MEASUREMENT SHEET

DETAILED ESTIMATE FOR CONSTRUCTION OF REGULATOR


AT KM 66.840 ON M.P.S.C

S.No. DESCRIPITION Nos Length Breadth Depth Quantity


in m (L) in m (B) in m (D) in Cum
Excavation in all kinds of soil including boulders upto 0.3 m
diameter for canal, seating of embankment, filter drains / catch
water drains etc., including dressing bed and sides to required
1 level and profile, cost of all materials, machinery, labour, placing
the excavated soil neatly in dump area or for the formation of
service road / embankment as directed etc., complete with initial
lead upto 1 km and all lifts.
i Abutments 2 1.500 2.600 4.155 32.409
ii Peir 2 3.800 2.000 0.950 14.440
iii For Vents 3 3.800 3.000 3.705 126.711
iv U/s Apron 1 5.000 19.700 0.638 62.843
v u/s Cut off wall 1 24.200 0.450 1.200 13.068
vi U/s wings 2 5.000 2.600 4.155 108.030
vii U/s Returns 2 1.900 2.600 4.155 41.051
viii D/s Apron 1 12.500 19.700 0.900 221.625
ix D/s Apron 1 12.500 7.200 0.769 69.210
x D/s Wings 2 12.500 2.600 4.155 270.075
xi D/s Returns 2 1.900 2.600 4.155 41.051
xii D/s Cutoff wall 1 12.500 0.450 1.200 6.750
Cum 1007.264
Providing soil filling behind abutments wing and return walls in
layers including cost of all materials, machinery, labour, watering,
2
ramming etc., complete with initial lead upto 50 m and initial lift
upto 3 m.
Abutments 2 1.500 0.750 3.655 8.224
U/s wings 2 5.000 0.850 3.655 31.068
U/s Returns 2 1.900 1.150 3.655 15.972
D/s Wings 2 12.500 0.850 3.655 77.669
D/s Returns 2 1.900 1.150 3.655 15.972
Cum 148.905
Providing and laying insitu vibrated M-15 ( 28 days cube
compressive strength not less than 15 N / sq mm ) grade cement
concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials,
3 machinery, labour, formwork, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.

i Abutments 2 1.500 2.600 0.500 3.900


ii U/s wings 2 5.000 2.600 0.500 13.000
iii U/s Returns 2 1.900 2.600 0.500 4.940
iv D/s Wings 2 12.500 2.600 0.500 32.500
v D/s Returns 2 1.900 2.600 0.500 4.940
vi U/s apron 1 5.000 19.700 0.500 49.250
vii U/s cut off wall 1 24.200 0.450 1.200 13.068
viii For Crerst (Vents) 2 1.500 2.500 0.705 5.288
ix For Glacis 1 5.100 5.000 0.769 19.610
x D/s Apron 1 12.500 19.700 0.500 123.125
xi D/s Cutoff wall 1 12.500 0.450 1.200 6.750
xii Apron lift 1 0.950 15.200 0.150 2.166
xiii levelling coarse under Abutments 2 1.500 2.600 0.150 1.170
xiv levelling coarse under Peirs 2 3.800 2.000 0.150 2.280
Cum 281.986
S.No. DESCRIPITION Nos Length Breadth Depth Quantity
in m (L) in m (B) in m (D) in Cum
Providing and laying insitu vibrated M-15 ( 28 days cube
compressive strength not less than 15 N / sq mm ) grade cement
concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including
cost of all materials, machinery, labour, formwork, scaffolding,
4
cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and
all lifts. ( Cement content : 260 kg / cum ) For Abutment, Wing
& Return Walls

i Abutments 2 0.900 1.500 3.250 8.775


ii U/s wings 2 5.000 1.100 3.325 36.575
iii U/s Returns 2 1.600 1.100 3.325 11.704
iv D/s Wings 2 11.900 1.100 3.469 90.818
v D/s Returns 2 1.900 1.200 3.625 16.530
Cum 164.402
Providing and laying insitu vibrated M-20 ( 28 days cube
compressive strength not less than 20 N / sq mm ) grade cement
concrete using 20 mm down size approved, clean, hard, graded
aggregates for Peir footings and Peirs including cost of all
materials,machinery, labour, formwork, scaffolding, cleaning,
5
batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.

i Peir Fotting 2 3.800 2.000 0.500 7.600


ii Peir 2 2.900 1.000 3.205 18.589
Cum 26.189
Providing and laying insitu vibrated M-20 ( 28 days cube
compressive strength not less than 20 N / sq mm ) grade cement
concrete using 20 mm down size approved, clean, hard, graded
aggregates for slabs including cost of all materials,machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing
6
in position, levelling, vibrating, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.

