Академический Документы
Профессиональный Документы
Культура Документы
If a firm accepts a project with a $10,000 NPV, what is the effect on the
value of the firm? If a firm accepts a project with a $10,000 NPV, it
will increase its value by $10,000.
3.
What are the five steps used in NPV analysis? The five-step process used
in the NPV analysis can be listed as follows: (1) Determine the cost of
the project. (2) Estimate the project’s future cash flows over its
expected life. (3) Determine the riskiness of a project and the
appropriate cost of capital. (4) Compute the project’s NPV. (5) Make a
decision.
Section 10.3 1. What is the payback period? The payback period is defined
as the number of years it takes to recover the project’s initial
investment. All other things being equal, the project with the shortest
payback period is usually the optimal investment. 2. Why does the payback
period provide a measure of a project’s liquidity risk? The payback
period determines how quickly you recover your investment in a project.
Thus, it serves as a good measure of the project’s liquidity. 3. What are
the main shortcomings of the payback method? The payback method does not
account for time value of money, nor does it distinguish between high-
and low-risk projects. In addition, there is no rationale behind choosing
the cutoff criteria. For all these reasons, the payback method is not the
ideal capital decision rule.
Section 10.4 1. What are the major shortcomings of using the ARR method
as a capital budgeting method? The biggest shortcoming of using ARR as a
capital budgeting tool is that it uses historical, or book value data
rather than cash flows and thus disregards the time value of money
principle. In addition, as in the payback method, it fails to establish a
rationale behind picking the appropriate hurdle rate.
Section 10.5 1. What is the IRR method? The IRR, or the internal rate of
return, is the discount rate that makes the net present value of the
project’s future cash flows zero. The IRR determines whether the
project’s return rate is higher or lower than the required rate of
return, which is the firm’s cost of capital. As a rule, a project should
be accepted if the IRR exceeds the firm’s cost of capital; otherwise the
project should be rejected. 2. In capital budgeting, what is a
conventional cash flow pattern? A conventional project cash flow in
capital budgeting is one in which an initial cash outflow is followed by
one or more future cash inflows. 3. Why should the NPV method be the
primary decision tool used in making capital investment decisions? Given
all the different methods to evaluate capital investment decisions, the
NPV method is the preferred valuation tool as it accounts for both time
value of money and the project’s risk. Furthermore, NPV is not sensitive
to nonconventional projects, and
therefore it is superior to the IRR technique and it gives a measure of
the value increase/decrease to the firm by undertaking the project.
Section 10.6 1. What changes have taken place in the capital budgeting
techniques used by U.S. companies? Over the years, there has been a shift
from using payback and ARR as the primary capital budgeting tools to
using NPV and IRR instead. Managers today understand the importance of
the time value of money and discounting and thus regard ARR as an
inaccurate and obsolete decision tool.
Self-Study Problems
10.1 Premium Manufacturing Company is evaluating two forklift systems to
use in its plant that produces the towers for a windmill power farm. The
costs and the cash flows from these systems are shown below. If the
company uses a 12 percent discount rate for all projects, determine which
forklift system should be purchased using the net present value (NPV)
approach. Year 0 Otis Forklifts Craigmore Forklifts Solution: NPV for
Otis Forklifts:
−$3,123,450 −$4,137,410
CFt t t = 0 (1 + k )
n
= −$3,123,450 +
NPV = ∑
Premium should purchase the Otis forklift since it has a larger NPV.
Rutledge, Inc., has invested $100,000 in a project that will produce cash
flows of $45,000, $37,500, and $42,950 over the next three years. Find
the payback period for the project.
10.2
10.3
Year 1 2 3 4
145,655
110,090
Payback period for Project A: Payback period = Years before cost recovery
+ = 3+ $35,565 $145,655 per year = 3.24 years Remaining cost to recover
Cash flow during the year
Payback period = Years before cost recovery + =2+ $141, 425 $153, 250 per
year = 2.92 years
10.4
The company’s tax rate is 34 percent.
Year 1 Year 2 Year 3 Year 4 Year 5 The company w ill accept all projects
that provi de an accou$255,440 nting rate of re turn (ARR) of at least 45
percent. Sh $123,450 $176,875 $242,455 $267,125 Sales Expenses
$137,410
$126,488
$141,289
$143,112
$133,556
The company will accept all projects that provide an accounting rate of
return (ARR) of at least 45 percent. Should the company accept the
project?
Sales Expenses Depreciation EBIT Taxes (34%) Net Income Beginning Book
Value Less: Depreciation Ending Book Value Average net income Average
book value
$ 93,800 $ 70,350
Refer to Problem 10.1. Compute the IRR for each of the two systems. Is
the investment decision different from the one determined by NPV?
