Вы находитесь на странице: 1из 8

Reliability Engineering and System Safety 96 (2011) 324–331

Contents lists available at ScienceDirect

Reliability Engineering and System Safety


journal homepage: www.elsevier.com/locate/ress

A framework for reliability and risk centered maintenance


J.T. Selvik a,n, T. Aven b,1
a
University of Stavanger and IRIS (International Research Institute of Stavanger), Norway
b
University of Stavanger, Norway

a r t i c l e in f o a b s t r a c t

Article history: Reliability centered maintenance (RCM) is a well-established analysis method for preventive
Received 15 January 2010 maintenance planning. As its name indicates, reliability is the main point of reference for the planning,
Received in revised form but consequences of failures are also assessed. However, uncertainties and risk are to a limited extent
3 August 2010
addressed by the RCM method, and in this paper we suggest an extension of the RCM to reliability and
Accepted 8 August 2010
risk centered maintenance (RRCM) by also considering risk as the reference for the analysis in addition
Available online 11 August 2010
to reliability. A broad perspective on risk is adopted where uncertainties are the main component of risk
Keywords: in addition to possible events and associated consequences. A case from the offshore oil and gas
Reliability centered maintenance industry is presented to illustrate and discuss the suggested approach.
Risk
& 2010 Elsevier Ltd. All rights reserved.
Uncertainties

1. Introduction ii. Application of logical decision diagrams: the so-called RCM logic,
to specify suitable categories of PMs (predictive maintenance
Planning of preventive maintenance (PM) of technical systems (PdM), replacement, etc.); see e.g. Bloom [3].
is a challenging task. A balance has to be made between the
frequency and extension of the maintenance on the one hand and
costs on the other. The preventive maintenance is introduced to The minimum criteria that a RCM process has to meet is defined
avoid the occurrence of failures of the system and reduce by the three technical standards IEC 60300-3-11 [4], SAE-JA1011
potential consequences of failures, but maintenance could in [5] and SAE-JA1012 [6], which are the RCM standards typically
some cases also introduce failures. Both of these counteracting used, e.g. for equipment in the oil and gas industry (see e.g. Khamis
aspects are of relevance to preventive maintenance planning. and Hiren [7] and Carretero et al. [8]). The RCM methodology has
Different tools have been developed to support the planning of extensive application also outside this industry. The methodology
PM and this paper addresses one of these, the Reliability Centered has its origin in the aircraft and aerospace industry and it was also
Maintenance (RCM) methodology. RCM is a widely accepted early applied by the military and the nuclear industry. According to
methodology that has been available in the industry for over 30 Khamis and Hiren [7] the methodology was used by more than 400
years, and has proved to offer an efficient strategy for preventive nuclear power stations. Applications are also found in railwork
maintenance optimization [1]. networks ([9] and [10]), metallurgical industries [11,1] and coal
The main objective of RCM is to reduce maintenance costs and mines [11]. For a good overview of various applications, see
at the same time increase reliability and safety. The system Carretero et al. [7], where also use in the following industries or
functionalities and reliability are highlighted as the name sectors are described: chemical & processing, medical (hospitals),
Reliability Centered Maintenance concept indicates. A two-step sawmill, shipping, transportation (Paris metro transportation
procedure is adopted: network—RATP) and water distribution.
Several methodological improvements of the method have also
been suggested, e.g. PM Optimization [12], RCM 2 [13], Stream-
i. Inductive analysis of the potential failures, where typically a lined RCM [14], Intelligent RCM Analysis [15] and also a so-called
variant of failure mode, effects and criticality analysis (FMECA) probabilistic approach by Eisinger and Rakowsky [16]. For the
is used, to determine critical components of the system; see purpose of the present paper we will concentrate on the ideas of
e.g. Rausand and Høyland [2]. Eisinger and Rakowsky. These researchers point out that it is
crucial to the decision process that the RCM is adjusted to reflect
uncertainties, as ignoring these may in many applications lead to
n
Corresponding author. Tel.: +47 51 87 50 00; fax: + 47 51 87 52 00.
‘‘non-optimal’’ maintenance strategies. Eisinger and Rakowsky
E-mail addresses: jts@iris.no (J.T. Selvik), terje.aven@uis.no (T. Aven). focus on the RCM logic specifically and suggest an adjustment of
1
Tel.: + 47 83 10 00; fax: + 47 51 83 10 50. this, where probabilities are assessed instead of the traditional

0951-8320/$ - see front matter & 2010 Elsevier Ltd. All rights reserved.
doi:10.1016/j.ress.2010.08.001
J.T. Selvik, T. Aven / Reliability Engineering and System Safety 96 (2011) 324–331 325

