Академический Документы
Профессиональный Документы
Культура Документы
Approval Sheet
Name Title Date Signature
Facility Engineering & Integrity Manager
Head of Facility Engineering
Head of Quallity Control
Lead of Field Engineering
DOCUMENT CLASS: I
Revision Status
Rev Issue Date Prepared Checked Approved Issue Purpose Owner Signature
_____________________________________________________________________________________________________
Page 2 of 15
PT. MALEA ENERGY ITP - Piping Fabrication and Installation
Revision : xx
_____________________________________________________________________________________________________
Page 3 of 15
PT. MALEA ENERGY ITP - Piping Fabrication and Installation
Table of Contents
1. Purpose ........................................................................................................................................... 5
2. Scope .............................................................................................................................................. 5
3. Reference ........................................................................................................................................ 5
4. Definition ......................................................................................................................................... 5
5. Abbreviation .................................................................................................................................... 6
6. Legend ............................................................................................................................................ 6
7. Appendix ......................................................................................................................................... 7
_____________________________________________________________________________________________________
Page 4 of 15
PT. MALEA ENERGY ITP - Piping Fabrication and Installation
1. Purpose
This inspection and test plan is intended to be used as a guide to control all
work steps in term of and inspection on piping fabrication at workshop and piping
instalation at Company site location. Assure that all inspection is performed according
to the approved documents and for acceptance criteria. Ensure that all parties involved
have clear responsibility for all work steps.
2. Scope
This document covers all works step of inspection and testing on piping
fabrication at workshop and piping installation at Company site location for new piping
spool, to repair the existing piping system in Company facility, performed by Technical
Maintenance (TM) team or Contractor (CTR) at workshop and site location.
The material scope in this ITP covers material carbon steel and stainless steel.
When any utility engaged with Company Bussines has their own ITP and/or
procedures, it shall be submitted to company for review and approval prior used.
3. Reference
a. ASME B31.3 Process Piping.
b. ASME Code Section II Part A Ferrous Material Specification.
c. ASME Code Section V Nondestructive Testing Qualification.
d. ASME Code Section IX Welding and Welder Qualification.
e. Project Procedures:
i. Insulation Procedure.
ii. Guideline for Lifting/Crane Operation Management System.
iii. General Piping Fabrication and Installation Procedure
iv. Joint Integrity Testing Procedure.
v. Non Conformance Procedure.
vi. Post Weld Heat Treatment Procedure.
vii. General Piping NDT Procedure.
viii. Piping Pressure Testing Procedure.
ix. Company Specification for Handhover System & Certification Manual.
x. WPS/PQR
4. Definition
a. CON shall mean construction is a person who is authorized by the company
to do the work
b. NDT shall mean Non Destructive Testing (RT, UT, MPI, DPT)
c. TM shall mean Technical Maintenance, a department within Company who
responsible for doing maintenance of Company facility.
_____________________________________________________________________________________________________
Page 5 of 15
PT. MALEA ENERGY ITP - Piping Fabrication and Installation
5. Abbreviation
a. AFC : Approved for Construction
b. ASME : American Society Mechanical Engineer
c. ASTM : American Standard Testing Material
d. COM : Company’s Commissionning Department
e. CON : Construction
f. DPT : Dye Penetrant Testing
g. MPI : Magnetic Particle Identification
h. NACE : National American Corrosion Engineer
i. OPS : Company’s Operation Department
j. PMI : Positive Material Identification
k. PQR : Procedure Qualification Record
l. QA/QC : Company’s Quality Assurance / Quality Control Department
m. RT : Radiography Testing
n. TM : Company’s Technical Maintenance Department
o. UT : Ultrasonic Testing
p. WPS : Welding Procedure Specification
6. Legend
a. H (Hold Point)
Work shall not be proceed without formal notification from the assigned
Quality Representative from Company. A signature signifying involvement of
the assigned Quality representative is required on the referenced Quality
Record
b. W (Witness)
Personnel doing the work shall notify assigned Quality Representative
from Company when the work is to be performed so that witnessing activities
could take place. Work does not stop if signed Quality Representative is not
present. A signature signifying involvement of the assigned quality
representative is required on referenced Qaulity record.
c. M (Monitoring)
Verifying work and testing activities on an ongoing basis as deemed
necessary, also known as patrol inspection or spot check.
d. R (Review)
Review of document such as procedure, drawing inspection and testing
records etc, at a direction of Company.
e. P (Perform)
Perform or provide or prepare or execute the inspection point
f. A (Approved)
Defined as acceptance/approving of an plan or action after review or
confirm documents.