i Bed Blocks over abutment 2 1.500 1.000 0.300 0.900


ii Dirt Wall 2 1.500 0.500 0.100 0.150
iv Hoist slab 1 12.000 1.500 0.100 1.800
v Side wall for Hoist 1 12.000 0.200 0.600 1.440
vi Peir Cap 2 3.800 1.000 0.300 2.280
Cum 6.570
Providing and laying insitu M- 25 ( 28 days cube compressive
strength not less than 25 N / sqmm ) grade cement concrete using
20 mm down size approved, clean, hard, graded aggregates for
wearing coat including cost of all materials, machinery, labour,
7 formwork, cleaning, batching, mixing, placing in position in
alternate panels, levelling, compacting, finishing, curing, packing
joints with asphalt mortar etc., complete with initial lead upto 50
m and all lifts.

i Wearing coat over u/s Apron 1 5.000 19.700 0.150 14.775


ii Wearing coat over Crest 3 1.000 1.500 0.150 0.675
iii Wearing coat over d/s slope 1 1.260 1.500 0.150 0.284
iv Wearing coat over d/s Apron 1 12.500 4.500 0.150 8.438
Cum 24.171
S.No. DESCRIPITION Nos Length Breadth Depth Quantity
in m (L) in m (B) in m (D) in Cum
Providing and laying insitu M- 30 ( 28 days cube compressive
strength not less than 30 N / sqmm ) grade cement concrete using
20 mm down size approved, clean, hard, graded aggregates for
wearing coat including cost of all materials, machinery, labour,
8 formwork, cleaning, batching, mixing, placing in position in
alternate panels, levelling, compacting, finishing, curing, packing
joints with asphalt mortar etc., complete with initial lead upto 50
m and all lifts.

i Wearing coat over Aprons 1 0.000 0.000 0.000 0.000


Cum 0.000
Providing and fixing 12 mm thick 380 mm depth tarfelt expansion
joint filler boards for stone masonry lining of canal including cost
9 of all materials, labour etc., complete with all leads and lifts.

For Abutments 2 1.500 Rmt 3.000


For Peirs 2 1.500 Rmt 3.000
Rmt 6.000
Providing and fixing 100 mm dia perforated PVC pipes 40 cm
10 long for Weep holes including cost of all materials, labour,
drilling 8 mm dia holes etc. complete with all leads and lifts.
For Abutments 1 1.500 2
for U/s wings and Returns 2 4.000 8
for D/s wings and Returns 2 4.000 8
Nos 18
18 x 0.40 say Rmt 7.00
Providing, fabricating and placing in position reinforcement steel
bars for RCC works including cleaning, straightening, cutting,
bending, hooking, lapping, welding wherever required,tying with
11
1.25 mm dia soft annealed steel wire, including cost of all
materials, machinery, labour etc., complete with initial lead upto 50
and all lifts.
As per Statement Kgs 1880
11 Providing, fabricating and placing in position reinforcement steel bars for RCC works including cleaning,
straightening, cutting, bending, hooking, lapping, welding wherever required,tying with 1.25 mm dia soft
annealed steel wire, including cost of all materials, machinery, labour etc., complete with initial lead upto 50
and all lifts.

Total Unit. Wt. Total Wt.


Dia. Spacing Span Nos Length
length In kg in kg

1 Hoist Slab
16mm Φ bars top/bot 16 0.2 1.5 18 12 216 1.59 343
12mm Φ bars stir 12 0.2 12 61 1.5 91.5 0.89 81
2 Bed block over abut
16mm Φ bars top/bot 16 2x(3x2+5x2 )= 32 1.5 48 1.59 76
10mm Φ bars stirr 8 0.2 1.5 18 2.6 46.8 0.395 18
3 Bed block over Peir
16mm Φ bars top/bot 16 2x6x2 = 24 3.8 91.2 1.59 145
8mm Φ bars stirr 8 0.2 3.8 40 2.4 96 0.4 38
4 Peir footing
12mm Φ bars top/bot 12 0.2 1.5 36 3.8 136.8 0.89 122
16mm Φ bars stirr 16 0.25 3.8 32 5 160 1.59 254
5 Peir Skin Reinforce
10mm Φ bars ver 10 0.2 11.94 122 4.92 600.24 0.62 372
10mm Φ bars hor 10 0.2 4.32 46 11.94 549.24 0.62 341
Total in Kgs 1790
wastage 5% 89.5
Total in Kgs 1879.5
Total in MT 1.880
dia wieght/kg weight/tons
16 858.9 0.8589
12 213.15 0.21315
10 748.65 0.74865
8 58.8 0.0588

total 1879.5 1.8795


DIA WEIGHT IN KG wastage 5% WEIGHT IN TON
16 343.000 17.150 360.150
16 76.000 3.800 79.800
16 145.000 7.250 152.250
16 254.000 12.700 266.700
12 81.000 4.050 85.050
12 122.000 6.100 128.100
10 372.000 18.600 390.600
10 341.000 17.050 358.050
8 18.000 0.900 18.900
8 38.000 1.900 39.900
1790.000 89.500 1879.500