Major Areas of Financial Divergence................ . . ............ 26
Part III: Findings on Capital and Earnings............... 27
Pillar I Capital & CRAR..................... . .... .............................. 27
Capital Management, ICAAP and Stress Tests (including SREP)... 28
Assessment of Internal Generation of Capital...... 29
Scope & ability to infuse capital... ... 30
Assessment of Leverage Ratio...... 30
Confidential Page 2 of 32
INTRODUCTION
A separate exercise of asset quality review (AQR), 2015 was conducted during the
current supervisory cycle with specific focus on compliance with regulatory guidelines
on IRACP norms. The review covered, inter alia, deficiencies in the systems and
processes in the bank which led to improper/ incorrect classification of assets. The
report containing findings of the AQR were shared with the bank and, after discussion,
the bank has been advised to take a review of the accounts covered under AQR by
following a proactive approach with regard to classification and provisioning by strictly
applying the IRACP norms in letter and spirit, by March 31, 2016. Further, with a view
to putting the viable assets back on track in case of failed CDR restructuring cases, the
bank was given time up to March 31,2017 to take a review of these cases. However, in
the interregnum, the bank will be required to build up prudential provision of 15%(
including 5% regulatory provision for restructured standard asset as on March 31,
2016) for failed CDR restructuring cases by March 31,2017.
In view of the above, the full impact of AQR on the bank's profitability, capital, earnings,
risk scores, etc., is not determinable in the current supervisory cycle. The impact of
AQR, therefore, has not been included while presenting the assessment in this
Inspection report.
The risk assessment of ICICI Bank for 2014-15 under the Supervisory Program for
Assessment of Risk and Capital (SPARC) was completed with March 31, 2015 as the
reference date. The assessment was made based on the off-site analysis of the data
and information furnished by the bank as well as the findings of the on-site Inspection
for Supervisory Evaluation (ISE) undertaken from October OS, 2015 to December 10,
2015 and various explanations offered by the bank in course of inspection.
As per the SPARC process, the aggregate Risk Score of the bank is arrived at 2.396,
which is indicative of high risk. On applying the assessed CRAR (16.87%) to the
aggregate risk score, the Risk of Failure score of the bank is arrived at 1.976.
Board 2.006
1.999
2.466
Confidential Page 8 of 32
deterioration of their external rating. Several top borrowers were externally
downgraded to default grade while they retained their internal rating at '888-',
which was investible grade in the bank. Further the external rating of some of
the big borrowers was treated as unrated for RWA purposes and did not truly
reflect the risk rating/RWAs.
2.1.8 Concentration Risk increased as compared to 2013-14 in respect of sensitive
sectors and top three industries.
2.1.9 Exposure & Tenor Risk
The appetite for concentration risk appeared to be high considering liberal
lending standards to large single/ group borrowers. The concentration risk was
heightened due to large borrowers having complex inter-connected
overleveraged group structure, inter-mingling of business and financial
transactions, common collaterals, etc. resulting in integration & compounding
of risks across the companies/ SPVs. The bank had not considered group level
aggregation of collateral as a dimension of concentration risk control. There
was also no formal and documented process for analyzing exposures to co-
related segments and it was not part of business decisions as well.
2.1.10 The weighted average residual maturity of the bank's exposure also increased
to 4.8 years in FY2015 which was 4.51 years in FY2014
2.1.11 The un-hedged foreign currency corporate exposure at 71 % was considered
high which may indirectly expose the bank to high risk in case of adverse
currency movements.
2.1.12 Recovery Risk
As much as 36.4% of the credit exposure was unsecured posing high recovery
risk. Moreover, proportion of readily redeemable non-financial collaterals and
financial collaterals was also low.
2.1.13 The progress in security creation during the year was almost at the same level
(70%) as in FY 2014 indicating no improvement in the processes in this regard.
2.1.14 The bank had a system of post sanction amendments of the sanction terms
loans. Such amendments allowed deviations in important aspects like security
conditions, financial covenants, etc. without having any linkage to the risk rating
of the borrowers. As a result, certain low rated borrowers were extended a
number of relaxations. Such concessions indicated relaxed credit standards
and inadequate risk picture in the WBG segment.
