SCHEDULE

BRIDGE APART. SIMPRUG SIGNATURE


JAKARTA

ID Task Name Duration Start Finish 2019


May June July August September
4/29 5/6 5/13 5/20 5/27 6/3 6/10 6/17 6/24 7/1 7/8 7/15 7/22 7/29 8/5 8/12 8/19 8/26 9/2 9/9 9/16 9/23 9/30 1
1 PEK. PERSIAPAN 97 days Mon 5/6/19 Wed 9/25/19

2 Mobilisasi & demobilisasi 97 days Mon 5/6/19 Wed 9/25/19 5/6 9/25

3 Fasilitas sementara 14 days Wed 5/8/19 Tue 5/21/19 5/8 5/21

4 Stacking Out 3 days Thu 5/9/19 Sat 5/11/19 5/9 5/11

5 Akses Jalan Masuk 14 days Wed 5/8/19 Tue 5/21/19 5/8 5/21

6 PEK. STRUKTUR 83 days Tue 5/14/19 Tue 9/17/19

7 Pek. Pondasi 22 days Tue 5/14/19 Mon 6/24/19

8 - Bored pile ø 600mm, l = 24m (26 titik) 18 days Tue 5/14/19 Tue 6/18/19 5/14 6/18

9 - Bored pile ø 800 mm, l= 18m (2 titik) 4 days Wed 6/19/19 Mon 6/24/19 6/19 6/24

10 - Test pda & lateral 4 days Tue 5/28/19 Tue 6/18/19 5/28 6/18

11 Pek. Struktur Bawah 50 days Sun 5/19/19 Thu 8/8/19

12 - Pas batu kali 21 days Sun 5/19/19 Fri 6/28/19 5/19 6/28

13 - Urugan tanah 10 days Tue 6/18/19 Mon 7/1/19 6/18 7/1

14 - Pek. Abutment & pilecap bp ø 800mm 14 days Fri 6/21/19 Wed 7/10/19 6/21 7/10

15 - Pier head 7 days Wed 7/31/19 Thu 8/8/19 7/31 8/8

16 Pek. Struktur Atas 31 days Tue 7/23/19 Tue 9/3/19

17 - Umur Beton Abutment (14 Days) 0 days Tue 7/30/19 Tue 7/30/19 7/30

18 - Perancah girder (Tool Erection Girder) 6 days Tue 7/23/19 Tue 7/30/19 7/23 7/30

19 - Install girder & stressing 14 days Wed 7/31/19 Mon 8/19/19 7/31 8/19

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks

Project: Bridge Apart Simprug Signatu Milestone Manual Task External Milestone
Date: 3 Mei 2019 Summary Duration-only Progress
Revision: 00
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only

Page 1 PT. NUSA RAYA CIPTA, Tbk.


SCHEDULE
BRIDGE APART. SIMPRUG SIGNATURE
JAKARTA

ID Task Name Duration Start Finish 2019


May June July August September
4/29 5/6 5/13 5/20 5/27 6/3 6/10 6/17 6/24 7/1 7/8 7/15 7/22 7/29 8/5 8/12 8/19 8/26 9/2 9/9 9/16 9/23 9/30 1
20 - Balok diafragma 12 days Thu 8/8/19 Fri 8/23/19 8/8 8/23

21 - Bridge deck & pedestrian 12 days Mon 8/19/19 Tue 9/3/19 8/19 9/3

22 - Plat injak 4 days Wed 7/31/19 Mon 8/5/19 7/31 8/5

23 - Pedestal pju & pipa ø600mm 2 days Fri 8/2/19 Mon 8/5/19 8/2 8/5

24 - Pipa air hujan ø100mm ~ 2500mm 10 days Wed 8/21/19 Tue 9/3/19 8/21 9/3

25 Pek. Struktur Baja 67 days Mon 6/17/19 Tue 9/17/19

26 - Pabrikasi curve pipe ø600mm 21 days Mon 6/17/19 Mon 7/15/19 6/17 7/15

27 - Pabrikasi railing 30 days Mon 6/17/19 Fri 7/26/19 6/17 7/26

28 - Install railing 14 days Wed 8/21/19 Mon 9/9/19 8/21 9/9

29 - Install curve pipe & strand bracing 14 days Thu 8/29/19 Tue 9/17/19 8/29 9/17

30 PEK. ARSITEKTUR 14 days Mon 9/2/19 Thu 9/19/19

31 - Pas. Kansteen 7 days Mon 9/2/19 Tue 9/10/19 9/2 9/10

32 - Median jalan 6 days Wed 9/4/19 Wed 9/11/19 9/4 9/11

33 - Stamped concrete pedestrian 4 days Wed 9/11/19 Mon 9/16/19 9/11 9/16

34 - Fill soil median jalan 3 days Fri 9/13/19 Tue 9/17/19 9/13 9/17

35 - Hotmix t.3cm 2 days Wed 9/18/19 Thu 9/19/19 9/18 9/19

36 Deffect List, Testing & commissioning 4 days Fri 9/20/19 Wed 9/25/19 9/20 9/25

37 SERAH TERIMA 0 days Wed 9/25/19 Wed 9/25/19 9/25

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks

Project: Bridge Apart Simprug Signatu Milestone Manual Task External Milestone
Date: 3 Mei 2019 Summary Duration-only Progress
Revision: 00
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only

Page 2 PT. NUSA RAYA CIPTA, Tbk.