Activity Progress

Saturday, 29 June 2019


Progress Accumulation Man Po
No Description Activities Location Works
Plan (%) Actual (%) Plan (%) Actual (%) Plan (%)
Euroasiatic
1 Site Coordinator 1 Person
2 Civil Engineer 0 Person
3 Site Officer 1 Person
4 Safety Officer ( HSE) 1 Person
5 Visit Management 0 Person
DCA Team
1 Preparation and Drill Pilling Works Utility Area 4.34% 0.00% 80.43% 78.26%
2 Continue Cleaning TOH Area ( After Drill Pile Finish) TOH Area 0.00% 0.00% 0.00% 0.00%
3 Continue Install Temporary Office and Toilet Project Area 0.00% 10.00% 0.00% 35.00%
4 Continue Mobilization Equipment, Tools and Matrials Project Area 0.00% 4.00% 0.00% 12.00%
23 Persons
5 Continue Surveyor Works Project Area 0.00% 14.30% 0.00% 20.00%
6 Continue Install Bowplank For Mark Foundation (Foudation Works) Project Area 0.00% 0.00% 0.00% 0.00%
7 Start Excavation Foudations Equipment GT Project Area 0.00% 3.33% 0.00% 3.33%
8
Gasindo Team
1 Continue Digging/Exavation MRS Area 33.00% 33.00% 66.00% 80.00%
2 Continue Mobilization Equipment, Tools and Matrials Utility/Project Area 0.00% 0.00% 0.00% 0.00%
16 Persons

Total 42 Person

Monday, 01 Juli 2019


Progress Man Po
No Description Activities Location Works
Plan (%) Actual (%) Plan (%)
Euroasiatic
1 Site Coordinator 1 Person
2 Civil Engineer 1 Person
3 Site Officer 1 Person
4 Safety Officer ( HSE) 1 Person
5 Visit Management 0 Person
DCA Team
1 Preparation and Drill Pilling Works Utility Area 2.17%
2 Continue Cleaning TOH Area ( After Drill Pile Finish) TOH Area 0.00%
3 Continue Install Temporary Office and Toilet Project Area 10.00%
4 Continue Mobilization Equipment, Tools and Matrials Project Area 4.00%
23 Persons
5 Continue Surveyor Works Project Area 20.00%
6 Continue Install Bowplank For Mark Foundation (Foudation Works) Project Area 0.00%
7 Continue Excavation Foudations Equipment GT Project Area 3.33%
8
Gasindo Team
1 Continue Digging/Exavation MRS Area 33.00%
2 Continue Mobilization Equipment, Tools and Matrials Utility/Project Area 0.00%
16 Persons
3 Wall Thickness MRS Area 100.00%

Total 43 Person

Prepared, Approved,

Euroasiatic Team PT. Indorama Ventures Indonesia


y Progress

Man Power Work Hours


Remark
Actual (%) Plan (%) Actual (%)

1 Person
0 Person
1 Person 08:00 - 16:00 08:00 - 16:00
1 Person
0 Person

23 Persons 08:00 - 16:00 08:00 - 16:00

Found Pile Existing at area Project

14 Persons 08:00 - 16:00 08:00 - 16:00

40 Person 7 Hours 7 Hours

Man Power Work Hours


Remark
Actual (%) Plan (%) Actual (%)

08:00 - 17:00
Toolbox Meeting Every Day Works
08:00 - 17:00

08:00 - 17:00

8 Hours
Activity Progress
Friday, 28 June 2019
Progress Man Power Work Ho
No Description Activities Location Works
Plan (%) Actual (%) Plan (%) Actual (%) Plan (%)
Euroasiatic
1 Site Coordinator 1 Person 1 Person
2 Civil Engineer 1 Person 1 Person
3 Site Officer 1 Person 1 Person 08:00 - 17:00
4 Safety Officer ( HSE) 1 Person 1 Person
5 Visit Management 0 Person 0 Person
DCA Team
1 Continue Drill Pilling Works for Pipe Rack Area TOH Area 100% 100%
2 Moving Equipment Drill Pile to Utility Area Utility Area 100% 100%
3 Continue Install Temporary Office and Toilet Project Area 14.30% 14.30%
4 Continue Mobilization Equipment, Tools and Matrials Project Area 8% 8%
26 Persons 23 Persons 08:00 - 17:00
5 Continue Surveyor Works Project Area 14.30% 14.30%
6 Continue Install Bowplank For Mark Foundation (Foudation Works) Project Area 28.60% 28.60%
7 Cleaning TOH Area ( After Drill Pile Finish) TOH Area
8
Gasindo Team
1 Continue Digging/Exavation MRS Area 33% 33%
2 Continue Mobilization Equipment, Tools and Matrials Utility/Project Area
17 Persons 16 Persons 08:00 - 17:00