2.2 Control Gap I Score: 2.622
Confidential Page 9 of 32
2.2.1 Policy Environment
As regards credit contingent liability (BGs), the bank had a policy for payment
of invoked BG within 48 hours from the date of claim. Such policy was not in
tune with Para 2.5 of MC on Guarantees & Co-acceptances, which required
that invoked BG should be honored immediately and no approval of the
superior authority was necessary. The time frame prescribed resulted in delay
in honoring the bank's commitment. Besides, the 48 hrs window facilitated the
applicant to legal recourse or other means for not honoring the invocation.
Some instances of such non-payment of invoked BGs were observed during
FY 2014 and in June 2015 as well.
2.2.2 Risk Identification & Assessment
Some deficiencies observed in appraisal and post-sanction processes are as
below:
1. The bank had adopted a method of financing the Net Cash Gap, which took
into account a company's total fund requirement for the next year factoring
all the cash flows including debt. While the well performing accounts posed
no major concerns, this method could conceal the stress and risk in the
account besides having the potential to circumvent the IRAC norms. Under
this arrangement, repayments on existing loans got paid off out of fresh
term loan disbursals. The sanction letters mentioned that the loan could be
utilized to payoff debts of other banks, for maintenance capex,
reimbursement of maintenance capex of earlier years etc. By this method
the debt servicing of the borrowal accounts was possible without the
borrower generating sufficient cash flows from business. This assessment
method was faulty and defied conventional methods of finance as term
loans are given for short term purposes and non-asset creating purposes.
2. In a few cases, while delays in security creation and perfection were
observed, extension for approvals for security creation was done as a
matter of routine.
3. Monitoring of the accounts suffered due to multiplicity of the IT systems.
For example, in case of a large borrower, the overdraft on account of
derivative settlement was not reckoned as part of credit review and
remained so for more than nine months. Similarly, improper aggregation
among multiple systems as well as multiple current accounts resulted in few
accounts not being effectively monitored. The bank had granted loans to
two SPVs (LDHIL & LHHIL - SPVs of Lanco Infratech Ltd) for onward
Confidential Page 10 of 32
funding of parent's needs as well as for reverse infusion of funds to SPVs.
The SPVs had acted as financial intermediaries and also· were not
bankruptcy remote as stipulated in para 2.3.8.3.(iv) of the Master Circular
on Loans and Advances - Statutory & Other Restrictions dated July 01,
2014.
2.2.3 Some of the top 20 borrowers belonging to mega corporate groups held multi-
currency, trans-geography assets and liabilities through complex web of
layered entities including those in tax havens with high leverage. The bank
considered promoters' strength and stature as well as their large sized global
operations as a positive factor from a credit risk perspective without factoring in
the risks in the complex structures holistically. Further, multiple lenders usually
lent short-term loans to these groups with frequent intra group transfers and the
bank did not have any formal system to measure and capture any early
warning signals manifested through strain in the real liquidity across the group.
2.2.4 Controls
There was no defined and documented process for fixation of moratorium
limits. Extension of moratorium for RTLs in the nature of short term loans and
for working capital purposes and non-project loans as well as for repayment of
existing bank's/other banks loans were extended without any rationale and
purely with a view to facilitate/delay repayment
2.2.5 The rating, pricing and NPV computation suffered from the following
deficiencies:
1. Proposals below BBB- were escalated to Credit Committee. Further
mapping of internal rating to rating accorded by external agencies in respect
of large corporates was absent.
2. The internal credit rating framework prescribed that improvements could be
effected by applying subjective overrides in rating and rating underwent
changes upto three notches. Overrides were used in 120 accounts, of
which, upgrades were effected in 63% (75 accounts) and in value terms it
was used in 94% (~426000 mn ) on subjective grounds like presence of
letter of comfort, letter of awareness, promoter's financial standing,
management change etc.
3. There was no effective control mechanism for monitoring unrated
exposures. (last done in July 2014). There was a system of preparing and
presenting a Risk Dashboard which was giving a broad indication of the risk
Confidential Page 11 of 32
in the bank. The direction of the risk (quarterly) was given on y-o-y basis.
The dashboard did not contain the rating migration of the credit portfolio.