Solution:
IRR for two forklift systems: Otis Forklifts: First compute the IRR by
the trial-and-error approach: NPV (Otis) = $337,075 > 0 Use a higher
discount rate to get NPV = 0! At k = 15%,
NPVOtis = −$3,123, 450 + $979, 225 $1, 358,886 $2,111, 497 + + (1 +
0.15)1 (1.15) 2 (1.15)3 = −$3,123, 450 + $851,500 + $1, 027,513 + $1,
388, 344 = $143, 907.
10.2
offered to donate the land, and as part of the agreement, the company
will have to build an access road from the main highway to the plant. How
will the project of building the road be classified in capital budgeting
analysis?
b. Sykes, Inc., is considering two projects: a plant expansion and a new
computer
firm’s computers. The firm can choose the Linux operating system that a
local
computer services firm has offered to install and maintain. Microsoft has
also put in a bid to install the new Windows operating system for
businesses. What type of project is this?
a. This is a contingent project. Acceptance of the road-building project
is contingent
on the new plant being a financially viable project. If the new plant
will not have a positive value, then the firm will not even consider this
project. However, this project’s cost will have to be considered along
with the cost of building the new plant in the capital budgeting
analysis.
b. These two projects are independent projects. Accepting or rejecting
one will not
influence the decision on the other project. The cash flows of the two
projects are unrelated.
c. These are two mutually exclusive projects. The company’s computers
need only
one operating system. Either the Linux or the Windows operating system
needs to be installed, not both. Hence, the selection of one will
eliminate the other from consideration. In the context of capital
budgeting, what is “capital rationing”? Capital rationing implies that a
firm does not have the resources necessary to fund all of the available
projects. In other words, funding needs exceed funding resources. Thus,
the available capital will be allocated to the projects that will benefit
the firm and its shareholders the most. Projects that create the largest
increase in shareholder wealth will be accepted until all the available
resources have been allocated. Provide two conditions under which a set
of projects might be characterized as mutually exclusive.
10.3
10.4
When projects are mutually exclusive, acceptance of one project precludes
the acceptance of others. Typically, mutually exclusive projects perform
the same function and so only one of them needs to be accepted. A funding
or resource constraint can also cause projects to be mutually exclusive.
10.5
cost of capital is also 12 percent, did the firm make the right decision.
Explain.
b. What is the impact on the firm if it accepts a project with a negative
NPV? a. We would normally argue that a firm should only accept projects
in which the
project’s return exceeds the cost of capital. In other words, only if the
net present value exceeds zero should a project be accepted. But in
reality, projects with a zero NPV should also be accepted because the
project earns a return that equals the cost of capital. For some firms
like the one above, this could be the situation because they may not have
projects that provide a return greater than the cost of capital for the
firm.
b. When a firm takes on positive NPV projects, the value of the firm
increases. By
the same token, when a project undertaken has a negative NPV, the value
of the firm will decrease by the amount of the net present value.
Identify the weaknesses of the payback period method. There are several
critical weaknesses in the payback period approach of evaluating capital
projects.
ƒ ƒ ƒ
10.6
The payback period ignores the time value of money by not discounting
future cash flows. When comparing projects, it ignores risk differences
between the projects. A firm may establish payback criteria with no
economic basis for that decision and thereby run the risk of losing out
on good projects.
ƒ
The method ignores cash flows beyond the payback period, thus leading to
nonselection of projects that may produce cash flows well beyond the
payback period or more cash flows than accepted projects. This leads to a
bias against longer-term projects.
10.7
What are the strengths and weaknesses of the accounting rate of return
(ARR) approach? The biggest advantage of ARR is that it is easy to
compute since accounting data is readily available, whereas estimating
cash flows is more difficult. However, the disadvantages outweigh this
specific advantage. Similar to the payback, it does not discount cash
flows, but merely averages net income over time. No economic rationale is
used in establishing an ARR cutoff rate. Finally, the ARR uses net income
to evaluate the project and not cash flows or market data. This is a
serious flaw in this approach. Under what circumstances might the IRR and
NPV approaches have conflicting results? IRR and the NPV methods of
evaluating capital investment projects might produce dissimilar results
under two circumstances. First, if the project’s cash flows are not
conventional—that is, if the sign of the cash flow changes more than once
during the life of a project—then multiple IRRs can be obtained as
solutions. We would be unable to identify the correct IRR for decision
making. (See Learning by Doing Application 10.3.) The second situation
occurs when two or more projects are mutually exclusive. The project with
the highest IRR may not necessarily be the one with the highest NPV and
thereby be the right choice. There is an important reason for this. IRR
assumes that all cash flows received during the life of a project are
reinvested at the IRR, whereas the NPV method assumes that they are
reinvested at the cost of capital. Since the cost of capital is the
better proxy for opportunity cost, NPV uses the better proxy, while the
IRR may use an unrealistically higher rate as proxy.