YES or NO options when navigating through the decision diagram. presence of corrosion and erosion, the flowline is designed with
Having only the choice between YES or NO, they argue that it is an inner coating. The arrangement also includes two hydraulically
not possible to adequately reflect the assessor’s confidence in the operated valves: one close to the production wells and one close
different choices. to the production riser. The case is motivated by an analysis by
In the present paper we take the uncertainty comment by Castanier and Rausand [20].
Eisinger and Rakowsky [16] a step further. We agree with Eisinger The structure of the remaining part of the paper is as follows. A
and Rakowsky [16] that uncertainties need to be reflected in the brief description of the RCM methodology is presented in the next
analysis, but a clarification is required as to what this means. In section, Section 2, where we apply RCM on the case presented
our analysis, uncertainties refer to the occurrences of failure above. Then in Section 3 the new reliability and risk centered
events and their consequences, and are not about vague methodology is explained, and in Section 4 it is discussed and
(ambiguous) statements and the assessors’ doubt concerning compared with the traditional RCM approach. The case is used as
what to do, as seem to a part of the Eisinger and Rakowsky [16] a basis for the comparison. Section 5 provides some conclusions.
rationale for incorporating uncertainties.
To some extent these uncertainties (about the occurrences of
failure events and their consequences) are addressed in the 2. RCM—description of the methodology
analysis. The FMECA assigns probabilities of failure events and
expected consequences. In some of the FMECAs the presentation The RCM methodology can be described by the following three
of expected values is extended by the use of worst-case phases:
consequences. However, the analysis is mainly expected-value
focused and an important uncertainty dimension is not revealed: i. Identification of Maintenance Significant Items (MSI).
the assessments are based on background knowledge, including ii. Assignment of suitable PM tasks for the MSI.
many assumptions, which could hide or camouflage uncertainties. iii. Implementation and update of the PM tasks.
For example, for assessments on a specific valve in a subsea
flowline system, there are assumptions on fluid pressures and
In this section we will give a brief presentation of these phases
amount of erosive particles. The probabilities produced are
using the flowline case as an illustration. The methodological
conditioned on these assumptions.
description is mainly based on Rausand [21], Rausand and Vatn
The traditional RCM approach can be viewed as founded on a
[22] and Bloom [3].
risk perspective where risk is equal to the expected value or the
A general aspect emphasized in the references above is that
combination of probabilities and events/losses. To take into
the RCM project group should include multiple disciplines and
account uncertainties as indicated above, we need to base the
create ownership of the process. The project group should include
RCM on a broader risk perspective and one way to do this is to
at least one person from the maintenance function and one
replace probability with uncertainty in the definition of risk. This
person from the operations function, in addition to a RCM
leads to a risk perspective as presented in Aven [17] (see also
specialist. And the group should work dynamically in the sense
[18]).
that expertise is rotated when needed in the analysis.
Risk is understood as the two-dimensional combination of:

i. Events (A) and the consequences of these events (C) 2.1. Description of the RCM phases
ii. Uncertainties U about A and C (will A occur and what will the
consequences C be?) The RCM phases listed above are described in the following
Sections 2.1.1–2.1.3.
Such a risk perspective is referred to as the (A, C, U)
perspective [19]. 2.1.1. Phase i—identification of MSI
In this way we obtain a shift in the methodological focus from The first phase is a screening phase, where the number of
reliability and probabilities (expected values) to reliability, items for analysis is reduced. The purpose of this phase is to
uncertainties and risk. We find that a proper name for this identify the Maintenance Significant Items (MSI), i.e. the items we
adjusted methodology would be ‘‘reliability and risk centered later feed into the RCM logic for specification of PM tasks. These
maintenance’’, where risk is given a definition as above with items are identified from criticality rankings performed for each
uncertainty being a main component. For short we refer to the of the items, where all functional failures for each of them are
methodology as RRCM. assessed, assuming that all other items are functioning perfectly.
The purpose of the present paper is to motivate this revised Typically a type of qualitative ranking is used based on a
methodology and describe its main features. criticality matrix including information on the various failure
To illustrate the applicability of this methodology we will use a modes, failure frequency and consequences. The assessments are
case from the oil and gas industry, where the aim is to determine performed on an overall system level, for the following conse-
the maintenance strategy for a subsea flowline arrangement in quence categories:
the North Sea. The flowline is placed about 300 metres below sea
level, and has a length of over 20 kilometres; see Fig. 1. It  Operational consequences (production availability).
transports a corrosive mix of oil, gas and water that contains  Hidden failure consequences (relevant for redundant systems).
varying amounts of sand particles. These sand particles are  Non-operational consequences (including both direct costs
erosive and may contribute to the shutdown of several production and commitments).
wells if leakage should occur. To prevent leakage due to the  Safety and environmental consequences.
Valve A Valve B For the other items, the non-MSI, the ‘‘optimal’’ maintenance
Wells Riser
strategy is assessed to be operation until failure occurs and then
to perform Corrective Maintenance (CM), i.e. Run-To-Failure
Fig. 1. Case flowline system. (RTF). RTF might also be a relevant maintenance strategy for
326 J.T. Selvik, T. Aven / Reliability Engineering and System Safety 96 (2011) 324–331

Continuous predictive
YES
maintenance
Does a failure YES Is continuous
alerting measurable monitoring
indicator exist? feasible? Scheduled predictive
NO maintenance
NO