There was no consolidated rating/migration review reckoning both credit
and investment (non-SLR) exposures leading to rating migration-
rebalancing
4. As regards computation of NPV (sacrifice) for restructured loans the bank
used the 'minimum quote to the client' as reflected in the pricing calculator
as the discount rate and the spreads over the base rate lacked
transparency. Such computation was not in tune with instructions contained
in para 12.4.2 of MC on IRAC norms dated July 01,2014.
5. In few weak accounts, where the internal credit rating was around 'BBB-' or
one/two notch/es below, the external credit rating was waived off
2.2.6 In cases of some restructured accounts the bank had sanctioned facilities
outside the consortium and considered the exposures as secured even though
the bank could not create the security as borrowers could not obtain NOCs
from the existing lenders, the bank continued to grant extension for creation of
security and treated the exposure as secured.
2.2.7 There were about 198 unrated accounts with sanctioned limit above ~1 00 mn in
wholesale banking. There were about 830 unrated accounts above ~ 50 mn
indicating relaxed credit system where a loan could be sanctioned without a
rating. Many of the accounts belong to large corporate who had availed
smaller limits. A large corporate with smaller limit should not be the cause for
not rating the borrower.
2.2.8 Monitoring & Review
The country rating was decided on the basis of some macroeconomic
parameters and with reference to the country ratings assigned by Banking
Industry Country Risk Assessment (BICRA). The bank's internal assessment of
the country rating did not focus on the legal developments / implications and
relied only on the observations by BICRA. Critical country exposure were
monitored and enhancements taken wherever necessary on account of
business requirement. However the exposure vis-a-vis the limit was not
considered as a breach prior to enhancement.
2.2.9 1. The bank had adopted rectification as CAP in 217 cases (78%) under JLF
which appeared to have been carried out as a matter of routine without
proper assessment of identifiable cash flows within the required time period.
Confidential Page 12 of 32
Moreover, additional finance was sanctioned under rectification in order to
prevent the account from slippage to NPA. Further interest rate charged
was substantially lower than that charged for the existing working capital
facilities.
2. Some of the accounts had gone into JLF within 15 months of restructuring
and / funding of certain borrowers post restructuring as well as through
conversion of loan into equity due to strain in debt servicing indicated stress
in restructured standard portfolio
2.2.10 Reporting
1. There was no integrated view about the collateral held against an exposure
as there was no central database on collateral. Moreover, the process of
collateral management was not automated.
2. There was no system of reporting differences in 'realized value' and value
as per last valuation. There were few instances, where contrary to the
extant instructions, fair market value of collateral was considered instead of
realizable value.
3. ICICI Home Finance, a group company was one of the empaneled valuers
and valuation done by ICICI HFC was broadly based only on the prevalent
market value and not on the recoverability, as the realizable value of
security was not documented as part of the valuation report.
2.2.11 The system of identification of NPAs suffered from the following lacunae:
1. In respect of non-fund based facilities, the devolvements / invocations were
mapped at Customer 10 level and not at the UCC level. Accounts with
multiple Customer IDs was a feature in most accounts and the rationale for
the same defied logic
2. In terms of para 4.2.2 of the MC on IRAC norms dated July 1, 2014, the
bank should establish appropriate internal systems to eliminate the
tendency to delay or postpone the identification of NPAs. The responsibility
and validation levels for ensuring proper asset classification had to be fixed
by the bank. However during the period under review no such system
existed. Many standard accounts were covered under AQR.
3. The implementation of policy prescription and IRAC norms were considered
for record of recovery instead of all conditions / parameters stipulated in the
IRAC norms such as genuineness of the sources of funds, security /
collateral position over the years, diversion of funds, infrastructure and
Confidential Page 13 of 32
project loan conditions, evergreening, improper assessment in viability, etc.
4. In the case of some of the NPA accounts existence of particularly
stock/current assets was inflated and was not realistic as pointed out in
AQR.
5. Contrary to extant instructions, the bank classified short duration crops as
NPA on the basis of 365 days after the due date instead of fixing the same
in line with crop durations set by SLBC
6. The policy was silent on aspects relating to process for repossession and
sale of collaterals in case of written-off accounts.