_____________________________________________________________________________________________________
Page 6 of 15
PT. MALEA ENERGY ITP - Piping Fabrication and Installation
7. Appendix
No Doc No Description
1 Cutting Report
2 Dimensional Report
3 Flange Joint Report
4 Inspection Release Notice (IRN)
5 Insulation Report
6 Material Certificate Register
7 Material Receiving Report
8 NDT MPI Report
9 NDT RT Report
10 NDT UT Report
11 NDT DPT Report
12 Non Conformance Report
13 Pad Pneumatic Report
14 PWHT Report
15 Torque Wrench Report
16 Traceability Report
17 Visual Report
18 Welder Certificate Register
19 Welding Report
20 WPS/PQR Register
21 JI1 Joint Integrity Certificate
22 MP1 Piping Completion
23 MW1 Welding Completion Summary
24 PL1 Punch List
25 SL1 System Leak Or Service Test
_____________________________________________________________________________________________________
Page 7 of 15
MALEA HEPP STAGE I (2 x 45 MW) ITP - Piping Fabrication and Instalation
Legend :
INSPECTION TEST PLAN M : Monitor P : Perform
PIPING FABRICATION A : Approve R : Review
Doc. No. : {put here doc no} W : Witness H : Hold Point
1.1 Shop Drawing AFC Drawing Approval Drawing Isometric Drawing P R/A
Fabrication Procedure;
1.2 Fabrication Procedure Fabrication Procedure Relevant specification P R/A
Code/Standard
Piping Pressure Testing
Piping Pressure Testing Piping Pressure
1.3 Pressure Testing Procedure Procedure; P R/A
Procedure Testing Procedure
ASME B31.3 Par.345.1
ASME B31.3
ASME Sec IX ASME Sec. IX, Art-2
1.4 WPS/PQR WPS/PQR Register P R/A
Migas Regulation ASME B31.3, P.328.2
84.K/38/DJM/1998
ASME B31.3
Welder Performance ASME Sec IX Welder Certificate ASME Sec. IX, Art-3
1.5 P R/A
Qualification Test Migas Regulation Register ASME B31.3, P.328.2
84.K/38/DJM/1998
ASME Section V
Approval General
ASME B31.3 ASME B31.3; Table
1.6 NDT Procedure Piping NDT P R/A
General Piping NDT 341.3.2
Procedure
Procedure
ASNT-TC-1A
1.7 NDT Personal Certificate Personal Certificate ASME Sec. V, P R/A
ASME Secton V
1.8 Insulation Procedure Insulation Procedure Approval Procedure Insulation Procedure P R/A
_________________________________________________________________________________________________________________________________________________________________
Page 8 of 15
MALEA HEPP STAGE I (2 x 45 MW) ITP - Piping Fabrication and Instalation
Legend :
INSPECTION TEST PLAN M : Monitor P : Perform
PIPING FABRICATION A : Approve R : Review
Doc. No. : {put here doc no} W : Witness H : Hold Point
1.9 PWHT Procedure ( If any ) PWHT Procedure Approval Procedure PWHT Procedure P R/A
2 MATERIAL
Data Sheet;
Material Certificate
2.1 Review Material Certificate Material Certificate Drawing; P R
Register
ASTM Material.
