Академический Документы
Профессиональный Документы
Культура Документы
Andreas Georgiades
Heriot-Watt University
School of Energy, Geoscience, Infrastructure and Society
Institute of Petroleum Engineering
Declaration:
Signed. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..
Date. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2
0.1 Summary
Over the past decade extensive natural gas fields have been discovered in the Levantine Sea, in east-
ern Mediterranean. In a politically tense region with no prior experience in large-scale hydrocarbon
production, with no existing upstream and midstream infrastructure and with the final quantities
being unknown each decision to be taken carries a vast risk. The depth of the prospective fields and
the fact that Cyprus is an island without the possibility of an overland gas export option method,
The purpose of the study is to analyze and compare the options Israel and Cyprus have and
designate which one (if not a combination) will yield the highest returns. Always taking in concern
the past, current and forecasted geopolitical conditions of the area, the energy demands of potential
exporting targets and the current gas transportation technology utilized globally.
Section 0.3 provides an overview of the recent discoveries as well as the inter-nation relation-
ships, the current and expected energy demands, and describes the three main gas transportation
methods applicable (CNG, LNG, PNG) and their limitations. Section 0.5 and 0.6 present the vari-
ous costs each method will incur and the respective profit based on current market prices in Europe
and Asia. The estimated Internal Rate of Return (IRR) is what is finally calculated and used to
The analysis shows that for the quantities already discovered, the distance from the fields to
European mainland, and the current gas prices, CNG would be the ideal option. Something that
verifies previous studies on the subject of optimum gas transportation methods based on distance
and gas reserves (Fig.5). This contrasts the current actions of the involved states which seem to
promote the option of an LNG plant and have already procured the construction of a pipeline to
Greece. The possible reasons for deciding on such solutions are addressed in Section 0.6
Contents
0.1 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
0.5 Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
0.6 Discussion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
0.7 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
Appendices 36
B Israel-Lebanon dispute . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
C Zohr field . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
D LNG projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
3
List of Tables
4 Major assumptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
4
List of Figures
6 Output Vs Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
8 Pipelined NG comparison . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
9 LNG comparison . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
10 CNG comparison . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
5
6
The report intends to analyze and define the optimum method for the countries in Levant region
to export the natural gas recently found in their Exclusive Economic Zones. The study will focus
mostly on Cyprus and Israel, as they are the only two countries along with Egypt that the upstream
stage has already started. Egypt’s energy needs do not allow for export, therefore those quantities
are not taken in concern. The scenario of both countries co-exploiting their reserves is also to be
investigated.
Three methods are going to be discussed. The -widely used- pipeline method to Europe, the
option of liquidizing natural gas and shipping it a) to Europe b) to Asian markets and the third
option of compressing the gas and shipping it to Europe. Shipping compressed gas to Asia will not
be investigated further, as the number of ships required to be built is unrealistic. The results will
be compared with previous literature on the subject of natural gas transportation in other regions
of the world.
For each case the estimates of country’s authorities are taken as a best-case scenario, as well
the author’s estimates based on previous projects as a more realistic-scenario. Different quantity
capabilities for each method will be also projected, since methods like Liquified Natural Gas (LNG)
The research will benefit not only the exporting states, but will also enable financial providers
to assess risk and opportunities of the various options. The process will also point out areas where
Since the ancient times Eastern Mediterranean was a theater of clashes and disputes. The geostrate-
gically important geographical location (being in the center of three continents), the mixture of
religions and the scarcity of basic life sustaining resources like water never gave the area a time to
catch its breath. However, the major hydrocarbon discoveries of the past decade can make-or-break
this fragile region. In the oldest oceanic crust of the world which dates approx. 340 million years
old [8] the U.S. Geological Survey estimates that in the Levant (or Levantine) Basin alone almost
120 Trillion cubic feet (TcF) of gas are present [9]. As a single field it would have been the fifth
largest gas field in the world (see table 2) however six countries have claimed a part of it. Out of
that six only Cyprus, Israel and Egypt have (at the current point) taken significant steps forward
Figure 2: EEZ on ”Median line principle” [5] Figure 3: Turkey’s suggested EEZ [5]
Cyprus, being the key player resulting from its position and it’s EU membership, relies on diesel
fuel to power up it’s electrical grid; though the main power plan at Vasillikos has the provisions to
switch to gas-powered turbines. The yearly needs of the island hover around 1410MW [10] which
means most, if not all, of the recoverable gas is destined to be exported. Cypriots, who went to war
for unification with Greece, were never in good terms with Turkey, considering the two countries
have been through an armed conflict, and an ongoing claim on the northern part of the island
(the self-declared Turkish Republic of Northern Cyprus (TRNC) from 1983). This causes major