2.2.12 The last ISE had pointed out that there was a system of opening of separate
account for each devolved LC facility and there was no aggregation. Presently
the bank had developed a system whereby aggregation was evidenced at
customer 10 level and not at borrower level (UCC). The bank may explore
possibility of aggregation at borrower level so that there would be a single
devolvement account for each borrower
Confidential Page 14 of 32
debentures can be through private placement which was contrary to the
regulatory requirement of limit on investment through private placement.
3.2.2 The strategy of the bank was oriented towards enhanced focus on new growth
areas like small business loans and loans in rural markets, , but the same did
not flow in the form of Fund Transfer Pricing incentives to reflect the strategy.
3.2.3 The bank was financial benchmark submitter but during the reference period
such submission was made without following the conflict of interest norm
relating to 'submitter-reviewer'.
3.2.4 Risk Identification & Assessment
The computation methodology for market risk tolerance limit was flawed as in
the bank has not computed all three stress scenarios (mild, moderate, severe)
and used results of only severe stress scenarios.
3.2.5 In written off equity accounts, the bank had considered Book Value of the
securities held by them as 'Zero' instead of arriving at the cost of holding and
subsequently the equity was marked to market, giving positive MTM offsetting
depreciation of other stocks.
The conversion of loan to investments had increased by more than 300% to
~6162 mn in FY15 as against ~1458 mn in FY14. Most of the conversions
involved accounts, which were either NPA or restructured, as result of which
the investment book was stressed and market risk stood elevated. The
valuation of an account converted from a loan classified as NPA into unlisted
equity (Aravali Infrapower Limited) was taken at breakup value instead of ~ 1
and hence additional provision of ~ 26.15 mn was suggested.
3.2.6 Controls
The bank conducted back testing of VaR and breaches for three days or more
was observed in respect of few groups (ALMG, Proprietary Trading group, MG
bullion). As the actual VaR at 99% confidence interval for 252 days indicated
that any breach above 1 % of 252 days (3 days or more) was considered an
unlikely event, a review of breaches mentioned above is warranted.
3.2.7 Reporting
1. Though enhanced internal limit for short term liquidity requirement of New
York branch had expired in March 2014, the New York branch continued
borrowings through Certificate of Deposits post March 2014 till March 10,
2015 without any approval. The control group at HO also failed to identify
the breach. However the position subsequently stood rectified
Confidential Page 15 of 32
2. Internal time period prescribed for appraising ALCO in case of rating
migration to below investment grade (M/s Punj Lloyd) was not adhered to.
3. The controls with regard to rate scan was lax as rate scan exceptions were
not reported to top management, non-availability of MIS on the subject and
exceptions getting resolved/ settled at Head of the Desk level without any
periodic reporting to top management.
Confidential Page 16 of 32
there were local regulatory restrictions (Singapore, Baharin) where free
movement of liability was not easy and thus asset liability mismatch would
pose a risk, though, it may not show in the SLS. Under the background,
rollover, asset-liability management from mismatch as well as gap
adjustment angle and interest rate risks stood enhanced.
4.1.4 The bank's average cost of term deposits at 8.12% and bulk deposits were on
a higher side as per market averages and suggested limited scope for raising
additional liabilities at competitive costs.
4.1.5 Asset Liquidity
The bank had limited liquidity available to it from foreign currency operations as
evident from its unswapped FX funds, which stood reduced from FY 2014
position at ~139840 mn to ~118090 mn for FY 15.
4.1.6 Market Liquidity
The liquidity available with the bank through unencumbered G-Secs/T-Bills was
limited. Given that 81.5% of the bank's loan book consisted of fixed tenor term
loan, emergent liquidity circumstances and illiquidity stood heightened. Further
dependence on short term interbank market was reflected in the bank being a
net borrower throughout the year.
4.1.7 The deposits of the bank was not keeping pace with the increase in advances
as dependence on borrowings had increased from ~1547590.54 mn to
~1724173.50 mn (by 11.41 %) over the last year with overseas jurisdictions
being heavily dependent on wholesale borrowings.
4.2 Control Gap I Score: 1.670
Major findings! observations
4.2.1 Policy Environment
The bank had raised several bulk deposits from Regional Rural Banks (RRB) in
FY15 at rates higher than the applicable card rates though the extant
guidelines do not permit raising of bulk deposits from RRB at rates higher than
the card rates.