10.8
10.9
The modified IRR (MIRR) alleviates two concerns with using the IRR method
for evaluating capital investments. What are they? IRR assumes that the
cash flows from a project are reinvested at the project’s IRR, while the
NPV assumes that they are invested at the firm’s cost of capital. The NPV
assumption is correct more often than not. The MIRR assumes that each
operating cash flow is reinvested at the firm’s cost of capital. The
second appeal of MIRR is that under this method all of the compounded
operating cash flow values are summed up to get the project’s terminal
value. Since most projects generate positive total net operating cash
flows, MIRR does not suffer from issues associated with unconventional
cash flows.
Project
Expected Return
Risk
13% 12 18 9 13
Project
Risk
Required Return
Expected Return
Low Average
10% 12
13% 12
3. Commercial 4. Single-family homes 5. Commercial
15 10 15
18 9 13
BASIC
10.1 Net present value: Riggs Corp. management is planning to spend
$650,000 on a new
Solution:
= $62,337
10.2
Solution:
= −$4,133,250 +
10.3
NCFt t t = 0 (1 + k )
n
NPV = ∑
NCFt t t = 0 (1 + k )
n
Year 0 1 2 3
10.6
10.7
Solution:
Cumulative Year 0 1 2 3 CF $(3,768,966) 979,225 1,158,886 1,881,497 Cash
Flow $(3,768,966) (2,789,741) (1,630,855) 250,642
10.8
10.9
$1,875,000. Management expects productivity gains and cost savings over
the next several years. If the firm is expected to generate cash flows of
$586,212, $713,277, $431,199, and $318,697 over the next four years, what
is the investment’s payback period? LO 3 Solution: Cumulative Year 0 1 2
3 4 CF $(1,875,000) 586,212 713,277 431,199 318,697 Cash Flow $(1,875,000
(1,288,788) (575,511) (144,312) 174,385
Average after - tax income Average book value $63,435 = = 29.9% $212,500
Since the project’s ARR is below the acceptance rate of 37.5 percent, the
project should be rejected. 10.11 Internal rate of return: Refer to
Problem 10.4. What is the IRR that Franklin Mints management can expect
on this project? LO 5
NPV = 0 = ∑
FCFt t t = 0 (1 + IRR )
n
FCFt t t = 0 (1 + IRR )
n
LO 5
Solution:
Initial investment = $7,800,000 Annual cash flows = $1,800,000 Length of
project = n = 6 years Required rate of return = k = 12% To determine the
IRR, a trial-and-error approach can be used. Set NPV = 0. Try IRR = 12%.
NPV = 0 = ∑
FCFt t t = 0 (1 + IRR )
n
LO 2
Solution:
Cost of Alpha 8300 = $3,122,300 Annual cost savings = $1,345,500 Length
of project = n = 5 years Required rate of return = k = 14%
NPV = ∑
10.15 Net present value: Cranjet Industries is expanding its product line
and its production capacity. The costs and expected cash flows of the two
independent projects are given in the following table. The firm typically
uses a discount rate of 16.4 percent. a. b What are the NPVs of the two
projects? Should both projects be accepted? Or either? Or neither?
Explain your reasoning.