Increasing failure YES Scheduled overhaul


YES Is overhaul
rate?
feasible?
NO Scheduled replacement
NO

Is the function YES Scheduled function


hidden? testing

NO

Run-To-Failure (RTF)

Fig. 2. Example of RCM logic (Rausand and Vatn [9]).

some of the MSI, depending on their failure and lifetime  Lifetime distribution: Exponential.
characteristics, failure consequences and maintenance costs.  Failure consequences: Contamination. Pollution in sea, process
For simple systems that include only a few items, it is in most medium.
cases quite obvious which of the items are important for the  Failure consequence type: Environmental.
reliability of the system and what their failure consequences are,  Failure severity: Critical (high criticality).
and the MSI may be identified without any rigid analysis.  Recommended PM task: addressed in text below.

2.1.2. Phase ii—assignment of suitable PM tasks for the MSI Based on the FMECA results, PM tasks are determined by
To describe the next phase, phase ii, we refer to the case application of RCM logic. These are decision diagrams that
presented in Section 1. For this case, based on crude criticality through various YES or NO questions navigate the assessor to
assessments we find all the items to be MSI: the ‘‘optimal’’ maintenance task for the item assessed (repeated
for all the relevant failure modes); see the above references; an
 Steel lines (including coating) between production wells and example of a simple version is provided in Fig. 2. The design of the
production riser. RCM logic determines the additional fields that are relevant for
 Valves A and B (hydraulically operated valves). the FMECA worksheet. Several variations of the RCM logic exist,
but they are all based on the same principle; by use of decision
Reliability data shows that failures on the above items are rare, logic we assign PM tasks based on failure characteristics, failure
but depending on the failure mode, all of the items are single- consequences and appropriate cost-effective maintenance tasks
handedly capable of taking out the production if a failure on one to mitigate these.
of these should occur. For the items in the referred case, we apply the RCM logic
In order to assign suitable PM tasks for the items, we first presented in Fig. 2. We start with the steel lines, and answer YES
apply an RCM-adjusted FMECA, which is basically a regular to the first question: does a failure alerting measurable indicator
FMECA worksheet to which some additional RCM relevant fields exist? And NO to the next question: is continuous monitoring
are added; see e.g. Rausand [21] and Rausand and Vatn [22,23]. feasible? The steel lines are thus, by use of this RCM logic,
An example of the FMECA worksheets applied for Valve A in navigated to ‘‘scheduled predictive maintenance’’. For the valves
the flowline case is presented below. This worksheet is not as we answer the first question by NO, which leads to another
extensive as the fields proposed by Rausand and Vatn [22], but second question: Increasing failure rate? Due to the limited data
shows some of the main points. available on such valves, we answer NO to this. Then we need to
FMECA worksheet: answer whether the function is hidden. Also this question is
answered NO, leading us to Run-To-Failure (RTF) as the appro-
 Item ID: Valve B; actuation: hydraulically operated. priate task. The information is then placed in the worksheet
 Generic item: Valve, process isolation. above.
 Equipment class: Flowline. When the PM tasks are in place, the next step is to assess their
 MSI item: Yes. intervals. This is in many cases a challenging task. Maintenance
 Operational mode: In operation, open position. optimization is and has been a well-studied field for several
 Functional mode: Ensure containment. decades. It includes use of mathematical models to determine the
 Functional failure: External leakage (process medium). optimal intervals; see e.g. Rausand and Vatn [23], Percy [24], Cui
 Failure cause: Corrosion/erosion. [25], Wang and Pham [26] and Dekker [27].
 Failure mechanism: External influence/material related. Some of these models are quite complicated to apply; they
 Failure characteristics: Unknown (constant failure rate assumed). might, for example, request use of advanced mathematics, input
 Probability of Failure: Subjective prob. assessment; failure rate: data of limited availability and failure rate functions that can be hard
0.6 critical failures/year and in range (1.2, 2.5) failures/year for to determine. Regarding the case for optimization of pipeline
all failure modes and criticalities. inspection intervals, see e.g. Castanier and Rausand [20]. Use of
J.T. Selvik, T. Aven / Reliability Engineering and System Safety 96 (2011) 324–331 327