4.2.2 Risk Identification & Assessment
The bucketing of SLS was deficient to the following extent:
1. The bank had not factored the committed liquidity support of USD 1000
mn to its overseas branches in the rupee leg of the SLS on the basis that
the aforesaid line was between the HO and its overseas branches and
hence not considered as a contingent liability.
Confidential Page 18 of 32
not linked on estimating the re-pricing of assets based on past experience and
future forecast for the changes in the base rate.
4.2.5 Monitoring & Review
As per the policy on retail pricing of loans, ALCO approved the range of
spreads for retail loans. Some of the existing loans (housing loans, consumer
loans, etc) had effective floating rates in the range between 15% to 18%. As
per bank's policy a floating rate retail loan with benchmark rate other than base
rate would be migrated at the same effective rate to the I-Base (Base Rate)
portfolio. Considering the effective rate above, it was observed that the spread
was adjusted to maintain the effective floating rate extended to a customer.
Such a system of charging interest rate lacked transparency as well as
defeated the concept of extension of loans on floating rate basis.
Confidential Page 19 of 32
1. Amidst decline in amount reported under external frauds by customers, the
cases pertaining to non-customers increased both in number and amount
(from ~247 mn to ~326 mn). There was also persistent rise in instances of
internal frauds (105 in FY 2014 to 129 in FY 2015). Frauds committed by
senior level branch officials in the first half of FY 2016 was a cause of
concern.
2. The risk perception was enhanced as complaints against outsourced
employees increased by 23.84% in FY 15.
5.1.4 Compliance Risk
The bank had a policy of zero tolerance for regulatory breach. However,
regulatory penalty levied by FIU-IND and RBI were imposed even during the
current year.
5.2 Control Gap Score: 1.872
I
5.2.1 Risk Identification & Assessment
Upfront name-screening prior to on-boarding of customers covered major
portion of customers but excluded customers under mobile money accounts,
travel cards and other small value products. Similarly name-screening was not
being done across the customer base and was limited to I-core system only.
The exclusion of other systems posed significant regulatory and reputational
risk to the bank.
5.2.2 Prescribed parameters for risk categorization were not fully implemented (e.g.
information about client's business and location, volume of turnover) despite
past observations in this regard. Further risk categorization did not cover
accounts residing in Finone and CTL Prime. Moreover the bank as per their
policy, by default reckoned all new customers as 'High Risk' for initial period of
two months. The new risk categorization model deployed in July 2015 was yet
to be linked to the AMLOCK system, which was the primary system for
transaction monitoring from STR.
Although Politically Exposed Persons (PEP) were categorized as high risk,
there was no tagging facility for the same in I-core, the primary system of the
bank.
In case of internet banking customers, the actual address proof was not being
obtained for address change requests, though online submissions were
accepted.
5.2.3 It was observed that the bank was in possession of educational certificates of
Confidential Page 20 of 32
7000 active employees and 10,000 inactive employees (who had left the bank).
Such practice of retaining educational certificates as 'collateral' was unethical
and fraught with severe reputational and possible legal risk.
5.2.4 Controls
The internal control mechanism for ensuring genuineness of export remittance
transactions based on Foreign Inward Remittance Certificate (FIRC) was found
to be inadequate, as verification of the authenticity of FIRC was absent.
Resultantly, the bank had issued Bank Realization Certificate (BRCs) to DGFT,
GOI against certain fake FIRCs of another bank.
5.2.5 For certain activities the bank was considering 3i-lnfotech as an outsourcing
vendor whereas in following instances the activities were not classified as
outsourced:
1. It was observed that 3i-infotech was involved in verification of AOF and
KYC documents in respect of a product i.e. mobile money saving account
and based on that a decision would be taken by the Service Provider for
approving the AOFs in the mobile money system. Through this process,
total 5,03,267 mobile money accounts were opened in FY.
2. An activity pertaining to 9% senior citizen savings scheme was undertaken
by 3i-infotech.
5.2.6 Internet banking related fraud cases, where credentials were reportedly parted
with by the customer, were not treated and classified as fraud. Such
transactions were 438 in number and amounted to ~44.8 mn in FY 2015. Delay
in detection of frauds was as long as more than two years in many instances.
