Академический Документы
Профессиональный Документы
Культура Документы
One of the main objectives for the drilling engineering is to create a possible
design of wells from the targets that has been given from the reservoir engineer
whenever possible.
This can be done by first aim is to know the location of the targets,
obtain information of any offset wells that may interfere with the targets, try
to get a proper location for the drilling platform and once the location has
Even though the trajectories are made, pore pressures need to be calculated to
get a possible casing designs for each of the trajectories while at the same time
fulfil the requirements for the production technologists to create their own
configurations to the well. All of the above requirements must be fulfilled to get a
plausible well design targets and as such, the objectives that was considered for
3. Within the limits of the capability of the drilling rig selected with the estimated
estimation
Drilling History
At the end of 2007 and early 2008, Located 57 km away from Cuyo Island and
117km from IloIlo City, two exploration wells were drilled in Tatusan whereby one
was a vertical well and the other was a sidetrack of the vertical well with the
coordinates of latitude 10° 59’ 19.43” N and longtitude 121° 31’ 36.25” E in offshore
Mindoro-Cuyo Basin. Reasons for the sidetrack are the possibility of finding
potential extra 5MMbbls of hydrocarbon in the up-dip position of Unit 9 and to make
full use of the availability of the drilling rig to minimize the cost and time of drilling.
mTVDSS
Seabed)(m)
angle
The wells were previously drilled by Baker Hughes, Inc using a semi-
submersible platform and took an overall duration of 28 days. There were issues
that rose during the drilling of the past wells mitigations to be suggested for drilling
corresponding depths mentioned after this has a datum point from the drilling floor.
Information from the wells were recorded in the form of Mudlogging and
wireline logging, four logging suites were ran on Well-1 which were the Super
Imager) and the SWC (Side-Wall Core). As for the case of Well-1 Sidetrack, only
the super combo was a successful run. An MDT logging was attempted but the
tool was stuck at 1571m which requires the tool to be fished out using the drillpipe.
In attempt to further understand the geology of the reservoir, the SWC was
done where 26 cores were shot between the depths of 1086m and 1617m and 22
cores were retrieved while 4 cores were empty although no particular reason was
mentioned on why it came up empty even though the recorded wireline logs has
shown the wellbore size to be quite consistent (12 ¼”) throughout the section.
Mudlogging evaluation was also recorded in both the Well-1 and the Well-1 Side
track wells and the recorded information from both wells and with information from
the cores are compiled below (Note that the compiled information is condensed
For Well-1:
Sandstone which are mainly soft to friable in texture, with partly medium hard,
which indicates that it is unconsolidated, Claystone that are mainly soft to firm
comprising of mainly of silt and very fine quartz grain with some traces of carbonate
rocks such as dolomite and pyrite. Dolomite was also present with a hard to very
hard texture. As for the Interval of 1120m to 1320m, there are interbedding of
claystone having soft texture, comprises of partly silt with traces of carbonaceous
matter and thin sandstone that are mainly soft to friable in texture, with a mixture
of silt.
sandstone and claystone. The sandstone is mainly soft to friable in texture, partly
medium hard again with traces of carbonaceous matter. For the claystone, it is
very soft to soft in texture, partly silty with very fine quartz grains and as before,
The Wel-1 ST well was drilled from a depth of 560m to a total depth of 1797m.
with claystone and dolomite were observed. The sandstone is mainly soft to friable
and partly moderately hard in texture with traces of carbonaceous matter, pyrite
and dolomite present. Claystone in the interval is very soft to soft in texture, partly
soluble and it comprises of mainly silt and some traces of very fine quartz grain
For the interval of 1200m-1600m, the layer is dominant with claystone with
minor sandstone. The claystone has a soft to moderately hard in texture, partly
soluble comprising of mainly silt and partly very fine quartz grains and as before,
claystone with minor dolomite were recorded. The sandstone here is moderately
carbonaceous, claystone having very soft to soft in texture. It comprises of slit and
traces of very fine quartz grains. Dolomite grains here are moderately hard to hard
in texture.
There is an evidence of erosion on layers U3.2, U4.0, U5.0, U6.0, U7.0, and
U8.0 as when they are correlated between the two wells, there are evidence
supported by the layers which are laterally discontinuous on Well-1 ST. The
and reservoir rocks. Correlation of layers U9.0, U9.1 and U9.2 through both wells
show that there is lateral continuity of these layers, although the thickness varies
Drilling Targets
One of the first item to make a decision for was the number of wells to be
drilled in the field. The number of producer wells and its coordinates must also be
identified, through this we can show the target locations with the exploration wells
in place in a diagram.
It can be seen clearly the location of the exploration wells may pose as a
problem in hitting the targets but this has been considered when attempting to
obtain the trajectories. Figure _ shows the structural map of Unc/U3.2 layer of the
Tatusan Field
Figure _ Structural map of Unc/U3.2 layer(PNOC, 2009)
Platform Location
Another decision required is the number of locations to place the well and it
was decided to drill using one drilling rig at one location to ensure that the costs of
the drilling to be kept as low as possible as multiple locations can lead to increasing
costs as well as the drilling time to be extended due to rig moves. The addition of
extra facilities will further escalate the price for the overall project and therefore
selecting multiple locations to drill the well has been taken out of consideration for
this project.
