Академический Документы
Профессиональный Документы
Культура Документы
I. INTRODUCTION
Fig. 3. GIL connection between OHL and GIS and GIL cross section
In this project, installation over long distances is the Fig. 5. Robotic GIL welding
subject of detailed investigations. The laying procedure is
considered systematically and rationalized as far as possible.
The different steps of assembling, i.e. welding and laying in
the trench, are illustrated in the following sequence. The
installation tent is located in the middle of the trench and can
be considered the logistic center at the site. Here, all
components are stored after just-in-time-delivery and
mechanical works are performed such as cutting the tubes to
exact length and grinding etc. As can be seen in Fig.4
completion of the GIL modules – in particular insertion of the
conductor - requires a special tool.
9m
loading in the range of the rated values could not be expected is clear that a continuous loading of the GIL of 3150A - i.e.
during the first period of operation, a current transformer was more than 15% above the rated value - is possible in the long-
applied for the current loading tests. The infeed into the GIL term range without any soil desiccation. In the short-term
duct under test at the interface to the GIS and the arrangement range, 2500MVA can be accepted. More detailed
of the current transformers is demonstrated in Figs. 7 a) / b). investigation will be carried out if the thermal simulation
model is adopted.
B. Corrosion Protection
In the first instance the outer tube of the GIL comprises
passive corrosion protection. The measure is comparable to
the plastic sheath of HV power cables: a black polyethylene
layer of some mm in thickness is applied to each tube in the
factory. After the welding procedure on site the welding
sections (approx. 30cm) are protected by the same plastic
material which is sprayed on joint by joint. To gain additional
Fig. 7 a / b. Test arrangement for current infeed into the GIL safety against corrosion which might occur due to external
damage of the plastic sheath, an active corrosion method is
By means of this test arrangement, a loading of 3000A applied.
could be obtained, which is about 10% above the rated value. Fig. 9 shows the circuit diagram of the active corrosion
Fig. 8 shows the record of the enclosure temperature at two protection of the GIL. In principle the outer housing of the
different locations on the GIL duct. From this record we learn GIL is separated from the ground potential of the earth (e.g.
that, after a loading time of about five days, a more or less the GIS ground potential). The tubes are connected to Kirk
stable condition is achieved, i.e. a temperature rise constant of cells which can ensure a negative potential of about 1.5 V
about 36 hours can be expected. The cooling time constant against ground. Overvoltage protection and the ability to
seems a little bit shorter, which might be associated with the withstand short-circuit currents are also implemented in the
special type of backfill material, a sort of liquid soil with a design of the active corrosion protection system.
thermal conductivity of about 2 W/mK.
36
34
enclosure temperature [°C]
location 1
32
location
30
28
26
24
22
20
10
10
10
10
10
10
10
10
0
1
1
.
8.
8.
8.
8.
.7
.7
.7
.7
.7
.7
.7
.7
.7
1.
2.
3.
4.
23
24
25
26
27
28
29
30
31
Fig. 8. Enclosure temperature in the temperature rise test on the complete GIL
installation at 3000 A C. High-Voltage Testing of GIL
The design of single-phase encapsulated GIL comprises
Furthermore, some remarkable findings can be taken from
only a few different parts, such as the enclosure, conductor
this record. The enclosure temperature is only 34°C and thus
and insulators. Prefabricated units are used for assembly of the
well short of the maximum admissible enclosure temperature
GIL by means of welding or flange joints. The conductor is
of 60°C, even regarding that in practice there is an impact of
fixed by conical and post insulators. The insulation system of
the neighbouring ducts which may lead to an additional
GIL is in principle the same as that of GIS. Nowadays N2/SF6
temperature increase of some degrees at 3000A. On the other
gas mixtures with high amounts of N2 are preferred for long
hand, a soil temperature of about 22°C can be detected, which
GIL. Development tests as well as the type tests on GIL are
is considerably higher than the maximum soil temperature of
similar to the related GIS tests, whereas a dielectric routine
15°C assumed in summertime. The reason for that is a
test is only applicable for the insulators.
prolonged period of air temperatures distinctly above 20°C,
Intensive development tests, routine tests and
even at night, which led to a warming of the soil in the area of
commissioning tests are the basis for a reliable design and
the installation in question. The data gained by our
proven product quality. It is also important to obtain a reliable
measurements were proven by data from a commercial
assessment of materials and manufacturing processes. In the
meteorological service. Taking into account all these results it
development test phase all tests on epoxy insulators (for
4
example) have been performed on real-size insulators, and the other test measures are necessary. An insulation breakdown
long-term test voltage amounts to two to five times the sets up travelling-wave oscillation, which can be recorded by
service-voltage stress. The durations of the long-term tests capacitive couplers and used for fault location.
were up to 15,000 hours, and the test results confirmed the Like GIS, GIL exhibits a high degree of reliability.
validity of the inverse power law and the required reliability Nevertheless, a dielectric failure cannot be totally excluded.
of the epoxy insulators [3]. Before initiating repair work the failure has to be detected and
located as precisely as possible. In principal, all methods
D. On-site Tests after Installation
known from other underground lines like cables can be
On-site tests must check the dielectric integrity of the applied. In the event of a breakdown, the voltage collapse
completed installation [4]. The test program identifies produces a travelling wave. This transient phenomenon can be
different types of defects which might give rise to an internal recorded by adequate sensors.
fault in service: incorrect assembly, presence of foreign bodies Since the installation is fitted with PD sensors, these
or other contaminants such as free metallic particles and sensors can be utilized for recording the transients, if the low-
protrusions, as well as damage during transport, storage or voltage capacity is properly adopted. In the pilot installation
installation. the arrangement of the PD sensors is shown in Fig. 11.
The IEC 61640 recommendation for on-site HV testing is
based on state-of-the-art GIS testing and takes into
consideration the characteristics of long GIL [5]. However,
the on-site test procedure is not fixed and an appropriate test
procedure should be agreed for each individual project. For
on-site testing of GIL the UHF PD detection method has been
used with good results. With GIL the distance between
adjacent PD sensors can be greater than several hundred
meters due to the low signal attenuation within a GIL. The
accuracy of on-site testing by power-frequency voltage and
UHF PD detection has already been proven in various past
GIL projects [6]. Fig. 11. Location of the partial discharge sensors
Fig. 10 shows the on-site test procedure which consists of
AC conditioning and testing with variable frequency and As shown in Fig. 12, in this GIL an arc location system
additional UHF PD detection, taking into consideration the (ALS) is installed which is based on analysis of the runtime
recommendations of IEC/CIGRE and manufacturer differences of Very Fast Transient (VFT) signals at various
experience with GIS and GIL testing. positions. At the beginning and at the end of the installation,
sensors with arc location converters are installed. These are
connected to communication modules. One of these acts as
master, the other as slave. Both are connected via a
communication bus system.
III. SUMMARY
Regarding the increasing interest in underground
transmission in EHV systems, GIL represents an attractive
alternative to cable solutions. In the course of this pilot
installation, different aspects were analyzed in detail: design
features, engineering, assembly, fitting on site and the laying
procedure as well as on-site testing were considered.
Temperature measurements have indicated a higher
transmission capability than originally calculated. By means
of a temperature monitoring system exact data has been
collected., thus confirming the operation at higher current
ratings. Along with GIL tunnel and overhead applications,
directly buried GIL will be applied as transmission grows
around the world.
IV. REFERENCES
V. BIOGRAPHIES