In spite of repeated supervisory references, the process of filing complaint with
police authorities for fraud cases was found to be tardy as undue delay was
observed in many instances.
5.2.7 A sum of ~72.8 mn was outstanding as receivable from State Bank of Bikaner
and Jaipur (SBBJ) w.r.t. the investment sold to SBBJ on account of merger of
Mewar Anchalik Gramin Bank Ltd. and Marudhara Gramin Bank Ltd. The bank
may take steps to recover the dues at the earliest.
5.2.8 Monitoring & Review
The sample check undertaken by MLRO team did not cover alerts emanating
from credit cards, Money21ndia (remittance), Direct Banking, etc. Further only
one business group handling retail accounts was considered for sample
checking. Further in some cases, STRs were filed after closure/freezing of
Confidential Page 21 of 32
accounts. Monitoring of forex remittance transactions from AML perspective
was not linked to risk rating of counter parties/countries.
5.2.9 In respect of import remittance transactions, the mechanism of follow-up with
the importer for submission of Bill of Entry as an evidence of import was not in
line with the internal policies. In certain instances, the Bill of Entry produced by
the importer was not found to be genuine and large value import remittances
were recorded against such importers. The total outstanding entries (receipt of
BOE) pertaining to Advance Import Remittances as on September 30, 2015
was USD 9410 mn. There was an instance of DRI seeking information on a
specific account for violation of AML guidelines. Several cases of breach of
KYC / AML violations in respect of certain customers connected to the
Advance Import Transactions were observed. In one case, the customer had
about 22000 outstanding BOEs pending for several years. Though the
outstanding reports were generated and flagged to the concerned branches,
appropriate action was not taken for follow-up and submission of BOEs. This
showed the ineffectiveness of the monitoring system
5.2.10 As per the bank's internal policy, the bank was supposed to perform a
reconciliation of all the relevant masters in the AMLOCK system at half yearly
intervals to ensure correctness of risk parameters in relation to introduction of
new product codes/schemes etc. However it was observed that the said
process was last conducted on June 28, 2014 and remained unreconciled till
date.
5.2.11 As on March 31, 2015, there were 16 nostro accounts available in the bank,
which were inoperative for more than one year and above and these accounts
were not rationalized.
5.2.12 On account of reconciliation issues emanated from balancing of Subsidiary
General Ledgers (Sub-GL) for I-Loans system (retail loans) with their
underlying schedules carried out in FY 2011, an amount of ~1 02.7 mn was
lying in other liabilities of the bank, which needed to be expeditiously resolved.
5.2.13 Reporting
The centralized MIS for outsourcing in the bank had no information for annual
pay-outs to the service providers. On perusal of a sample of thirty annual
review of SPs for FY 2015, it was observed that the template used by the bank
for review could not adequately capture the rationale for continuity of the SP.
Further, no financial analysis of SPs was carried out.
Confidential Page 22 of 32
'.
Confidential Page 24 of 32
7.2.2 Risk Identification & Assessment
The business strategy was in alignment with the risk appetite but the risk
appetite statement was generic in nature. The risk appetite and capital
planning was not adjusted as per change in business strategy, particularly on
a consolidated basis, as exit from subsidiary, stake sale in group company
did not get factored. The strategy of the bank was also not factored into
business decisions as the strategies were not incentivized through FTP.
7.2.3 Controls
1. The bank was handling complaints that were made against its group
company (ICICI Home Finance), which was not only a source of
reputation risk but also borders on the conflict of interest principle. The
quantum of complaints was deterrent in the growth of the bank. The bank
was susceptible to reputation risk, as it was holding educational
certificates of employees who had quit the services of the bank in lieu for
compensation of expenses incurred by bank on their training.
2. The bank had resorted to shifting of assets between overseas
jurisdictions particularly from Singapore branch of the bank to banks
operating in gulf region in respect of accounts which displayed
weaknesses or were on the verge of turning into NPA. Such accounts
were transferred 'at Par' and were not linked to FTP as well as were done
to take advantage of regulatory arbitrage
7.2.4 Monitoring & Review
Two SPVs/SPEs were floated during FY 2015. Though the group
companies/SPVs had independent governance structures, the need for
existence of several group entities (including SPV/ SPEs) needed to be
reviewed. The system of parking/shifting stressed assets to OBU required a
relook.