Product Line Year 0 1 2 3 4 5 LO 2 Solution: a. Required rate of return =
16.4% Product Line Expansion: Cost of product line expansion = $2,575,000
NPV = ∑ FCFt t t = 0 (1 + k )
n
= −$2,575,000 +
Year 0 1 2 3 4 LO 2
= −$56,667
= $75,758
Since System 200 has a positive NPV, select that system. Reject System
100 as it has negative NPV. 10.17 Payback: Creative Solutions, Inc., has
just invested $4,615,300 in equipment. The firm
uses payback period criteria of not accepting any project that takes more
than four years to recover its costs. The company anticipates cash flows
of $644,386, $812,178, $943,279, $1,364,997, $2,616,300, and $2,225,375
over the next six years. Does this investment meet the firm’s payback
criteria? LO 3
Payback period = Years before cost recovery + =4+ $850, 460 $2,616,300 =
4.33 years
Since the project payback period exceeds the firm’s target of four years,
it should not have been accepted. 10.18 Discounted payback: Timeline
Manufacturing Co. is evaluating two projects. It uses payback criteria of
three years or less. Project A has a cost of $912,855, and project B’s
cost is $1,175,000. Cash flows from both projects are given in the
following table. What are their discounted payback periods, and which
will be accepted with a discount rate of 8 percent? Year Project A
Project B
1 2 3 4 LO 3
Year 0 1 2 3 4 5 6 LO 3
Type 2 Cumulative CF
$(1,415,888) 586,212 413,277 331,199 141,442
Type 3 Cumulative CF
$(1,612,856) 786,212 175,000 175,000 175,000 175,000 175,000
CF
$(1,311,450) 212,566 269,825 455,112 285,552 121,396
CF
$(1,311,450) (1,098,884) (829,059) (373,947) (88,395) 33,001
CF
$(1,415,888) (829,676) (416,399) (85,200) 56,242
CF
($1,612,856) (826,644) (651,644) (476,644) (301,644) (126,644) 48.356
Type 1:
Payback period = Years before cost recovery + =4+ $88,395 $121,396 = 4.73
years
Payback period = Years before cost recovery + = 3+ $85, 200 $141, 442 =
3.6 years
Type 3:
Select Type 2 because it has the lowest payback period. 10.20 Discounted
payback: Nugent Communication Corp. is investing $9,365,000 in new
technologies. The company expects significant benefits in the first three
years after installation (as can be seen by the cash flows), and smaller
constant benefits in each of the next four years. What is the discounted
payback period for the project assuming a discount rate of 10 percent?
acquiring a new machine that can create customized window treatments. The
equipment will cost $263,400 and will generate cash flows of $85,000 over
each of the next six years. If the cost of capital is 12 percent, what is
the MIRR on this project?
LO 5
Solution:
Years
1–4 5–7 8–10
Cash Flow
$23,500,000 $72,000,000 $80,000,000
LO 5
Solution:
Years
Initial investment = Length of project = Required rate of 1–4 5–7 8–10
Cash Flow
$23,500,000 $72,000,000 $80,000,000 $161,000,000 n = 10 years return = k
= 15%
FCFt t t = 0 (1 + IRR )
n
NPV = 0 = ∑
FCFt t t = 0 (1 + IRR )
n
FCFt t t = 0 (1 + IRR )
n
10.24 Internal rate of return: Refer to problem 10.5. Compute the IRR for
both
production system 1 and production system 2. Which has the higher IRR?
Which production system has the highest NVP? Explain why the IRR and NPV
rankings of systems 1 and 2 are different?
LO 5
Solution
The IRR of system 1 is 83.93 percent and the IRR of system 2 is 50.07%.
The NPV of system 1 is $22,969.42 and the NPV of system 2 is $36,001.43.
System 1 delivers a higher IRR because it requires a lower initial
investment and the cost is recovered the first year. Thus, even with
lower cash inflows in the years after startup, system 1is able to deliver
a higher return on the initial investment. System 2 has a higher initial
investment but delivers a higher net cash flow for the firm.
10.25 Internal rate of return: Ancala Corporation is considering
investments in two new golf
apparel lines for next season: golf hats and belts. Due to a funding
constraint, these lines are mutually exclusive. A summary of each
project’s estimated cash flows over its three year life, as well as the
IRRs and NPVs of each are outlined below. The CFO of the firm has decided
to manufacture the belts; however, the CEO of Ancala is questioning this
decision given that the IRR is higher for manufacturing hats. Explain to
the CEO why the IRRs and NPVs of the belt and hat projects disagree? Is
the CFO’s decision the correct .
The IRRs and NPVs of the belt and hat lines disagree because of the
differences in the scale of the project. Hats deliver a higher IRR
because they require a lower initial investment. Thus, even with lower
cash inflows in the years after startup, the hat project is able to
deliver a higher return on the initial investment. While the golf belts
project does cost more, it delivers a higher net cash flow for Ancala
investors. This NPV factors in the initial cost of the project, and
reflects the total net cash flow for the firm’s shareholders. The CFO’s
decision to choose the golf belts project is the right choice because it
yields the higher net cash flows for Ancala’s investors.
10.26 Internal rate of return: Compute the IRR on the following cash flow
streams: a.
An initial investment of $25,000 followed by a single cash flow of
$37,450 in year 6. An initial investment of $1 million followed by a
single cash flow of $1,650,000 in year 4. An initial investment of $2
million followed by cash flows of $1,650,000 and $1,250,000 in years 2
and 4, respectively.
b.
c.
LO 5
Solution: a.
Try IRR = 7%.