such models may also be combined with expert judgements based 2.2. Potential for methodological improvements: uncertainty
on the available information, as for example described in Apeland assessments
and Scarf [28]. There is no defined ‘‘one-way’’ to determine the
intervals. In many cases the intervals are not optimized at all and According to Bloom [3], it is estimated that more than 60% of
simply determined as a combination of expert recommendations, all RCM programmes initiated have failed to be successfully
operational experience, various requirements and available implemented. One of the main reasons for this is failure to assess
resources, see e.g. Bloom [3]. In a study involving two oil companies and communicate uncertainties in the assessments. This reason
operating on the Norwegian Continental Shelf [29], it was found that depends somewhat on the type of industry and the complexity of
the RCM interval determination for the involved participants was the systems analyzed, as well as the resources assigned to the
mainly based on operational experience and established practice RCM project, e.g. external resources such as consultants and
rather than direct use of mathematical models. This practice is purpose-built software. See also Cheng et al. [15]. Although there
in line with the main standards for establishing maintenance is high industrial awareness on the relevance of uncertainties, the
programmes within the oil and gas industry, such as the NORSOK uncertainty issue is often given rather limited attention in the
standards Z-008 [30] and Z-016 [31] (the latter now replaced by assessments in practice. This is illustrated by the changes in the
international standard ISO 20815 [32]). procedures for handling of uncertainty when the NORSOK Z-016
A mix of various maintenance tasks and intervals is typically [31] was replaced by ISO 20815 [32]. In the ISO standard the focus
the result of the above assessments, and in order to apply the on uncertainties was reduced compared with the original
results in practice a form of ‘‘packing’’ is necessary; see e.g. NORSOK document.
Rausand [21]. The PM tasks and intervals are grouped such that In Section 1 we argued that the RCM process should be
maintenance resources are able to handle the tasks efficiently. In adjusted to take into account broader uncertainty assessments.
such grouping it might also be decided to include some of the Already some uncertainty assessments are included, but as
items that are not analyzed in detail (the non-MSI). Thus a pointed out in Section 1, these are restricted to probabilities of
‘‘packed PM interval’’ field is added to the FMECA worksheets. failure events and expected consequences in the FMECA assess-
ments, and do not reflect all of the relevant uncertainty
2.1.3. Phase iii - implementation and update of the PM tasks dimensions; they especially exclude uncertainties ‘‘hidden’’ in
The third phase, phase iii, describes the managerial processes the assumptions made. These uncertainties are referred to as
for how the results are applied in practice. It consists of ‘‘uncertainty factors’’. As mentioned earlier, it may be possible to
communication of the results from the project group to manage- reveal some of the assumptions in the RCM documentation and
ment, the operational processing and later update of the results treat them in later updates, but it will not give the assessors the
when new and relevant information becomes available. relevant uncertainty information for decision-making.
A quality assurance process is performed as part of this phase, In the following section we present an extended RCM
with the aim of identifying issues that are overlooked or ignored approach, referred to as the Reliability and Risk Centered
in the FMECA. The process also addresses methodological Maintenance (RRCM) framework, based on these ideas for broader
limitations in the use of FMECA, for example related to the uncertainty assessments. The RCM will still be the methodological
generation of relevant alternatives, and the treatment of multiple- platform, but the approach to risk and uncertainties will be more
failure interactions (as failures are assessed individually, the comprehensive. The (A, C, U) risk perspective introduced in
effect of some failures may not be accounted for). Section 1 constitutes the formal conceptual basis for the frame-
The general aspect pointed out at the beginning of this section work.
on how the project group should be composed, is of relevance for
the communication of the results (PM tasks and intervals), but
also for the treatment of uncertainties and later updates. The 3. Reliability and risk centered maintenance (RRCM)
results should be well documented for later updates to be
efficient, including documentation of general conditions and In this section we present the reliability and risk centered
assumptions used in the assessments. maintenance (RRCM) framework. The main features of the
For further description of this phase, see e.g. Rausand [21], framework are illustrated in Fig. 3, showing a process defined
Rausand and Vatn [23], Bloom [3] and Moubray [13]. by seven boxes of assessments to determine the PM programme.

1. 2. 3. 4.
Identification PM task PM interval Packing of
of MSI assessments assessments PM tasks

5. Uncertainty analysis

7. 6.
Preventive Managerial Uncertainty
maintenance review and evaluation &
programme judgement presentation
of results

Fig. 3. RRCM framework.


328 J.T. Selvik, T. Aven / Reliability Engineering and System Safety 96 (2011) 324–331

Table 1
Uncertainty assessment score interpretation.

Aspect Score Interpretation

Uncertainty Low (L) One or more of the following conditions are met:

 The assumptions made are seen as very reasonable.


 Much reliable data are available.
 There is broad agreement/consensus among experts.
 The phenomena involved are well understood; the models used are known to give
predictions with the required accuracy.

Medium (M) Conditions between those characterising low and high uncertainty.
High (H) One or more of the following conditions are met:

 The assumptions made represent strong simplifications.


 Data are not available, or are unreliable.
 There is lack of agreement/consensus among experts.
 The phenomena involved are not well understood; models are non-existent or known/believed
to give poor predictions.

Sensitivity L Unrealistically large changes in base case values needed to bring about altered conclusions.
M Relatively large changes in base case values needed to bring about altered conclusions.
H Relatively small changes in base case values needed to bring about altered conclusions.
Importance L, M or H Average of the other two aspect scores.