implications from the moment Turkey-backed TRNC disputes Republic of Cyprus (RoC)’s Exclu-
sive Economic Zone (EEZ) and threatens with military action any attempts from RoC for further
exploration and production. Turkey, (who along Israel and USA never signed the United Nations
Convention on the Law of the Sea (UNCLOS)) also disputes Greece’s EEZ limits. They argue that
the island of Kastellorizo shouldn’t have it’s own EEZ (crucial point since it allows Greece’s EEZ
to connect with Cyprus’) but rather Turkey’s EEZ connects with the one of Egypt’s. Fig. 2 and
3 show how the limits would have been under UNCLOS ”median line principle” and how Turkey
argues they should be. This is a key point, as Article 79 of UNCLOS states that ”The delineation
of the course for the laying of pipelines (i.e. the EastMed) on the continental shelf is subject to the
consent of the coastal State” [11]; in our case Turkey. This is the same issue Israel would possibly
The country divided its potentially hydrocarbon-bearing area in 12 blocks (Appendix A), and
awarded Exploration License and Production Sharing Contracts (EPSC) to companies based not
only on economic criteria but also taking in concern the ”nationality” of each corporation; a move
10
that down the road proved wise. Based on the above, Noble got Block 12 awarded, ENI-Kogas
Blocks 2,3,9 and Total 10 and 11. Total didn’t renew its license for Block 10 and ExxonMobil with
Qatar Gas jumped on board. Cyprus Hydrocarbon Company (CHC) offers three types of licenses,
Prospection which allows only geophysical surveying(1 year), Exploration which allows 2D/3D sur-
veying and drilling (3 years with 2 renewals allowed), and Exploitation which includes production,
storage and transportation but not refining (25 years with an extension of 10 allowed) [5]. Assuming
the companies achieved a similar agreement with the one Noble did for Block 12, then the govern-
ment is entitled to around 60% of the production [12]. Cyprus agreed on EEZ delimitation with
Egypt in 2003 [13] and with Israel in 2010 [14]. Although an agreement was signed with Lebanon
in 2007, it was never ratified by the latter, as they dispute Israel’s maritime limits and therefore
Cyprus-Israel’s agreement [15]. Point 1 in the graph (Appendix B) is claimed by both countries.
The island’s first major (and still the only confirmed) field is ”Aphrodite”, discovered by Noble
in 2011 inside Block 12. The estimates quantify the Levant-basin field at 7 TcF of natural gas,
with a gross of 5 to 8 Tcf [16]. Although some dry holes by Total and Eni brought some initial
disappointment, the recent discovery of ”Zohr” field in Egypt, amongst the largest in the world
(see table 2), restored the hopes of everyone. The reason behind it being the fact that Zohr is only
6km away from Cyprus’ Block 11 (Appendix C), but also that the source of Zohr is assumed to be
the ”Eratosthenis” seamount [17], the latter being inside Cyprus’ EEZ.
Israel followed a parallel timeline, though with totally different complications. Constantly in
a hostile relationship with the arab states surrounding him, he did manage to move the gears of
its gas-powered industry covering 40% of its needs from Egypt (along with Jordan the only two
countries officially in peace with Israel) [18]. This came to an abrupt end in 2011, when the Egyp-
tian president Hosni Mubarak was overthrown and replaced with Mohamed Morsi. Morsi, unlike
his predecessor, didn’t enjoy the idea of his country providing Israel with gas. As a result of the
reduced security measures in the Sinai peninsula, the ”El-Arish” pipeline was attacked, terminating
the gas supply not only to Israel but also Jordan [19]. When Abdel Fattah el-Sisi replaced Morsi in
2014 the situation normalized, but by that time Egypt requirements in gas were far more than what
it could produce. In less than a decade, the same pipeline that was feeding Israel from Egypt can
now provide Egypt the much needed gas from Israel’s fields. Its relationship with Turkey is equally
11
stormy. Once the closest of allies, however Recep Tayyip Erdogan’s transformation of the country
to a more theocratic state and the ”Mavi Marmara” incident in 2010 were 8 Turkish nationals
were killed by Israeli commandos shattered any chance of the two powerful states becoming what
they used to be. Nevertheless and in the unlikely case Israel would want to export gas to Turkey
through a pipeline, it would still be unable to do so, since Cyprus wouldn’t allow the pipeline to
pass through its waters and Syria doesn’t even recognize Israel as a legitimate country. As a result,
the realpolitik of the area formed a new strong alliance, that of Cyprus and Israel. The two nations
graduated from a neutral relationship to a stage where Israeli fighter jets are now the most frequent
users of Cyprus military airfields. In 2013 the duo signed with Greece a Memorandum of Under-
standing (MoU) which, amongst others, included military cooperation to protect the region’s O&G
infrastructure [20] [21] and in April, 2017 a preliminary agreement for ”EastMed” was signed. A
2,200Km underwater gas pipeline that would connect the Levant fields to mainland Europe through
Israel’s gas fields discoveries came like manna from heaven. The estimates for the yet-to-be
developed fields -including ”Tamar” that came in production 4 years ago- reach approximately 40
TcF (see Table 1), enough to make the country a major regional exporter. Unexpectedly though,
the issues arise when the government was unable to attract the big O&G firms (unlike neighboring
Cyprus). People argue that two major reasons contributed to that, first and obvious, the relation-
ship the Jewish state has with it’s Arab neighbors. Big energy players wouldn’t want to see their
piece of the pie in countries like Qatar and Iran shrink, for the prospect of a possibly marginal
profit in Israel. The second but equally important reason is the hesitation -and internal legislative
”instability”- of the state to decide if and how much to export [22]. It was the same reason that
led Australian Woodside to resign of her rights to buy 25% of Leviathan’s field. That was a ma-
jor step-back, as Woodside’s expertise in LNG was something Tel Aviv was counting on [23] [24] [25].