NPV = 0 = ∑ FCFt t t = 0 (1 + IRR ) $37,450 0 ≠ −$25,000 + (1.07)6 ≠
−$25,000 + $24,955 ≠ −$45
n
b.
c.
10.27 Internal rate of return: Compute the IRR for the following project
cash flows. a.
An initial outlay of $3,125,000 followed by annual cash flows of $565,325
for the next eight years
b.
c.
LO 5
Solution: a.
Initial investment = $3,125,000 Annual cash flows = $565,325 Length of
investment = n = 8 years Try IRR = 8%. 1 ⎤ ⎡ 1− ⎢ FCFt (1.08)8 ⎥ NPV = ∑ $
3 , 125 , 000 $ 565 , 325 = − + × ⎢ ⎥ t t = 0 (1 + k ) ⎢ 0.08 ⎥ ⎢ ⎥ ⎣ ⎦
n
b.
1 ⎤ ⎡ 1− ⎢ FCFt (1.12)5 ⎥ NPV = ∑ = −$33,750 + $9,430 × ⎢ ⎥ t t = 0 (1 + k )
⎢ 0.12 ⎥ ⎢ ⎥ ⎣ ⎦
n
c.
Year
0 1 2 3 4 5 6 7
Project 1
$(8,425,375) $3,225,997 $1,775,882 $1,375,112 $1,176,558 $1,212,645
$1,582,156 $1,365,882
Project 2
$(11,368,000) $2,112,589 $3,787,552 $3,125,650 $4,115,899 $4,556,424
LO 2
Solution: Project 1:
Cost of Project 1 = $8,425,375 Length of project = n = 7 years Required
rate of return = k = 13.8%
NPV = ∑ FCFt t t = 0 (1 + k )
n
Project 2:
Cost of Project 2 = $11,368,000 Length of project = n = 5 years Required
rate of return = k = 13.8% NPV = ∑ FCFt t t = 0 (1 + k )
n
Solution: a. Project 1:
At the required rate of return of 13.8 percent, Project 1 has a NPV of
$(668,283). To find the IRR, try lower rates. Try IRR = 11%.
NPV = ∑
FCFt t t = 0 (1 + k )
n
Project 2:
At the required rate of return of 13.8 percent, Project 1 has a NPV of $
375,375. To find the IRR, try higher rates. Try IRR = 15%. NPV = 0 = ∑
FCFt t t = 0 (1 + IRR ) $2,112,589 $3,787,552 $3,125,650 $4,115,889
$4,556,424 + + + + 0 = −$11,368,000 + (1.15)1 (1.15) 2 (1.15)3 (1.15) 4
(1.15)5 = −$11,368,000 + $1,837,034 + $2,863,933 + $2,055,166 +
$2,353,279 + $2,265,348 = $6,760
n
Try IRR = 15.1%. NPV = 0 = ∑ FCFt t t = 0 (1 + IRR ) $2,112,589
$3,787,552 $3,125,650 $4,115,889 $4,556,424 + + + + 0 = −$11,368,000 +
(1.151)1 (1.151) 2 (1.151)3 (1.151) 4 (1.151)5 = −$11,368,000 +
$1,835,438 + $2,858,959 + $2,049,814 + $2,345,111 + $2,255,524 = −$23,154
n
The IRR of the project is between 15 and 15.1 percent. Using a financial
calculator, we find that the IRR is 15.023 percent. Based on the IRR,
Project 1 will be rejected and Project 2 will be accepted. These
decisions are identical to those based on NPV. (Given that Project 1 had
a negative NPV, the IRR will always be less than the required rate of
return 0. Management would use the decision spelled out by NPV, although
in this case the IRR has come up with the same decision.
b.
c.