Material Inspection & Material Receiving
2.2 Material Specification; ASME B31.3 Par-323.1 P W
Verification Report
3 FABRICATION
3.1 Marking and cutting AFC Drawing Cutting Report AFC Drawing, P M
_________________________________________________________________________________________________________________________________________________________________
Page 9 of 15
MALEA HEPP STAGE I (2 x 45 MW) ITP - Piping Fabrication and Instalation
Legend :
INSPECTION TEST PLAN M : Monitor P : Perform
PIPING FABRICATION A : Approve R : Review
Doc. No. : {put here doc no} W : Witness H : Hold Point
Piping Fabrication
4.1 Weld visual check Visual Report ASME B31.3 T.341.3.2 P W
ASME B31.3
Temporary Attachment (tack Piping Fabrication Visual Report;
4.2 ASME B31.3 T.341.3.2 P W
weld) ASME B31.3 NDT Report
Approved Drawing
4.3 Identification Weld Traceability Report ASME B31.3 T.341.3.2 P W
ASME B31.3
PWHT, include hardness test, PWHT Procedure PWHT Procedure
4.4 PWHT Report P W
(if any) ASME B31.3 ASME B31.3 Par.331.1
5 NDT
RT Procedure;
5.1 Radiography Test ( If any ) NDT Requirement Proc RT Report ASME B31.3, T.341.3.2 P W
ASME Sec V Article 2
DPT Procedure Agency
5.2 Dye Penetrant Test NDT Requirement Proc DPT Report ASME B31.3, T.341.3.2 P W
ASME Sec V Article 6
MPI Procedure Agency:
5.3 Magnetic Particle Test (if any) NDT Requirement Proc MPI Report ASME B31.3, T.341.3.2 P W
ASME Sec V Article 7
_________________________________________________________________________________________________________________________________________________________________
Page 10 of 15
MALEA HEPP STAGE I (2 x 45 MW) ITP - Piping Fabrication and Instalation
Legend :
INSPECTION TEST PLAN M : Monitor P : Perform
PIPING FABRICATION A : Approve R : Review
Doc. No. : {put here doc no} W : Witness H : Hold Point
UT Procedure Agency:
5.4 Ultrasonic Test (if any) NDT Requirement Proc UT Report ASME B31.3, T.341.3.2 P W
ASME Sec V Article 5
General Piping NDT Welding Completion General Piping NDT
5.5 NDT Clearance P R
Procedure Summary (MW1) Procedure
6 Pressure Testing
7 PAINTING
_________________________________________________________________________________________________________________________________________________________________
Page 11 of 15
MALEA HEPP STAGE I (2 x 45 MW) ITP - Piping Fabrication and Instalation
Legend :
INSPECTION TEST PLAN M : Monitor P : Perform
PIPING FABRICATION A : Approve R : Review
Doc. No. : {put here doc no} W : Witness H : Hold Point
Final Paint
Completion (AS1)
8 HANDOVER
8.2 Punch List Fabrication Procedure Punc List (PL1) Punch List Close P A
_________________________________________________________________________________________________________________________________________________________________
Page 12 of 15
MALEA HEPP STAGE I (2 x 45 MW) ITP - Piping Fabrication and Instalation
Legend :
INSPECTION TEST PLAN M : Monitor P : Perform
PIPING INSTALLATION A : Approve R : Review
Doc. No. : {put here doc no} W : Witness H : Hold Point
Level Inspection
No Work Activities Reference Document Verified Documents Acceptance Criteria Remark
CTR QA/QC COM OPS
1 DOCUMENT REVIEW
Material/Equipment
1.1 Certificates Certificate Certificates P R - -
Certificate/Calibration
1.6 Insulation Procedure (If any) Insulation Procedure Approval Procedure Insulation Procedure P R R R
_________________________________________________________________________________________________________________________________________________________________
Page 13 of 15
MALEA HEPP STAGE I (2 x 45 MW) ITP - Piping Fabrication and Instalation
Legend :
INSPECTION TEST PLAN M : Monitor P : Perform
PIPING INSTALLATION A : Approve R : Review
Doc. No. : {put here doc no} W : Witness H : Hold Point
Level Inspection
No Work Activities Reference Document Verified Documents Acceptance Criteria Remark
CTR QA/QC COM OPS
_________________________________________________________________________________________________________________________________________________________________
Page 14 of 15
MALEA HEPP STAGE I (2 x 45 MW) ITP - Piping Fabrication and Instalation
Legend :
INSPECTION TEST PLAN M : Monitor P : Perform
PIPING INSTALLATION A : Approve R : Review
Doc. No. : {put here doc no} W : Witness H : Hold Point
Level Inspection
No Work Activities Reference Document Verified Documents Acceptance Criteria Remark
CTR QA/QC COM OPS
Final check
Insulation Procedure Insulation Procedure
5.2 (thickness, cover/clamp, condition Insulation Report P W R R
NACE NACE
after installation)
6 HANDOVER
Non Conformance
6.1 NCR (Non Conformance Report) NCR NCR Close P A R R
Procedure
6.2 Punch List Installation Procedure. Punch List (PL1) Punch List Closed P W W R
_________________________________________________________________________________________________________________________________________________________________
Page 15 of 15