Академический Документы
Профессиональный Документы
Культура Документы
1 2 3 4
Legacy DCS What is Rockwell How We Can
Market Dilemma Modernization? Automation® Help
& Outlook Solutions
Challenges:
$65B >20%
Legacy DCS Specialists have
Installed DCS nearing • Downtime
End of Life; many Retired; 3rd Parties in • Risk
demand; often Retirees called • Financial
>25 YEARS old back = Increased Risk Justification
ARC Link
Resource Loss
System / Retirement Inadequate
Failures/Faults Documentation
Support System New Standards
Costs Limitations / Technology
MODERNIZATION
PUBLIC | Copyright ©2019 Rockwell Automation, Inc. | 5
Is it Obsolete… or Not?
Once parts start failing, MANY may fail around the same time
Most users have no model for equipment failures
May need to replace lots of hardware at the same time
Further complicated with loss of competent in-house DCS expertise
1 2 3 4
Legacy DCS What is Rockwell How We Can
Market Dilemma Modernization? Automation® Help
& Outlook Solutions
HA Bus IT Networks
Requirements Integration
Instrument
Updates
Panel Reuse
Drawing Most users don’t have staff focusing on latest
Updates
trends, technologies & best practices.
Resource
Cutover Plan
Training
They don’t know… what they don’t know…
Installation Optimization MAC
PROCESS It’s a process for providing engineering evaluation and assessment prior
to the actual project implementation
THREE FEL is typically broken into three steps: FEL1, FEL2, & FEL3
STEPS
BUDGET Each step has a different technical focus and includes a cost estimate and
SCHEDULE
schedule for implementation
ACCURACY The accuracy of the cost estimate improves through each phase
System architecture
Project schedule
1. Early Planning
2. Establish Standards Ease
3.Execution Discipline
4.Engage Experts
5. Expect Innovation (Don’t Replicate!)
1 2 3 4
Legacy DCS What is Rockwell How We Can
Market Dilemma Modernization? Automation® Help
& Outlook Solutions
Next Replace HMI & controllers Above, plus I/O Scanner Modules
Later Replace HMI, controllers & I/O Above, plus Custom Cable Solutions
IPC-620
ne
available
yw
PlantScape/Experion
el
l
Moore APACS
Si
e
Teleperm M
m
en
s
Fisher PROVOX
Westinghouse WDPF
Blank = no
Rosemount RS3 current solution
Em
Rosemount RMV9000
er
so
n
DeltaV
Ovation
Foxboro I/A
Recent Focus &
Sc
Wonderware
hn
ei
Foxboro Spectrum
d
Improvements
er
Centum CS
Yo
Centum 1000
ko
ga
Micro XL
w
ENABLERS to
a
Freelance
B
System Six
SATTline Modernizations
PUBLIC | Copyright ©2019 Rockwell Automation, Inc. | 20
Tool Assisted Migration Services
Exports from Crawlers / ACM
Legacy System
Reduce Risk
Application Code
Manager
Automated Reduce Timelines
Conversion
Leverage SME’s
Global Consistency
Enforce PlantPAx®
Manual
Conversion
Guidelines &
Recommendations
Fully migrated system
• Review data extracted from Legacy • Graphical representation of Legacy • Graphical representation of Legacy
system logic displays
• Full report containing: • Supports navigation between pages • Identifies animated graphical
• A complete list of all instructions • Click on instructions to: objects
• 1 sheet / instruction type, including all • Review instruction configuration • Report lists all objects & animation
instances & all configuration details • Launch instruction help file • Click graphical objects to Review:
for each instance • Configuration
• Formatted for ACM import • Animation
• Connections
•Commercially Available –
Field Proven
Foxboro IA
Benefits
APACS
• Eliminates
Field Re-wiring
• Reduces
Downtime
• Mitigates Risks
Bailey Provox
• Cost-effective
PUBLIC | Copyright ©2019 Rockwell Automation, Inc. | 25
From 2010 ARC
publication:
Benefits
• 2 modes – Shadow
& Run
Includes
• Cuts costs – retain
SMART
™ I/O legacy I/O
• Fast, low risk
legacy controller
cutover
I/O Bus PROVOX Serial I/O network Serial Remote I/O network
CLASS 1, DIV 2,
GROUPS A, B, C, D
Ethernet
Serial to Enet
Converter Serial to Enet
1. Deploy new EWS Servers
Converter & Networks
CIU
CIU CIU
2. Deploy legacy network
interface
CIU Plant Loop or Infi Loop
3. Create/Test new graphics in
parallel with legacy consoles
PCU 1 PCU 2
4. Replace remaining legacy
consoles with new technology
TU TU
Ethernet Nodebus
CP30/40/60 CP30/40/60
legacy DCS
FBM’s FBM’s
3. Deploy new DCS
Technology
Converts legacy RSLogix™ 5 Graphical, user-friendly software tool that Seamless conversion without
or 500 project export file to automatically defines and configures a removing any field wires in
Logix project for MicroLogix™, contemporary ControlLogix®-based architecture minutes
SLC™ and PLC-5® based on your legacy PLC-5® system
Free download Builds a detailed bill of materials based on your
current PLC-5® based control system
7 step conversion
• Modicon 984
• Modicon Quantum
• GE Series Six
• GE 90/70
• Honeywell IPC620
emphatec.com Link PUBLIC | Copyright ©2019 Rockwell Automation, Inc. | 35
Third-party PLC I/O Scanners from ProSoft
Enet/IP > S908 Enet/IP > TI RIO Enet/IP > Genius Enet/IP > SQD RIO
1 2 3 4
Legacy DCS What is Rockwell How We Can
Market Dilemma Modernization? Automation® Help
& Outlook Solutions
Honeywell Migration Bailey Migration PROVOX Migration Foxboro Migration APACS Migration
MIGDCS-PP005B-EN-E MIGDCS-PP006B-EN-E MIGDCS-PP007B-EN-E MIGDCS-PP008B-EN-E MIGDCS-PP009A-EN-E
Technical Leaders/SME’s
ABB
Emerson
Honeywell
Rockwell Automation®
Siemens
A large global ecosystem for solutions and support of your Rockwell Automation® installed base.