Year
1 2 3 4
Project 1
0 $125,000 $150,000 $375,000
Project 2
0 0 $500,000 $500,000
Project 3
$245,125 $212,336 $112,500 $74,000
LO 2
Solution:
Cost of projects = $500,000 Length of project = n = 4 years Required rate
of return = k = 14.8%
Project 1:
NPV = ∑ FCFt $0 $125,000 $150,000 $375,000 = −$500,000 + + + + t 1
(1.148) (1.148) 2 (1.148)3 (1.148) 4 t = 0 (1 + k ) = −$500,000 + $0 +
$94,848 + $99,144 + $215,906
n
= −$90,103
Project 2:
NPV = ∑ FCFt $0 $0 $500,000 $500,000 = −$500,000 + + + + t 1 2 (1.148)
(1.148) (1.148)3 (1.148) 4 t = 0 (1 + k ) = −$500,000 + $0 + $0 +
$330,479 + $287,874
n
= $118,353
Project 3:
NPV = ∑ FCFt $245,125 $212,336 $112,500 $74,000 = −$500,000 + + + + t
(1.148)1 (1.148) 2 (1.148)3 (1.148) 4 t = 0 (1 + k ) = −$500,000 +
$213,524 + $161,116 + $74,358 + $42,605
n
= −$8,397
Year
0 1
Project 1
$(500,000)
−
PVCF
$(500,000)
−
Project 2
$(500,000)
−
PVCF
$(500,000)
−
Project 3
$(500,000) 245,125
PVCF
$(500,000) 215,779
2 3 4
500,000 500,000
341,063 300,232
NPV
(75,645)
141,295
1,491
Year
0 1 2 3 4
Project 1
$(275,000) $63,000 $85,000 $85,000 $100,000
Project 2
$(312,500) $153,250 $167,500 $112,000
Project 3
$(500,000) $212,000 $212,000 $212,000 $212,000
LO 5
Solution: Project 1:
Cost of Project 1 = $275,000 Length of project = n = 4 years Required
rate of return = k = 14.5% NPV = ∑ FCFt t t = 0 (1 + k )
n
Project 2:
Cost of Project 2 = $312,500 Length of project = n = 3 years Required
rate of return = k = 14.5%
NPV = ∑ FCFt $153,250 $167,500 $112,000 = −$312,500 + + + t (1.145)1
(1.145) 2 (1.145)3 t = 0 (1 + k ) = −$312,500 + $ 133,843 + $127,763 +
$74,611
n
= $23,717
Project 3:
Cost of Project 3 = $500,000 Length of project = n = 4 years Required
rate of return = k = 14.5% 1 ⎡ ⎤ 1− 4 ⎥ ⎢ FCFt (1.145) = −$500,000 +
$212,000 × ⎢ NPV = ∑ ⎥ t t = 0 (1 + k ) ⎢ 0.145 ⎥ ⎢ ⎥ ⎣ ⎦ = −$500,000 +
$611,429
n
= $111,429
Try IRR=25.1%.
NPV = 0 = ∑ FCFt t t = 0 (1 + IRR )
n
10.32 Jekyll & Hyde Corp. is evaluating two mutually exclusive projects.
The cost of capital is
15 percent. Costs and cash flows are given in the following table. Which
project should be accepted?
Year
0 1 2 3 4 5
Project 1
$(1,250,000) $250,000 $350,000 $450,000 $500,000 $750,000
Project 2
$(1,250,000) $350,000 $350,000 $350,000 $350,000 $350,000
LO 5
Solution: Project 1:
Cost of project = $1,250,000 Length of project = n = 5 years Required
rate of return = k = 15% NPV = ∑ FCFt t t = 0 (1 + k )
n
0 = −$1,250,000 +
Project 2:
Cost of project = $1,250,000 Length of project = n = 5 years Required
rate of return = k = 15% 1 ⎤ ⎡ 1− ⎢ FCFt (1.15)5 ⎥ = − + × NPV = ∑ $ 1 ,
250 , 000 $ 350 , 000 ⎢ ⎥ t t = 0 (1 + k ) ⎢ 0.15 ⎥ ⎢ ⎥ ⎣ ⎦ = −$1,250,000 +
$1,173,254
n
= −$76,746
Year
0
Project 1
$(475,000)
Project 2
$(500,000)
1 2 3 4
LO 5
Solution: Project 1:
Cost of project = $475,000 Length of project = n = 4 years Required rate
of return = k = 17% NPV = ∑ FCFt t t = 0 (1 + k )
n
FCFt t t = 0 (1 + k )
n
Project 2:
Cost of project = $500,000 Length of project = n = 4 years Required rate
of return = k = 17% NPV = ∑ FCFt t t = 0 (1 + k )
n
Project 1
$(10,000) $4,750 $3,300 $3,600 $2,100
Project 2
$(10,000) $1,650 $3,890 $5,100 $2,750 $800
Project 3
$(10,000) $800 $1,200 $2,875 $3,400 $6,600
LO 5
Solution: Project 1:
Cost of project = $10,000 Length of project = n = 4 years NPV = 0 = ∑
FCFt t t = 0 (1 + IRR ) $4,750 $3,300 $3,600 $2,100 + + + 0 = −$10,000 +
(1.16)1 (1.16) 2 (1.16) 3 (1.16) 4 = −$10,000 + $4,095 + $2,452 + $2,306
+ $1,160 = $13 ≅ 0
n
Project 2:
Cost of project = $10,000 Length of project = n = 5 years NPV = 0 = ∑
FCFt t t = 0 (1 + IRR ) $1,650 $3,890 $5,100 $2,750 $800 + + + + 0 =
−$10,000 + 1 2 3 4 (1.137) (1.137) (1.137) (1.137) (1.137)5 = −$10,000 +
$1,451 + $3,009 + $3,470 + $1,545 + $421 = −$4 ≅ 0
n
The IRR of the project is approximately 13.7 percent. Using a financial
calculator, we find that the IRR is 13.685 percent.