12
In Egypt the political turbulences that brought the country to the brink of a civil war shook
the energy foundations as well. Once a heavy exporter of oil and gas, Sisi’s maneuvers diverted
the production to the country’s own plants. And while an obvious buyer for Israel’s and Cyprus’
exports, the recent discovery of ”Zohr” came to switch balances again. ”Zohr”, estimated to hold
up to 30 TcF of gas [26] [27], will be the 20th biggest field globally (see Table 2), driving the
country’s production to surpass its consumption by 2020 [26]. It is worth noting that Egypt has
two underutilized LNG plants, one ENI-supoorted in Damietta, and one BG-supported in Idku.
Energy forecasts. Before one identifies exporting targets, demand for natural gas must be es-
tablished. Fortunately, the future looks bright for the major gas-producers as the majority of
technical reports forecast an increasing demand in the upcoming years. BP estimates that by 2040
the daily gas consumption will rise to 500 Billion cubic feet (BcF) from approximately 350 which
is now [28]. In EU alone, McKinsey demonstrates a 5.5% import growth from 2016 to 2017 [29]. In
2012 the Union imported 11 TcF, last year it rose to 14.4 [30] [29]. Various reasons are behind this
13
increased demand, one major being the fact that many countries due to environmental regulations
are switching from ”dirtier” energy sources to greener ones (e.g. China from coal), but also to re-
duce dependence on one source/supplier. Another notable reason as this report investigates further,
is the reduction of gas transportation costs (with methods like LNG); something that made the
valuable energy source a global commodity rather than just being traded in closed regional markets
like before. The reduced costs, the increased availability and the ability to negotiate better prices
(now ”spot contracts” were possible), all contributed to the rising demand. A point to be made
is that Europe’s only ”own” field (Croningen) is depleting fast, with Netherlands already cutting
Gas transportation. The targeted buyer and the transportation mean (therefore cost) are not
only interconnected but they create a loop. More isolated buyer, higher price to pay, higher the
transportation cost. That is, if the estimated reserves verify; otherwise the exporter stays with
a multi-billion dollar investment but not enough gas to make it profitable. The report compares
three major ways of transporting gas. Transported as underwater Pipelined Natural Gas (PNG),
shipped as Liquified Natural Gas (LNG) and shipped as Compressed Natural Gas (CNG). There is
a fourth way called Gas To Wire (GTW), however it is neither in the author’s technical expertise,
Gas transportation through pipeline is up to now the most common practice implemented. The
straight-forward construction and technical simplicity provided a cheap way to transfer gas straight
from the wells to the buyer. However PNG has three major disadvantages. Firstly it will tie you
to only one market. If the buyer decides for any reason that he does not want to buy more gas
from you then another pipeline has to be build to reach other markets, if any. Similarly, if more
gas fields come to production but the buyer does not require more than what was agreed. Second,
a single pipeline -especially if overground- its totally exposed and offers an easy target to anyone
ill-intended. While this may not be a problem in e.g. Northern Europe, in Middle East (as the
Egypt-Israel pipeline case) definitely poses an issue. The third reason and the most important
being that a pipeline becomes unprofitable in large distances. Currently the longest operational
underwater pipeline is the ”Nord Steam”, which transfers gas from Russia to Germany. At 1,224
Km it cost $9.76 billion to be built, and transfers 1.94x1012 f t3 per year [32]. As a reference, the
proposed ”EastMed” will have to cover a distance approximately 2,000 km. Fig. 4 and 5 show
14
a comparison of the optimum distance for each transportation method, the left being from 2008,
the right from 2012. Although many small parameters make each study unique, the reduction in
costs in just 4 years was tremendous. The shrinkage of the pipeline area was not because it became
more expensive, rather than other means became more affordable. Where CNG was profitable up
Figure 4: Optimum transp. methods 2008 [6] Figure 5: Optimum transp. methods 2012 [7]
While a precise cost of the ”EastMed” is yet to be defined, the officials agree that it will cost
around $7 billion [18] [33]. Some argue that the number is a very optimistic approach and doesn’t
represent reality so for analysis purposes both cases ($7 and $10 billion) will be examined. How-
ever, they seem to disagree on the capacity of the pipeline under that cost. Israel’s energy minister
talks for approximately 8 to 10 bcm/year [33], while the official contractor of the project says 10
bcm/year [34] and the Greek Public Gas Corporation argues for 8 bcm/year [5].