The first four boxes are described by phases i and ii of the The RRCM framework also includes managerial review and
traditional RCM process (see Sections 2.1.1 and 2.1.2). These judgement, as shown in the seventh box in Fig. 3, in line with the
boxes provide already established methodologies to the frame- decision framework presented in Aven [19]. The inputs to
work, where a dashed line is drawn around the boxes to indicate management from the various assessments are placed into a
the boundaries of the traditional process i and ii. A fifth box (no. 5) broader context, where the boundaries and limitations of the
is then introduced, attached to the boxes 2 and 3, to integrate various assessments are taken into account, and also additional
dedicated uncertainty assessments into the framework. These aspects and inputs are taken into consideration, for example
assessments are included as an integrated part of the PM task and manufacturer recommendations and existing PM programmes.
interval assessments (i.e. these two boxes), and adds to the The managerial review and judgement may also request revisions
uncertainty assessments performed as integral parts of the or analytic changes results should appear unreasonable.
traditional RCM methodology (steps nos. 1–4), for example Section 3.1 presents the results from the uncertainty assess-
assessments in FMECA, where uncertainties are partially covered ment for the flowline case.
through subjective (epistemic) probabilities for failure events and
their consequences. 3.1. RRCM—uncertainty assessment in the flowline case
In the fifth box (see Fig. 3) we specifically address the
uncertainty factors. Many of these factors are derived from the Our focus is on the uncertainty factors that have the potential
assumptions made in the established assessment tasks in boxes 2 to change the probability of an event and consequence pair to
and 3, as the uncertainty factors cannot be revealed and assessed such an extent that it may have an effect on the PM tasks or
before the traditional probability based analysis has been intervals assessed.
conducted. In line with Aven [19] and Flage and Aven [33], the The uncertainty factors can be integrated into one of the
uncertainty analyses cover the following main tasks: FMECA worksheets, as an extension of this to also include the
uncertainty assessments. The fields in the extended FMECA
1. Identification of uncertainty factors. worksheet below may be used. We give a short description of
2. Assessment and categorization of the uncertainty factors with these fields before moving on to show how to perform the
respect to degree of uncertainty. assessments of the uncertainty factors in the flowline case.
3. Assessment and categorization of the uncertainty factors with Extended FMECA worksheet (refer to list in Section 2.1.2):
respect to degree of sensitivity.
4. Summarization of the uncertainty factors’ importance.  Recommended PM task: Result from the RCM logic; in this case:
Table 1 indicates a score system for tasks 2–4, inspired by Selvik Run-To-Failure (RTF).
and Aven [34] and Flage and Aven [33]. All the tasks 1–4 are applied  Uncertainty factors for PM task assessments: List the re-
for both the PM task assessment and the PM interval assessment. levant uncertainty factors identified related to the PM task
When we apply this system for box 2, the judgement of the assessment.
sensitivity score is linked to the extent that the factor is able to  Uncertainty factor score: For the uncertainty factors identified,
change the PM task. To integrate these scores into the PM task and give a qualitative score on degree of uncertainty, sensitivity
interval assessments we expand the FMECA to include all the results and importance in line with the score system given in Table 1.
from the assessments in steps (boxes) nos. 1–5. Such expansion will  Sensitivity of PM task recommendation: Check if an uncertainly
also benefit the later presentation of the results. factor has the potential to produce a different PM task than the
Steps 1–4 (see Fig. 3) together with 5 thus provide the input for one recommended. List the adjusted tasks and the correspond-
the total uncertainty evaluation of the system studied; see box no. 6. ing uncertainty factors.
An important part of the uncertainty evaluation is communication of  PM interval determination: Description of how the PM interval
the results to the management function. The value of the assessment is performed; type of optimization model used and
information should be considered, to not overload the management relevant constraints. In this case the interval is assessed by the
with information not relevant to the decision-making. use of expert judgements.
J.T. Selvik, T. Aven / Reliability Engineering and System Safety 96 (2011) 324–331 329

Table 2
Case uncertainty assessment.

No. Assumption Degree of uncertainty Degree of sensitivity Degree of importance

1 Data selection criterion based on item size (inner diameter) and fluid type M M M
2 Data are able to describe the items’ failure characteristics H H H
3 Mobilisation history found in database is representative H M H/M
4 All of the other items are functioning M H M
5 Only one failure occurs at the time / within a short time interval L M L/M
6 Item failures are observed shortly after they occur M H M/H
7 Regular pigging will prevent flowline blockage L H M
8 Use of smart pig provides accurate sensor readings inside the flowline M M M
9 Company and industry requirements are followed L L L
10 Items are properly tested and inspected before and during installation M M M