Confidential Page 25 of 32
Part II: MAJOR AREAS OF FINANCIAL DIVERGENCE
The summary of major areas of financial divergence, including assessed risk weighted
assets, which determined assessed capital of the bank, is given below. Details are in
Annex 1.
Understatement of -
Expenses' Liabilities
- - -
Others (to be -
specified)
- - -
Total additional -
provisions' accounts' 1 26 26
outstanding
Confidential Page 26 of 32
Part III: FINDINGS ON CAPITAL AND EARNINGS
1. Pillar I Capital & CRAR
The summary of reported and assessed capital position of the bank as on March 31,
2015 is given below: Details are in Annex-4.
Basel III Capital under Basel III (In ~ mn)
(ii) The bank was mainly dependent on internal accrual for maintaining the CRAR,
which had declined to 17.02% in FY2015 from 17.70% in the previous year, under
Basel-III due to various reductions from Tier II capital. The assessed CRAR stood
reduced further to 16.87%.
Confidential Page 27 of 32
(b) Assessment of Pillar I & " Capital and Internal Capital Ratio
(iii) The bank had assessed internal CRAR at 11 % under ICAAP. Other assessments
and reviews always considered regulatory minimum as the primary objective.
The bank had assessed ~154420 mn additional capital under various stress scenarios.
At the current level of RWA, this would reduce the CRAR by approximately 283 bps. As
the bank was engaged in various para-banking activities and coupled with the stress in
the credit portfolio, capital planning required enhanced attention. Further applying the
higher capital ratio of 11 % along with CCB requirement, the bank's capital buffer would
stand considerably reduced within the next few Financial Years.
(iv) The deficiencies mentioned below were adjusted to arrive at assessed Risk
Weighted Assets:
• A retail loan product, Loan against Property, was risk weighted at 100%.
However, the purpose of the loan depended on a broad declaration taken from
the borrower as "Business or Other" in most of the cases. As the risk weight for a
loan for consumption purpose was higher at 125%, the bank was required to
identify all such loans and apply risk weight to them accordingly. Exposure to
such cases was ~194290 mn as on March 31,2015.
• In some of the borrowal accounts the requirement of external rating was waived
due to inability of borrower to furnish the same as well as extension of
unjustifiable timelines. Instances of poorly rated account (BB and below) were
treated as unrated as external rating was suspended. In view of supervisory
concern, a higher risk weight had been suggested.
• Instances of reckoning better ratings than that accorded externally were also
found.
• In a few overseas accounts external rating was waived due to lack of market
practice in the respective overseas jurisdictions
• Though external rating was available, certain accounts that displayed stress
were treated as unrated and risk weighted accordingly
• In several instances the RWA was recorded as 150% in proposal notes however
for CRAR computation RWA was taken as 'unrated' and 100% was applied (E.g.
Madhucon projects Ltd., Swiber Offshore, Gems Chicago Inc. etc.)
Taking into account the above deficiencies the assessed RWA was reworked to
~5498246.9 mn as against reported RWA of ~5448957.90 mn.
(c) ICAAP
(i) One of the six general risk appetite statements stated that the bank would endeavor
to maintain AAA rating from domestic rating agencies at all times
Confidential Page 29 of 32
"
(iii) Net stable income had increased from ~226524 mn to ~257438 mn during FY2015
as compared to previous year. It increased to 94% of the net total income during FY-15
as compared to 93% for FY-14 and FY-13. The proportion of fee-based income to gross
stable income had decreased from 11.79% during FY-14 to 11.65% during FY-15.
However, the same was higher than FY-13 ratio at 11 .41 %.
(iv) The operational expenses as percentage of net stable income had improved from
45.51 % during FY-14 to 44.65% during FY-15.
(v) The bank's ability to generate internal capital could be constrained on account of
increased credit risk as mentioned in the AQR.
Page 30 of 32
Confidential
PART IV: MAJOR AREAS OF NON-COMPLIANCE (REGULATORY GUIDELINES)
Confidential Page 31 of 32
Regulation Reference Area I Subject Nature & Description of Non-
(Para & Circular no.) of Non- Compliance
Compliance
July 02,2012
Para 2.14 of Know Your Operational (Non Non screening of newly opened account to verify
Customer (KYC) Norms dated IT) Risk linkage to any of the entities/individuals included in
July 02,2012 the negative list across all systems.