LNG allowed for the economically-feasible transportation of gas in large distances. This is
achieved by liquidizing the product at a temperature of -162 Celsius (-260 Fahrenheit), which in
turn reduces the volume of the gas to 1/600th of what it would have been in normal surface condi-
tions. The liquefied product is then transported globally using specialized LNG ships, which they
will transport the gas to re-gasification plants. Most of the ships currently operating or being built
have a capacity of 140,000 m3 (5,000,000 f t3 ) however the range extends up to 260,000 m3 [35].
As per 2017 prices, a 174,000cm ship costs $182 million and these numbers are going to be used
as a benchmark for our analysis [36]. Charter rates for such vessels vary around $70-$80,000 per
Estimating LNG plant costs is even harder to do. The statistical sample is a very small one and
spans from different years all over the globe. While technology improved and allowed for shrinking
costs, the rise in price of raw materials like steel counter-effected that. What is accepted widely
though, is that LNG follows economics of scale, meaning that the higher the production the lower
the cost. However, caused by the reasons mentioned above, is hard to quantify that ratio. Appendix
D shows the variance of CAPEX Vs output for various projects in different time periods. The only
qualitative meaningful comparison one can make is of projects of the same year in the same area.
The only such case is 2009 in Qatar, where indeed a higher output plant dropped the production
cost per unit. Ernst and Young claim that you should assume $2.6 billion per Million Metric
Tonnes Per Annum (MMTPA) of the plant’s output [3]. A analysis of Table 3 provides a similar
value and an equation (Fig. 6) which will be used to estimate the proposed Cyprus LNG plant cost.
As a general rule of thumb, for every MMTPA capacity of the plant, a reserve of 1 TcF should
be there in order for the project to be economically viable [37]. Noble in 2012 estimated the cost of
exporting LNG from Cyprus to Asia around $7.8/MMBTU. Cypriot authorities claimed that the
proposed plant on the island would cost $9 billion ($3 billion for the infrastructure and $6 billion
for one train) [10]. However it would only cost $3 billion more for each extra train they would want
to add to the plant. This translates to a $12 billion plant with a 10 MMTPA output. Although
this seems like an over-optimistic approach, for comparison purposes it will be included as a best
case scenario.
CNG is a relatively new technology, which acts as an alternative solution when the distance or
quantity do not justify LNG or pipelines. CNG requires minimum infrastructure as the compres-
sion of the gas is being done on-board. This low CAPEX is the main advantage of the method.
However, a CNG vessel can carry much less than an LNG one, almost 2.4 times less [38]. A typical
new-generation ship has a capacity of up to 500 MMf t3 [39]. For the subsequent analysis is taken
as a given that a 330 MMf t3 coselle-type ship costs $115 million and as a worst case that the cost
rises to $200 million [40]. Another, downside of the CNG method is that the first vessel -the Jayanti
Baruina- was only delivered 2 years ago. This means there are not many vessels globally available
and, assuming they are all tied to a long-term contract, an interested party would have to construct
them from scratch; obviously delaying economical exploitation of the products by a large margin.
17
• For the majority of data regarding gas consumptions, productions and imports, the statistics
• Technical data for LNG, CNG, and pipelines were taken from SPE publications and conference
proceedings.
• The timeline and the sequence of events was constructed from reputable news agencies.
• Regarding legal definitions, the Law of the Seas, delineation agreements and EEZ maps, those
• The stance of regional (and-non) geopolitical powers was researched in the press but also in
• Lastly, agreements between Government entities and hydrocarbon corporations regarding (but
not limited to) the terms of Exploration License and Production Sharing Contracts (EPSCs)
• For the Internal Rate of Return (IRR) calculations we assume 1 year for con-
necting/tapping on the live wells and 20 years of production. However for the
CNG plan due to the unavailability of ships (and the time-consuming production
of them) we assume 1 year for each ship to be constructed before the full fleet
starts sailing.
0.5 Results
Two cases were analyzed for the pipeline scenario estimations; Case 1 being the cost as argued by
region’s officials, and Case 2 acting a worst case scenario where the cost rises to $10 billion USD.
For each of the two cases the costs of three different capacities were calculated, in order to assess
the profit impact a higher or lower performance pipeline would have. Based on the cost/capacity
relationship the cost per MMBTU was estimated and the respective revenue by use of the cur-
rent gas prices given in Table4. The Total Net Revenue was calculated assuming one year of zero
production and the full construction cost deducted, followed by 20 years continuous production at
the respective capacity. Maintenance costs were not taken in concern as they were considered minor.
