Compliance of the project to its ECC and EMP was strictly observed.
The summary status of it is shown in Table 1.
A. Compliance Monitoring
The project proponent is conducting close monitoring on the project’s compliance to the issued ECC and approved
EMP. This is summarized in Table 2.
B. Impact Monitoring
Quantitative analysis of environmental parameters was carried out. It was assessed on how it is seen or felt by the
community stakeholders including the workers. The implementation of the piggery project can give additional
income to the LGU, Villasis, Pangasinan and the workers near the site.
A. Compliance Status
Based on the compliance monitoring, the project is complying with its Environmental Compliance Certificate (ECC)
conditions and Environmental Management Plan (EMP). The total head population did not exceeded its approved
total stocking population and no other facilities were added
V. ATTACHMENTS
The following document(s) was/were attached in support of this report, to wit:
Environmental Compliance Certificate (ECC)