 Recommended PM interval: Result from the PM interval Another factor related to the database is the maintenance
assessment. vessel mobilisation time, which could be a significant contributor
 Uncertainty factors for PM interval assessments: List the relevant to system downtime. It is assumed that the mobilisation history
uncertainty factors identified related to the PM interval in the database is representative, but this assumption may be
assessment. challenged as it is difficult to determine the correct mobilisation
 Uncertainty factor score: For the uncertainty factors identified, times for the relevant items from the available data.
give a qualitative score on degree of uncertainty, sensitivity By using FMECA, criticality assessments are carried out
and importance. assuming that only one failure event or failure mode occurs at
 Sensitivity of PM interval recommendation: Check if an the time. It is assumed that all the other items are working
uncertainly factor has the potential to produce a significant perfectly. None of the other items are then in a failure mode, are
change in the PM interval compared with the one recom- waiting for maintenance or have hidden failures. However, real
mended. List the adjusted intervals and the corresponding life may very well be different.
uncertainty factors. It is also assumed that failures are immediately detected when
they occur. However, this assumption may not hold in practice for
In the following we address the uncertainty factors related to the valves as failures of these may be hidden due to redundancies.
the PM tasks for the specific flowline case. Several critical Some valve failures may be detectable only by function testing or
assumptions made in the basic FMECA were identified. Below the appearance of a second failure of another item within the
we present and list some of the derived uncertainty factors based redundant system.
on these assumptions. They are relevant for both the steel lines The flowline is regularly pigged by use of a smart pig that
and the valves. monitors flowline inside parameters, for example the inner
Following are some of the identified uncertainty factors: diameter and temperature. The reliability and accuracy of this
smart pig is not assessed by the FMECA, nor is the assumption
1. Data selection criterion based on item size (inner diameter) that pigging prevents blockage. These assumptions may lead us to
and fluid type. ignore failure modes concerning flowline blockage.
2. Data are able to describe the items’ ‘‘failure characteristics’’. The last two uncertainty factors are related; they address the
3. Mobilisation history in database is representative. assumptions that the items installed are adequately tested and
4. All of the other items are functioning. inspected prior to production start up and that production is
5. Only one failure occurs at the time/within a short time inside the design criteria and requirements/recommendations,
interval. e.g. design pressure and sand concentration limits.
6. Item failures are observed shortly after they occur. Now, having identified a list of uncertainty factors and
7. Regular pigging will prevent flowline blockage. included these in the extended FMECA worksheet, we next assess
8. Use of smart pig provides accurate sensor readings inside the and categorize these with respect to degrees of uncertainty and
flowline. sensitivity, which combined provides a basis for making a
9. Company and industry requirements are followed. judgement of importance. The importance classification points
10. Items are properly tested and inspected before and during to factors that should, if time and resources allow, be followed-up
installation. in further analyses.
The result of the uncertainty assessment is shown in Table 2,
These factors are briefly described in the following. based on the score system presented in Table 1. The results are
The FMECA is, to a large extent, based on data found in placed in the uncertainty factor score field in the worksheet.
company internal databases. However, the selection criterion Table 2 shows that both the uncertainty factors nos. 2 and 3
used may lead to failure probabilities that do not reflect the are classified with high uncertainty. Of these two uncertainty
erosive properties of the fluid. It is not clear to what extent the factors, only factor 2 is classified with high importance as the
criterion adopted has included flowlines and valves that are mobilisation times alone do not have a high enough potential
subject to similar conditions. to change the PM task assessment. Factor no. 2 is found to have
There are limited amounts of relevant data available to predict a potential to produce a different PM task than the one
the performance of the equipment. The data represent newer first recommended, as it was revealed in the sensitivity assess-
flowline systems, and for these few events have occurred. The ments that this uncertainty factor naturally lead to the PM
relevant items’ sizes are not found in older data. Thus, one may tasks ‘‘scheduled overhaul’’ or ‘‘replacement’’ instead of RTF.
question to what extent the data are dominated by the items’ Thus, this factor and the two new PM tasks are placed in
‘‘childhood events’’. the FMECA worksheet into the field Sensitivity of PM task
330 J.T. Selvik, T. Aven / Reliability Engineering and System Safety 96 (2011) 324–331