Para 2.21 & 2.22 of Know Your Operational (Non Non-filing/delayed filing of STRs, STRs filed after
Customer (KYC) Norms dated IT) Risk closure/freezing of accounts
July 02,2012
Para 6 of MC on Frauds- Operational (Non Undue delay in filing of police complaint within 30
classification and reporting IT) Risk days in fraud cases.
dated July 02,2012
Para A.1 of MC on Remittances Operational (Non The bank was unable to track the aggregate limit
from India- Facilities for IT) Risk for remittance through foreign currency purchased
Residents dated July 02,2012 in the form of Foreign currency/ Foreign Travelers
cheques / Travel Cards/ Retail outward remittance
across all the channels put together.
Para 2.4 (g) of MC on Know Operational (Non Coverage of re-KYC exercise was found to be
Your Customer (KYC) Norms IT) Risk tardy. Further, KYC updation yet to be done in case
dated July 02,2012 of some legacy high risk accounts opened 28 years
before.
Para (i) of guideline on Interest Operational (Non Raised several such deposits from RRB's in FY
on Deposits to be non- IT) Risk 2015 at rates higher than the applicable card rates.
discriminatory dated January 24,
2013
Para 3.1.4 of RBI MC on Frauds Operational (Non Delay in reporting of fraud cases of amount greater
dated July 01,2014 IT) Risk than ~0.1 mn individually was observed in several
cases (Six instances).
Para 2.1 and 2.3 (a)(ii) of Know Operational (Non Risk profiling of customers was not in line with
Your Customer (KYC) Norms IT) Risk regulatory guidelines as prescribed parameters for
dated July 02,2012 risk categorization were not fully implemented
Confidential Page 32 of 32
ICiCI Bank - Annex to RAR
" RWA
T a bl e- II : D"Ivergence In
Particulars
As per bank As per SSM Shortfall Remark
Credit Risk - RWA 4741559 4790848 49289 As per Annex
1
ICiCI Bank - Annex to RAR
Target Achieved
Direct
1.
Agriculture
371811 208733 - 208733 163078 -
Indirect
2.
Agriculture
123937 45588 - 45588 78349 -
TOTAL
AGRICULTURE
495748 254321 - 254321 241427 -
Micro and Small
3.
Enterprises
408271 - 408271 -
Education /
4.
Housing / others
224248 - 224248 -
TOTAL Priority
Sector
1101661 886840 - 886840 214821* -
2
ICICI Bank - Annex to RAR
Sr.
Particulars Amount
No.
A Total Liabilities excluding capital & reserves as
6030792
on March 31, 2015
Upper Tier II Instruments 154410
Subordinated debt 216744
Deposits 3615627
Borrowings 1353020
Other liabilities and provisions 690991
B Internal Liabilities 169768
Provision for standard assets 23336
Provision for diminution in fair value of restructured accounts 25227
Provision for NPAs 88392
Floating provision 2
Provision for NPI 8262
Provision for depreciation in investments 18593
Any other (to be specified)
Provision for assets on lease 263
'Provision for other assets 2047
DICGC/ECGC claim received 35
Provision for securitization sell down 1260
Provision for contingencies 569
Provision for operational risk 365
Provision for country risk exposure 345
Reserve for Profit on sell down to ARCILlPhoenix 236
Fraud Risk Recovery from staff 15
Provision - Collecting Bank Fraud Risk 16
Specific provision for standard assets 781
Other provisions 24
C Total outside liabilities [A-B] 5861024
3
ICiCI Bank - Annex to RAR
Sr.
Particulars Amount
No.
A Paid up capital
11597
4
ICiCI Bank - Annex to RAR
5
ICiCI Bank - Annex to RAR
6
ICICI Bank - Annex to RAR
7
ICiCI Bank - Annex to RAR
8
ICiCI Bank - Annex to RAR
47 Net Interest Income [1-8] (Nil Growth Rate) 177193 154824 126842
9
ICiCI Bank - Annex to RAR
10