Case 1 Case 2
9
Construction cost (10 ) $7 $10
Capacity (109 f t3 /yr) 250 353 424 250 353 424
LNG costs were broken down to two parts, one being the construction of the LNG plant and the
other buying the vessels. As seen in section 3.0 the construction costs are depended on the output
capacity of the plant (which is in turn bounded with the estimated discoveries), hence three different
plant sizes were analyzed. These three scenarios were investigated in Case 1 using the estimated
costs Cyprus government provided, and in Case 2 the author’s estimate based on previous projects
(Fig. 6 and Table 3). Since the LNG carriers are assumed to be bought and not built the IRR
calculation was based again on one year construction and 20 years of continuous export. The same
construction estimations were used for the case where LNG was to be exported to Asian markets
(table 7). In this case there is a higher cost associated with the larger amount of vessels required,
but an increased revenue due to the higher LNG price currently in that region.
20
Case 1 Case 2
Reserves (1012 f t3 ) 5 10 15 5 10 15
(1-train) (2-trains) (3-trains) (1-train) (2-trains) (3-trains)
Capacity (109 f t3 /yr) 250 500 750 250 500 750
Capacity (1012 BTU/yr) 273 546 819 273 546 819
No. of LNG vessels(109 $)* 0.55 1.11 1.66 0.55 1.11 1.66
LNG vessel Cost (109 $)** 0.182 0.364 0.364 0.182 0.364 0.364
LNG vessel Cost 0.035 0.035 0.024 0.035 0.035 0.024
($/MMBTU)
*,** Although, under these calculations, the ship would be idle half the year it would still be
more beneficial than leasing one. The leasing option can be examined in the 10 TcF case. For the
calculations we assumed 1 ship to be bought in the 5 TcF case and 2 ships for the 10 and 15 Tcf cases.
The same three possible reserve quantities were used to evaluate the option of CNG (Table
8). The complication in this case would be the fact that the vessels will have to be ordered and
constructed, as is a relatively new technology and not a market pool where one can buy from.
Hence, the IRR (contrary to the other two cases) was calculated with the assumption that each
ship required would take a year to complete. In a real life scenario exports are to start as soon as
the first ship is delivered therefore our study acts as a worst case scenario where no profit exists
Case 1 Case 2
Reserves (1012 f t3 ) 5 10 15 5 10 15
(1-train) (2-trains) (3-trains) (1-train) (2-trains) (3-trains)
Capacity (109 f t3 /yr) 250 500 750 250 500 750
Capacity (1012 BTU/yr) 273 546 819 273 546 819
Reserves (1012 f t3 ) 5 10 15
Capacity (109 f t3 /yr) 250 500 750
Capacity (1012 BTU/yr) 273 546 819
0.6 Discussion
The analysis tried to cover the various estimations provided by the respective authorities and
key persons. Although, in all cases the project is profitable, it is easily noticeable that if the cost
increases to 10 billion US dollars -as critics argue- there will be a major drop in profits. This is
not a distant scenario and should not be treated as such, since the depth and uncertainties of the
project classify it as high risk, which will probably incur unexpected expenses. In the most likely
case of the approximately 10 BcM per year, which is the contractor’s estimate, this cost increase
Another useful extract, is the fact that even in the highly unlikely scenario that Cyprus alone
does not discover any more natural gas, Aphrodite on it’s own with the 5 TcF proven reserves can
sustain the construction of the pipeline. However, this is not a decision that is to be made purely
on economical criteria. As mentioned in the previous chapter, a laid pipeline requires permission
from the states their EEZ is being affected. Given the conditions in the east Mediterranean and the
claims over the area west of Cyprus, it is not expected for the construction to proceed smoothly.
Any delays in a project of this magnitude will increase an already negative cash flow and lower the
expected IRR.
The variation grows wider in the analysis of the LNG option and this is mainly caused by the es-
timates given by the Cyprus government. The projected cost for the construction of a 1-train plant
seems reasonable (Uni. of Columbia gives a typical 11-16% IRR for LNG projects [41]), however
the $3 billion extra cost per train can be considered over-optimistic. Although the calculations do
not take in concern the cost of bringing the gas to wellhead, it is still widely deviated from Noble’s
$7.8/MMBTU estimation. Under Noble’s price, exporting in LNG even to Asia is not economically
beneficial.
24
Using a more realistic scenario (Case 2) based on the cost of previous projects (which match the
E&Y estimations) the LNG option would only make sense to be examined further if Asia was the
targeted destination. As previously mentioned, the LNG method provides freedom of altering your
buyers, however the seller enters a more competitive market. Asian countries have no geopolitical
reason to buy from an EU member state; unlike the case of pipelined gas to Europe. An extra
cost which could also have an impact would be the tolling system at the Suez canal. These costs
have not been incorporated in the study, and should be before a final decision is to be made. For
reference purposes, an average-sized LNG carrier with a Suez Canal Net Tonnage (SCNT) of 30,000
One must also not overlook existing agreements/investments made by the involved production
companies. ENI owns 40% of Damietta’s LNG idle plant. Given the recent Zohr discovery it would
make much more sense for the Italian giant to divert all the produced gas to an already constructed
CNG analysis display a different pattern. Contrary to the previous methods investigated, it is
25
observed that the rate of return acts in reverse of the quantities planned for export. This has to do
with the fact that CNG is a relatively new technology and ships are not available to be immediately
bought, therefore they have to be constructed. This adds years (assumed 1 year for each ship to
be constructed) before profit can be made. The analysis covers the East Med - Greece route but
not Asia, since building 75 ships to transport the minimum of 250 Bcf to Korea is not a realistic
case. However, as seen on the next figure, even in the worst case scenario that there will be no cash
income until the whole fleet is completed, the IRR is still the best possible option in all cases (with
one exception to be discussed). That value can only increase, since some ships will start delivering
before the whole order is delivered. If multiple shipyards are employed the construction time will
What is clear from the overall method comparison, is the fact that CNG looks as the most
profitable way to go, whether is to develop a single field the size of Aphrodite or combined fields.