Project 3:
Cost of project = $10,000 Length of project = n = 5 years NPV = 0 = ∑
FCFt t t = 0 (1 + IRR ) $800 $1,200 $2,875 $3,400 $6,600 + + + + 0 =
−$10,000 + 1 2 3 4 (1.109) (1.109) (1.109) (1.109) (1.109)5 = −$10,000 +
$721 + $976 + $2,108 + $2,248 + $3,934 = −$13 ≅ 0
n
a. b. c.
LO 2, LO 3, LO 5
Solution: a. Year
0 1 2 3 4
Project 1
$(7,125,000) 1,875,000 1,875,000 1,875,000 1,875,000
Cumulative CF
$(7,125,000) (5,250,000) (3,375,000) (1,500,000) 375,000
5 6 7 8
b.
c.
To compute the IRR, try rates higher than 12 percent. Try IRR = 20%.
NPV = 0 = ∑ FCFt t t = 0 (1 + k )
n
FCFt t t = 0 (1 + k )
n
10.36 Quasar Tech Co. is investing $6 million in new machinery that will
produce the nextgeneration routers. Sales to its customers will amount to
$1,750,000 for the next three years and then increase to $2.4 million for
three more years. The project is expected to last six years and cost,
excluding depreciation will be $898,620 annually. The machinery will be
depreciated to a salvage value of 0 over 6 years using the straight-line
method. The company’s tax rate is 30 percent, and the cost of capital is
16 percent. What is the payback period? What is the average accounting
return (ARR)? Calculate the project NPV. What is the IRR for the project?
a. b. c. d.
LO 2, LO 3, LO 5 Solution:
a. Project 1 Year
0 1 2 3 4 $(104,034) $(104,034) $(104,034) 350,966 $1,000,000 $1,000,000
$1,000,000 $1,000,000
Cumulative CF
$(6,000,000) (5,104,034) (4,208,068) (3,312,102) (1,961,136)
Net Income
Depreciation
Cash Flows
$(6,000,000) 895,966 895,966 895,966 1,350,966
5 6
350,966 350,966
$1,000,000 $1,000,000
1,350,966 1,350,966
(610,170) 740,796
b. Year 1
Sales Expenses Depreciation EBIT Taxes (30%) Net income Beginning BV
Less: Depreciation Ending BV $ 5,000,000 $ 4,000,000 $ 3,000,000 $
2,000,000 $ 1,000,000 Average after-tax income = $123,466 Average book
value of equipment = $3,000,000
Accounting rate of return = Average after - tax income Average book value
$123,466 = = 4.1% $3,000,000
Year 2
898,620 1,000,000 $(1,48,620) 44,586 $ (104,034) 5,000,000 1,000,000
Year 3
898,620 1,000,000 $(1,48,620) 44,586 $ (104,034) 4,000,000 1,000,000
Year 4
898,620 1,000,000 $ 501,380 (150,414) $ 350,966 3,000,000 1,000,000
Year 5
898,620 1,000,000 $ 501,380 (150,414) $ 350,966 2,000,000 1,000,000
Year 6
898,620 1,000,000 $ 501,380 (150,414) $ 350,966 1,000,000 1,000,000 $ 0
c.
FCFt t t = 0 (1 + k )
n
LO 2, LO 3, LO 4, LO 5
Year 0 1 2 3 4 5
c.
d.
To compute the IRR, try rates much higher than 17 percent. Try IRR = 30%.
NPV = 0 = ∑ FCFt t t = 0 (1 + IRR )
n
NPV = 0 = ∑
FCFt t t = 0 (1 + IRR )
n
a. b. c.
= −$395,000 +
b.
Project A: Since NPV > 0, to compute the IRR, try rates higher than 10
percent. Try IRR = 27%.
NPV = 0 = ∑ FCFt t t = 0 (1 + IRR )
n
FCFt t t = 0 (1 + IRR )
n
c.
d.
a. b. c.
Compute the payback and discounted payback period for the project. What
is the NPV for the project? Should the firm go ahead with the project?
What is the IRR, and what would be the decision under the IRR?
LO 2, LO 3, LO 5
b.
