Introduction
When one thinks about its background, MRP was essentially SAP’s rst major
supply chain functionality. Before advanced planning, optimization, or other
material planning capabilities, there was the rst MRP in SAP ERP. Originally
developed in the 1960’s, MRP software was at one time sold as an independent
application. However, by the 1980’s it had migrated into ERP systems.
Sales Orders
Purchase Orders
Materials
Stock (there are many di erent types of stock, by only unrestricted and
valuated can be included in MRP) – Also, while optional, MRP should be
set to incorporate the stock in transit.
Material lead times
Components
https://www.brightworkresearch.com/sapplanning/2010/05/01/mrp-in-sap-erp-vs-sap-scm/ 2/10
7/15/2019 What Data MRP System Includes and Excludes • *Brightwork | SAP Planning
Assemblies
Lot Size
Resources / Work Centers
Just as useful is to understand what data a MRP system does not include.
Normal Stock Transfers: Notice that unlike APS systems or DRP, MRP does
not create stock transfers.
Inventory Balancing Stock Transfers: MRP is not rebalancing inventory to
meet future demand the way several supply planning methods do.
Prioritization: MRP does not understand priority. It only knows quantities
and dates, so if a higher priority customer places an order for the product
later than a lower priority customer, the lower priority customer gets the
inventory. However, many companies operate on the basis of customer
priority in addition to the need date, so this is where inventory is either
manually allocated, or allocation software comes into the equation.
Constraints: MRP does not know what is feasible, rather it works backward
from requirements and simply develops a plan based upon this. This is
one of the great limitations of MRP and is one of the main reasons that
constraint-based planning was developed and ourished in the late
1990’s.
Aside from all the related items (or objects) listed about, a bit part of what MRP
does is the arrangement of timings of objects.
To get an idea of how useful MRP is, imagine a material with 100 sub-
components, each with a di erent lead time. MRP uses all of these lead times,
the order date to calculate the planned production or planned procurement
order date. (the material BOM level is also known as the lower level code, with
each level in the BOM having a di erent low-level code.) On the other hand, the
https://www.brightworkresearch.com/sapplanning/2010/05/01/mrp-in-sap-erp-vs-sap-scm/ 3/10
7/15/2019 What Data MRP System Includes and Excludes • *Brightwork | SAP Planning
degree to which the BOM is exploded is a setting in SAP ERP. The BOM does not
necessarily have to be exploded at all.
One of the common questions I receive regarding MRP is how it di ers from
heuristics, which is the next level up in complexity. I will restrict my discussion
here to MRP as it relates to supply planning within SAP (that is comparing MRP
in SAP ERP to the Network Heuristic in SNP).
The rst answer I give is that MRP has many fewer options than does the SNP
Network Heuristic. I will demonstrate this by going through all the options in
MRP and then compare them to the SNP Heuristic.
MRP Settings
1. Here is the rst choice, which is the processing key. This relates to
whether MRP will reprocess everything (called regenerative planning, or
just perform a net change).
2. The second option relates to whether purchase requisitions within the
planning horizon. If they are not created by the system, they can be
https://www.brightworkresearch.com/sapplanning/2010/05/01/mrp-in-sap-erp-vs-sap-scm/ 4/10
7/15/2019 What Data MRP System Includes and Excludes • *Brightwork | SAP Planning
As you can see, these are basic options that have to do with
speci c detailed related to whether to reprocess all orders, how far out to create
procurement orders, etc..
Conclusion
Critics of MRP point out that it was originally designed for manufacturing, and
has been overly or misapplied to distribution. While this is certainly historically
accurate, MRP does a fair job with supply planning, if it not called on to do too
much. However, it is important to understand that MRP contains some
assumptions that are not true (as does advanced planning) and it has
particular limitations. I discuss the assumptions of MRP in my book “Supply
Planning with MRP, DRP and APS Software.“
What may be surprising to many is that MRP was initially developed in the
1960s and widely rolled out to at least large manufacturing rms by the 1970s.
At this time it was considered “leading edge.” Now it’s old hat and not many
academics publish papers on MRP concepts, as operations research and supply
https://www.brightworkresearch.com/sapplanning/2010/05/01/mrp-in-sap-erp-vs-sap-scm/ 5/10
7/15/2019 What Data MRP System Includes and Excludes • *Brightwork | SAP Planning
We have a better track record of being correct than any of the well-known
brands.
Name
First
Last
Email *
Your Question *
CAPTCHA
https://www.brightworkresearch.com/sapplanning/2010/05/01/mrp-in-sap-erp-vs-sap-scm/ 6/10
7/15/2019 What Data MRP System Includes and Excludes • *Brightwork | SAP Planning
References
https://rockfordconsulting.com/the-rise-and-fall-of-mrp.htm
In addition to the book mentioned above, I cover MRP in depth in the following
book.
systems but have shown little interest in tuning MRP systems to work to meet their
potential.
Chapters
Chapter 1: Introduction
Chapter 2: The Opportunities to Improve MRP
Chapter 3: Where Supply Planning Fits Within the Supply Chain
Chapter 4: MRP Versus MRP II
Chapter 5: MRP Explained
Chapter 6: Net Requirements and Pegging in MRP
Chapter 7: Where MRP is Applicable
Chapter 8: Specific Steps for Improving MRP
Chapter 9: Conclusion
Appendix A: Calculating MRP
Software Ratings
Brightwork Research & Analysis offers the following free supply planning software
analysis and ratings. See by clicking the image below:
https://www.brightworkresearch.com/sapplanning/2010/05/01/mrp-in-sap-erp-vs-sap-scm/ 8/10
7/15/2019 What Data MRP System Includes and Excludes • *Brightwork | SAP Planning
SAP ERP
MRP System
Flaws in SAP’s Collaboration Technology
Finite and In nite Scheduling in PP/DS
Our Focus
Our primary focus is on performing and selling research on SAP and Oracle. This is both in-depth
and realistic research that is not available to our customers anywhere else.
Brightwork Research & Analysis provides entirely independent research in many areas in enterprise
software without any in uence from vendors or consulting rms. None of the articles on the site are
paid for by external entities. We o er independent consulting matching our research. To see our