The only case CNG is not the way to go is if Cyprus estimates for it’s LNG plant are achievable
and if Israel agrees to co-export. However, the previous case studies and currently running LNG
plants indicate a much lower return. In fact, based on those rates, LNG is the least profitable way
to go in all cases. A case where pipelined natural gas to Greece could be more profitable is the
possibility of the pipeline being able to carry 12 BcF/yr as Israeli officials mentioned, not a likely
26
option though since most official technical reports insist on the 10 BcF/yr.
It’s surprising that Cyprus has not investigated the CNG option despite the fact that it has been
suggested by many established engineers and scientists [42] [43] [44] [3] while the pipeline agreement
is already signed and LNG studies present that option as ideal. It is the author’s opinion that this
is based on three reasons. One being the pressure as well as the financial support from EU to
access the East Med gas. The pipeline will bind a steady supply to an energy-thirsty market, and
the funds already released for the construction lower the cost making it the quickest and cheapest
option for the involved parties. Second reason being the LNG numbers CHC presents, as well as the
high expectations for further discoveries. The later is not to be taken lightly as is highly unlikely
Aphrodite will be the only field available for export. In fact the most promising blocks are yet to be
drilled and quantities might reach levels being less profitable with CNG. The third possible reason
LNG option is promoted is a geopolitical one. As seing in the previous chapters, Israel -and the
companies involved- favor the option of a plant that would be based in an EU state, unreachable
from insurgents and possible extremist acts. Cyprus will benefit as well, since increased quantities
will lower the cost and they will be having a powerful neighbor with active interests on the island.
However, the lack of confirmed reserves at the time, the cost of opportunity with CNG, PNG op-
tions, and the assumed preference of ENI in utilizing it’s own plants in Egypt do not favor this
option.
Comparing with the figures from previous studies [4,5], some expected conclusions are extracted.
If one compares with the most recent study 5, this report’s findings match perfectly. CNG is by
far the preferred method and as quantities increase the pipeline option becomes more profitable;
this follows the trend shown in Fig.11. However, going four years back, LNG would have been the
most profitable option. The advances in CNG technology almost doubled the profitable distance
There are two options that have not been analyzed for reasons to be explained. The first being
the construction of a pipeline from Cyprus to Turkey, which in turn to be connected to the existing
network transferring natural gas to Europe. This would require only a minor (less than 100km)
underwater pipe laying, with previous studies arguing a cost of approximately $2.4 billion; the
27
above including the cost of the pipeline from the fields to mainland Cyprus [5]. For a 10bcm/year
pipeline -and the remaining assumptions unaltered- this translates to a rough IRR of 32%. Under
this case, the pipeline is now marginally the most profitable option, a result that is being verified by
the ”optimum transportation methods” (chart: 5). The reason for this development scenario not
presented or suggested is the author’s point of view that the possibility of such an agreement taking
place is close to zero. This, given the troublesome relation between the two countries, including
the non-existing will to recognize any official entities from both sides, the presumed wish of EU to
detach from a single gas supplying route and maximize its options, and lastly the fact that no nation
would want its main source of income to be controlled by a third party other than him and the buyer.
The later is the reason that the option of Cyprus (and probably Israel) liquidizing the gas in
Egypt’s LNG plants under a tolling scheme and then selling them as LNG is not investigated.