recommendation. The sensitivity of this factor is also addressed in The managerial review and judgement allows for quality
Section 4. assurance and second opinions in the RRCM process. Also other
The uncertainty assessments for the PM intervals are risk methodologies, for example risk based inspection (RBI),
performed in same way as for the PM tasks. To avoid repetition, which is frequently used for assessment of inspection intervals for
the details are omitted. pipeline systems in the Norwegian oil and gas industry, could be
The uncertainty analysis is combined with the results of the included in the overall considerations in the managerial review
other tasks, including the probability assessments for failure and judgement.
events and consequences in the FMECA, which are evaluated as a Within the RRCM framework, we apply subjective (epistemic)
basis for communication to management. The evaluations high- probabilities as a quantitative measure of uncertainty. These
light which uncertainties to give weight to in the presentation of probabilities are used in FMECA. In RCM often a relative
the results. frequency-based perspective on probabilities is used. The way
probability and risk are understood strongly influences the
presentation and communication of the results.
3.2. Managerial review and judgement The RCM assessments are quite demanding for larger systems
due to all the failure modes that are to be analyzed by FMECA and
The results presented in Table 2 provide additional decision RCM logic. By adding additional assessments we also increase the
support to that which is included in the RCM process. When these time needed to perform the process, as well as the resources
results are communicated to management, weight is also given to required. However, the extra time and costs due to the
the limitations in the traditional RCM assessments. uncertainty factor assessments should not be very large compared
Although management performs review and judgement late in with the overall costs used for RCM. If uncertainty and risk are to
the RRCM process, this is not to say that management is not be adequately incorporated in the assessments, some extra
involved in early assessments. Management may, for example, resources are required.
influence who will perform the various analyses and provide
guidelines to the PM optimization. Management involvement in
early phases is often considered a key success factor in project 5. Conclusions
management, so also for the implementation of the RRCM process.
RCM is a systematic analysis method for planning the
preventive maintenance (PM) of technical systems. Reliability
4. Discussion—comparison of RCM and the RRCM framework and consequences of the relevant system items are assessed in
order to identify and determine suitable PM tasks and intervals.
Applying the RRCM framework may or may not result in Over the years, RCM has gained a solid reputation for being a
different decisions compared with the RCM analysis methodology. successful method, but also for having some shortcomings. One of
For the flowline case, the RCM assessments (RCM logic) and the these is traced to the limited assessments of risk and uncertainties.
first parts of the RRCM framework led to scheduled PM for the In this paper we have presented and discussed the RRCM
steel lines and RTF for the valves. The importance of the factors framework: a framework based on the existing RCM, which
identified may however change this, the conclusion being that the improves the risk and uncertainty assessments by adding some
valves should be subject to predictive maintenance (condition additional features to the existing RCM methodology. An extended
monitoring) – maybe even continuous instead of scheduled – to uncertainty assessment is added, to address uncertainties ‘‘hid-
prevent failure events. den’’ in assumptions of the standard RCM analyses. The un-
Consider, for example, the hydraulic valves in the case certainties are then communicated to management through an
presented (see Fig. 1): Valve B say, located about 20 km from extended uncertainty evaluation, which integrates the results from
the riser base. As condition monitoring (predictive maintenance) the FMECA (and the formal maintenance optimization if optimiza-
is unfeasible due to the long distance from the topside installation tion models are established) and the separate uncertainty analysis.
and the harsh seabed conditions, we are, by use of the RCM logic An essential feature of the presented framework is the managerial
(see Fig. 2), led to answer the following question: is the failure review and judgement, which places the decision process into a
rate of the valve increasing for the specific failure mode? Then we broader management context. In this step consideration is given to
consider the second of the uncertainty factors; that we assume the boundaries and limitations of the tools used.
our data to be able to describe the ‘‘failure characteristics’’ of the A case from the oil and gas industry is presented to
valve. Having limited experience and no failures recorded in the demonstrate the applicability of RRCM. The approach is, however,
data set, we may make the judgement that the probability of general and could also be used for other types of applications. We
failure for this failure mode is low and we see no indication of believe that by applying the RRCM, an improved basis can be
increase in failure rate. However, corrosion and erosion wear on established for informing decision makers compared with the
the valves could result in an increase in failure trend over time, for RCM method, as the importance of risk and uncertainties is more
example for the failure modes ‘‘leakage in closed position’’ and adequately taken into account.
‘‘fail to close’’. The consequence is that the suitable PM task is to
perform scheduled overhaul or replacement instead of RTF.
The presented case covers a rather limited system and it is Acknowledgements
easy to see the total picture. But the process is not much more
difficult to carry out for larger systems, although more demanding The authors are grateful to three anonymous referees for their
with respect to amount of time needed to perform the analyses. constructive comments and suggestions to the original version of
All the items are listed and then assessed one at a time, for all this paper.
failure modes, both within RCM and RRCM.
In a project development, a number of assumptions are made References
and these need to be followed up in coming project phases. The
RRCM provides a methodology for assessing the importance of the [1] Desphande VS, Modak JP. Application of RCM to a medium scale industry.
various assumptions and support decision-making. Reliability Engineering and System Safety 2002;77:31–43.
J.T. Selvik, T. Aven / Reliability Engineering and System Safety 96 (2011) 324–331 331