CFA Problems
10.40. Given the following cash flows for a capital project, calculate
the NPV and IRR. The required rate of return is 8 percent. Year 0 CASH
FLOW –50,000 1 15,000 2 15,000 3 20,000 4 10,000 5 5,000
LO 2
SOLUTION:
c is correct.
NPV = −50, 000 + 15, 000 15, 000 20, 000 10, 000 5, 000 + + + + 1.08
1.082 1.083 1.084 1.085
LO 3
SOLUTION: c is correct.
YEAR CASH FLOW CUMULATIVE CASH
FLOW
DISCOUNTED CASH
FLOW
CUMULATIVE DCF
As the table shows, the cumulative cash flow offsets the initial
investment in exactly three years. The payback period is 3.00 years. The
discounted payback period is between four and five years. The discounted
payback period is 4 years plus 24.09/3,402.92 = 0.007 of the fifth year
cash flow, or 4.007 = 4.01 years. The discounted payback period is 4.01 –
3.00 = 1.01 years longer than the payback period.
10.42. An investment of $100 generates after-tax cash flows of $40 in
Year 1, $80 in Year 2, and $120 in Year 3. The required rate of return is
20 percent. The net present value is closest to a. b. c. d. $42.22 $58.33
$68.52 $98.95
LO 2
SOLUTION: b is correct.
NPV = ∑
t =0 3
LO 5
PRESENT VALUE 28.19% –150,000 78,009 73,025 1,034 28.39% –150,000 77,888
72,798 686 28.59% –150,000 77,767 72,572 338 28.79% –150,000 77,646
72,346 –8
0 1 2 Total
LO 2
Solution:
Cost of this project = $675,000 Annual cash flows = $195,000 Required
rate of return = 14% Length of project = n = 6 years 1 ⎤ ⎡ 1− ⎢ FCFt
(1.14)6 ⎥ NPV = ∑ $ 675 , 000 $ 195 , 000 = − + × ⎥ ⎢ t t = 0 (1 + k ) ⎢
0.14 ⎥ ⎥ ⎢ ⎦ ⎣
n
10.2
CF
$(168,000) 43,500 43,500 43,500 36,875 36,875
CF
$(168,000) (124,500) (81,000) (37,500) (625) 36,250
10.3
Solution:
Annual after-tax income = $156,435 Average after-tax income = $156,435
Average book value of equipment = $322,500
Accounting rate of return = Average after - tax income Average book value
$156,435 = = 48.5% 322,500
Since the project’s ARR is above the acceptance rate of 40 percent, the
project should be accepted.
10.4
Internal rate of return: Refer to Sample Test Problem 10.1. What is the
IRR on this
project?
Solution:
= −$675,000 + $758,290 = $83,290 Since NPV > 0, try IRR > k. Try IRR =
18%. 1 ⎤ ⎡ 1− ⎢ FCFt (1.18) 6 ⎥ NPV = 0 = ∑ 0 $ 675 , 000 $ 195 , 000 = − +
× ⎥ ⎢ t t = 0 (1 + IRR ) ⎢ 0.18 ⎥ ⎥ ⎢ ⎦ ⎣ = −$675,000 + $682,033
n
10.5
Net present value: Raycom, Inc. needs a new overhead crane and two
alternatives are
available. Crane T costs $1.35 million and will produce cost savings of
$765,000 for the next three years. Crane R will cost $1.675 million and
will yield cost savings of $815,000
for the next three years. The required rate of return is 15 percent.
Which of the two options should Raycom choose based on NPV criteria and
why?
Solution: Crane T:
Cost of this project = $1,350,000 Annual cash flows = $765,000 Required
rate of return = 15% Length of project = n = 3 years 1 ⎤ ⎡ 1− ⎢ FCFt
(1.15) 3 ⎥ NPV = ∑ $ 1 , 350 , 000 $ 765 , 000 = − + × ⎥ ⎢ t t = 0 (1 + k
) ⎢ 0.15 ⎥ ⎥ ⎢ ⎦ ⎣ = −$1,350,000 + $1,746,667
n
= $396,667
Crane R:
Cost of this project = $1,675,000 Annual cash flows = $815,000 Required
rate of return = 15% Length of project = n = 3 years 1 ⎤ ⎡ 1 − ⎢ (1.15)3 ⎥
n FCFt NPV = ∑ $ 1 , 675 , 000 $ 815 , 000 = − + × ⎥ ⎢ t t = 0 (1 + k ) ⎢
0.15 ⎥ ⎥ ⎢ ⎦ ⎣ = −$1,675,000 + $1,860,829 = $185,829 Raycom should choose
Crane T since it has the higher NPV.