Added to that, and although the numbers for such a speculative scenario are not known, it is
highly unlikely that quantities more than 5 TcF in a 20-yar period would justify ”renting” and not
Given the willingness of EU to fund the EastMed pipeline, the fact that the majority of the
blocks are yet to be explored (therefore quantities are still unknown) and that Noble’s Aphrodite
will come on-line much earlier than the remaining fields, it is the author’s opinion that Cyprus
and Israel should proceed with two options. First constructing the pipeline to Greece with the cost
covered in the biggest percentage possible from European funds, to an extend that would shrink the
profitability gap with CNG. The fast construction of the pipeline will allow a guaranteed income as
soon as the two countries have quantities to be exported, with the minimum risk as this scenario
can be sustained with the smallest quantities. Meanwhile, and as soon as there is a clearer picture
for the remaining quantities the construction of CNG ships can be initiated (provided that there
are more than 5 TcF for export, on top of the 5 TcF covered by the pipeline). In the unlikely
event that a Zohr-size field is discovered then the option of LNG can be re-evaluated. This will also
depend on the LNG price in the Asian markets which is expected to rise; a possible scenario since
the region is vastly growing with new markets in Indochina emerging. The above suggestions are
based on the assumption that the numbers Cyprus provided for the LNG plant are not achievable
and that previous case studies’ costs are more accurate. If a verified business plan can indicate
28
otherwise, then the option of the LNG plant on the island is to be discussed again. The above
variables establish the need to wait for a more accurate reserve estimation, before a development
0.7 Conclusions
As clearly seen in Fig.12 if Cyprus or Israel decide to export on their own, with the current verified
discoveries, CNG would be the most profitable (in terms of IRR) option. Even with the LNG’s best
case scenario, which are the numbers Cyprus’ authorities provided, as long as the exported quan-
tity is 10 TcF or less the LNG is not an attractive option; although economically viable if chosen.
However, if the upcoming discoveries match the two nation’s expectations and the gas prices in Asia
stay or increase from the current benchmark, then the liquefied gas option can possibly exceed the
returns of a CNG project. These optimistic expectations combined with the decision to co-exploit
some of the fields, the risk of CNG’s relatively new technology and the time it will take to construct
the ships is possibly what drives the two countries to favor the option of constructing an LNG plant.
The option of a pipeline, although not as profitable as the CNG, offers a faster and cheaper
option at least for the first exported quantities. Europe’s need for new energy sources and it’s
willingness to finance a percentage of the pipeline’s cost, the lower CAPEX required, the option
of neighboring countries tapping in at the future and the uncertainty of the final volume of gas
available for export justify the decision made to proceed with the construction of the EastMed
at the current stage. The only certainty derived from the analysis is that Cyprus and Israel will
increase their profits if they proceed with exporting their natural resources together, and given the
tense geopolitical conditions in the region they have both to gain by cooperating and deciding on
• Wellhead costs/price should be estimated. Added to the the costs estimated above might
make some of the suggested methods unprofitable. This is more likely in the case of an LNG
• The tolling scheme in Suez must be analyzed and taken in concern since it will make the LNG
• Floating LNG plants are now emerging and they provide a cheaper and therefore a financially
more attractive option for smaller export quantities. Depending on the discovered fields they
• The potential returns of the pipeline should be recalculated after the final contribution of EU
• A further analysis into Asia’s energy requirements forecast will give a more reliable prediction
about possible price fluctuations and possibly higher returns of the LNG option.
• Jordan can provide a promising export target for Israel given the low cost of an overground
• The increased use of green technologies and regulations in EU (with the rising carbon taxes/fines)
that drive its members to shift to alternative energy sources might reduce the possible profit,
and will make the Asian market (thus the LNG project) a more attractive option.
• Although Greece’s exploration process is still in its early stages, the fields investigated are
located around the island of Crete and in close proximity to the EastMed route. Possible
discoveries will make the pipeline drastically more profitable and extend the utilization period,
in Israel
[2] “Global natural gas reserves – a heuristic viewpoint,” 2017. [Online]. Available:
GlobalNaturalGasReservesAHeuristicViewpoint
[3] A. Pourbozorgi and T. Celik, “Pipeline, CNG top Cyprus gas export options,” Oil & Gas
14D36B5F3DA83182C2257F37003FBE28/$file/MP20111270101.pdf?OpenElement
[5] A. Gürel, F. Mullen, and H. Tzimitras, “The Cyprus hydrocarbons issue: context,
positions and future scenarios,” 2013, oCLC: 903136957. [Online]. Available: https:
//www.prio.org/Global/upload/Cyprus/Publications/Hydrocarbons Report-ENG.pdf
Natural Gas Sea Transport,” in SPE Russian Oil and Gas Technical Conference and
http://www.onepetro.org/doi/10.2118/115310-MS
http://www.onepetro.org/doi/10.2118/161583-MS
31
32
[8] B.-G. University of Negev, “Three hundred million years under the sea,” 2016. [Online].
Available: http://in.bgu.ac.il/en/Pages/news/Palaeozoic-oceanic-crust.aspx
of undiscovered oil and gas resources of the levant basin province, eastern mediterranean,” U.S.
