Академический Документы
Профессиональный Документы
Культура Документы
different grade of concrete like M5, M7.5, M10, M15 and M20. if you don’t want to learn the math
involved in the design, you can use the table given at the end of the article to produce different
grade of concrete.
There are two ways to design the concrete mix. They are Design mix method and nominal mix
method. Once you know the math behind the design you can easily design any grade of concrete for
different purposes in different units.
In the design mix method, materials are proportioned based on the procedure and rules given in
IS456(2000) and IS10262(2009) codebooks. In this method, cement, sand and aggregates are always
batched in terms of weight, and concrete can be designed for different environmental conditions
and different needs. Hence, if you prepare concrete using design mix method you can save cost and
get good quality of concrete.
In nominal mix method, materials are proportioned based on prescribed approximation and
experience to attain the different grade of concrete. Cement, sand and aggregates are usually
batched in terms of volume using pans, batching boxes etc.., Nominal mix method is easier to follow
in site and they are easier to design and measure hence they are often used in site to produce
concrete up to M20 grade.
UNDERSTANDING CONCRETE GRADE AND CONCRETE MIX RATIOS
Concrete is classified into different grades like M5, M7.5, M10, M15 etc., where M stands for Mix
and the following number stands for characteristic compressive strength(fck) of concrete in 28 days
in the Direct Compression test. So, if you produce M20 grade concrete then you will get the
compressive strength of 20 N/mm2 in 28 days after mixing and casting.
The strength of concrete is based on the ratio of cement, sand, aggregate used to prepare concrete.
Hence it is important to determine the mix ratio through previous experience and Guidelines.
Concrete mix ratios are usually in the form of cement : Sand: Aggregate. For example, if the concrete
mix ratio of M20 concrete is 1:1.5:3 then 1 part of cement, 1.5 part of sand and 3 part of aggregate
in volume should be taken to produce concrete.
Prescribed concrete Mix ratios for all grades of concrete are given below
M5 1 : 5 : 10
M 7.5 1:4:8
M 10 1:3:6
M 15 1:2:4
M 20 1 : 1.5 : 3
Above concrete mix ratios are not strictly practised in the site. You will often notice that the
contractors increase the quantity of sand and reduce the quantity of cement to reduce the cost.
Increasing the sand content will increase the workability of concrete which is good for mixing and
placing but increasing the sand content will decrease the percentage of cement in concrete hence
the strength and durability of the concrete will be affected. It is advisable not to increase the sand
content more than 30 per cent than the above-prescribed ratio.
DESIGN OF NOMINAL MIX CONCRETE FOR ONE CUBIC METER OF M20 CONCRETE
Though you want to prepare 1 cubic meter of concrete, the total volume of cement sand and
aggregate required will be more than 1 cu.m. Because, while mixing, cement and sand has to fill the
gaps between the aggregate(crushed stone) before taking their own place. Hence if you want to
produce concrete with 20 mm aggregate then the total volume of cement sand and aggregate you
require will be 1.55 cubic meters, and if you want to produce concrete with 40 mm aggregate then
the total volume of cement sand and aggregate you require will be 1.52 cubic meters.
Let’s calculate material required for M20 grade to prepare one cubic meter concrete.
Cement sand and aggregate ratio for M20 grade concrete is 1:1.5:3
Cement = 1 Part
Sand = 1.5 Part
Aggregate = 3 Part
= 0.282 cu.m
= 1 x 0.282
= 0.282 cu.m
= 1.5 x 0.282
= 0.423 cu.m
= 3 x 0.282
= 0.846 cu.m
Cement is often bought in 50kg bags hence we must convert our calculated quantity to bags.
= 0.282x 1440
= 406kg
Aggregates are often bought in Units through lorries and tippers. One cubic meter is 35.32 Cubic
feet. One unit is equal to 100 cubic feet.
= 0.423 x 35.32
= 15 cft
=0.15 unit
Hence we require 15 cft of aggregate to prepare one cubic meter of M20 grade
=15 cft x 2
= 302 cft
= 0.30 unit
Hence we require 30 cft of aggregate to prepare one cubic meter of M20 grade concrete.