[2] Rausand M, Høyland A. System reliability analysis: models, statistical [18] Aven T, Renn O. On risk defined as an event where the outcome is uncertain.
methods, and applications. 2nd ed.. Hoboken, N.J.: Wiley-Interscience; 2003. Journal of Risk Research 2009;12:1–11.
[3] Bloom N. Reliability centered maintenance: implementation made simple. [19] Aven T. A semi-quantitative approach to risk analysis, an alterative to QRAs.
NY: McGraw-Hill Companies; 2006. Reliability Engineering and System Safety 2008;93(6):790–7.
[4] IEC. IEC 60300-3-11/ NEK IEC 60300-3-11: Dependability management, Part [20] Castanier B, Rausand M. Maintenance optimization for subsea pipelines.
3–11: Application guide Reliability centred maintenance. Norsk elektrote- International Journal for Pressure Vessels and Piping 2006;83:236–43.
knisk komite (NEK), 1999. [21] Rausand M. Reliability centered maintenance. Reliability Engineering and
[5] SAE. SAE-JA1011: Evaluation criteria for reliability-centered maintenance System Safety 1998;60:121–32.
(RCM) processes, Society of Automotive Engineers, 1999. [22] Rausand M, Vatn J. Reliability centred maintenance. In: Kobbacy KAH, Murthy
[6] SAE. SAE-JA1012: A guide to the reliability-centered maintenance (RCM) DNP, editors. A Complex System Maintenance Handbook (Springer Series in
standard, Society of Automotive Engineers, 2002. Reliability Engineering). London: Springer-Verlag Limited; 2008. p. 79–108.
[7] Khamis B, Hiren S. Use of reliability centered maintenance (RCM) analysis in [chapter 4].
Petroleum Development Oman (PDO) for maintenance rationalization. SPE [23] Rausand M, Vatn J. Reliability Centered Maintenance. In: Guedes Soares C,
paper 87249. In: Proceedings of the 2000 Abu Dhabi International Petroleum editor. Risk and Reliability in Marine Technology. Rotterdam: Balkema;
Exhibition and Conference, 2000. 1998. p. 421–40.
[8] Carretero J, Garcı́a F, Pérez M, Peña JM, Pérez JM, Cotaina N, et al. Study of [24] Percy DF. Preventive maintenance models for complex systems. In: Kobbacy
existing reliability centered maintenance (RCM)—approaches used in KAH, Murthy DNP, editors. Complex System Maintenance Handbook.
different industries. Informe Técnico FIM/110.1/DATSI/00, Facultad de London: Springer-Verlag Limited; 2008. p. 179–208. [chapter 8].
Informática, UPM, 2000. [25] Cui L. Maintenance models and optimization. In: Misra KB, editor.
[9] Carretero J, Pérez JM, Garcı́a-Carballeira F, Calderón A, Fernández J, Handbook of Performability Engineering. London: Springer-Verlag Limited;
Garcı́a JD, et al. Applying RCM in large scale systems: a case study 2008. p. 789–806. [chapter 48].
with railway networks. Reliability Engineering and System Safety [26] Wang H, Pham H. Reliability and Optimal Maintenance. London: Springer-
2003;82:257–73. Verlag Limited; 2006.
[10] Vatn J. Maintenance in the rail industry. Preventive maintenance models for [27] Dekker R. Applications of maintenance optimization models: a review and
complex systems. In: Kobbacy KAH, Murthy DNP, editors. Complex System analysis. Reliability Engineering and System Safety 1996;51:229–40.
Maintenance Handbook. London: Springer-Verlag Limited; 2008. p. 509–32. [28] Apeland S, Scarf PA. A fully subjective approach to modelling inspection
[chapter 21]. maintenance. European Journal of Operational Research 2003;148:410–25.
[11] Desphande VS, Modak JP. Application of RCM for safety considerations [29] Selvik JT, Flage R and Aven T. The use of maintenance optimization
in a steel plant. Reliability Engineering and System Safety 2002;3(78): models—an empirical study from the Norwegian oil and gas industry. In:
325–34. Proceedings of the European safety and reliability conference, ESREL 2010,
[12] Johnson LP, Improving equipment reliability and plant efficiency through PM 2010.
optimization. Fractal Solutions, Inc., 1995, /http://www.fractalsoln.com/ [30] NORSOK. Z-008: Criticality analysis for maintenance purposes. Rev. 2.
Papers/PMO_Analysis.pdfS. Norwegian Technology Centre, 2001.
[13] Moubray J. Reliability-centered maintenance. 2nd ed.. NY: Industrial Press [31] NORSOK. Z-016: Regularity management & reliability technology. Rev. 1.
Inc; 1997. Norwegian Technology Centre. [Now replaced by ISO 20815], 1998.
[14] Bookless C, Sharkey M. Streamlined RCM in the nuclear industry. [32] International Organization for Standardization (ISO). ISO 20815: Petroleum,
Maintenance and Asset Management 1999;14(1):27–30. petrochemical and natural gas industries–Production assurance and relia-
[15] Cheng Z, Jia X, Gao P, Wu S, Wang J. A framework for intelligent reliability bility management. 1st ed., 2008.
centered maintenance analysis. Reliability Engineering and System Safety [33] Flage R, Aven T. Expressing and communicating uncertainty in relation to
2008;93:784–92. quantitative risk analysis. Reliability and Risk Analysis: Theory & Application
[16] Eisinger S, Rakowsky UK. Modeling of uncertainties in reliability centered 2009;2(13):9–18.
maintenance—a probabilistic approach. Reliability Engineering and System [34] Selvik JT, Aven T. An extended Bayesian updating approach to support
Safety 2001;71:159–64. product selection based on performance testing—a drilling jar case. In:
[17] Aven T. A unified framework for risk and vulnerability analysis and Bris R, Guedes Soares C, Martorell S, editors. Reliability, Risk and Safety:
management covering both safety and security. Reliability Engineering and Theory and Applications, vol. 2. Leiden: CRC Press, Taylor & Francis Group;
System Safety 2007;92:745–54. 2009. p. 813–9.

Вам также может понравиться