REKAPITULASI OPNAME

PEKERJAAN PLAFOND Pembayaran ke : 5 ( Lima )


PROYEK MAYAPADA HOSPITAL KUNINGAN Periode : 13 Juni ~ 27 Juni 2019

Opname Index
No Uraian Volume Total Harga Sat Total Total Qty Terpasang Nilai Material
Rangka Gypsum Compound Checklist Potongan

A PENUTUP CEILING UTAMA


1 Ceiling gypsum Topline 9 mm ex. Gyproc 7.735,90 m2 90.000,00 696.231.000,00 88.694.441,68 70.769.362,39 26.538.510,90 - 186.002.314,96 26,72% 2.463,73 37.257,27 91.792.028
2 Ceiling gypsum Topline 12 mm ex. Gyproc 1.678,70 m2 95.000,00 159.476.500,00 - - - - - 0,00% - 41.263,64 -
3 Ceiling gypsum Aqualine 12 mm (WR) ex. Gyproc 709,90 m2 110.000,00 78.089.000,00 420.200,00 420.200,00 157.575,00 997.975,00 1,28% 9,55 53.990,91 515.613
4 Ceiling akustik Classic Lite RH95 600x600 mm ex. Armstrong 74,90 m2 155.000,00 11.609.500,00 - - - -
5 Shadowline standard 10 x 10 mm 8.975,20 m1 17.000,00 152.578.400,00 9.515.559,60 9.515.559,60 3.568.334,85 22.599.454,05 14,81% 1.399,35 10.000 13.993.470

B AKSESORIS CEILING
Drop ceiling
- H : 100 mm 67,20 m1 18.000,00 1.209.600,00 160.416,00 160.416,00 60.156,00 380.988,00 31,50% 22,28 7.956,19 177.264
- H : 200 mm 314,50 m1 25.000,00 7.862.500,00 - - - - 0,00% - 10.661,46 -
- H : 300 mm 126,00 m1 32.000,00 4.032.000,00 390.656,00 390.656,00 146.496,00 927.808,00 23,01% 30,52 12.254,02 373.993
- H : 500 mm 28,70 m1 46.000,00 1.320.200,00 - - - - 0,00% - 25.741,16 -
- H : 600 mm 13,40 m1 60.000,00 804.000,00 - - - - 0,00% - 26.322,90 -
- H : 800 mm 6,30 m1 80.000,00 504.000,00 - - - - 0,00% - 29.508,00 -
- H : 1400 mm 8,00 m1 115.000,00 920.000,00 - - - - 0,00% - 55.019,11 -
Cove lampu uk. 250x150x50 mm 368,70 m1 62.000,00 22.859.400,00 - - - - 0,00% - 32.555,81 -
Box lampu uk. 150x50 mm 16,30 m1 45.000,00 733.500,00 - - - - 0,00% - 22.173,30 -
Box lampu uk. 200x50 mm 3,00 m1 50.000,00 150.000,00 - - - - 0,00% - 22.875,63 -
Akrilik box uk. 100 mm 349,90 m1 55.000,00 19.244.500,00 - - -
Akrilik box uk. 300 mm 34,80 m1 145.000,00 5.046.000,00 - - - - 0,00% - -
Curtain box -
- Uk. 200x200, bracket plywood 9 mm 587,87 m1 53.000,00 31.156.845,00 3.686.340,80 3.686.340,80 1.382.377,80 8.755.059,40 28,10% 173,88 21.089,14 3.667.065
- Uk. 750x200, bracket plywood 9 mm - m1 - -
Dinding partisi Baseline 12 mm dua sisi ex. Gyproc 265,10 m2 196.000,00 51.959.600,00 19.744.648,00 18.705.456,00 7.014.546,00 2.338.182,00 47.802.832,00 92,00% 251,85 42.272,73 10.646.175

C PLAFOND AREA BANK MAYAPADA


- Ceiling gypsum Topline 9 mm ex. Gyproc 122,24 m2 90.000,00 11.001.780,00 4.400.712,00 4.400.712,00 1.650.267,00 10.451.691,00 95,00% 122,24 37.257,27 4.554.404
- Curtain box uk. 700x200, braket plywood 9mm 17,45 m1 75.000,00 1.308.525,00 523.410,00 523.410,00 196.278,75 1.243.098,75 95,00% 17,45 27.774,32 484.579
- Up Ceiling, H : 200 mm 7,45 m1 25.000,00 186.175,00 74.470,00 74.470,00 27.926,25 176.866,25 95,00% 7,45 10.661,46 79.396
- Cuve lamp uk. 250x150x50 mm 7,28 m1 62.000,00 451.484,00 180.593,60 180.593,60 67.722,60 428.909,80 95,00% 7,28 32.555,81 237.071

1.258.734.509,00 Total Kumulatif 279.766.997,21


126.521.056

Pengambilan
- Periode 1 7.980.000,00
- Periode 2 30.000.000,00
- Periode 3 50.000.000,00
- Periode 4 50.000.000,00

Subtotal Pengambilan 137.980.000,00

Total Opname 15.265.940,77

Dibuat oleh, Disetujui oleh,


PT CIPTA BANGUN INDAH PENERIMA TUGAS

( Sudhiastono ) ( Hobin Iswara )


Project Manager