The first objective is to consider a decent location where all the targets could
The target is given covering a wide range of the reservoir, a best location
on which will ensure the objectives could be attained. Another is the number of
locations to place the well and it was decided to drill using one drilling rig at one
location to minimize the costs of the drilling as multiple locations can result to
rig moves. The needs of additional facilities will further increase the cost for the
overall development plan and therefore choosing multiple locations to drill the well
Well Trajectories
With a rig location, it is now possible to create trajectories for the well. There
are a few matters that require further study. In particular is the location of the offset
wells that can create problems in the drilling design. This is where using the
This enabled the study of trajectories with a selected drilling platform location and
will ensure that the trajectories made will not collide with any existing offset wells.
Another factor to be taken into account when designing the well is the dog-
leg severity. For the designs for all of the wells, the dog-leg severity is to be kept
at a minimum angle as possible while still maintaining the trajectory to hit the
targets. The basis in designing the trajectories into the well will have the following
software to calculate a trajectory at the lowest build up rate as possible to hit the
targets
make sure that the wells are not close to each other in accordance to its algorithm
and by having it to calculate the distance from the center of the wellbore from one
Rig Selection
Drilling rig selection is crucial. With the known approximation of the required
to be drilled for all the wells, the technical capability of the drilling rig must be
able to drill all the objectives safely. For the rig selection, these are the following
needed.
Solids control capable of handling fine sands as records from past wells
Specifications of some of the available marine offshore drilling units (MODU) are
(USD)
Submersible
After getting the possible trajectories for each of the producer wells, there
are a few items which require considerations. The foremost information that needs
to be decided first the final hole size at the target depths of each well and this
information can only be planned after the following information was known:
• The type of completion to be done to the well (is sand control required?)
• There is a need to know if the rig is capable to drill the proposed producer
wells
The main reason for the above consideration is that when attempting to
calculate for the casing size, kick, setting depths and given that the well
configurations are all horizontal, this is a serious decision as it will affect the entire
project.
Bits are selected based on the performance of similar bits at offset wells.
Parameters affecting a bit performance have a complex pattern. For a given field,
studied were variables such as bit size, weight on bit, rotary speed, pump rate,
drilled interval, and bit type. Factors such as hydraulics, formation hardness, bit
design, and operational parameters are also considered in the selection process.
For the case of drilling the exploration wells, two types of bits were used
which is the roller cone bit and the PDC bit but there were problems encountered
when using the PDC bit as it did not performed as expected and hence, there was
a need to have a bit change back to a roller cone to finish of the hole section. A
Drilling Fluid
subsurface conditions. Selection of the best fluid to meet anticipated conditions will
minimize well costs and reduce the risk of catastrophes such as stuck drill pipe,
There are nine distinct categories of drilling fluids according to World Oil’s annual
Freshwater systems
To determine the type of fluid to be selected for a specific well, three factors
are considered:
Cost
Environmental Impact
Technical Performance
Water-based liquids (WBFs) are the most generally utilized drilling fluid
system, and are viewed as more affordable than oil-based liquids (OBFs) or
synthetic based liquids (SBFs). The OBFs and SBFs—otherwise called invert
outside) stage, and brackish water as the interior stage. Invert emulsion system
have a greater expense for each unit than most water-based liquids, so they
regularly are chosen when well conditions call for solid shale hindrance or
Water-based fluids
Approximately 80% of all wells were drilled using water-based drilling fluids.
The base fluid can be formate brine, saturated brine, seawater, or freshwater. The
These systems incorporate natural clays in the course of the drilling operation.
Shale inhibition and salt formations are commonly drilled using salt water
drilling fluids. They also are recognized to inhibit the formation of ice-like hydrates
that can gather around subsea wellheads and equipment for well-control, impeding
critical operations and blocking lines. Solids-free and low-solids systems can be
Calcium chloride
Calcium bromide
Zinc bromide
KCL PHPA
enough to fit between the clay platelets without distorting the shale lattice.
The Potassium ions are adsorbed on the exchangeable cation sites in the
shale lattice and this holds the platelets together, which helps to minimize
weight polymer that adsorbs onto clay and shale surfaces to encapsulate
drilled cuttings and coat the wellbore with a viscous polymer layer. This acts
as a barrier to prevent water coming into contact with clays and shales,
which again helps minimize clay and shale hydration, swelling and
dispersion.
The PHPA coating helps keep drilled cuttings intact as they travel up
the annulus, improving solids control efficiency on the surface and helping
control the build-up of solids in the drilling fluid. The KCL-PHPA Polymer
system is easy to mix and inhibitive properties are easy to adjust according
to clay and shale reactivity while drilling. However, the Potassium ion
Regular treatments are usually required to maintain Potassium ion and PHPA
concentrations that gradually deplete through cuttings removal at the surface. The
drilling fluid system is versatile and can be converted into more inhibitive water-
based drilling fluid systems using appropriate additives. With increasing focus on
When drilling the exploration wells, the type of mud used when drilling both of the
26" hole phase (70.1m to 110m) Seawater with high viscosity sweep