Total 48 Person 43 Person 8 Hours

Saturday, 29 June 2019


Progress Man Power Work Ho
No Description Activities Location Works
Plan (%) Actual (%) Plan (%) Actual (%) Plan (%)
Euroasiatic
1 Site Coordinator 1 Person
2 Civil Engineer 0 Person
3 Site Officer 1 Person 08:00 - 16:00
4 Safety Officer ( HSE) 1 Person
5 Visit Management 0 Person
DCA Team
1 Preparation Drill Pilling Works Utility Area 4.34%
2 Continue Cleaning TOH Area ( After Drill Pile Finish) TOH Area 0.00%
3 Continue Install Temporary Office and Toilet Project Area 0.00%
4 Continue Mobilization Equipment, Tools and Matrials Project Area 0.00%
23 Persons 08:00 - 16:00
5 Continue Surveyor Works Project Area 0.00%
6 Continue Install Bowplank For Mark Foundation (Foudation Works) Project Area 0.00%
7 Start Excavation Foudations Equipment GT Project Area 0.00%
8
Gasindo Team
1 Continue Digging/Exavation MRS Area 33%
2 Continue Mobilization Equipment, Tools and Matrials Utility/Project Area 0%
16 Persons 08:00 - 16:00

Total 42 Person 7 Hours

Prepared, Approved,

Euroasiatic Team PT. Indorama Ventures Indonesia


y Progress

Work Hours
Remark
Actual (%)

08:00 - 17:00

Weekly Meeting

16:00 1 Point
17.30
17:00
17:00
17:00
17:00
17:00

17:00
17:00

8 Hours

Work Hours
Remark
Actual (%)
Activity Progress
Thursday, 27 June 2019
Progress Man Power Work Ho
No Description Activities Location Works
Plan (%) Actual (%) Plan (%) Actual (%) Plan (%)
Euroasiatic
1 Site Coordinator 1 Person
2 Civil Engineer 1 Person
3 Site Officer 1 Person 08:00 - 17:00
4 Safety Officer ( HSE) 1 Person
5 Visit Management 1 Person
DCA Team
1 Continue Drill Pilling Works for Pipe Rack Area TOH Area 100% 100%
2 Moving Equipment Drill Pile to Utility Area Utility Area 100% 100%
3 Continue Install Temporary Office and Toilet Project Area 7.15% 7.15%
4 Continue Mobilization Equipment, Tools and Matrials Project Area 4% 4%
26 Persons 08:00 - 17:00
5 Continue Surveyor Works Project Area 7.15% 7.15%
6 Continue Install Bowplank For Mark Foundation (Foudation Works) Project Area 14.30% 14.30%
7 TOH Area
8
Gasindo Team
1 Continue Digging/Exavation MRS Area 33% 33%
2 Continue Mobilization Equipment, Tools and Matrials Utility/Project Area
17 Persons 08:00 - 17:00

Total 48 Person 8 Hours

Friday, 28 June 2019


Progress Man Power Work Ho
No Description Activities Location Works
Plan (%) Actual (%) Plan (%) Actual (%) Plan (%)
Euroasiatic
1 Site Coordinator 1 Person
2 Civil Engineer 1 Person
3 Site Officer 1 Person 08:00 - 17:00
4 Safety Officer ( HSE) 1 Person
5 Visit Management 0 Person
DCA Team
1 Continue Drill Pilling Works for Pipe Rack Area TOH Area 100%
2 Moving Equipment Drill Pile to Utility Area Utility Area 100%
3 Continue Install Temporary Office and Toilet Project Area 14.30%
4 Continue Mobilization Equipment, Tools and Matrials Project Area 8%
26 Persons 08:00 - 17:00
5 Continue Surveyor Works Project Area 14.30%
6 Continue Install Bowplank For Mark Foundation (Foudation Works) Project Area 28.60%
7 Cleaning TOH Area ( After Drill Pile Finish) TOH Area
8
Gasindo Team
1 Continue Digging/Exavation MRS Area 33%
2 Continue Mobilization Equipment, Tools and Matrials Utility/Project Area
17 Persons 08:00 - 17:00

Total 47 Person 8 Hours

Prepared, Approved,

Euroasiatic Team PT. Indorama Ventures Indonesia


y Progress

Work Hours
Remark
Actual (%)

Weekly Meeting

2 Point Pile

Work Hours
Remark
Actual (%)