Gauge boxes, pans are used for Volume batching in site. Volume of a gauge box is 0.35 cu.m(1cft)
which is a volume of 1 bag of cement. For M20 grade, use 1 bag of cement, 1.5 boxes of sand and 3
boxes of aggregate. These are our results….
Likewise, cement, sand and aggregate for different concrete grades with 20mm aggregate (Total dry
material = 1.55)….
GRADE CEMENT SAND AGG.
QUANTITY OF CEMENT SAND AND AGGREGATE IN WEIGHT PER BAG (50KG) OF CEMENT
IS456 Code book recommends the following quantities of total aggregate per 50kg of cement to
produce nominal mix concrete.
GRADE TOTAL ( FINE + COARSE )
M5 800 kg
M 7.5 625 kg
M 10 480 kg
M 15 330 kg
M 20 250 kg
Note: General ratio of fine aggregate to coarse aggregate is 1:2, but it can be adjusted between 1:1.5
to 1:2.5 based on the grading of fine aggregate and size of coarse aggregate.
Let’s find out the quantity needed to produce M20 grade by the codal procedure. Sand is confirmed
to Zone II – average grading. The ratio of fine to coarse aggregate is chosen as usual as 1:2. From the
above table we know we need 250kg of total dry aggregate for our concrete.
=83 kg ~ 85 kg
= 166 kg ~ 165 kg
Likewise, the weight of cement, sand and aggregate per bag of cement for different concrete grades
…
Water is taken based on the weight of cement and the required workability. For design mix concrete
codebook suggests to use suitable Water/Cement ratio based on different factors but for nominal
mix concrete codebook suggests the following quantities per bag of cement.
M5 60
M7.5 45
M10 34
M15 32
M20 30
Tweet
Post navigation
76 thoughts on “Calculate Cement Sand and Aggregate for Nominal mix concrete in Volume and in
Weight”
Reply
Reply
Since many readers are asking the same question I have updated the post. Read the post again or
click here
Reply
Kathavarayan says:
Reply
I will publish about steel calculation soon. In the meantime You can refer “Estimation and quantity
surveying” book by Dutta
Reply
I have updated the post. In the end of the post you will find what you are looking for.
Reply
Reply
prakashkumarsekar says:
Reply
Is this method also applicable for designing nominal mixture of M15 grade
Reply
Yes of course but instead of multiply 1.5 in the volume required formula, you should multiply 1.55.
Reply
Anonymous says:
NIRANJAN DASH
Reply
Anonymous says:
Reply
veerababu says:
Reply
Anonymous says:
May 11, 2016 at 9:42 am
Reply
prakashkumarsekar says:
1:3:6 is a M10 grade concrete. As per IS456, for 50kg bag of cement you will need 480 kg of total
aggregate i.e., 160kg of sand and 320kg of coarse aggregate.
Reply
Anonymous says:
i think its 450kg for total aggregate , so 150kg sand and 300kg CA
Reply
Yes that’s what code book suggests If you are looking for weigh batching
Anonymous says:
M 35
Reply
The ratio is same for river sand and Robo sand( M-Sand).
Reply
Sathish says:
Yes
Reply
desta says:
how can we apply this for different dimensions(cross section)?¡.e in my case i do have
1.7m*1.7m*0.5 footing pad which is prepared to be filled.
Reply
Calculate the concrete quantity required in cubic meter and then multiply the quantity with the
cement sand and aggregate for 1 cubic meter of concrete.
In your case
Volume of concrete = 1.7 x 1.7 x 0.5 = 1.4 cu.m
It looks like you are using m20 grade mix with extra sand. If you follow that mix proportion then to
calculate use this following method.
Total ratio = 1 + 2 + 3 = 6
Cement required = (1/6) x 1.5 = 0.25 cu.m (refer the post to change cu.m to bags)
Sand = 0.25 x 2 = 0.5 cu.m
Aggregate = 0.25 x 3 = 0.75 cu.m
Reply
Akram says:
Sir int his case we did calculate sand and aggregate in cubic feet but how we cn use it at site in
execution plz tell me quickly
Reply
You can calculate by counting head Pan. If you are using M15 grade concrete then for every 1 pan of
cement use 2 pan of fine aggregate and 4 pan of coarse aggregate.
Reply
Anonymous says:
Reply
Anonymous says:
Reply
Reply