[10] S. Henderson, “Natural Gas Export Options For Israel And Cyprus,” The German Marshall
[11] UN, “Submarine cables and pipelines on the continental shelf.” [Online]. Available:
cy/posa-aksizei-kai-posa-xanei-h-kypros-ean-yiotheththoyn-oi-aksiwseis-ths-noble-sto-afrodith
LEGISLATIONANDTREATIES/PDFFILES/TREATIES/EGY-CYP2003EZ.pdf
[14] “Cyprus israel agreement for eez,” 2010. [Online]. Available: http://www.un.org/depts/los/
[15] M. Wählisch, “Israel-Lebanon Offshore Oil & Gas Dispute – Rules of International Maritime
20120313041648/http://www.cyprus-mail.com/gas/historic-day-cyprus/20111229
[17] E. Hazou, “Egypt’s gas bonanza sourced in cyprus’ eez,” Carbonlab, 2016. [Online]. Available:
http://www.carbonlab.eu/2016/03/17/egypts-gas-bonanza-sourced-in-cyprus-eez/
[18] “Israel has a gas conundrum,” Aug. 2017. [Online]. Available: https://www.economist.com/
middle-east-and-africa/2017/08/17/israel-has-a-gas-conundrum
[19] D. Fink, “Turning Off the Egyptian Gas Spigot: Implications for Israel,” May 2011.
turning-off-the-egyptian-gas-spigot-implications-for-israel&catid=116:content0411&Itemid=
375
33
[20] Y. Azulai, “Israel, Greece, Cyprus sign new energy MOU,” Aug. 2013. [Online]. Available:
https://en.globes.co.il/en/article-1000870108
[21] “Israel, Greece, Cyprus to export electricity to EU,” Aug. 2013. [Online]. Available:
http://www.financialmirror.com/news-details.php?nid=30669
[22] A. Barkat, “Where are the oil majors?” Jun. 2012. [Online]. Available: https:
//en.globes.co.il/en/article-1000754393
[23] K. Yeshayahou, “Energy minister warns Tamar partners not to sign export deals,” Mar. 2013.
[24] “Israel takes step towards becoming a gas exporter,” Feb. 2014.
update-2-woodside-pays-up-for-smaller-stake-in-israels-leviathan-gas-field-idUSL3N0LB5KU20140207
[25] G. Luft, “Israel’s Zero Gas Game,” Journal of Energy Security, Aug.
israels-zero-gas-game&catid=137:issue-content&Itemid=422
05/euregas
eni-discovers-largest-known-mediterranean-gas-field
energy-economics/energy-outlook/demand-by-fuel/natural-gas.html
[29] M. Czajkowski, “The 2017 european gas market in 10 charts,” McKinsey, Tech.
the-2017-european-gas-market-in-10-charts/
[30] M. Ratner, P. Belkin, J. Nichol, and S. Woehrel, “Europe’s Energy Security: Options and
Challenges to Natural Gas Supply Diversification,” CRS Report for Congress, p. 33, Aug.
2013.
34
[31] G. A. Brooks, “A dutch gas bubble could create global indigestion,” 2014. [Online].
features/featureunderwater-arteries-the-worlds-longest-offshore-pipelines-4365616/
[33] “Israel expects decision on east med gas pipeline to europe in 2019,”
israel-expects-decision-on-east-med-gas-pipeline-to-europe-in-2019-idUKKCN1GK2OI
[35] “The world fleet of lng carriers,” 2010. [Online]. Available: http://www.shipbuildinghistory.
com/today/highvalueships/lngactivefleet.htm
koreas-three-shipbuilders-expected-to-receive-orders-of-lng-carrier/
[37] “Rules of thumb for screening lng developments,” 2012. [Online]. Available:
https://web.archive.org/web/20161008030558/https://www.engineersaustralia.org.au/
sites/default/files/shado/Divisions/Western%20Australia%20Division/Groups/Oil Gas/
lng technical presentation ieaustralia oil and gas division perth october 2012.pdf
Content/ProductsServices/ConferenceandEvents/2013/pc302/presentations/Lyndon Ward.
16-from-shore-to-ship-cng-marine-transportation.html
[40] “Coselle cng: Economics and opportunities,” 2000. [Online]. Available: http://www.ivt.ntnu.
no/ept/fag/tep4215/innhold/LNG%20Conferences/2000/Data/Papers/Stenning.pdf
[41] “Translating gas and lng into money,” 2016. [Online]. Available: http://ccsi.columbia.edu/
files/2016/02/CCSI-Mitro-Webinar-Open-LNG-model-presentation-March-2016-.pdf
35
ural gas. a viable alternative to pipeline or lng,” SPE, Tech. Rep., 2002. [On-
SPE-77925-MS?id=conference-paper%2FSPE-77925-MS
[43] M. J. Economides, K. Sun, and G. Subero, “Compressed Natural Gas (CNG): An Alternative
to Liquefied Natural Gas (LNG),” SPE Production & Operations, vol. 21, no. 02, pp. 318–324,
[44] X. Wang and M. J. Economides, “Modern Marine Transport of Compressed Natural Gas
in 2010,” in SPE Annual Technical Conference and Exhibition. Florence, Italy: Society
133512-MS
[45] B. Ravid, “U.S. Backs Lebanon on Maritime Border Dispute With Israel,” Haaretz, Jul. 2011.
natural-gas-prices-forecast-long-term-2018-to-2030-data-and-charts
Appendices
36
37
[4]
B Israel-Lebanon dispute
[45]
38
C Zohr field
[26]
39
D LNG projects
[3]
40
[46]