2 Mobilisasi & demobilisasi 97 days Mon 5/6/19 Wed 9/25/19 5/6 9/25
5 Akses Jalan Masuk 14 days Wed 5/8/19 Tue 5/21/19 5/8 5/21
8 - Bored pile ø 600mm, l = 24m (26 titik) 18 days Tue 5/14/19 Tue 6/18/19 5/14 6/18
9 - Bored pile ø 800 mm, l= 18m (2 titik) 4 days Wed 6/19/19 Mon 6/24/19 6/19 6/24
10 - Test pda & lateral 4 days Tue 5/28/19 Tue 6/18/19 5/28 6/18
12 - Pas batu kali 21 days Sun 5/19/19 Fri 6/28/19 5/19 6/28
14 - Pek. Abutment & pilecap bp ø 800mm 14 days Fri 6/21/19 Wed 7/10/19 6/21 7/10
17 - Umur Beton Abutment (14 Days) 0 days Tue 7/30/19 Tue 7/30/19 7/30
18 - Perancah girder (Tool Erection Girder) 6 days Tue 7/23/19 Tue 7/30/19 7/23 7/30
19 - Install girder & stressing 14 days Wed 7/31/19 Mon 8/19/19 7/31 8/19
Project: Bridge Apart Simprug Signatu Milestone Manual Task External Milestone
Date: 3 Mei 2019 Summary Duration-only Progress
Revision: 00
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only
21 - Bridge deck & pedestrian 12 days Mon 8/19/19 Tue 9/3/19 8/19 9/3
23 - Pedestal pju & pipa ø600mm 2 days Fri 8/2/19 Mon 8/5/19 8/2 8/5
24 - Pipa air hujan ø100mm ~ 2500mm 10 days Wed 8/21/19 Tue 9/3/19 8/21 9/3
26 - Pabrikasi curve pipe ø600mm 21 days Mon 6/17/19 Mon 7/15/19 6/17 7/15
29 - Install curve pipe & strand bracing 14 days Thu 8/29/19 Tue 9/17/19 8/29 9/17
33 - Stamped concrete pedestrian 4 days Wed 9/11/19 Mon 9/16/19 9/11 9/16
34 - Fill soil median jalan 3 days Fri 9/13/19 Tue 9/17/19 9/13 9/17
36 Deffect List, Testing & commissioning 4 days Fri 9/20/19 Wed 9/25/19 9/20 9/25
Project: Bridge Apart Simprug Signatu Milestone Manual Task External Milestone
Date: 3 Mei 2019 Summary Duration-only Progress
Revision: 00
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only